XML 107 R51.htm IDEA: XBRL DOCUMENT v3.20.1
ASSET UNDER DEVELOPMENT (Tables)
12 Months Ended
Dec. 31, 2019
Extractive Industries [Abstract]  
Schedule of Asset Under Development
(in thousands of $)20192018
As of January 120,000  1,177,489  
Additions372,849  118,942  
Transfer to vessels and equipment, net (note 16)
—  (1,296,431) 
Transfer from vessels and equipment, net (note 16)—  20,000  
Transfer from other non-current assets (note 17)

31,048  —  
Interest costs capitalized10,351  —  
As of December 31434,248  20,000  
Contractual Obligation, Fiscal Year Maturity
As of December 31, 2019, the estimated timing of the outstanding payments in connection with the Gimi conversion are as follows:
(in thousands of $)
Period ending December 31,
2020349,246  
2021218,704  
2022242,985  
2023102,686  
913,621