XML 28 R18.htm IDEA: XBRL DOCUMENT v3.20.2
Asset Under Development
9 Months Ended
Sep. 30, 2020
Extractive Industries [Abstract]  
Assets Under Development ASSETS UNDER DEVELOPMENT
(in thousands of $)September 30, 2020December 31, 2019
Opening asset under development balance434,248 20,000 
Additions200,245 372,849 
Transfer from vessels and equipment, net77,172 — 
Transfer from other non-current assets (see note 13)16,213 31,048 
Interest costs capitalized35,629 10,351 
Closing asset under development balance763,507 434,248 

Gimi conversion

In February 2019, we entered into an agreement with BP for the employment of a FLNG unit, the Gimi, after conversion for 20-years. In April 2019, we completed the sale of 30% of the total issued ordinary share capital of Gimi MS to First FLNG Holdings. In October 2020, we announced that we had confirmed a revised project schedule with BP for the Gimi GTA Project. The revised project schedule will result in the target connection date for the Gimi, previously scheduled for 2022, as set out in the LOA, being extended by 11 months. Notice has been given and received by us and BP that no FM event (as defined in the LOA) is ongoing. The terms of the LOA are unchanged. We have concluded discussions with both engineering, procurement and construction contractors and lending banks regarding the adjustment of the related construction and financing schedules, respectively, for the Gimi GTA Project and we have commenced the approval process to reflect these changes in the respective agreements. The conversion cost including financing cost is approximately $1.5 billion of which $700 million is funded by the Gimi facility (see note 14).


As at September 30, 2020, the estimated timing of the outstanding payments in connection with the Gimi conversion are as follows:
(in thousands of $)
Period ending December 31,
2020 (1)
134,781 
2021213,613 
2022319,235 
2023201,104 
202461,757 
930,490 
(1) For the three months ending December 31, 2020

LNG Croatia conversion
In March 2019, we entered into agreements with LNG Hrvtska relating to the conversion and subsequent sale of the converted carrier LNG Croatia into a FSRU. Under the agreement, we will also operate and maintain the FSRU for a minimum of 10 years following its sale. In January 2020, the LNG Croatia completed her charter and entered the yard for conversion. In September 2020, the LNG Croatia completed construction work in a shipyard in China for its conversion to a FSRU. She is currently completing remaining automation and equipment pre-commissioning works in a shipyard in Croatia prior to commissioning and acceptance of the vessel by LNG Hrvatska, which is expected to occur on or about December 31, 2020.$75.0 million of the conversion is funded by the financing agreement with CSSC of which $60.2 million was drawn down during the nine months ended September 30, 2020 (see note 14). The remaining conversion cost is approximately $18.6 million payable within the next three months ending December 31, 2020.