oda_PartialOrCompleteSuspensionOrImposssibilityOfOperationsAbstract|
|
|
||||||||
|
oda_UpdateAnnouncementFlag|
|
|
Evet (Yes)
|
|||||||
|
oda_CorrectionAnnouncementFlag|
|
|
Hayır (No)
|
|||||||
|
oda_DateOfThePreviousNotificationAboutTheSameSubject|
|
|
18.11.2024
|
|||||||
|
oda_DelayedAnnouncementFlag|
|
|
Hayır (No)
|
|||||||
|
oda_AnnouncementContentSection|
|
|
||||||||
|
oda_NatureOfSituationOccured|
|
|
The stop of Rotary Kiln 1 continues
|
|||||||
|
oda_InformationAboutOperationsSupendedOrBecameImpossible|
|
|
Continuing the stop of the 1st kiln,where our company produces clinker.
|
|||||||
|
oda_ReasonOfSuspensionOrImpossibilityOfOperations|
|
|
Planned revision continues
|
|||||||
|
oda_DecisionDateOfAuthorizedBodyIfExits|
|
|
None.
|
|||||||
|
oda_ValidityDateOfSuspensionOrImpossibilityOfOperations|
|
|
16.11.2024
|
|||||||
|
oda_EffectOfSuspensionOrImpossibilityOfOperationsOnTotalProductionOfCompany|
|
|
None.
|
|||||||
|
oda_EffectOfSuspensionOrImpossibilityOfOperationsOnTotalSalesOfCompany|
|
|
None.
|
|||||||
|
oda_ShareOfPartiallySuspendedOperationsInTotalProductionAndSalesOfCompany|
|
|
Due to our planned clinker stock, this stoppage does not affect our sales.
|
|||||||
|
oda_NumberOfPersonnelWhoseEmploymentContractsWereOrWillBeTerminated|
|
|
None.
|
|||||||
|
oda_TotalAmountOfSeveranceAndTerminationPaysThatWasOrWillBePaid|
|
|
None.
|
|||||||
|
oda_PrecautionsTookIntoConsiderationByCompanyManagement|
|
|
There is a planned clinker stock.
|
|||||||
|
oda_ConditionsRequiredForGoingIntoOperationAgain|
|
|
Completion of planned revision.
|
|||||||
|
oda_ExpectedDateToBeginOperations|
|
|
27.12.2024
|
|||||||
|
oda_EffectsOnContinuityAssumptionOfCompany|
|
|
The stop has no effect on the continuity of the company.
|
|||||||
|
oda_ExplanationSection|
|
|
||||||||
|
oda_AdditionalExplanationTextBlock|
|
Due to the continuing of the planned revision on our Kiln 1, for which we announced the stop of Kiln 1 in the material event disclosure on November 18, 2024, it is expected to be operational again on December 27, 2024. Our clinker stock is at a sufficient level to produce cement at full capacity, and our cement production and sales will not be affected by this period.
|
||||||||