oda_NatureOfSituationOccured|
|
|
The stop of Rotary Kiln 1 continues
|
|||||||
|
oda_InformationAboutOperationsSupendedOrBecameImpossible|
|
|
Continuing the stop of the 1st kiln,where our company produces clinker.
|
|||||||
|
oda_ReasonOfSuspensionOrImpossibilityOfOperations|
|
|
Planned revision continues
|
|||||||
|
oda_DecisionDateOfAuthorizedBodyIfExits|
|
|
None.
|
|||||||
|
oda_ValidityDateOfSuspensionOrImpossibilityOfOperations|
|
|
16.11.2024
|
|||||||
|
oda_EffectOfSuspensionOrImpossibilityOfOperationsOnTotalProductionOfCompany|
|
|
None.
|
|||||||
|
oda_EffectOfSuspensionOrImpossibilityOfOperationsOnTotalSalesOfCompany|
|
|
None.
|
|||||||
|
oda_ShareOfPartiallySuspendedOperationsInTotalProductionAndSalesOfCompany|
|
|
Due to our planned clinker stock, this stoppage does not affect our sales.
|
|||||||
|
oda_NumberOfPersonnelWhoseEmploymentContractsWereOrWillBeTerminated|
|
|
None.
|
|||||||
|
oda_TotalAmountOfSeveranceAndTerminationPaysThatWasOrWillBePaid|
|
|
None.
|
|||||||
|
oda_PrecautionsTookIntoConsiderationByCompanyManagement|
|
|
There is a planned clinker stock.
|
|||||||
|
oda_ConditionsRequiredForGoingIntoOperationAgain|
|
|
Completion of planned revision.
|
|||||||
|
oda_ExpectedDateToBeginOperations|
|
|
10.02.2025
|
|||||||
|
oda_EffectsOnContinuityAssumptionOfCompany|
|
|
The stop has no effect on the continuity of the company.
|
|||||||
|
oda_ExplanationSection|
|
|
||||||||
|
oda_AdditionalExplanationTextBlock|
|
On 18.11.2024 and 06.12.2024, it has been decided to extend the maintenance works of our 1st kiln, for which we have notified the stoppage with the material event disclosure made on 18.11.2024 and 06.12.2024, for another 6 weeks by bringing forward the revision plan for 2025, taking into account the market and seasonal conditions, and Our clinker stock is at a sufficient level to produce cement at full capacity, and our cement production and sales will not be affected by this period.
|
||||||||