XML 49 R28.htm IDEA: XBRL DOCUMENT v3.8.0.1
Commitments and Contingencies (Tables)
3 Months Ended
Mar. 31, 2018
Commitments and Contingencies [Abstract]  
Schedule of Planned Capital Expenditures
At March 31, 2018, estimated capital expenditures for the remainder of 2018 through 2022 for which applicable internal approvals (and also, if required, regulatory approvals such as FPSC approvals for FPL) have been received were as follows:
 
Remainder of 2018
 
2019
 
2020
 
2021
 
2022
 
Total
 
(millions)
FPL:
 
 
 
 
 
 
 
 
 
 
 
Generation:(a)
 
 
 
 
 
 
 
 
 
 
 
New(b)(c)
$
430

 
$
465

 
$
1,245

 
$
1,100

 
$
1,105

 
$
4,345

Existing
980

 
855

 
460

 
550

 
490

 
3,335

Transmission and distribution
1,870

 
2,135

 
2,280

 
2,545

 
2,570

 
11,400

Nuclear fuel
130

 
150

 
135

 
145

 
165

 
725

General and other
385

 
320

 
290

 
300

 
280

 
1,575

Total
$
3,795

 
$
3,925

 
$
4,410

 
$
4,640

 
$
4,610

 
$
21,380

NEER:
 

 
 

 
 

 
 

 
 

 
 

Wind(d)
$
1,550

 
$
1,750

 
$
40

 
$
30

 
$
25

 
$
3,395

Solar(e)
90

 

 

 

 

 
90

Nuclear, including nuclear fuel
200

 
225

 
205

 
195

 
240

 
1,065

Natural gas pipelines(f)
850

 
50

 
25

 
15

 
25

 
965

Other
450

 
50

 
50

 
40

 
45

 
635

Total
$
3,140

 
$
2,075

 
$
320

 
$
280

 
$
335

 
$
6,150

Corporate and Other
$
40

 
$
20

 
$
30

 
$
15

 
$

 
$
105

———————————————
(a)
Includes AFUDC of approximately $74 million, $46 million, $47 million, $31 million and $14 million for the remainder of 2018 through 2022, respectively.
(b)
Includes land, generation structures, transmission interconnection and integration and licensing.
(c)
Excludes capital expenditures of approximately $800 million for the modernization of two generating units at FPL's Lauderdale facility to a high-efficiency natural gas-fired unit (Dania Beach Clean Energy Center), which is pending approval by the Florida Power Plant Siting Board, comprised of the Florida governor and cabinet.
(d)
Consists of capital expenditures for new wind projects, repowering of existing wind projects and related transmission totaling approximately 4,050 MW.
(e)
Includes capital expenditures for new solar projects and related transmission totaling approximately 100 MW.
(f)
Includes equity contributions associated with joint venture equity investments for the construction of natural gas pipelines.

Required capacity and/or minimum payments under contracts
The required capacity and/or minimum payments under contracts, including those discussed above, at March 31, 2018 were estimated as follows:
 
Remainder of 2018
 
2019
 
2020
 
2021
 
2022
 
Thereafter
 
(millions)
FPL:
 
 
 
 
 
 
 
 
 
 
 
Capacity charges(a)
$
15

 
$
20

 
$
20

 
$
20

 
$
20

 
$
225

Minimum charges, at projected prices:(b)
 

 
 

 
 

 
 

 
 

 
 

Natural gas, including transportation and storage(c)
$
1,485

 
$
980

 
$
940

 
$
905

 
$
895

 
$
11,240

Coal, including transportation
$
30

 
$
5

 
$

 
$

 
$

 
$

NEER(d)
$
2,145

 
$
540

 
$
175

 
$
145

 
$
170

 
$
1,330

Corporate and Other(e)(f)
$
205

 
$
15

 
$
15

 
$
10

 
$

 
$

———————————————
(a)
Capacity charges, substantially all of which are recoverable through the capacity clause, totaled approximately $5 million and $20 million for the three months ended March 31, 2018 and 2017, respectively. Energy charges, which are recoverable through the fuel clause, totaled approximately $7 million and $16 million for the three months ended March 31, 2018 and 2017, respectively.
(b)
Recoverable through the fuel clause.
(c)
Includes approximately $220 million, $290 million, $360 million, $390 million, $390 million and $7,175 million for the remainder of 2018 through 2022 and thereafter, respectively, of firm commitments related to the natural gas transportation agreements with Sabal Trail and Florida Southeast Connection.
(d)
Includes approximately $65 million, $65 million, $65 million, $65 million and $1,035 million in 2019 through 2022 and thereafter, respectively, of firm commitments related to a natural gas transportation agreement with a joint venture, in which NEER has a 31% equity investment, that is constructing a natural gas pipeline. These firm commitments are subject to the completion of construction of the pipeline which is expected at the end of 2018.
(e)
Includes an approximately $70 million commitment to invest in clean power and technology businesses through 2021.
(f)
Excludes approximately $170 million for the remainder of 2018 of joint obligations of NEECH and NEER which are included in the NEER amounts above.