Ship Purchase Obligations
Our future capital commitments consist primarily of new ship orders. As of December 31, 2024, we had two Icon-class ships and one Oasis-class ship on order for our Royal Caribbean brand with an aggregate capacity of approximately 16,900 berths. As of December 31, 2024, we had one Edge-class ship on order for our Celebrity brand with capacity of approximately 3,250 berths. The following provides further information on recent developments with respect to our ship orders.
During 2017, we entered into a credit agreement for the unsecured financing of Star of the Seas, the second Icon-class ship for up to 80% of the contract price. Finnvera plc, has agreed to guarantee 100% of a substantial majority of the financing to the lenders, with a smaller portion of the financing to be 95% guaranteed by Euler Hermes. The maximum loan amount under the facility is not to exceed €1.4 billion, or approximately $1.4 billion, based on the exchange rate at December 31, 2024. Interest on approximately 75% of the loan will accrue at a fixed rate of 3.76%, and the balance will accrue interest at a floating rate ranging from Term SOFR plus 1.58% to 1.63%. The loan will amortize semi-annually and will mature 12 years following delivery of the ship. Star of the Seas will have a capacity of approximately 5,600 berths. In December 2024, we amended the credit agreement for Star of the Seas, to increase the maximum loan amount by €364 million or $377 million based on exchange rate at December 31, 2024. Interest on the incremental portion will accrue at a floating rate equal to Term SOFR plus 0.85%.
In December 2023, we entered into a credit agreement for the unsecured financing of Celebrity Xcel, the fifth Edge-class ship for approximately 80% of the ship’s contract price and our building contract with Chantiers de l'Atlantique became effective. Bpifrance Assurance Export, the official French export credit agency, has agreed to guarantee to the lenders 100% of the financing. The maximum loan amount under the facility is not to exceed the United States dollar equivalent of €850 million, or approximately $880 million based on the exchange rate at December 31, 2024. The loan will amortize semi-annually and will mature 12 years following delivery of the ship. Interest on the loan will accrue at a floating rate equal to Term SOFR + 1.45%. Celebrity Xcel will have a capacity of approximately 3,250 berths.
In December 2019, we entered into a credit agreement for the unsecured financing of the third Icon-class ship for up to 80% of the ship’s contract price. Finnvera plc, the official export credit agency of Finland, has agreed to guarantee 95% of the substantial majority of the financing, with a smaller portion of the financing to be 95% guaranteed by Euler Hermes. The maximum loan amount under the facility is not to exceed the United States dollar equivalent of €1.4 billion, or approximately $1.4 billion based on the exchange rate at December 31, 2024. The loan, once funded, will amortize semi-annually and will mature 12 years following the delivery of the ship. Approximately 60% of the loan will accrue interest at a fixed rate of 3.29%. The balance of the loan will accrue interest at a floating rate of Term SOFR plus 1.28%. The third Icon-class ship will have a capacity of approximately 5,600 berths.
As of December 31, 2024, our Global Brands and our Partner Brands have the following ships on order:
ShipShipyardExpected to be deliveredApproximate
Berths
Royal Caribbean —
Oasis-class:
UnnamedChantiers de l’Atlantique2nd Quarter 20285,700
Icon-class:
Star of the SeasMeyer Turku Oy3rd Quarter 20255,600
UnnamedMeyer Turku Oy2nd Quarter 20265,600
Celebrity Cruises —
Edge-class:
Celebrity XcelChantiers de l’Atlantique4th Quarter 20253,250
TUI Cruises (50% joint venture) —
Mein Schiff RelaxFincantieri1st Quarter 20254,100
Mein Schiff FlowFincantieri2nd Quarter 20264,100
Total Berths28,350
During the quarter ended December 31, 2024, we received commitments for the unsecured financing of the seventh Oasis-class ship for up to 80% of the ship’s contract price and our building contract with Chantiers de l'Atlantique became effective. Bpifrance Assurance Export, the official French export credit agency, has agreed to guarantee to the lenders 100% of the financing.
In addition, during 2024, we entered into an agreement with Meyer Turku Oy and Chantiers de l' Atlantique to build a fourth Icon-class ship for delivery in 2027 and a sixth Edge-class ship for delivery in 2028. The agreements are contingent upon completion of certain conditions precedent including financing.
In January 2025, we announced the launch of Celebrity River Cruises, a premium river cruise vacation. We entered into agreements for the commitment to an initial order of 10 ships with plans to sail in 2027.
As of December 31, 2024, the aggregate cost of our ships on order, presented in the table above, not including any ships on order by our Partner Brands, was approximately $7.8 billion, of which we had deposited $815 million. Refer to Note 16. Fair Value Measurements and Derivative Instruments for further information.
Litigation
As previously reported, a lawsuit was filed against us in August 2019 in the U.S. District Court for the Southern District of Florida (the "Court") under Title III of the Cuban Liberty and Democratic Solidarity Act, also known as the Helms-Burton Act. The complaint filed by Havana Docks Corporation ("Havana Docks Action") alleges it holds an interest in the Havana Cruise Port Terminal, was expropriated by the Cuban government. The complaint further alleges that we trafficked in the terminal by embarking and disembarking passengers at these facilities. The plaintiffs seek all available statutory remedies, including the value of the expropriated property, plus interest, treble damages, attorneys’ fees and costs.
The Court entered final judgment in December 2022 in favor of the plaintiff and awarded damages and attorneys' fees to the plaintiff in the aggregate amount of approximately $112 million. We then appealed the judgment to the United States Court of Appeals for the 11th Circuit. On October 22, 2024, the 11th Circuit issued an opinion reversing the lower court’s judgment. The plaintiff's petition for a rehearing by the full 11th Circuit was subsequently denied. The plaintiff has the right to petition the United States Supreme Court for a writ of certiorari. During the fourth quarter of 2022, we recorded a charge of approximately $130 million to Other (expense) income within our consolidated statements of comprehensive income (loss) related to the Havana Docks Action, including post-judgment interest and related legal defense costs and bonding fees. Following the 11th Circuit's denial of the rehearing petition, we released approximately $124 million of the previously recorded loss contingency for the year ended December 31, 2024, recognized within Other (expense) income within our consolidated statements of comprehensive income (loss).
In addition, we are routinely involved in claims typical within the cruise vacation industry. The majority of these claims are covered by insurance. We believe the outcome of such claims, net of expected insurance recoveries, will not have a material adverse impact on our financial condition or results of operations and cash flows.
During the third quarter of 2024, we entered into agreements to acquire the Port of Costa Maya and adjacent land in Mahahual, Mexico for approximately $292 million. The transaction is expected to close in the first half of 2025, subject to regulatory approval and customary closing conditions.
Other
Some of the contracts that we enter into include indemnification provisions that obligate us to make payments to the counterparty if certain events occur. These contingencies generally relate to changes in taxes, increased lender capital costs and other similar costs. The indemnification clauses are often standard contractual terms and are entered into in the normal course of business. There are no stated or notional amounts included in the indemnification clauses and we are not able to estimate the maximum potential amount of future payments, if any, under these indemnification clauses. We have not been required to make any payments under such indemnification clauses in the past and, under current circumstances, we do not believe an indemnification in any material amount is probable.
If any person acquires ownership of more than 50% of our common stock or, subject to certain exceptions, during any 24-month period, a majority of our board of directors is no longer comprised of individuals who were members of our board of directors on the first day of such period, we may be obligated to prepay indebtedness outstanding under our credit facilities, which we may be unable to replace on similar terms. Our public debt securities also contain change of control provisions that would be triggered by a third-party acquisition of greater than 50% of our common stock coupled with a ratings downgrade. If this were to occur, it would have an adverse impact on our liquidity and operations.
At December 31, 2024, we have future commitments to pay for our usage of certain port facilities, marine consumables, services and maintenance contracts as follows (in millions):
Year
2025$178 
2026188 
2027167 
2028124 
2029118 
Thereafter797 