Major classes of property, plant and equipment and their respective balances for the Companies are as follows:

 

 

 

Dominion Energy

 

 

Virginia Power

 

At December 31,

2024

 

2023

 

2024

 

2023

 

(millions)

 

 

 

 

 

 

 

Utility:

 

 

 

 

Generation

$

26,854

 

$

24,903

 

 

$

20,219

 

$

18,580

 

Transmission

 

17,856

 

 

16,540

 

 

 

15,514

 

 

14,268

 

Distribution

 

23,572

 

 

21,836

 

 

 

17,261

 

 

15,934

 

Nuclear fuel

 

2,393

 

 

2,424

 

 

 

1,823

 

 

1,815

 

General and other

 

1,865

 

 

1,758

 

 

 

1,134

 

 

1,036

 

Plant under construction(1)

 

13,816

 

 

8,230

 

 

 

12,826

 

 

7,548

 

Total utility

 

86,356

 

 

75,691

 

 

68,777

 

 

59,181

 

Non-jurisdictional - including plant under construction

 

 

1,763

 

 

 

1,772

 

 

 

1,763

 

 

 

1,772

 

Nonutility:

 

 

 

 

 

Nonregulated generation-nuclear

 

1,962

 

 

1,855

 

 

 

 

 

 

Nonregulated generation-solar

 

 

1,207

 

 

 

945

 

 

 

 

 

 

Nuclear fuel

 

 

1,173

 

 

 

1,009

 

 

 

 

 

 

 

Other-including plant under construction

 

 

2,383

 

 

 

2,145

 

 

 

10

 

 

10

 

Total nonutility

 

 

6,725

 

 

 

5,954

 

 

10

 

 

10

 

Total property, plant and equipment

 

$

94,844

 

 

$

83,417

 

$

70,550

 

$

60,963

 

 

(1)
Includes $5.8 billion and $2.9 billion of costs associated with the CVOW Commercial Project at December 31, 2024 and 2023, respectively. The amount at December 31, 2024 is net of $206 million of costs not expected to be recovered from customers.
Schedule of Jointly Owned Utility Plants

The Companies’ proportionate share of jointly-owned power stations at December 31, 2024 is as follows:

 

 

 

Bath County Pumped Storage Station(1)

 

 

North Anna Units 1 and 2(1)

 

 

Clover Power Station(1)

 

 

Millstone Unit 3(2)

 

 

Summer Unit 1 (2)

 

(millions, except percentages)

 

 

 

 

 

 

 

 

 

 

 

Ownership interest

 

60

%

 

 

88.4

%

 

 

50

%

 

 

93.5

%

 

 

66.7

%

Plant in service

 

1,069

 

 

 

2,906

 

 

 

616

 

 

 

1,528

 

 

 

1,598

 

Accumulated depreciation

 

(774

)

 

 

(1,403

)

 

 

(312

)

 

 

(628

)

 

 

(755

)

Nuclear fuel

 

 

 

 

767

 

 

 

 

 

 

619

 

 

 

570

 

Accumulated amortization of nuclear fuel

 

 

 

 

(620

)

 

 

 

 

 

(475

)

 

 

(345

)

Plant under construction

 

12

 

 

 

408

 

 

 

9

 

 

 

93

 

 

 

58

 

 

(1)
Units jointly owned by Virginia Power.
(2)
Units jointly owned by Dominion Energy.
Virginia Electric and Power Company  
Schedule of Nonregulated Solar Projects

The following table presents acquisitions by Virginia Power of non-jurisdictional solar projects (reflected in Dominion Energy Virginia). Virginia Power has claimed federal investment tax credits on the projects, except as otherwise noted.

 

Project Name

 

Date Agreement
Entered

 

Date Agreement
Closed

 

Project Location

 

Project Cost
(millions)
(1)

 

 

Date of Commercial
Operations

 

MW Capacity

 

Ft. Powhatan

 

June 2019

 

June 2019

 

Virginia

 

$

267

 

 

January 2022

 

 

150

 

Maplewood

 

October 2019

 

October 2019

 

Virginia

 

 

210

 

 

December 2022

 

 

120

 

Pumpkinseed

 

May 2020

 

May 2020

 

Virginia

 

 

138

 

 

September 2022

 

 

60

 

 

(1)
Includes acquisition costs.
Dominion Energy  
Schedule of Nonregulated Solar Projects

In addition, the following table presents acquisitions by Dominion Energy of solar projects (reflected in Contracted Energy unless otherwise noted). Dominion Energy has claimed or expects to claim federal tax credits on the projects.

 

Project Name

 

Date Agreement
Entered

 

Date Agreement
Closed

 

Project Location

 

Project Cost
(millions)
(1)

 

 

Date of Commercial
Operations

 

MW Capacity

 

Madison(2)

 

July 2020

 

July 2020

 

Virginia

 

 

165

 

 

N/A

 

 

62

 

Hardin II

 

August 2020

 

Terminated(3)

 

 

 

 

 

 

 

 

 

 

Atlanta Farms

 

March 2022

 

May 2022

 

Ohio

 

 

390

 

 

January 2025(4)

 

 

200

 

Foxhound

 

March 2023

 

February 2024

 

Virginia

 

 

195

 

 

April 2024(4)

 

 

83

 

(1)
Includes acquisition costs.
(2)
Madison was reflected in the Corporate and Other segment before its sale 2024. See Note 3 for discussion.
(3)
In January 2023, Dominion Energy terminated its agreement, without penalty, to acquire Hardin II.
(4)
Dominion Energy expects to claim production tax credits on the energy generated and sold by these projects.