Liabilities related to associates and joint ventures
6 Months Ended
Jun. 30, 2023
Liabilities Related To Associates And Joint Ventures  
Liabilities related to associates and joint ventures

 

23.Liabilities related to associates and joint ventures

 

a) Samarco dam failure

 

In November 2015, the Fundão tailings dam owned by Samarco Mineração S.A. (“Samarco”) experienced a failure, releasing mine tailings downstream, flooding certain communities and impacting communities and the environment along the Doce River. The dam failure resulted in 19 fatalities and caused property and environmental damage to the affected areas. Samarco is a joint venture equally owned by Vale S.A. and BHP Billiton Brasil Ltda. (‘‘BHPB’’).

 

In 2016, Vale, Samarco and BHPB, entered into a Framework Agreement with the Federal Government of Brazil, the states of Espírito Santo and Minas Gerais and certain other public authorities to establish the Renova Foundation that is developing and executing environmental and socio-economic programs to remediate and provide compensation for damage caused by the Samarco dam failure.

 

In June 2018, Samarco, Vale and BHPB entered into a comprehensive agreement with the offices of the federal and state (Minas Gerais and Espírito Santo) prosecutors, public defenders and attorney general, among other parties (“TacGov Agreement”), improving the governance mechanism of Renova Foundation and establishing, among other things, a process for potential revisions to the remediation programs under the Framework Agreement.

 

Under the Framework Agreement, Samarco has primary responsibility for funding Renova Foundation’s annual calendar year budget for the duration of the Framework Agreement. However, to the extent that Samarco does not meet its funding obligations, Vale and BHPB have secondary funding obligations under the Framework Agreement in proportion to their 50 per cent shareholding in Samarco.

 

Samarco began to gradually recommence operations in December 2020, however, there remains significant uncertainty regarding Samarco’s long-term cash flow generation.

b) Changes on the provisions in the period

 

         
  December 31, 2022 Monetary and present value adjustments Disbursements Translation adjustments June 30, 2023
Renova Foundation reparation and compensation programs 3,124 128 (108) 257 3,401
De-characterization of the Germano dam 197 5 - 16 218
Liabilities  3,321  133  (108)  273  3,619
           
Current liabilities 1,911       1,044
Non-current liabilities 1,410       2,575
Liabilities  3,321        3,619
           
Discount rate in nominal terms 6.20% - 9.51%       5.46% - 9.20%

 

c)Judicial reorganization of Samarco

 

In April 2021, Samarco filed for Judicial Reorganization (“JR”) with the Courts of Minas Gerais.

 

In May 2023, Vale S.A. entered into a binding agreement jointly with BHPB, Samarco and certain creditors which hold together more than 50% of Samarco's debt, setting the parameters of Samarco’s debt restructuring to be implemented through a consensual restructuring plan (“Agreement”), subject for approval by the creditors and to be confirmed by the JR court. The plan aims to establish an independent and sustainable financial position for Samarco by resuming its high-quality pellets production, allowing Samarco to comply with its socio-environmental obligations.

 

Under the Agreement, the payments to the financial creditors will be made from 2024 to 2030, in line with Samarco's operational ramp-up and cash flow generation.

 

The Agreement also provides that additional cash demands that exceed these payments will be made to Fundação Renova through capital contributions to Samarco. The contributions have been carried out directly by Vale and BHPB to the Renova Foundation on behalf of Samarco and, therefore, they were deemed tax deductible as incurred, according to the Brazilian tax regulation.

 

Therefore, due to the change in the mechanism to fund Renova, Vale will no longer be allowed to deduct future payments from its income tax computation as they are not tax deductible in Brazil. Thus, the deferred income tax asset over the provision in the amount of US$1,078 was reversed in full, with the corresponding impact in the income statement for the three-month period ended June 30, 2023 recorded as “Income taxes”.

 

In addition, the Agreement does not require the capitalization of the expenses of US$699 (R$3,371 million) that were incurred in the past and so, there are no change in relation to the tax treatment adopted. This matter was disclosed in the annual financial statements for the year ended December 31, 2022 in the uncertain tax positions note.

 

d)Contingencies related to Samarco accident

 

These proceedings include public civil actions brought by Brazilian authorities and multiple proceedings involving claims for significant amounts of damages and remediation measures. The Framework Agreements represents a model for the settlement of the public civil action brought by the MPF and other related proceedings. There are also putative securities class actions in the USA against Vale and some of its current and former officers and a criminal proceeding in Brazil. The main updates regarding the lawsuits in the year were as follows:

 

Public Civil Action filed by the Federal Government and others and public civil action filed by the Federal Public Ministry ("MPF")

 

Vale is a defendant in several legal proceedings brought by governmental authorities and civil associations claiming socioenvironmental and socioeconomic damages and a number of specific remediation measures as a result of the Samarco’s Fundão dam failure, including a claim brought by the Federal Public Prosecution Office in 2016 seeking US$32 billion (R$155 billion) (the effect for Vale would be 50% of this amount), which has been suspended from the date of ratification of the TacGov Agreement.

 

However, as pre-requisites established in the TacGov Agreement, for renegotiation of the Framework Agreement were not implemented during the two-year period ended September 30, 2020, the Brazilian Federal and State prosecutors and public defenders filed a request for the immediate resumption of the US$32 billion (R$155 billion) claim.

 

Therefore, Vale, Samarco, BHPB and Federal and State prosecutors have been engaging in negotiations to seek a definitive settlement of the obligations under the Framework Agreement and the US$32 billion (R$155 billion) Federal Public Prosecution Office claim. The goal in signing a potential agreement is to provide a stable framework for the execution of reparation and compensation programs.

 

The potential agreement is still uncertain as it is subject to conclusion of the negotiations and approval by the Company, relevant authorities and intervenient parties.

 

The estimate of the economic impact of a potential agreement will depend mainly on (i) a detailed assessment of the estimates of the amounts to be spent on the reparation and compensation projects being discussed, (ii) an analysis of the detailed scope of such projects to determine their overlap with the initiatives and amounts already provisioned; and (iii) the timing of the execution of projects and disbursements, which will impact the present value of the obligations.

 

Therefore, until any revisions to the Programs are agreed, Renova Foundation will continue to implement the Programs in accordance with the terms of the Framework Agreement and the TacGov Agreement, for which the expected costs are reflected in the Company’s provision.

 

Judicial decision requesting cash deposits

 

In March 2023, as part of a proceeding related to a potential increase on the number of territories recognized as affected by the collapse of Samarco’s Fundão dam and covered by the TTAC, a Federal Court issued a decision ordering Vale and BHP Brasil to make judicial deposits in the total amount of US$2.1 billion (R$10.3 billion), in ten installments, which the effect for Vale would be 50% of this amount. On April 28, 2023, the Federal Court granted the companies' request for a suspensive effect on the decision that determined this deposit. The Company believes its provisions are sufficient to comply with the TTAC obligations.

 

Criminal proceedings

 

In September 2019, the federal court dismissed all criminal charges against Vale representatives relating to the first group of charges, which concerns the results of the Fundão dam failure, remaining only the legal entity in the passive pole. The second group of charges against Vale S.A. and one of the Company’s employees, which concerns the accusation of alleged crimes committed against the Environmental Public Administration, remained unchanged. The Company cannot estimate when a final decision on the case will be issued. The likelihood of a financial loss to the Company is classified as possible and it is not yet possible to reliably estimate the amount of a potential loss to Vale.

 

United Kingdom contribution claim

 

As a result of the rupture of Samarco’s Fundão dam failure, BHP Group Ltd (“BHP”) was named as defendant in group action claims for damages filed in the courts of England and Wales (The “UK Claim”). The UK Claim includes only BHP and was filed on behalf of certain individuals and municipalities in Brazil only against BHP, for the allegedly damages caused by the Fundão dam failure.

 

In December 2022, BHP filed a contribution claim against Vale, requesting the Company to be responsible for the indemnification payments in the proportion to its interest held in Samarco. The Company believes that it is not subject to the jurisdiction of the English Court and it does not have any contractual obligation in relation to this matter, therefore, the Company has assessed the risk of loss as remote.