XML 98 R25.htm IDEA: XBRL DOCUMENT v3.25.1
Provisions
12 Months Ended
Dec. 31, 2024
Provisions [Abstract]  
Provisions
16.
 
Provisions
Reclamation
Waste disposal
Total
Beginning of year
$
1,051,167
$
10,817
$
1,061,984
Changes in estimates and discount rates [note 9]
Capitalized in property, plant and equipment
(17,308)
-
(17,308)
Recognized in earnings [note 9]
(37,683)
331
(37,352)
Provisions used during the period
(34,064)
(682)
(34,746)
Unwinding of discount [note 20]
35,941
302
36,243
Effect of movements in exchange rates
26,986
-
26,986
End of period
$
1,025,039
$
10,768
$
1,035,807
Current
$
34,063
$
3,911
$
37,974
Non-current
990,976
6,857
997,833
$
1,025,039
$
10,768
$
1,035,807
A.
 
Reclamation provision
Cameco's estimates of future decommissioning obligations are based on reclamation standards that satisfy regulatory
requirements. Elements of uncertainty in estimating these amounts include potential changes in regulatory requirements,
decommissioning and reclamation alternatives and amounts to be recovered from other parties.
Cameco estimates total undiscounted future decommissioning and reclamation costs for its existing operating assets to be
$
1,382,661,000
 
(2023 - $
1,356,018,000
). The expected timing of these outflows is based on life-of-mine plans with the
majority of expenditures expected to occur after
2029
. These estimates are reviewed by Cameco technical personnel as
required by regulatory agencies or more frequently as circumstances warrant. In connection with future decommissioning and
reclamation costs, Cameco has provided financial assurances of $
1,125,194,000
 
(2023 - $
1,060,769,000
) in the form of letters
of credit to satisfy current regulatory requirements.
The reclamation provision relates to the following segments:
2024
2023
Uranium
$
865,574
$
874,773
Fuel services
159,465
176,394
Total
$
1,025,039
$
1,051,167
B.
 
Waste disposal
The fuel services segment consists of the Blind River refinery, Port Hope conversion facility and Cameco Fuel Manufacturing
Inc.. The refining, conversion and manufacturing processes generate certain uranium contaminated waste. These include
contaminated combustible material (paper, rags, gloves, etc.) and contaminated non-combustible material (metal parts, soil
from excavations, building and roofing materials, spent uranium concentrate drums, etc.). These materials can in some
instances be recycled or reprocessed. A provision for waste disposal costs in respect of these materials is recognized when
they are generated.
Cameco estimates total undiscounted future costs related to existing waste disposal to be $
9,663,000
 
(2023 - $
9,681,000
).
The majority of these expenditures are expected to occur within the next
three years
.