Impairments
9 Months Ended
Sep. 30, 2019
Property, Plant and Equipment [Abstract]  
Impairments Impairments
2019 Impairment Losses
Petra Nova — During the third quarter of 2019, NRG contributed $95 million in cash to Petra Nova and posted a $12 million letter of credit to cover certain project debt reserve requirements. The cash portion of the contribution was used by Petra Nova to prepay a significant portion of the project debt. As a result, the previously disclosed guarantee of up to $124 million related to the project level debt provided by NRG was canceled and the remaining project debt has now become non-recourse to NRG. In relation to this contribution, the Company evaluated the project for impairment and determined that the carrying amount of the Company’s equity method investment exceeded the fair value of the investment and that the decline is considered to be other-than-temporary. In determining the fair value, the Company utilized an income approach and considered project specific assumptions for the estimated future project cash flows. The Company measured the impairment loss as the difference between the carrying amount and the fair value of the investment and recorded an impairment loss of $101 million.
Other Impairments — During the nine months ended September 30, 2019, the Company recorded $7 million of impairment losses on cost investments and intangible assets.
2018 Impairment Losses
Keystone and Conemaugh — On June 29, 2018, the Company entered into an agreement to sell its approximately 3.7% interests in the Keystone and Conemaugh generating stations. NRG recorded impairment losses of $14 million for Keystone and $14 million for Conemaugh to adjust the carrying amount of the assets to fair value based on the contractual sale price. The transaction closed on September 5, 2018.
Dunkirk — During the second quarter of 2018, NRG ceased its development of the project to add gas capability at the Dunkirk generating station. The project was put on hold in 2015 pending the resolution of a lawsuit filed by Entergy Corporation against the NYSPSC, which challenged the legality of its contract with Dunkirk. The lawsuit was later dropped and development continued, but the delay imposed a new requirement on Dunkirk to enter into the NYISO interconnection study process. The NYISO studies concluded that extensive electric system upgrades would be necessary for the station to return to service. This would cause the Company to incur a material increase in cost and delay the project schedule, which would render the project impractical. Consequently, the Company recorded an impairment loss of $46 million during the second quarter of 2018, reducing the carrying amount of the related assets to $0.
Other Impairments — During the nine months ended September 30, 2018, the Company recorded impairment losses on equity method investments of $16 million.