Schedule of restructuring Restructuring and other transformation related to Project Matterhorn included in the accompanying Consolidated Statement of Operations for the year ended December 31, 2022, is as follows:
YEAR ENDED
DECEMBER 31, 2022
Restructuring$13,292 
Other transformation28,641 
Restructuring and other transformation
$41,933 
Restructuring costs for Project Matterhorn, included as a component of Restructuring and other transformation in the accompanying Consolidated Statement of Operations, by segment for the year ended December 31, 2022 are as follows:
YEAR ENDED
DECEMBER 31, 2022
Global RIM Business$13,083 
Global Data Center Business— 
Corporate and Other209 
Total restructuring costs$13,292 
Restructuring costs for Project Summit are included as a component of Restructuring and other transformation in the accompanying Consolidated Statements of Operations for the years ended December 31, 2021 and 2020, and from the inception of Project Summit through December 31, 2021 is as follows:
YEAR ENDED DECEMBER 31, 2021YEAR ENDED DECEMBER 31, 2020FROM INCEPTION OF PROJECT SUMMIT THROUGH
DECEMBER 31, 2021
Employee severance$22,809 $47,349 $91,008 
Professional fees and other183,617 147,047 358,411 
Total restructuring costs
$206,426 $194,396 $449,419 
As Project Summit was completed as of December 31, 2021, there were no restructuring costs for Project Summit for the year ended December 31, 2022.
Restructuring costs for Project Summit included in the accompanying Consolidated Statements of Operations by segment for the years ended December 31, 2021, and 2020 are as follows:
YEAR ENDED DECEMBER 31, 2021YEAR ENDED DECEMBER 31, 2020FROM INCEPTION OF PROJECT SUMMIT THROUGH
DECEMBER 31, 2021
Global RIM Business $59,033 $67,140 $148,073 
Global Data Center Business3,062 1,632 5,000 
Corporate and Other144,331 125,624 296,346 
Total restructuring costs
$206,426 $194,396 $449,419 
A rollforward of the accrued restructuring costs, which is included as a component of Accrued expenses and other current liabilities in our Consolidated Balance Sheets for December 31, 2021 through December 31, 2022, is as follows:
EMPLOYEE SEVERANCEPROFESSIONAL FEES AND OTHERTOTAL ACCRUED RESTRUCTURING COSTS
Balance as of December 31, 2020$16,278 $23,775 $40,053 
Amounts accrued22,809 183,617 206,426 
Payments(29,956)(199,664)(229,620)
Other, including currency translation adjustments2,858 — 2,858 
Balance as of December 31, 2021$11,989 $7,728 $19,717 
Payments(11,989)(7,728)(19,717)
Balance as of December 31, 2022$— $— $—