XML 43 R20.htm IDEA: XBRL DOCUMENT v3.23.1
Restructuring And Other Transformation
3 Months Ended
Mar. 31, 2023
Restructuring and Related Activities [Abstract]  
Restructuring And Other Transformation RESTRUCTURING AND OTHER TRANSFORMATION
PROJECT MATTERHORN
In September 2022, we announced Project Matterhorn, a global program designed to accelerate the growth of our business. Project Matterhorn investments will focus on transforming our operating model to a global operating model. Project Matterhorn will focus on the formation of a solution-based sales approach that is designed to allow us to optimize our shared services and best practices to better serve our customers' needs. We will be investing to accelerate growth and to capture a greater share of the large, global addressable markets in which we operate. We expect to incur approximately $150,000 in costs annually related to Project Matterhorn from 2023 through 2025. Costs are comprised of (1) restructuring costs, which include (i) site consolidation and other related exit costs, (ii) employee severance costs and (iii) certain professional fees associated with these activities, and (2) other transformation costs, which include professional fees such as project management costs and costs for third party consultants who are assisting in the enablement of our growth initiatives. Total costs related to Project Matterhorn during the three months ended March 31, 2023 were approximately $36,913 and are included in Restructuring and other transformation in our Condensed Consolidated Statement of Operations. There were no Restructuring and other transformation costs related to Project Matterhorn for the three months ended March 31, 2022.
Restructuring and other transformation related to Project Matterhorn included in the accompanying Condensed Consolidated Statement of Operations for the three months ended March 31, 2023, and from the inception of Project Matterhorn through March 31, 2023, is as follows:
THREE MONTHS ENDED MARCH 31, 2023
FROM INCEPTION OF PROJECT MATTERHORN THROUGH MARCH 31, 2023
Restructuring$11,957 $25,249 
Other transformation24,956 53,597 
Restructuring and other transformation
$36,913 $78,846 
Restructuring costs for Project Matterhorn, included as a component of Restructuring and other transformation in the accompanying Condensed Consolidated Statement of Operations, by segment for the three months ended March 31, 2023, and from the inception of Project Matterhorn through March 31, 2023, is as follows:
THREE MONTHS ENDED MARCH 31, 2023
FROM INCEPTION OF PROJECT MATTERHORN THROUGH MARCH 31, 2023
Global RIM Business$9,525 $22,608 
Global Data Center Business78 78 
Corporate and Other2,354 2,563 
Total restructuring costs$11,957 $25,249 
Other transformation costs for Project Matterhorn, included as a component of Restructuring and other transformation in the accompanying Condensed Consolidated Statement of Operations, by segment for the three months ended March 31, 2023, and from the inception of Project Matterhorn through March 31, 2023, is as follows:
THREE MONTHS ENDED MARCH 31, 2023
FROM INCEPTION OF PROJECT MATTERHORN THROUGH MARCH 31, 2023
Global RIM Business$3,485 $7,386 
Global Data Center Business870 928 
Corporate and Other20,601 45,283 
Total other transformation costs$24,956 $53,597 
Accrued restructuring costs and accrued other transformation costs included in the accompanying Condensed Consolidated Balance Sheet as of March 31, 2023 were approximately $4,600 and $12,000, respectively.