Schedule of Long-term Purchase Commitment
As of September 30, 2023, other than discussed below, undiscounted minimum purchase obligations are approximately:
CenterPoint EnergyCERC
Natural Gas
Supply
Electric Supply (1)
Other (2)
Natural Gas Supply
(in millions)
Remaining three months of 2023
$220 $51 $71 $218 
2024683 160 181 678 
2025588 492 39 584 
2026501 342 39 497 
2027425 105 — 421 
2028380 68 — 376 
2029 and beyond1,710 719 332 1,685 

(1)CenterPoint Energy’s undiscounted minimum payment obligations related to PPAs with commitments ranging from 15 years to 25 years and its purchase commitments under its BTA in Posey County, Indiana and its BTA in Pike County, Indiana are included above.
(2)The undiscounted payment obligations relate primarily to technology hardware and software agreements.
Schedule of Environmental Loss Contingencies by Site
Total costs that may be incurred in connection with addressing these sites cannot be determined at this time. The estimated accrued costs are limited to CenterPoint Energy’s and CERC’s share of the remediation efforts and are therefore net of exposures of other PRPs. The estimated range of possible remediation costs for the sites for which CenterPoint Energy and CERC believe they may have responsibility was based on remediation continuing for the minimum time frame given in the table below.
September 30, 2023
CenterPoint EnergyCERC
(in millions, except years)
Amount accrued for remediation$17 $15 
Minimum estimated remediation costs12 11 
Maximum estimated remediation costs51 44 
Minimum years of remediation55
Maximum years of remediation5050