A.    Contractual Obligations. We have certain contractual obligations requiring payments at specified periods. The obligations include long-term debt, lease obligations, energy commodity contracts and obligations for various services including pipeline capacity and outsourcing of IT services. The total contractual obligations in existence at December 31, 2020 and their maturities were:
(in millions)Total20212022202320242025After
Long-term debt (1)
$9,135.0 $— $30.0 $— $— $1,260.0 $7,845.0 
Interest payments on long-term debt6,046.3 336.3 335.7 334.1 334.1 334.1 4,372.0 
Finance leases(2)
264.7 32.7 32.2 28.8 20.8 16.1 134.1 
Operating leases(3)
48.0 11.7 5.2 4.7 4.5 3.7 18.2 
Energy commodity contracts42.1 42.1 — — — — — 
Service obligations:
Pipeline service obligations(4)
1,495.6 468.7 422.5 256.0 150.5 56.2 141.7 
IT service obligations240.3 74.9 74.0 38.1 30.5 22.8 — 
Other service obligations(5)
12.6 12.6 — — — — — 
Other liabilities(6)
116.9 26.0 0.8 90.1 — — — 
Total contractual obligations$17,401.5 $1,005.0 $900.4 $751.8 $540.4 $1,692.9 $12,511.0 
(1) Long-term debt balance excludes unamortized issuance costs and discounts of $86.9 million.
(2) Finance lease payments shown above are inclusive of interest totaling $69.7 million.
(3) Operating lease payments shown above are inclusive of interest totaling $7.8 million. Operating lease balances do not include obligations for possible fleet vehicle lease renewals beyond the initial lease term. While we have the ability to renew these leases beyond the initial term, we are not reasonably certain (as that term is defined in ASC 842) to do so as they are renewed month-to-month after the first year. If we were to continue the fleet vehicle leases outstanding at December 31, 2020, payments would be $30.0 million in 2021, $27.7 million in 2022, $24.9 million in 2023, $22.0 million in 2024, $19.0 million in 2025 and $21.5 million thereafter.
(4)In February 2021, the demand rate increased for our pipeline service obligations, resulting in a total increase of $638.6 million in addition to our future pipeline service obligations shown above.
(5)On February 9, 2021, a rail transportation contract for the transportation of coal was fully executed between NIPSCO and a counterparty, replacing the prior agreement. The minimum coal tonnage shipment commitment for 2021 was eliminated under the new agreement, reducing our contractual obligation for 2021 by $12.1 million.
(6)Other liabilities shown above are inclusive of the Rosewater Developer payment due in 2023.
Purchase and Service Obligations. We have entered into various purchase and service agreements whereby we are contractually obligated to make certain minimum payments in future periods. Our purchase obligations are for the purchase of physical quantities of natural gas, electricity and coal. Our service agreements encompass a broad range of business support and maintenance functions which are generally described below.
Our subsidiaries have entered into various energy commodity contracts to purchase physical quantities of natural gas, electricity and coal. These amounts represent the minimum quantity of these commodities we are obligated to purchase at both fixed and variable prices. To the extent contractual purchase prices are variable, obligations disclosed in the table above are valued at market prices as of December 31, 2020.
NIPSCO has power purchase arrangements representing a total of 500 MW of wind power, with contracts expiring between between 2024 and 2040. No minimum quantities are specified within these agreements due to the variability of electricity generation from wind, so no amounts related to these contracts are included in the table above. Upon early termination of one of these agreements by NIPSCO for any reason (other than material breach by the counterparties), NIPSCO may be required to pay a termination charge that could be material depending on the events giving rise to termination and the timing of the termination.
We have pipeline service agreements that provide for pipeline capacity, transportation and storage services. These agreements, which have expiration dates ranging from 2021 to 2038, require us to pay fixed monthly charges.
NIPSCO has contracts with three major rail operators providing for coal transportation services for which there are certain minimum payments. These service contracts extend for various periods through 2021.
We have executed agreements with multiple IT service providers. The agreements extend for various periods through 2025.
B.        Guarantees and Indemnities. We and certain subsidiaries enter into various agreements providing financial or performance assurance to third parties on behalf of certain subsidiaries as part of normal business. Such agreements include guarantees and stand-by letters of credit. These agreements are entered into primarily to support or enhance the creditworthiness otherwise attributed to a subsidiary on a stand-alone basis, thereby facilitating the extension of sufficient credit to accomplish the subsidiaries’ intended commercial purposes. At December 31, 2020 and 2019, we had issued stand-by letters of credit of $15.2 million and $10.2 million , respectively, for the benefit of third parties.
We have provided guarantees related to our future performance under BTAs for our renewable generation projects. At December 31, 2020, our guarantees for the Rosewater and Indiana Crossroads BTAs totaled $40.7 million. The amount of each guaranty will decrease upon the substantial completion of the construction of the facilities. See “- E. Other Matters - NIPSCO 2018 Integrated Resource Plan,” below for more information.
C.         Legal Proceedings. On September 13, 2018, a series of fires and explosions occurred in Lawrence, Andover and North Andover, Massachusetts related to the delivery of natural gas by Columbia of Massachusetts (the "Greater Lawrence Incident"). The Greater Lawrence Incident resulted in one fatality and a number of injuries, damaged multiple homes and businesses, and caused the temporary evacuation of significant portions of each municipality. The Massachusetts Governor’s Office declared a state of emergency, authorizing the Massachusetts DPU to order another utility company to coordinate the restoration of utility services in Lawrence, Andover and North Andover. The incident resulted in the interruption of gas for approximately 7,500 gas meters, the majority of which served residences and approximately 700 of which served businesses, and the interruption of other utility service more broadly in the area. Columbia of Massachusetts has replaced the cast iron and bare steel gas pipeline system in the affected area and restored service to nearly all of the gas meters. See “- E. Other Matters - Greater Lawrence Pipeline Replacement” below for more information. On September 1, 2020, the Massachusetts Governor terminated the state of emergency declared following the Greater Lawrence Incident.
We have been subject to state and federal inquiries and investigations by government authorities and regulatory agencies regarding the Greater Lawrence Incident, including the Massachusetts DPU and the Massachusetts Attorney General's Office. On February 26, 2020, the Company and Columbia of Massachusetts entered into agreements with the U.S. Attorney’s Office for the District of Massachusetts to resolve the U.S. Attorney’s Office’s investigation relating to the Greater Lawrence Incident, as described below. The Company and Columbia of Massachusetts entered into an agreement with the Massachusetts Attorney General’s Office (among other parties) to resolve the Massachusetts DPU and the Massachusetts Attorney General’s Office investigations, that was approved by the Massachusetts DPU on October 7, 2020 as part of the sale of the Massachusetts Business to Eversource.
NTSB Investigation. As previously disclosed, the NTSB concluded its investigation into the Greater Lawrence Incident. On November 24, 2020, the NTSB closed NiSource’s one remaining open safety recommendation.
U.S. Department of Justice Investigation. On February 26, 2020, the Company and Columbia of Massachusetts entered into agreements with the U.S. Attorney’s Office to resolve the U.S. Attorney’s Office’s investigation relating to the Greater Lawrence Incident. Columbia of Massachusetts agreed to plead guilty in the United States District Court for the District of Massachusetts (the “Court”) to violating the Natural Gas Pipeline Safety Act (the “Plea Agreement”), and the Company entered into a Deferred Prosecution Agreement (the “DPA”).
On March 9, 2020, Columbia of Massachusetts entered its guilty plea pursuant to the Plea Agreement, which the Court accepted. Subsequently, Columbia of Massachusetts and the U.S. Attorney’s Office modified the Plea Agreement. On June 23, 2020, the Court sentenced Columbia of Massachusetts in accordance with the terms of the modified Plea Agreement. Under the modified Plea Agreement, Columbia of Massachusetts is subject to the following terms, among others: (i) a criminal fine in the amount of $53,030,116, which has been paid; (ii) a three year probationary period that will terminate early upon a sale of Columbia of Massachusetts or a sale of its gas distribution business to a qualified third-party buyer consistent with certain requirements, but in no event before the end of the one-year mandatory period of probation; (iii) compliance with each of the NTSB recommendations stemming from the Greater Lawrence Incident; and (iv) employment of an in-house monitor until the end of the term of probation or until the sale of Columbia of Massachusetts or its gas distribution business, whichever is earlier. On October 13, 2020, the Court, upon agreement of the U.S. Attorney's Office and Columbia Gas of Massachusetts, modified the terms of probation by ending the term of the in-house monitor.
Under the DPA, the U.S. Attorney’s Office agreed to defer prosecution of the Company in connection with the Greater Lawrence Incident for a three-year period (which three-year period may be extended for twelve (12) months upon the U.S.
Attorney’s Office’s determination of a breach of the DPA) subject to certain obligations of the Company, including, but not limited to, the following: (i) the Company will use reasonable best efforts to sell Columbia of Massachusetts or Columbia of Massachusetts’ gas distribution business to a qualified third-party buyer consistent with certain requirements, and, upon the completion of any such sale, the Company will cease and desist any and all gas pipeline and distribution activities in the District of Massachusetts; (ii) the Company will forfeit and pay, within 30 days of the later of the sale becoming final or the date on which post-closing adjustments to the purchase price are finally determined in accordance with the agreement to sell Columbia of Massachusetts or its gas distribution business, a fine equal to the total amount of the profit or gain, if any, from any sale of Columbia of Massachusetts or its gas distribution business, with the amount of profit or gain determined as provided in the DPA; and (iii) the Company agrees as to each of the Company’s subsidiaries involved in the distribution of gas through pipeline facilities in Massachusetts, Indiana, Ohio, Pennsylvania, Maryland, Kentucky and Virginia to implement and adhere to each of the recommendations from the NTSB stemming from the Greater Lawrence Incident. Pursuant to the DPA, if the Company complies with all of its obligations under the DPA, including, but not limited to those identified above, the U.S. Attorney’s Office will not file any criminal charges against the Company related to the Greater Lawrence Incident. If Columbia of Massachusetts withdraws its plea for any reason, if the Court rejects any aspect of the Plea Agreement, or if Columbia of Massachusetts should fail to perform an obligation under the Plea Agreement prior to the sale of Columbia of Massachusetts or its gas distribution business, the U.S. Attorney's Office may, at its sole option, render the DPA null and void. The sale of the Massachusetts Business was completed on October 9, 2020. The Company was not required to forfeit or pay any funds because the Company did not realize a profit or gain from the sale as provided in the DPA.
U.S. Federal Government Activity. On December 27, 2020, the Protecting Our Infrastructure of Pipelines and Enhancing Safety (PIPES) Act of 2020 was signed into law reauthorizing funding for federal pipeline safety programs through September 30, 2023. Among other things, the PIPES Act requires that PHMSA revise the pipeline safety regulations to require operators to update, as needed, their existing distribution integrity management plans, emergency response plans, and O&M plans. The PIPES Act also requires PHMSA to adopt new requirements for managing records and updating, as necessary existing district regulator stations to eliminate common modes of failure that can lead to overpressurization. PHMSA must also require that operators implement leak detection and repair programs that meet safety needs and consider the environment, require the use of advance leak detection practices and technologies, and require operators to be able to locate and categorize all leaks that are hazardous to human safety or the environment, or that can become hazardous. Natural gas companies, including the Company, may see increased costs depending on how PHMSA implements the new mandates resulting from the PIPES Act.
Private Actions. Various lawsuits, including several purported class action lawsuits, have been filed by various affected residents or businesses in Massachusetts state courts against the Company and/or Columbia of Massachusetts in connection with the Greater Lawrence Incident.
On July 26, 2019, the Company, Columbia of Massachusetts and NiSource Corporate Services Company, a subsidiary of the Company, entered into a term sheet with the class action plaintiffs under which they agreed to settle the class action claims in connection with the Greater Lawrence Incident. Columbia of Massachusetts agreed to pay $143 million into a settlement fund to compensate the settlement class and the settlement class agreed to release Columbia of Massachusetts and affiliates from all claims arising out of or related to the Greater Lawrence Incident. The following claims are not covered under the proposed settlement because they are not part of the consolidated class action: (1) physical bodily injury and wrongful death; (2) insurance subrogation, whether equitable, contractual or otherwise; and (3) claims arising out of appliances that are subject to the Massachusetts DPU orders. Emotional distress and similar claims are covered under the proposed settlement unless they are secondary to a physical bodily injury. The settlement class is defined under the term sheet as all persons and businesses in the three municipalities of Lawrence, Andover and North Andover, Massachusetts, subject to certain limited exceptions. The motion for preliminary approval and the settlement documents were filed on September 25, 2019. The preliminary approval court hearing was held on October 7, 2019 and the court issued an order granting preliminary approval of the settlement on October 11, 2019. The Court granted final approval of the settlement on March 12, 2020.
With respect to claims not included in the consolidated class action, many of the asserted wrongful death and bodily injury claims have settled, and we continue to discuss potential settlements with remaining claimants. The outcomes and impacts of such private actions are uncertain at this time.
Shareholder Derivative Lawsuit. On April 28, 2020, a shareholder derivative lawsuit was filed by the City of Detroit Police and Fire Retirement System in the United States District Court for the District of Delaware against certain of our current and former directors, alleging breaches of fiduciary duty with respect to the pipeline safety management systems relating to the distribution of natural gas prior to the Greater Lawrence Incident and also including claims related to our proxy statement
disclosures regarding our safety systems. The remedies sought include damages for the alleged breaches of fiduciary duty, corporate governance reforms, and restitution of any unjust enrichment. The defendants have filed a motion to dismiss the lawsuit. The motion to dismiss is fully briefed. On January 5, 2021, the judge set the defendants’ motion to dismiss for oral argument on March 2, 2021. Because of the preliminary nature of this lawsuit, we are not able to estimate a loss or range of loss, if any, that may be incurred in connection with this matter at this time.
Financial Impact. Since the Greater Lawrence Incident, we have recorded expenses of approximately $1,036 million for third-party claims and fines, penalties and settlements associated with government investigations. We estimate that total costs related to third-party claims and fines, penalties and settlements associated with government investigations resulting from the incident will range from $1,036 million to $1,050 million, depending on the number, nature, final outcome and value of third-party claims. With regard to third-party claims, these costs include, but are not limited to, personal injury and property damage claims, damage to infrastructure, business interruption claims, and mutual aid payments to other utilities assisting with the restoration effort. These costs do not include costs of certain third-party claims and fines, penalties or settlements associated with government investigations that we are not able to estimate. These costs also do not include non-claims related and government investigation-related legal expenses resulting from the incident, the capital cost of the pipeline replacement and the payment in lieu of penalties, which are set forth in " - D. Other Matters - Greater Lawrence Incident Restoration," "- Greater Lawrence Incident Pipeline Replacement," and Note 1-A, "Company Structure and Principles of Consolidation," respectively.
The process for estimating costs associated with third-party claims relating to the Greater Lawrence Incident requires management to exercise significant judgment based on a number of assumptions and subjective factors. As more information becomes known, management’s estimates and assumptions regarding the financial impact of the Greater Lawrence Incident may change.
The aggregate amount of third-party liability insurance coverage available for losses arising from the Greater Lawrence Incident is $800 million. We collected the entire $800 million as of December 31, 2019. Total expenses related to the incident have exceeded the total amount of insurance coverage available under our policies. Refer to "- E. Other Matters - Greater Lawrence Incident Restoration," below for a summary of third-party claims-related expense activity and associated insurance recoveries recorded since the Greater Lawrence Incident.
We are also party to certain other claims, regulatory and legal proceedings arising in the ordinary course of business in each state in which we have operations, none of which is deemed to be individually material at this time.
Due to the inherent uncertainty of litigation, there can be no assurance that the resolution of any particular claim, proceeding or investigation related to the Greater Lawrence Incident or otherwise would not have a material adverse effect on our results of operations, financial position or liquidity. Certain matters in connection with the Greater Lawrence Incident have had or may have a material impact as described above. If one or more of such additional or other matters were decided against us, the effects could be material to our results of operations in the period in which we would be required to record or adjust the related liability and could also be material to our cash flows in the periods that we would be required to pay such liability.
D.        Environmental Matters. Our operations are subject to environmental statutes and regulations related to air quality, water quality, hazardous waste and solid waste. We believe we are, in all material respects, in compliance with the environmental regulations currently applicable to our operations.
It is management's continued intent to address environmental issues in cooperation with regulatory authorities in such a manner as to achieve mutually acceptable compliance plans. However, there can be no assurance that fines and penalties will not be incurred. Management expects a significant portion of environmental assessment, improvement and remediation costs to be recoverable through rates for certain of our companies.
As of December 31, 2020 and 2019, we had recorded a liability of $92.6 million and $104.4 million, respectively, to cover environmental remediation at various sites. The current portion of this liability is included in "Other Accruals" in the Consolidated Balance Sheets. The noncurrent portion is included in "Other noncurrent liabilities." We recognize costs associated with environmental remediation obligations when the incurrence of such costs is probable and the amounts can be reasonably estimated. The original estimates for remediation activities may differ materially from the amount ultimately expended. The actual future expenditures depend on many factors, including currently enacted laws and regulations, the nature and extent of impact and the method of remediation. These expenditures are not currently estimable at some sites. We periodically adjust our liability as information is collected and estimates become more refined.
Electric Operations' compliance estimates disclosed below are reflective of NIPSCO's Integrated Resource Plan submitted to the IURC on October 31, 2018. See section " - E. Other Matters - NIPSCO 2018 Integrated Resource Plan," below for additional information.
Air
Future legislative and regulatory programs could significantly limit allowed GHG emissions or impose a cost or tax on GHG emissions. Additionally, rules that require further GHG reductions or impose additional requirements for natural gas facilities could impose additional costs. NiSource will carefully monitor all GHG reduction proposals and regulations.
ACE Rule. On July 8, 2019, the EPA published the final ACE rule, which establishes emission guidelines for states to use when developing plans to limit carbon dioxide at coal-fired electric generating units based on heat rate improvement measures. The U.S. Court of Appeals for the D.C. Circuit vacated and remanded the rule on January 19, 2021. NIPSCO will continue to monitor this matter.
Waste
CERCLA. Our subsidiaries are potentially responsible parties at waste disposal sites under the CERCLA (commonly known as Superfund) and similar state laws. Under CERCLA, each potentially responsible party can be held jointly, severally and strictly liable for the remediation costs as the EPA, or state, can allow the parties to pay for remedial action or perform remedial action themselves and request reimbursement from the potentially responsible parties. Our affiliates have retained CERCLA environmental liabilities, including remediation liabilities, associated with certain current and former operations. These liabilities are not material to the Consolidated Financial Statements.
MGP. A program has been instituted to identify and investigate former MGP sites where Gas Distribution Operations subsidiaries or predecessors may have liability. The program has identified 54 such sites where liability is probable. Remedial actions at many of these sites are being overseen by state or federal environmental agencies through consent agreements or voluntary remediation agreements.
We utilize a probabilistic model to estimate our future remediation costs related to MGP sites. The model was prepared with the assistance of a third party and incorporates our experience and general industry experience with remediating MGP sites. We complete an annual refresh of the model in the second quarter of each fiscal year. No material changes to the estimated future remediation costs were noted as a result of the refresh completed as of June 30, 2020. Our total estimated liability related to the facilities subject to remediation was $85.0 million and $102.2 million at December 31, 2020 and 2019, respectively. The liability represents our best estimate of the probable cost to remediate the facilities. We believe that it is reasonably possible that remediation costs could vary by as much as $20 million in addition to the costs noted above. Remediation costs are estimated based on the best available information, applicable remediation standards at the balance sheet date, and experience with similar facilities.
CCRs. On April 17, 2015, the EPA issued a final rule for regulation of CCRs. The rule regulates CCRs under the RCRA Subtitle D, which determines them to be nonhazardous. The rule is implemented in phases and requires increased groundwater monitoring, reporting, recordkeeping and posting of related information to the Internet. The rule also establishes requirements related to CCR management and disposal. The rule will allow NIPSCO to continue its byproduct beneficial use program.
To comply with the rule, NIPSCO completed capital expenditures in 2019 to modify its infrastructure and manage CCRs. The CCR rule also resulted in revisions to previously recorded legal obligations associated with the retirement of certain NIPSCO facilities. The actual asset retirement costs related to the CCR rule may vary substantially from the estimates used to record the increased asset retirement obligation due to the uncertainty about the requirements that will be established by environmental authorities, compliance strategies that will be used and the preliminary nature of available data used to estimate costs. As allowed by the rule, NIPSCO will continue to collect data over time to determine the specific compliance solutions and associated costs and, as a result, the actual costs may vary. NIPSCO will also continue to work with EPA and the Indiana Department of Environmental Management to obtain administrative approvals associated with the CCR rule. In the event that the approvals are not obtained, future operations could be impacted. We believe the possibility of such an outcome is remote.
E.         Other Matters.
NIPSCO 2018 Integrated Resource Plan. NIPSCO concluded in its October 2018 Integrated Resource Plan submission that NIPSCO’s current fleet of coal generation facilities will be retired earlier than previous Integrated Resource Plans had indicated. The Integrated Resource Plan evaluated demand-side and supply-side resource alternatives to reliably and cost effectively meet NIPSCO customers' future energy requirements over the ensuing 20 years. The preferred option within the Integrated Resource Plan retires the R.M. Schahfer Generating Station by mid-2023 and the Michigan City Generating Station by the end of 2028. These units represent 2,080 MW of generating capacity, equal to 72% of NIPSCO’s remaining generating capacity and 100% of NIPSCO's remaining coal-fired generating capacity. NIPSCO will refresh its 2018 Integrated Resource Plan in 2021.
In the second quarter of 2020, the MISO approved NIPSCO's plan to retire the R.M. Schahfer Generating Station in 2023. In accordance with ASC 980-360, the net book value of certain plant and equipment for the R.M. Schahfer Generating Station was reclassified as "Non-Utility and Other" as described in Note 6, "Property, Plant and Equipment." The December 2019, NIPSCO electric rate case order included approval to create a regulatory asset upon the retirement of the R.M. Schahfer Generating Station. The order allows for the recovery of and on the net book value of the station by the end of 2032. Refer to Note 6, "Property, Plant and Equipment" for further information.
In connection with the MISO's approval of NIPSCO's planned retirement of the R.M. Schahfer Generating Station, we recorded $4.6 million of plant retirement-related charges in the second quarter of 2020. These charges are presented within "Operation and maintenance" and were comprised of write downs of certain capital projects that have been cancelled and materials and supplies inventory balances deemed obsolete due to the planned retirement. As more information becomes available, the retirement date of the R.M. Schahfer Generating Station will be finalized, and additional plant retirement-related charges may be incurred. In February 2021, NIPSCO decided to submit modified Attachment Y Notices to MISO requesting accelerated retirement of two of the four coal fired units at R.M. Schahfer Generating Station. The two units are now expected to be retired by the end of 2021, with the remaining two units still scheduled to be retired in 2023. At retirement, the net book value of the retired units will be reclassified from "Non-Utility and Other property", to current and long-term “Regulatory Assets,” as described above.
In connection with the planned retirement of the Schahfer Generating Station and the Michigan City Generating Station, the current capacity replacement plan includes lower-cost, reliable, cleaner energy resources to be obtained through a combination of NIPSCO ownership and PPAs. To this effect, NIPSCO has entered into a number of agreements with counterparties.
NIPSCO has executed several PPAs to purchase 100% of the output from renewable generation facilities at a fixed price per MWh. Each facility supplying the energy will have an associated nameplate capacity, and payments under the PPAs will not begin until the associated generation facility is constructed by the owner/seller. NIPSCO has also executed several BTAs with developers to construct renewable generation facilities. NIPSCO's purchase requirement under the BTAs is dependent on satisfactory approval of the BTA by the IURC, successful execution of an agreement with a tax equity partner and timely completion of construction. NIPSCO and the tax equity partner are obligated to make cash contributions to the partnership at the date construction is substantially complete. Once the tax equity partner has earned their negotiated rate of return and we have reached the agreed upon contractual date, NIPSCO has the option to purchase at fair market value from the tax equity partner the remaining interest in the aforementioned joint venture.
Greater Lawrence Incident Restoration. In addition to the amounts estimated for third-party claims and fines, penalties and settlements associated with government investigations described above, we have recorded expenses for other incident-related costs. Such costs include certain consulting costs, legal costs, vendor costs, claims center costs, labor and related expenses incurred in connection with the incident, and insurance-related loss surcharges. These amounts do not include the capital cost of the pipeline replacement, which is set forth below.
The following table summarizes expenses incurred and insurance recoveries recorded since the Greater Lawrence Incident. This activity is presented within "Operation and maintenance" and "Other, net" in our Statements of Consolidated Income (Loss).
Total Costs Incurred throughYear Ended
(in millions)December 31, 2019December 31, 2020Incident to Date
Third-party claims and government fines, penalties and settlements$1,041 $(5)$1,036 
Other incident-related costs420 22 442 
Total1,461 17 1,478 
Insurance recoveries recorded(800) (800)
Total costs incurred$661 $17 $678 
As discussed in "- C. Legal Proceedings," the aggregate amount of third-party liability insurance coverage available for losses arising from the Greater Lawrence Incident is $800 million. While we collected the entire $800 million, expenses related to the incident exceeded the total amount of insurance coverage available under our policies.

The following table summarizes the total estimated incident-related expenses.
(in millions)
Current Total Estimated Amount
Third-party claims and government fines, penalties and settlements
$1,036 - $1,050
Other incident-related costs
$445 - $450
Greater Lawrence Pipeline Replacement. In connection with the Greater Lawrence Incident, Columbia of Massachusetts, in cooperation with the Massachusetts Governor’s office, replaced the entire affected pipeline system. We invested approximately $258 million of capital spend for the pipeline replacement; this work was completed in 2019. We maintain property insurance for gas pipelines and other applicable property. Columbia of Massachusetts has filed a proof of loss with its property insurer for the pipeline replacement. In January 2020, we filed a lawsuit against the property insurer, seeking payment of our property claim. We are currently unable to predict the timing or amount of any insurance recovery under the property policy. Refer to Note 1-A, "Company Structure and Principles of Consolidation," for more information.
State Income Taxes Related to Greater Lawrence Incident Expenses. As of December 31, 2018, expenses related to the Greater Lawrence Incident were $1,023 million. In the fourth quarter of 2019, we filed an application for Alternative Apportionment with the MA DOR to request an allocable approach to these expenses for purposes of Massachusetts state income taxes, which, if approved, would result in a state deferred tax asset of approximately $50 million, net. The MA DOR issued a denial during the first quarter of 2020. We filed an application for abatement in the second quarter of 2020, resulting in a hearing with the MA DOR during the fourth quarter of 2020. We believe it is reasonably possible that an alternative method will be proposed by the MA DOR during the first half of 2021.

Voluntary Separation Program. On August 5, 2020, we commenced a voluntary separation program for certain employees. Expense for the voluntary separation program was predominantly recognized in the third quarter of 2020, when the employees accepted the offer, absent a retention period. For employees that have a retention period, expense will be recognized over the remaining service period. Employee acceptance under the voluntary separation program was determined by management based on facts and circumstances of the benefits being offered. The total severance expense for employees who were accepted under the voluntary separation program offered in August 2020 is approximately $38 million, which will be recognized over the remaining service period of the applicable employees. A rollforward of the voluntary separation program accrual for the year ended December 31, 2020 is presented below:
(in millions)
Balance as of
January 1, 2020
Changes Attributable to Costs Incurred(1)
Costs PaidAdjustments
Balance as of
December 31, 2020(2)
Voluntary Separation Program$— 33.5$(21.2)(1.2)$11.1 
(1)This activity is presented within "Operation and maintenance" in our Statements of Consolidated Income (Loss).