XML 60 R29.htm IDEA: XBRL DOCUMENT v3.24.0.1
Restructuring and Related Charges Restructuring and Related Charges (Tables)
3 Months Ended 18 Months Ended
Dec. 30, 2023
Dec. 31, 2022
Dec. 30, 2023
Restructuring Cost and Reserve [Line Items]      
Total Pretax Anticipated Expenses of Restructuring Program The following table reflects the total pretax anticipated expenses associated with the 2022 Program (in millions):
BeefPorkChickenPrepared FoodsInternational/OtherTotal
Severance costs$25 $$24 $54 $19 $130 
Relocation and related costs23 22 57 
Accelerated depreciation— 12 — 19 
Contract and lease terminations— — — 24 — 24 
Professional and other fees— 
Total 2022 Program$55 $18 $28 $115 $22 $238 
   
Schedule of Restructuring Reserve by Type of Cost
The following table reflects our liability related to the 2022 Program, which was recognized in other current liabilities in our Consolidated Condensed Balance sheet as of December 30, 2023 (in millions):
Balance at September 30, 2023Restructuring ExpensePaymentsChanges in EstimatesBalance at December 30, 2023
Severance costs$58 $10 $(20)$(2)$46 
Relocation and related costs(5)— 
Contract and lease termination— (6)— — 
Professional and other fees— — — 
Total$65 $22 $(31)$(2)$54 
   
Restructuring and Related Costs [Table Text Block]
The following table reflects the pretax impact of the 2022 Program’s restructuring and related charges during the first quarter of fiscal 2024 by reportable segment (in millions):
BeefPorkChickenPrepared FoodsInternational/OtherTotal
Severance costs$$$$$— $
Relocation and related costs— — — 
Accelerated depreciation— — — — — — 
Contract and lease terminations— — — 16 — 16 
Professional and other fees— — — — — — 
Total$$$$21 $— $30 
The following table reflects the pretax impact of the 2022 Program’s restructuring and related charges during the first quarter of fiscal 2023 by reportable segment (in millions):
BeefPorkChickenPrepared FoodsInternational/OtherTotal
Severance costs$$$— $$$12 
Relocation and related costs— 
Accelerated depreciation— — — 
Contract and lease terminations— — — (2)— (2)
Professional and other fees— — — — 
Total$$$$$$21 
The following table reflects the pretax 2022 Program charges to date by reportable segment (in millions):
BeefPorkChickenPrepared FoodsInternational/OtherTotal
Severance costs$25 $$24 $54 $18 $129 
Relocation and related costs21 19 — 48 
Accelerated depreciation— 12 — 19 
Contract and lease terminations— — — 18 — 18 
Professional and other fees— — 
Total$53 $17 $26 $106 $18 $220 
Schedule of Accrued Liabilities Related to Plant Closures
The following table reflects our liability related to plant closures as of December 30, 2023 (in millions):
Balance at September 30, 2023Plant Closure ChargesPaymentsBalance at December 30, 2023
Contract termination$151 $$(29)$127 
Severance and retention14 (5)10 
Total$165 $$(34)$137