COMMITMENTS AND CONTINGENCIES
3 Months Ended
Mar. 31, 2021
Commitments and Contingencies Disclosure [Abstract]  
COMMITMENTS AND CONTINGENCIES COMMITMENTS AND CONTINGENCIES
Los Angeles International Airport
In October 2017, the Company executed a lease agreement with Los Angeles World Airports ("LAWA") (the "T1.5 Lease"). Under the T1.5 Lease, the Company oversaw and managed the design, development, financing, construction, and commissioning of a passenger processing facility between Terminal 1 and 2 (the "Terminal 1.5 Project"). The Terminal 1.5 Project includes ticketing, baggage claim, passenger screening, and a bus gate at a cost not to exceed $464 million for site improvements and non-proprietary improvements. Construction on the Terminal 1.5 Project began during third quarter 2017 and was substantially completed at December 31, 2020; however, the Terminal 1.5 Project will not be placed into service until second quarter 2021, at which time LAWA is expected to repay the outstanding loan and purchase the remaining completed assets for accounting purposes. The costs incurred to fund the Terminal 1.5 Project are included within Assets Constructed for Others ("ACFO") and all amounts that have been or will be reimbursed will be included within Construction obligation on the accompanying unaudited Condensed Consolidated Balance Sheet. Upon completion of any individual asset as part of the overall project, the asset and associated liability on the balance sheet are de-recognized in accordance with applicable accounting guidance.

Funding for this project is primarily through the Regional Airports Improvement Corporation (the "RAIC"), which is a quasi-governmental special purpose entity that is acting as a conduit borrower under a syndicated credit facility provided by a group of lenders. A loan made under the credit facility for the Terminal 1.5 Project is being used to reimburse the Company for the site improvements and non-proprietary improvements of the Terminal 1.5 Project, and the outstanding loan will be repaid with the proceeds of LAWA’s payments to purchase completed construction phases. The Company guaranteed the obligation of the RAIC under the credit facility associated with the Terminal 1.5 Project. As of March 31, 2021, the Company's outstanding guaranteed obligation under the credit facility for the Terminal 1.5 Project was $364 million.
Construction costs recorded in ACFO for the Terminal 1.5 Project, which exclude costs associated with assets that were previously completed and placed into service, were $341 million and $309 million, as of March 31, 2021, and December 31, 2020, respectively.

Dallas Love Field
During 2008, the City of Dallas approved the Love Field Modernization Project ("LFMP"), a project to reconstruct Dallas Love Field with modern, convenient air travel facilities. Pursuant to a Program Development Agreement with the City of Dallas and the Love Field Airport Modernization Corporation (or the "LFAMC," a Texas non-profit "local government corporation" established by the City of Dallas to act on the City of Dallas' behalf to facilitate the development of the LFMP), the Company managed this project. Major construction was effectively completed in 2014. During second quarter 2017, the City of Dallas approved using the remaining bond funds for additional terminal construction projects, which were effectively completed in 2018.

Although the City of Dallas received commitments from various sources that helped to fund portions of the LFMP project, including the Federal Aviation Administration ("FAA"), the Transportation Security Administration, and the City of Dallas' Aviation Fund, the majority of the funds used were from the issuance of bonds. The Company guaranteed principal and interest payments on bonds issued by the LFAMC. As of March 31, 2021, $399 million of principal remained outstanding. The net present value of the future principal and interest payments associated with the bonds was $438 million as of March 31, 2021, and was reflected as part of the Company's operating lease right–of–use assets and lease obligations in the unaudited Condensed Consolidated Balance Sheet.

Contractual Obligations and Contingent Liabilities and Commitments

On March 24, 2021, the Company entered into Supplemental Agreement No. 12 (the "Supplement") to its aircraft purchase agreement with The Boeing Company ("Boeing") relating to the Company's purchase of Boeing 737 MAX 7 and 737 MAX 8 aircraft. Pursuant to the Supplement (i) the Company added 100 firm orders for the MAX 7, with the first 30 to be delivered in 2022; (ii) the Company added 155 MAX aircraft options; (iii) the order book was extended to include deliveries through 2031; and (iv) the Company converted 70 MAX 8 firm orders to MAX 7 firm orders. The Supplement also includes certain confidential credits, discounts, and other concessions provided to the Company by Boeing.
As of March 31, 2021, based on the Supplement to its aircraft purchase agreement with Boeing, the Company had firm deliveries and options for Boeing 737 MAX 7 and 737 MAX 8 aircraft as follows:

The Boeing Company
MAX 7
Firm Orders
MAX 8
Firm Orders
MAX 7 or 8 OptionsAdditional MAX 8sTotal
2021— 19 — 28 (a)
202230 — 42 — 72 
202330 — 38 — 68 
202430 — 40 — 70 
202530 — 40 — 70 
202615 15 40 — 70 
202715 15 30 — 60 
202815 15 30 — 60 
202920 30 10 — 60 
203015 45 — — 60 
2031— 10 — — 10 
200149(b)2709(c)628
(a) Includes 20 737 MAX 8s delivered as of March 31, 2021, consisting of 12 owned and 8 leased aircraft.
(b) The Company has flexibility to designate firm orders or options as MAX 7 or MAX 8, upon written advance notification as stated in the contract.
(c) These 9 additional MAX 8 aircraft are leases to be acquired from various third parties, including 8 leased MAX 8 aircraft delivered in first quarter 2021. The Company also received 7 leased MAX 8 aircraft in fourth quarter 2020, for a total of 16 MAX 8 operating leased aircraft from third parties in 2020 and 2021, combined.

Based on the Company's existing agreement with Boeing as reflected in the delivery schedule above, the Company's cash capital commitments associated with its firm orders are as follows: none for 2021 (due to previously agreed upon delivery credits provided by The Boeing Company to the Company due to the settlement of 2020 estimated damages relating to the FAA grounding of the 737 MAX aircraft and progress payments made to date on undelivered aircraft), $700 million in 2022, $1.1 billion in 2023, $1.0 billion in 2024, $1.1 billion in 2025, $1.2 billion in 2026, and $7.2 billion thereafter.

Contingencies
The Company is from time to time subject to various legal proceedings and claims arising in the ordinary course of business, including, but not limited to, examinations by the Internal Revenue Service ("IRS"). The Company's management does not expect that the outcome of any of its currently ongoing legal proceedings or the outcome of any adjustments presented by the IRS, individually or collectively, will have a material adverse effect on the Company's financial condition, results of operations, or cash flow.