XML 77 R65.htm IDEA: XBRL DOCUMENT v3.10.0.1
Commitments and Contingencies (Details) - USD ($)
$ in Millions
1 Months Ended 3 Months Ended
May 24, 2018
Jul. 21, 2017
Jul. 03, 2017
Apr. 01, 2017
Dec. 31, 2014
Dec. 31, 2018
Sep. 02, 2016
Advatech LLC              
Commitments and Contingencies              
Percentage of ownership in joint venture           60.00%  
Advatech LLC | Genco              
Commitments and Contingencies              
Damages claimed, value   $ 81.0          
Invoice amount             $ 81.0
DOE Deactivation, Demolition, And Removal Project | Department of Energy | Maximum              
Commitments and Contingencies              
Cost-reimbursement at risk           $ 106.0  
DOE Deactivation, Demolition, And Removal Project | WGI Ohio and DOE | Minimum              
Commitments and Contingencies              
Cost-reimbursement at risk           106.0  
DOE Deactivation, Demolition, And Removal Project | WGI Ohio and DOE | Maximum              
Commitments and Contingencies              
Cost-reimbursement at risk           146.0  
DOE Deactivation, Demolition, And Removal Project | WGI Ohio              
Commitments and Contingencies              
Claim to DOE, including additional fees         $ 103.0    
Possible costs which may exceed contracted amounts         $ 100.0    
DOE Deactivation, Demolition, And Removal Project | WGI Ohio | Minimum              
Commitments and Contingencies              
Cost-reimbursement at risk           146.0  
AECOM-Canyon Equity Fund, L.P              
Commitments and Contingencies              
Capital commitments           $ 35.0  
Term of capital commitments           10 years  
URS | Design build contractor              
Commitments and Contingencies              
Damages claimed, value $ 11.9   $ 70.0 $ 8.2      
Standby letter of credit              
Commitments and Contingencies              
Contingency liability           $ 537.0  
Surety Bond              
Commitments and Contingencies              
Surety bonds issued           $ 5,600.0