XML 9 R3.htm IDEA: XBRL DOCUMENT v3.24.3
Payments, by Project - 12 months ended Dec. 31, 2023 - CAD ($)
Taxes
Royalties
Fees
Infrastructure
Total Payments
Total $ 199,200,000 $ 49,600,000 $ 9,570,000 $ 880,000 $ 259,250,000
Manantial Espejo Mine [Member]          
Total [1] 2,510,000 1,040,000   100,000 3,650,000
Argenta [Member]          
Total [1] 220,000       220,000
Estelar [Member]          
Total [1] 8,220,000 9,220,000   110,000 17,550,000
Suyai [Member]          
Total [1] 260,000       260,000
Agua Rica [Member]          
Total [1] 140,000       140,000
San Vincente Mine [Member]          
Total [1] 9,080,000 17,030,000     26,110,000
Jacobina Mine [Member]          
Total [1] 20,440,000 5,550,000   250,000 26,240,000
Timmins West Mines [Member]          
Total [1] 1,260,000 2,580,000 140,000   3,980,000
El Péñon Mine [Member]          
Total [1] 59,580,000 8,680,000 600,000 $ 420,000 69,280,000
Minera Florida Mine [Member]          
Total [1]   1,920,000     1,920,000
Escobal Mine [Member]          
Total [1] 530,000 190,000     720,000
Alamo Dorado Mine [Member]          
Total [1]     430,000   430,000
La Colorada Mine [Member]          
Total [1] 15,140,000 1,110,000 730,000   16,980,000
Dolores Mine [Member]          
Total [1] 10,780,000 $ 2,280,000 4,840,000   17,900,000
Huaron Mine [Member]          
Total [1] 12,580,000   840,000   13,420,000
Morococha Mine [Member]          
Total [1] 350,000       350,000
La Arena Mine [Member]          
Total [1] 13,330,000   1,080,000   14,410,000
Shahuindo Mine [Member]          
Total [1] $ 44,780,000   $ 910,000   $ 45,690,000
[1]
The functional currency is USD which was converted from local currency. The following are the average annual exchange rates: BOB 6.9062; CAD 1.3497; ARS 295.6761; MXN 17.7306; PEN 3.7438; BRL 4.9935; CLP 840.67 and GTQ 7.8337.
Amounts were subsequently converted into CAD from USD using the average exchange rate for the year ended December 31, 2023 of 1USD = 1.3497 CAD.