Restructuring and Related Activities
3 Months Ended
Sep. 30, 2022
Restructuring and Related Activities [Abstract]  
Restructuring, Impairment, and Other Activities Disclosure Esterhazy Closure CostsDue to increased brine inflows, on June 4, 2021, the Company made the decision to accelerate the timing of the shutdown of our K1 and K2 mine shafts at our Esterhazy, Saskatchewan potash mine. Closing the K1 and K2 shafts were key pieces of the transition to the K3 shaft, but the timeline for the closure was accelerated by approximately nine months. In the second quarter of 2021, we had pre-tax costs of $158.1 million related to the permanent closure of these facilities. These costs consisted of $109.9 million related to the write-off of fixed assets, $37.1 million related to AROs, and $11.1 million related to inventory and other reserves.