XML 54 R12.htm IDEA: XBRL DOCUMENT v3.19.3.a.u2
Revenue from Customers
12 Months Ended
Dec. 31, 2019
Revenue from Contract with Customer [Abstract]  
Revenue from Customers
4.
REVENUE FROM CUSTOMERS
Backlog
The Company had the following backlog, by segment:
 
 
December 31,
 
 
2019
 
2018
Heavy Civil Backlog
 
$
834,049

 
$
780,706

Specialty Services Backlog
 
233,976

 
70,019

Total Heavy Civil and Specialty Services Backlog
 
$
1,068,025

 
$
850,725


The Company expects to recognize approximately 70% of its backlog as revenue during the next twelve months, and the balance thereafter.
Revenue Disaggregation
The following tables present the Company’s revenue disaggregated by major end market and contract type:
 
 
Years Ended December 31,
Revenue by major end market
 
2019
 
2018
 
2017
Heavy Highway
 
$
483,175

 
$
513,376

 
$
579,157

Aviation
 
141,371

 
111,824

 
77,399

Water Containment and Treatment
 
65,795

 
66,928

 
59,593

Other
 
69,984

 
73,510

 
85,503

Heavy Civil Revenue
 
$
760,325

 
$
765,638

 
$
801,652

 
 
 
 
 
 
 
Land Development
 
$
84,637

 
$

 
$

Commercial
 
128,187

 
120,333

 
48,314

Specialty Services Revenue
 
$
212,824

 
$
120,333

 
$
48,314

 
 
 
 
 
 
 
Residential Revenue
 
$
153,129

 
$
151,696

 
$
107,992

 
 
 
 
 
 
 
Revenues
 
$
1,126,278

 
$
1,037,667

 
$
957,958

 
 
 
 
 
 
 
Revenue by contract type
 
 
 
 
 
 
Fixed-Unit Price
 
$
708,638

 
$
733,047

 
$
755,840

Lump Sum
 
262,237

 
146,874

 
57,823

Residential and Other
 
155,403

 
157,746

 
144,295

Revenues
 
$
1,126,278

 
$
1,037,667

 
$
957,958


Each of these contract types presents advantages and disadvantages. Typically, the Company assumes more risk with lump-sum contracts. However, these types of contracts offer additional profits if the work is completed for less than originally estimated. Under fixed-unit price contracts, the Company’s profit may vary if actual labor-hour costs vary significantly from the negotiated rates. Also, because some contracts can provide little or no fee for managing material costs, the components of contract cost can impact profitability.
Variable Consideration
The Company has projects that it is in the process of negotiating, or awaiting final approval of, unapproved change orders and claims with its customers. The Company is proceeding with its contractual rights to recoup additional costs incurred from its customers based on completing work associated with change orders, including change orders with pending change order pricing, or claims related to significant changes in scope which resulted in substantial delays and additional costs in completing the work. Unapproved change order and claim information has been provided to the Company’s customers and negotiations with the customers are ongoing. If additional progress with an acceptable resolution is not reached, legal action will be taken.
Based upon the Company’s review of the provisions of its contracts, specific costs incurred and other related evidence supporting the unapproved change orders and claims, together in some cases as necessary with the views of the Company’s outside claim consultants, the Company concluded it was appropriate to include in project price amounts of $3,000 and $9,300, at December 31, 2019 and 2018, respectively. Provisions for estimated losses on uncompleted contracts are made in the period in which such losses are determined.
Contract Estimates
Accounting for long-term contracts and programs involves the use of various techniques to estimate total contract revenue and costs. For long-term contracts, the Company estimates the profit on a contract as the difference between the total estimated revenue and expected costs to complete a contract and recognizes such profit over the life of the contract.
Contract estimates are based on various assumptions to project the outcome of future events that often span several years. These assumptions include labor productivity and availability, the complexity of the work to be performed, the cost and availability of materials and the performance of subcontractors. Changes in job performance, job conditions and estimated profitability, including those changes arising from contract penalty provisions and final contract settlements may result in revisions to costs and income and are recognized in the period in which the revisions are determined.
In December 2019, Sterling was able to come to an interim agreement related to a 2014 project involving the construction of three separate bridges in Texas that had suffered from significant schedule delays and cost overruns due to major owner design flaws. This agreement enabled Sterling to recover approximately $17,000 in costs to date related to these delays and defined a better dispute resolution process along with agreed upon rates for future work if there are further delays. As part of this agreement, Sterling agreed to work on all three bridges simultaneously (versus doing one at a time) to accelerate the final completion schedule. This revised schedule has significantly increased the amount of labor, equipment and infrastructure required to complete the project under the new terms of the agreement and resulted in a reduction of gross profit in the quarter of $10,200.
Changes in estimated revenues and gross margin resulted in a net decrease of $9,044 for the year ended December 31, 2019, and net increases of $7,098 and $923 for the years ended December 31, 2018 and 2017 respectively, included in “Operating income” on the Consolidated Statements of Operations. The 2019 decrease primarily related to the aforementioned bridge project in Texas.