Concession agreement / authorization of the equityInterest %Maturity
Copel DISContract 046/1999, extended by 5th addendum to the contract10007.07.2045
Elejor Contract 125/2001 – HPP Fundão7006.11.2040
Contract 125/2001 – HPP Santa Clara 05.10.2040
Authorization – SHP Fundão I and SHP Santa Clara I – 753/2002 and 757/2002  (a)
Dona Francisca Energética Contract 188/1998 – HPP Dona Francisca2309.21.2037
Usina de Energia Eólica São João S.A.MME Ordinance 173 /2012 – WPP São João4903.26.2047
Usina de Energia Eólica Carnaúba S.A.MME Ordinance 204 /2012 – WPP Carnaúbas4904.09.2047
Usina de Energia Eólica Reduto S.A.MME Ordinance 230 /2012 – WPP Reduto4904.16.2047
Usina de Energia Eólica Santo Cristo S.A.MME Ordinance 233/2012 – WPP Santo Cristo4904.18.2047
(a) Projects had the conversion of authorization into registration, according to Authorizing Resolutions No. 14,744/2023 and 14,745/2023.
Hydroelectric Power Plant – HPP
Small Hydroelectric Plant – SHP
Wind Power Plant – WPP
Schedule of concession contracts or authorizations obtained by Copel Get and its investees
Generation concessionInterest %Maturity
Generation Concession Contract 002/2024 - HPP Gov. Ney Aminthas de Barros Braga (Segredo) (Note 1)10011.19.2054
Generation Concession Contract 002/2024 - HPP Gov. José Richa (Salto Caxias) (Note 1)10011.19.2054
Generation Concession Contract 003/2016 – HPP Gov. Pedro Viriato Parigot de Souza (GPS)10001.03.2053
Authorization – Ordinance 133/2011 – SHP Cavernoso II 10012.06.2050
Generation Concession Contract 002/2012 – HPP Baixo Iguaçu3012.03.2049
Generation Concession Contract 001/2007 – HPP Gov. Jayme Canet Júnior (Mauá)5106.28.2049
Generation Concession Contract 001/2011 – HPP Colíder10001.30.2046
Generation Concession Contract 005/2024 - HPP Cavernoso (Note 37)10006.23.2033
Generation Concession Contract 007/2013 - HPP Derivação do Rio Jordão10006.21.2032
Authorization – Resolution 278/1999 – WPP Palmas (Note 37)10029.09.2029
Generation Concession Contract 004/2024 - HPP Chaminé (Note 37)10008.02.2028
Generation Concession Contract 001/2020 - HPP Guaricana (Note 37)10007.21.2028
Generation Concession Contract 003/2024 - HPP Apucaraninha (Note 37)10001.27.2027
Generation Concession Contract 006/2024 - HPP São Jorge (Note 37)10007.24.2026
Concession contract 045/1999 - TPP Figueira (Note 37)10003.26.2019
Dispatch 182/2002 - Hydroelectric Generating Plant - HGP Melissa, HGP Pitangui and HGP Salto do Vau (only register with ANEEL)100
HPP Marumbi - Power generating plant registration: CGH. PH. PR. 001501-6.02100
Authorization Aneel 5,373/2015 – HGP Chopim I (only register with ANEEL)100
Concession agreement / authorization of the equity
Nova Asa Branca IMME Ordinance 267/2011 – WPP Asa Branca I 10004.25.2046
Nova Asa Branca IIMME Ordinance 333/2011 – WPP Asa Branca II 10005.31.2046
Nova Asa Branca IIIMME Ordinance 334/2011 – WPP Asa Branca III 10005.31.2046
Nova Eurus IVMME Ordinance 273/2011 -WPP Eurus IV 10004.27.2046
Santa MariaMME Ordinance 274/2012 – WPP SM 10005.08.2047
Santa HelenaMME Ordinance 207/2012 – WPP Santa Helena 10004.09.2047
Ventos de Santo UrielMME Ordinance 201/2012 – WPP Santo Uriel 10004.09.2047
GE Boa VistaMME Ordinance 276 /2011 – WPP Dreen Boa Vista 10004.28.2046
GE FarolMME Ordinance 263 /2011 – WPP Farol 10004.20.2046
GE Olho D’ÁguaMME Ordinance 343 /2011 – WPP Dreen Olho D'Água 10006.01.2046
GE São Bento do NorteMME Ordinance 310 /2011 – WPP Dreen São Bento do Norte 10005.19.2046
Esperança do NordesteMME Ordinance 183/2015 – WPP Esperança do Nordeste10005.11.2050
Paraíso dos Ventos do NordesteMME Ordinance 182/2015 – WPP Paraíso dos Ventos do Nordeste10005.11.2050
Usina de Energia Eólica JangadaResolution 3,257/2011 – WPP GE Jangada10001.05.2042
Maria HelenaResolution 3,259/2011 – WPP GE Maria Helena10001.05.2042
Usina de Energia Eólica PotiguarMME Ordinance 179/2015 – WPP Potiguar10005.11.2050
Usina de Energia Eólica GuajiruResolution 3,256/2011 – WPP Dreen Guajiru10001.05.2042
Usina de Energia Eólica CutiaResolution 3,258/2011 – WPP Dreen Cutia10001.05.2042
São Bento do Norte IOrdinance 349/2015 – WPP São Bento do Norte I10008.04.2050
São Bento do Norte II Ordinance 348/2015 – WPP São Bento do Norte II10008.04.2050
São Bento do Norte IIIOrdinance 347/2015 – WPP São Bento do Norte III 10008.04.2050
São Miguel IOrdinance 352/2015 – WPP São Miguel I10008.04.2050
São MigueI lIOrdinance 351/2015 – WPP São Miguel II10008.04.2050
São Miguel IIIOrdinance 350/2015 – WPP São Miguel III10008.04.2050
Foz do ChopimAuthorization 114/2000 – SHP Arturo Andreoli 35.807.07.2034
SHP Bela VistaResolution 913/2017 – transfer of title under Resolution 7,802/2019 10001.02.2041
F.D.A. Electricity Generation (Note 1)Generation Concession Contract contract 002/202010011.19.2054
Jandaíra I Energias RenováveisOrdinance 140/2020 – WPP Jandaíra I10004.02.2055
Jandaíra II Energias RenováveisOrdinance 141/2020 – WPP Jandaíra II10004.02.2055
Jandaíra III Energias RenováveisOrdinance 142/2020 – WPP Jandaíra III10004.02.2055
Jandaíra IV Energias RenováveisOrdinance 139/2020 – WPP Jandaíra IV10004.02.2055
EOL Potiguar B 141 SPE S.A.Ordinance 02/2019 – WPP Vila Maranhão I10001.11.2054
EOL Potiguar B 142 SPE S.A.Ordinance 12/2019 – WPP Vila Maranhão II10001.14.2054
EOL Potiguar B 143 SPE S.A.Ordinance 13/2019 – WPP Vila Maranhão III10001.14.2054
EOL Potiguar B 61 SPE S.A.Ordinance 453/2019 – WPP Ventos de Vila Mato Grosso I10012.06.2054
Ventos de Vila Paraíba IV SPE S.A Ordinance 10/2019 - WPP Vila Ceará I10001.14.2054
EOL Aventura IIOrdinance 209/2018 - Aventura II10006.05.2053
EOL Aventura IIIOrdinance 220/2018 - Aventura III - REA n° 7.820/201910006.11.2053
Generation concessionInterest %Maturity
EOL Aventura IVOrdinance 215/2018 - Aventura IV10006.05.2053
EOL Aventura VOrdinance 213/2018 - Aventura V10006.05.2053
EOL SRMN I S.A.Ordinance 196/2018 - Santa Rosa e Novo Mundo I10006.04.2053
EOL SRMN II S.A.Ordinance 194/2018 - Santa Rosa e Novo Mundo II10006.04.2053
EOL SRMN III S.A.Ordinance 197/2018 - Santa Rosa e Novo Mundo III10006.04.2053
EOL SRMN IV S.A.Ordinance 188/2018 - Santa Rosa e Novo Mundo IV10006.01.2053
EOL SRMN V S.A.Ordinance 189/2018 - Santa Rosa e Novo Mundo V - Resolution 7.783/201910006.01.2053
Transmission lines and substations concession agreementsInterest %Maturity Next tariff
review
Contract 060/2001 – Transmission facilities (sundry Transmission lines and Substations) – extended by the 3rd additive term10001.01.20432028 (b)
Contract 075/2001 – Transmission line 230 kV Bateias – Jaguariaíva10008.17.2031(a)
Contract 006/2008 – Transmission line 230 kV Bateias – Pilarzinho10003.17.20382028 (c)
Contract 027/2009 – Transmission line 525 kV Foz do Iguaçu – Cascavel Oeste10011.19.20392025
Contract 010/2010 – Transmission line 500 kV Araraquara II – Taubaté 10010.06.20402026
Contract 015/2010 – Substation Cerquilho III 230/138 kV10010.06.20402026
Contract 022/2012 – Transmission line 230 kV Londrina – Figueira and Transmission line 230 kV Foz do Chopim – Salto Osório10008.27.20422028
Contract 002/2013 – Transmission line 230 kV Assis – Paraguaçu Paulista II e Substation Paraguaçu Paulista II 230 kV 10002.25.20432028 (c)
Contract 005/2014 – Transmission line 230 kV Bateias – Curitiba Norte e Substation Curitiba Norte 230/138 kV10001.29.20442029 (d)
Contract 021/2014 – Transmission line 230 kV Foz do Chopim – Realeza e Substation Realeza 230/138 kV 10009.05.20442025
Contract 022/2014 – Transmission line 500 kV Assis – Londrina10009.05.20442025
Contract 006/201610004.07.20462026
Contract 006/2016 – Transmission line 525 kV Curitiba Leste – Blumenau
Contract 006/2016 – Transmission line 230 kV Baixo Iguaçu – Realeza
Contract 006/2016 – Transmission line 230 kV Curitiba Centro – Uberaba
Contract 006/2016 – Substation Medianeira 230/138 kV
Contract 006/2016 – Substation Curitiba Centro 230/138 kV
Contract 006/2016 – Substation Andirá Leste 230/138 kV
Concession agreement / authorization of the equity
Costa Oeste TransmissoraContract 001/2012:10001.12.20422027
Transmission line 230 kV Cascavel Oeste – Umuarama
Substation Umuarama 230/138 kV
Caiuá Transmissora Contract 007/2012:4905.10.20422027
Transmission line 230 kV Umuarama - Guaíra
Transmission line 230 kV Cascavel Oeste – Cascavel Norte
Substation Santa Quitéria 230/138/13,8 kV
Substation Cascavel Norte 230/138/13,8 kV
Marumbi TransmissoraContract 008/2012:10005.10.20422027
Transmission line 525 kV Curitiba – Curitiba Leste
Substation Curitiba Leste 525/230 kV
Integração MaranhenseContract 011/2012: Transmission line 500 Kv Açailândia – Miranda II4905.10.20422027
Matrinchã TransmissoraContract 012/2012:4905.10.20422027
Transmission line 500 kV Paranaíta – Cláudia
Transmission line 500 kV Cláudia – Paranatinga
Transmission line 500 kV Paranatinga – Ribeirãozinho
Substation Paranaíta 500 kV
Substation Cláudia 500 kV
Substation Paranatinga 500 kV
Guaraciaba TransmissoraContract 013/2012:4905.10.20422027
Transmission line 500 kV Ribeirãozinho – Rio Verde Norte
Transmission line 500 kV Rio Verde Norte – Marimbondo II
Substation Marimbondo II 500 kV
Paranaíba TransmissoraContract 007/2013:24.505.02.20432028 (c)
Transmission line 500 kV Barreiras II – Rio das Éguas
Transmission line 500 kV Rio das Éguas – Luziânia
Transmission line 500 kV Luziânia – Pirapora 2
Mata de Santa GenebraContract 001/2014:50.105.14.20442029 (d)
Transmission line 500 kV Itatiba – Bateias
Transmission line 500 kV Araraquara 2 – Itatiba
Transmission line 500 kV Araraquara 2 – Fernão Dias
Substation Santa Bárbara D ́Oeste 440 kV
Substation Itatiba 500 kV
Substation Fernão Dias 500/440 kV
Cantareira TransmissoraContract 019/2014: Transmission line Estreito – Fernão Dias 4909.05.20442025
Uirapuru TransmissoraContract 002/2005: Transmission line 525 kV Ivaiporã – Londrina10003.04.2035(a)
(a) Do not undergo tariff review and RAP reduces to 50% in the 16th year.
(b) Approval Resolution No. 3,344/2024 approved the result of the Periodic Tariff Reviews of the Permitted Annual Revenue – RAP of the extended Concession Contracts, including Concession Contract No. 060/2001.
(c) Approval Resolution No. 3,342/2024 approved the complementary result of the Periodic Tariff Reviews of the Permitted Annual Revenue - RAP of 2023 of the auctioned concession contracts, including concession contracts 006/2008, 002/2013 and 007/2013. In 2028, the 4th RTP of concession contract 006/2008 will take place, therefore, there will no longer be a recalculation of the cost of third-party capital of this contract.
(d) Approval Resolution No. 3,343/2024 approved the result of the Periodic Tariff Reviews of the Annual Permitted Revenue – RAP of 2024 of the auctioned transmission contracts, including concession contracts No. 001/2014 and 005/2014.