v2.3.0.15
Contingencies and Commitments
9 Months Ended
Sep. 30, 2011
Contingencies and Commitments 
Contingencies and Commitments

(13)    The company and certain of its subsidiaries are involved in various litigation matters. Additionally, the company and certain of its subsidiaries are contingently liable for commitments and performance guarantees arising in the ordinary course of business. The company and certain of its clients have made claims arising from the performance under its contracts. The company recognizes revenue, but not profit, for certain significant claims when it is determined that recovery of incurred costs is probable and the amounts can be reliably estimated. Under ASC 605-35-25, these requirements are satisfied when the contract or other evidence provides a legal basis for the claim, additional costs were caused by circumstances that were unforeseen at the contract date and not the result of deficiencies in the company’s performance, claim-related costs are identifiable and considered reasonable in view of the work performed, and evidence supporting the claim is objective and verifiable. Recognized claims against clients amounted to $276 million and $209 million as of September 30, 2011 and December 31, 2010, respectively, and are primarily included in contract work in progress in the accompanying Condensed Consolidated Balance Sheet. The company periodically evaluates its position and the amounts recognized in revenue with respect to all its claims. Amounts ultimately realized from claims could differ materially from the balances included in the financial statements. The company does not expect that the ultimate resolution of these matters will have a material adverse effect on its consolidated financial position or results of operations.

 

As of September 30, 2011, a number of matters were in the litigation and dispute resolution process.  The following discussion provides a background and current status of the more significant of these matters:

 

Greater Gabbard Offshore Wind Farm Project

 

The company is involved in a dispute in connection with the Greater Gabbard Project, a $1.8 billion lump-sum project to provide engineering, procurement and construction services for the client’s offshore wind farm project in the United Kingdom. The dispute relates to the company’s claim for additional compensation for schedule and cost impacts arising from delays in the fabrication of monopiles and transition pieces, along with certain disruption and productivity issues associated with construction activities and weather-related delays. The company believes these schedule and cost impacts are attributable to the client and other third parties.

 

As of September 30, 2011, the company had recorded $243 million of claim revenue related to this issue for costs incurred to date. Additional project costs related to the claim are expected to be incurred in future quarters and, as a result, claim revenue will increase during the life of the project. The company believes the ultimate recovery of incurred and future costs related to the claim is probable under ASC 605-35-25. The company will continue to periodically evaluate its position and the amount recognized in revenue with respect to this claim. As of September 30, 2011, the client had also withheld the contractual maximum for liquidated damages related to the dispute of approximately $150 million. The company will also seek to recover in arbitration the withheld liquidated damages. Should the company not be successful in its pursuit of schedule relief related to certain delays covered by the claim, the liquidated damages not recovered from the client could result in a charge to earnings, as would any unrecovered claim amounts. The project is expected to be substantially complete in early 2012. However, the resolution of the claims is expected to extend beyond the completion date of the project.

 

Alexander, Preston, et al. v. Fluor Corporation, et al

 

Since 1995, the company has been named as a defendant in lawsuits alleging injuries resulting from the lead business of St. Joe Minerals Corporation (“St. Joe”) and The Doe Run Company (“Doe Run”) in Herculaneum, Missouri. The company was named as a defendant in these lawsuits as a result of its ownership or other interests in St. Joe and Doe Run in the period between 1981 and 1994. In 1994, the company sold its interests in St. Joe and Doe Run, along with all liabilities associated with the lead business, pursuant to a sale agreement in which the buyer agreed to indemnify the company for those liabilities. Until December 2010, substantially all the lawsuits were settled and paid by the buyer; and in all cases the company was fully released.

 

In December 2010, the buyer settled with 16 plaintiffs without obtaining a release for the benefit of the company, leaving the company to defend its case with these 16 plaintiffs in the City of St. Louis Circuit Court. In late July 2011, the jury reached an unexpected verdict in this case, ruling in favor of the plaintiffs and against the company and certain former subsidiaries for $38.5 million in compensatory and economic damages and $320 million in punitive damages. In August 2011, the court entered judgments based on the verdict.

 

The company intends to appeal the judgments of the court and believes that it is probable that such judgments will be overturned. The company strongly believes that the judgments are not supported by the facts or the law, and intends to pursue all possible avenues for reconsideration or appeal. Based upon the present status of this matter, the company does not believe it is probable that a loss will be incurred. Accordingly, the company has not recorded a charge as a result of the judgments. The company has also taken steps to enforce its rights to the indemnification described above.

 

The company, the buyer of the smelter operations and other entities are defendants in 24 additional lawsuits relating to the lead business of St. Joe and Doe Run. The company believes it has strong defenses to these lawsuits and is vigorously defending its position. In addition, the company believes it is entitled to indemnification under the sale agreement for each of the matters raised in these lawsuits.

 

Embassy Projects

 

The company constructed 11 embassy projects for the U.S. Department of State under fixed-price contracts. Some of these projects were adversely impacted by higher costs due to schedule extensions, scope changes causing material deviations from the Standard Embassy Design, increased costs to meet client requirements for additional security-cleared labor, site conditions at certain locations, subcontractor and teaming partner difficulties and the availability and productivity of construction labor.  All embassy projects were completed prior to 2011.

 

There are outstanding claims on two embassy projects, totaling $33 million, that had been recognized in revenue in previous years. Total claims-related costs incurred to date for these two projects, along with claims for equitable adjustment submitted or identified, exceed the amount recorded in claims revenue. All claims have been certified in accordance with federal contracting requirements.

 

Conex International v. Fluor Enterprises, Inc.

 

In November 2006, a Jefferson County, Texas, jury reached an unexpected verdict in the case of Conex International (“Conex”) v. Fluor Enterprises Inc. (“FEI”), ruling in favor of Conex and awarding $99 million in damages related to a 2001 construction project.

 

In 2001, Atofina (now part of Total Petrochemicals Inc.) hired Conex International to be the mechanical contractor on a project at Atofina’s refinery in Port Arthur, Texas. FEI was also hired to provide certain engineering advice to Atofina on the project. There was no contract between Conex and FEI. Later in 2001 after the project was complete, Conex and Atofina negotiated a final settlement for extra work on the project. Conex sued FEI in September 2003, alleging damages for interference and misrepresentation and demanding that FEI should pay Conex the balance of the extra work charges that Atofina did not pay in the settlement. Conex also asserted that FEI interfered with Conex’s contract and business relationship with Atofina. The jury verdict awarded damages for the extra work and the alleged interference.

 

The company appealed the decision and the judgment against the company was reversed in its entirety in December 2008. Both parties appealed the decision to the Texas Supreme Court, which denied both petitions. The company requested rehearing on two issues to the Texas Supreme Court, and that request was denied.  The Texas Supreme Court remanded the matter back to the trial court for a new trial. Based upon the present status of this matter, the company does not believe that there is a reasonable possibility that a loss will be incurred.