XML 25 R13.htm IDEA: XBRL DOCUMENT v3.5.0.2
Percentage-Of-Completion Contracts
9 Months Ended
Sep. 30, 2016
Contractors [Abstract]  
Percentage-of-Completion Contracts
Costs and Estimated Earnings in Excess of Billings on Uncompleted Contracts and Billings in Excess of Costs and Estimated Earnings on Uncompleted Contracts
Our CIE balances by business segment are as follows:
 
September 30,
 
December 31,
Dollars in millions
2016
 
2015
Technology & Consulting
$
25

 
$
42

Engineering & Construction
123

 
114

Government Services
242

 
68

Subtotal
390

 
224

Non-strategic Business

 

Total
$
390

 
$
224


Our BIE balances by business segment are as follows:
 
September 30,
 
December 31,
Dollars in millions
2016
 
2015
Technology & Consulting
$
52

 
$
72

Engineering & Construction
347

 
307

Government Services
67

 
69

Subtotal
466

 
448

Non-strategic Business
71

 
61

Total
$
537

 
$
509


Unapproved change orders and claims

The amounts of unapproved change orders and claims included in determining the profit or loss on contracts are as follows:
Dollars in millions
2016
 
2015
Amounts included in project estimates-at-completion at January 1,
$
46

 
$
31

Additions
12

 
48

Approved change orders
(32
)
 
(40
)
Adjustment due to disposition of business

 
(6
)
Amounts included in project estimates-at-completion at September 30,
$
26

 
$
33

 
 
 
 
Amounts recorded in revenues on a percentage-of-completion basis at September 30,
$
24

 
$
32


The table above excludes unapproved change orders and claims related to our unconsolidated affiliates. Our proportionate share of unapproved change orders and claims was $65 million as of September 30, 2016 and $59 million as of September 30, 2015 on a project in our E&C business segment.

Liquidated damages

Some of our engineering and construction contracts have schedule dates and performance obligations that if not met could subject us to penalties for liquidated damages. These generally relate to specified activities that must be completed by a set contractual date or by achievement of a specified level of output or throughput. Each contract defines the conditions under which a customer may make a claim for liquidated damages. However, in some instances, liquidated damages are not asserted by the customer, but the potential to do so is used in negotiating or settling claims and closing out the contract. Any accrued liquidated damages are recognized as a reduction in revenues in our condensed consolidated statements of operations.

It is possible that liquidated damages related to several projects totaling $5 million and $6 million at September 30, 2016 and December 31, 2015, respectively, could be incurred if the projects are completed as currently forecasted. However, based upon our evaluation of our performance, we have concluded these liquidated damages are not probable and therefore, they have not been recognized.