Commitments and Contingencies - Stipulation Filed with the NMPRC (Details)
$ in Millions
Apr. 08, 2015
USD ($)
MW
Oct. 01, 2014
USD ($)
$ / kw
MW
Dec. 20, 2013
USD ($)
$ / kw
MW
Jun. 30, 2015
USD ($)
MW
May. 19, 2015
MW
Jan. 15, 2015
MW
Jun. 26, 2014
MW
San Juan Generating Station Unit 4 [Member] | Public Service Company of New Mexico [Member] | Clean Air Act, SNCR [Member]              
Public Utilities, Commitments And Contingencies [Line Items]              
Public Utilities, Additional Ownership To Be Obtained, in Megawatts | MW   132 78 132 132   132
Public Utilities, Estimated rate base value at 1/1/2018   $ 26.0          
Public Utilities, Ownership in Megawatts PNM has agreed not to obtain | MW           65  
San Juan Generating Station Unit 4 [Member] | Public Service Company of New Mexico [Member] | Clean Air Act, SNCR Hearing Examiner Recommended Denial [Member]              
Public Utilities, Commitments And Contingencies [Line Items]              
Public Utilities, Additional Ownership To Be Obtained, in Megawatts | MW 132            
Period of time to accept or reject modifications in recommendation 7 days            
San Juan Generating Station Unit 3 [Member] | Public Service Company of New Mexico [Member] | Clean Air Act, SNCR [Member]              
Public Utilities, Commitments And Contingencies [Line Items]              
Public Utilities, Proposed reduction in carrying value   26.0          
Public Utilities, Estimated unrecoverable increase in operations and maintenance   20.0          
San Juan Generating Station Unit 3 [Member] | Maximum [Member] | Public Service Company of New Mexico [Member] | Clean Air Act, SNCR [Member]              
Public Utilities, Commitments And Contingencies [Line Items]              
Public Utilities, Estimated pre-tax regulatory disallowance $ 155.0 70.0          
San Juan Generating Station Unit 3 [Member] | Minimum [Member] | Public Service Company of New Mexico [Member] | Clean Air Act, SNCR [Member]              
Public Utilities, Commitments And Contingencies [Line Items]              
Public Utilities, Estimated pre-tax regulatory disallowance 145.0 $ 60.0          
San Juan Generating Station Units 2 and 3 [Member] | Public Service Company of New Mexico [Member]              
Public Utilities, Commitments And Contingencies [Line Items]              
Net book value       $ 278.0      
San Juan Generating Station Units 2 and 3 [Member] | Public Service Company of New Mexico [Member] | Clean Air Act, SNCR [Member]              
Public Utilities, Commitments And Contingencies [Line Items]              
Public Utilities, Recovery Percentage of Estimated undepreciated value at 12/31/17   50.00%          
Public Utilities, Estimated undepreciated value at 12/31/17 $ 128.5 $ 231.0          
Public Utilities, Requested Time Period to Recover Retired Units NBV   20 years 20 years        
Public Utilities, Write-off Percentage of Estimated undepreciated value at 12/31/17 50.00% 50.00%          
Palo Verde Nuclear Generating Station Unit 3 [Member] | Public Service Company of New Mexico [Member]              
Public Utilities, Commitments And Contingencies [Line Items]              
Net book value       $ 147.0      
Palo Verde Nuclear Generating Station Unit 3 [Member] | Public Service Company of New Mexico [Member] | Clean Air Act, SNCR [Member]              
Public Utilities, Commitments And Contingencies [Line Items]              
Public Utilities, Estimated rate base value at 1/1/2018   $ 221.1          
Public Utilities, Proposed value per Kilowatt effective January 1, 2018 | $ / kw   1,650          
Palo Verde Nuclear Generating Station Unit 3 [Member] | PNMR and PNM [Member]              
Public Utilities, Commitments And Contingencies [Line Items]              
Public Utilities, Number of Megawatts Nuclear Generation | MW       134      
Palo Verde Nuclear Generating Station Unit 3 [Member] | PNMR and PNM [Member] | Clean Air Act, SNCR [Member]              
Public Utilities, Commitments And Contingencies [Line Items]              
Public Utilities, Number of Megawatts Nuclear Generation | MW   134 134        
Public Utilities, Proposed value per Kilowatt effective January 1, 2018 | $ / kw     2,500        
Public Utilities, Percentage capacity factor 7-year performance threshold   75.00%          
Public Utilities, Period over which to measure capacity performance   7 years          
San Juan Generating Station Units 1 and 4 [Member] | Installation Costs Including Construction Management, Gross Receipts Taxes, AFUDC, and Other PNM Costs [Member] | Maximum [Member] | Public Service Company of New Mexico [Member] | Clean Air Act, SNCR [Member]              
Public Utilities, Commitments And Contingencies [Line Items]              
Estimated Installation Capital Costs   $ 90.6 $ 82.0