XML 106 R53.htm IDEA: XBRL DOCUMENT v3.3.0.814
Commitments and Contingencies - The Clean Air Act (Details)
$ in Millions
9 Months Ended
Oct. 01, 2014
USD ($)
$ / kw
MW
Dec. 20, 2013
USD ($)
$ / kw
MW
Sep. 30, 2015
T / yr
state
$ / kw
MW
Aug. 13, 2015
MW
May. 19, 2015
MW
Jul. 31, 2014
MW
Jun. 26, 2014
MW
Oct. 31, 2012
USD ($)
Clean Air Act related to Regional Haze [Member]                
Public Utilities, Commitments And Contingencies [Line Items]                
Public utilities, number of states to address regional haze (in states) | state     50          
Public utilities, potential to emit tons per year of visibility impairing pollution, maximum (in tons per year) | T / yr     250          
San Juan Generating Station [Member] | Public Service Company of New Mexico [Member]                
Public Utilities, Commitments And Contingencies [Line Items]                
Jointly owned utility plant, proportionate ownership share               46.30%
San Juan Generating Station [Member] | Public Service Company of New Mexico [Member] | Clean Air Act, SNCR [Member]                
Public Utilities, Commitments And Contingencies [Line Items]                
Public utilities, overall reduction of ownership (in megawatts)   340            
San Juan Generating Station [Member] | Installation Costs Including Construction Management, Gross Receipts Taxes, AFUDC, and Other PNM Costs [Member] | Minimum [Member] | Public Service Company of New Mexico [Member] | Clean Air Act, SCR [Member] [Member]                
Public Utilities, Commitments And Contingencies [Line Items]                
Estimated total capital cost if requirement occurred | $               $ 824.0
San Juan Generating Station [Member] | Installation Costs Including Construction Management, Gross Receipts Taxes, AFUDC, and Other PNM Costs [Member] | Minimum [Member] | Public Service Company of New Mexico [Member] | Clean Air Act, SNCR [Member]                
Public Utilities, Commitments And Contingencies [Line Items]                
Estimated installation capital costs | $               85.0
Estimated portion of total capital costs if requirement occurred | $               105.0
San Juan Generating Station [Member] | Installation Costs Including Construction Management, Gross Receipts Taxes, AFUDC, and Other PNM Costs [Member] | Maximum [Member] | Public Service Company of New Mexico [Member] | Clean Air Act, SCR [Member] [Member]                
Public Utilities, Commitments And Contingencies [Line Items]                
Estimated total capital cost if requirement occurred | $               910.0
San Juan Generating Station [Member] | Installation Costs Including Construction Management, Gross Receipts Taxes, AFUDC, and Other PNM Costs [Member] | Maximum [Member] | Public Service Company of New Mexico [Member] | Clean Air Act, SNCR [Member]                
Public Utilities, Commitments And Contingencies [Line Items]                
Estimated installation capital costs | $               90.0
Estimated portion of total capital costs if requirement occurred | $               $ 110.0
San Juan Generating Station Units 2 and 3 [Member] | Public Service Company of New Mexico [Member] | Clean Air Act, SNCR [Member]                
Public Utilities, Commitments And Contingencies [Line Items]                
Public utilities, requested time period to recover retired units NBV 20 years 20 years 20 years          
Public utilities, newly identified replacement gas-fired generation, December 2013 (in megawatts)   177            
Public utilities, newly identified replacement solar generation, December 2013 (in megawatts)   40            
Public utilities, newly identified replacement gas-fired generation (in megawatts)     187          
Palo Verde Nuclear Generating Station Unit 3 [Member] | Public Service Company of New Mexico [Member] | Clean Air Act, SNCR [Member]                
Public Utilities, Commitments And Contingencies [Line Items]                
Public utilities, proposed value per kilowatt effective January 1, 2018 (in dollars per kilowatt) | $ / kw 1,650   1,118          
Palo Verde Nuclear Generating Station Unit 3 [Member] | PNMR and PNM [Member]                
Public Utilities, Commitments And Contingencies [Line Items]                
Public utilities, number of megawatts nuclear generation (in megawatts)     134          
Palo Verde Nuclear Generating Station Unit 3 [Member] | PNMR and PNM [Member] | Clean Air Act, SNCR [Member]                
Public Utilities, Commitments And Contingencies [Line Items]                
Public utilities, number of megawatts nuclear generation (in megawatts) 134 134   134        
Public utilities, proposed value per kilowatt effective January 1, 2018 (in dollars per kilowatt) | $ / kw   2,500            
San Juan Generating Station Units 1 and 4 [Member] | Installation Costs Including Construction Management, Gross Receipts Taxes, AFUDC, and Other PNM Costs [Member] | Maximum [Member] | Public Service Company of New Mexico [Member] | Clean Air Act, SNCR [Member]                
Public Utilities, Commitments And Contingencies [Line Items]                
Estimated installation capital costs | $ $ 90.6 $ 82.0            
San Juan Generating Station Unit 4 [Member] | Public Service Company of New Mexico [Member] | Clean Air Act, SNCR [Member]                
Public Utilities, Commitments And Contingencies [Line Items]                
Public utilities, additional ownership to be obtained (in megawatts) 132 78 132 65 132 132 132  
San Juan Generating Station Unit 3 [Member] | Public Service Company of New Mexico [Member] | Clean Air Act, SNCR [Member]                
Public Utilities, Commitments And Contingencies [Line Items]                
Public utilities, ownership to be exchanged (in megawatts)   78