XML 102 R67.htm IDEA: XBRL DOCUMENT v3.19.3
Regulatory and Rate Matters - SJGS Abandonment Application (Details) - San Juan Generating Station - PNM
$ in Millions
Jul. 01, 2019
USD ($)
scenario
MW
Public Utilities, General Disclosures [Line Items]  
Number of megawatts in natural gas-fired peaking plant (in megawatts) | MW 280
Number of megawatts in battery storage facilities (in megawatts) | MW 70
Solar generation capacity (in megawatts) | MW 350
Number of megawatts in battery storage facilities, replacement resource scenario (in megawatts) | MW 60
Number of replacement resource scenarios | scenario 3
Request issuance of energy transition bonds $ 361.0
Forecasted undepreciated investment 283.0
Plant decommissioning and coal mine reclamation costs 28.6
Upfront financing costs 9.6
Severance costs 20.0
Proceeds from securitization bonds $ 19.8