XML 128 R107.htm IDEA: XBRL DOCUMENT v3.22.0.1
Construction Program and Jointly-Owned Electric Generating Plants (Details)
$ in Thousands
12 Months Ended
Dec. 31, 2021
USD ($)
generating_unit
Dec. 31, 2020
USD ($)
Dec. 31, 2019
USD ($)
Jointly Owned Utility Plant Interests [Line Items]      
Construction expenditures $ 935,016 $ 679,028 $ 616,273
Plant in Service 9,357,849 8,480,799  
Accumulated Depreciation 2,952,743 2,835,170  
Public Service Company of New Mexico      
Jointly Owned Utility Plant Interests [Line Items]      
Construction expenditures 602,180 335,055 341,847
Plant in Service 6,602,015 6,022,753  
Accumulated Depreciation 2,235,068 2,158,915  
Texas-New Mexico Power Company      
Jointly Owned Utility Plant Interests [Line Items]      
Construction expenditures 311,909 321,505 $ 254,006
Plant in Service 2,475,859 2,193,270  
Accumulated Depreciation 563,004 $ 537,707  
Joint Projects | Public Service Company of New Mexico      
Jointly Owned Utility Plant Interests [Line Items]      
Construction expenditures 602,200    
Joint Projects | Texas-New Mexico Power Company      
Jointly Owned Utility Plant Interests [Line Items]      
Construction expenditures 311,900    
Joint Projects | PNMR      
Jointly Owned Utility Plant Interests [Line Items]      
Construction expenditures $ 935,000    
SJGS (Coal) | Unit 4 | Other Unrelated Entities 2      
Jointly Owned Utility Plant Interests [Line Items]      
Jointly owned utility plant, ownership percentage 12.80%    
SJGS (Coal) | Unit 4 | Other Unrelated Entities 3      
Jointly Owned Utility Plant Interests [Line Items]      
Jointly owned utility plant, ownership percentage 8.475%    
SJGS (Coal) | Unit 4 | Other Unrelated Entities 4      
Jointly Owned Utility Plant Interests [Line Items]      
Jointly owned utility plant, ownership percentage 7.20%    
SJGS (Coal) | Unit 4 | Other Unrelated Entities 5      
Jointly Owned Utility Plant Interests [Line Items]      
Jointly owned utility plant, ownership percentage 7.028%    
SJGS (Coal) | Public Service Company of New Mexico      
Jointly Owned Utility Plant Interests [Line Items]      
Plant in Service $ 815,361    
Accumulated Depreciation 455,159    
Construction Work in Progress $ 10    
Composite Interest 66.35%    
SJGS (Coal) | Public Service Company of New Mexico | Unit 4      
Jointly Owned Utility Plant Interests [Line Items]      
Composite Interest 77.297%    
Palo Verde Nuclear Generating Station | Public Service Company of New Mexico      
Jointly Owned Utility Plant Interests [Line Items]      
Plant in Service $ 869,363    
Accumulated Depreciation 403,764    
Construction Work in Progress $ 38,770    
Composite Interest 10.20%    
Number of units (in generating units) | generating_unit 3    
Period of time for the original full power operating licenses 40 years    
Operating lease, option term extensions 20 years    
Four Corners Units 4 and 5 (Coal) | Public Service Company of New Mexico      
Jointly Owned Utility Plant Interests [Line Items]      
Plant in Service $ 316,033    
Accumulated Depreciation 100,156    
Construction Work in Progress $ 6,294    
Composite Interest 13.00%    
Luna (Gas) | Public Service Company of New Mexico      
Jointly Owned Utility Plant Interests [Line Items]      
Plant in Service $ 80,159    
Accumulated Depreciation 31,244    
Construction Work in Progress $ 46    
Composite Interest 33.33%    
SJGS Units 1 and 2 | Other Unrelated Entities 1      
Jointly Owned Utility Plant Interests [Line Items]      
Composite Interest 50.00%    
SJGS Units 1 and 2 | Public Service Company of New Mexico      
Jointly Owned Utility Plant Interests [Line Items]      
Composite Interest 50.00%    
Four Corners | Public Service Company of New Mexico      
Jointly Owned Utility Plant Interests [Line Items]      
Number of units (in generating units) | generating_unit 2