Mine standby costs
12 Months Ended
Dec. 31, 2023
Analysis of income and expense [abstract]  
Mine standby costs
31. Mine standby costs
December 31, 2023December 31, 2022
Stratoni (1)
$11,507 $24,245 
Skouries (2)
— 7,782 
Other mine standby costs4,599 2,340 
$16,106 $34,367 
(1) Operations were suspended at Stratoni at the end of 2021 and the mine and plant were placed on care and maintenance during 2022.
(2) A decision was made in December 2022 to re-start the construction of Skouries, conditional upon the initial drawdown of the Term Facility (Note 16 (a)); Skouries is no longer considered to be on care and maintenance as at December 31, 2023.