OTHER ITEMS AND CHARGES
12 Months Ended
Dec. 31, 2023
Unusual or Infrequent Items, or Both [Abstract]  
OTHER ITEMS AND CHARGES OTHER ITEMS AND CHARGES
Legal Settlement
In fiscal year 2023, we recorded a charge of $6,150 accrued for in other accrued liabilities due to reaching an agreement at a mediation held on June 20, 2023 with the collective class members of a class action lawsuit relating to certain claims under the Fair Labor Standards Act of 1938 as well as state wage and hours laws. The settlement agreement was executed July 24, 2023 and has received court approval. See Note 13, Commitments and Contingencies for disclosure regarding our aggregate legal proceedings accrual.
Landfill Capping Charge - Veneer Failure
In fiscal year 2023, we recorded a charge of $3,870 consisting of both (i) the write-off of historical payments associated with capping work that has been deemed no longer viable due to a veneer failure and (ii) the related operating expenses incurred to clean up the affected capping material at the Ontario County Landfill that we operate. Engineering analysis is currently underway to determine root causes and responsibility for the event. See Note 10, Final Capping, Closure and Post-Closure Costs for disclosure over our remaining estimated costs associated with obligations for final capping closure and post-closure of our landfills.
Southbridge Landfill Closure Charge, Net
In the fiscal year ended December 31, 2017, we initiated a plan to cease operations of the Town of Southbridge, Massachusetts landfill (“Southbridge Landfill”) and later closed it in November 2018 when Southbridge Landfill reached its final capacity. Accordingly, in fiscal years 2023, 2022 and 2021, we recorded charges associated with the closure of the Southbridge Landfill as follows:
 Fiscal Year Ended
December 31,
 202320222021
Legal and transaction costs (1)
$412 $684 $868 
Contract settlement charge (2)
— — 572 
Landfill closure project charge (credit) (3)
55 752 (944)
Southbridge Landfill closure charge, net$467 $1,436 $496 
(1)We incurred legal costs as well as other transaction costs associated with various matters as part of the Southbridge Landfill closure.
(2)We updated the cost estimates associated with a contract settlement charge associated with the Southbridge Landfill closure and the remaining future obligations due to the Town of Southbridge under the landfill operating agreement with the Town of Southbridge.
(3)We recorded a landfill closure project charge (credit) each fiscal year associated with revised costs under the closure plan at Southbridge Landfill.
Expense from Acquisition Activities
In the fiscal years 2023, 2022 and 2021, we recognized expenses of $15,038, $4,613 and $5,304, respectively, comprised primarily of legal, consulting and other similar costs associated with the due diligence, acquisition and integration of acquired businesses, including the GFL Acquisition and the Twin Bridges Acquisition, in fiscal year 2023, or select development projects. See Note 5, Business Combinations for disclosure regarding acquisition activity.
Environmental Remediation Charge
In fiscal year 2022, we recorded a charge of $759 associated with the investigation of potential remediation at an inactive waste disposal site that adjoins one of the landfills we operate. In fiscal year 2021, we recorded a charge of $924 associated with a settlement agreement to conduct restoration of a stream bed on lands adjoining one of our landfills. See Note 13, Commitments and Contingencies for disclosure regarding environmental remediation liabilities.