XML 33 R17.htm IDEA: XBRL DOCUMENT  v2.3.0.11
Commitments and Contingencies
6 Months Ended
Jun. 30, 2011
Commitments and Contingencies  
Commitments and Contingencies
13. COMMITMENTS AND CONTINGENCIES

American Centrifuge Plant

Project Funding

USEC needs significant additional financing in order to complete the American Centrifuge Plant ("ACP"). USEC believes a loan guarantee under the DOE Loan Guarantee Program, which was established by the Energy Policy Act of 2005, is essential to obtaining the funding needed to complete the ACP. In July 2008, USEC applied under the DOE Loan Guarantee Program for $2 billion in U.S. government guaranteed debt financing for the ACP.  In August 2009, DOE and USEC announced an agreement to delay a final review of USEC's loan guarantee application to provide additional time to address technical and financial concerns raised by DOE. In the following months, USEC focused on addressing DOE's concerns and, based on its progress in reducing program risks, submitted a comprehensive update to its application in July 2010. USEC has been working with DOE since October 2010 on the terms for a conditional commitment for a $2 billion loan guarantee. In April 2011, the DOE Loan Guarantee Program Office substantially completed the due diligence and negotiation stage of the application process, including a draft term sheet, and advanced the ACP application to the next phase for review in parallel by DOE's credit group and by the Office of Management and Budget ("OMB"), the Department of the Treasury and the National Economic Council ("NEC"). This review includes the establishment of an estimated range of credit subsidy cost. As discussed below, on June 30, 2011, USEC entered into a standstill agreement with Toshiba Corporation ("Toshiba") and Babcock & Wilcox Investment Company ("B&W") through August 15, 2011, to provide an additional limited period of time to complete this review process and obtain a decision from DOE on the conditional commitment. DOE has recently indicated that it believes that USEC needs to further improve its financial and project execution depth to achieve a manageable credit subsidy cost estimate and to proceed with the DOE loan guarantee. USEC is working with DOE and DOE's advisors on reviewing structuring options to address DOE's remaining concerns in order to move forward on the American Centrifuge Project and to obtain a conditional commitment and DOE loan guarantee. In addition, USEC has retained financial and other advisors to assist USEC in this review of structuring options and in reviewing and pursuing strategic alternatives.

In May 2010, Toshiba and B&W signed a securities purchase agreement to make a $200 million investment in USEC. Under the terms of the agreement, Toshiba and B&W will each invest $100 million over three phases, each of which is subject to specific closing conditions. In September 2010, the first closing of $75 million occurred. The second closing of the strategic investment by Toshiba and B&W of $50 million is conditioned on USEC having entered into a conditional commitment in an amount of not less than $2 billion for the American Centrifuge project with DOE. The securities purchase agreement provides that if the second closing did not occur by June 30, 2011, the agreement may be terminated by USEC or each of the investors (as to such investor's obligations). USEC did not receive a conditional commitment from DOE by June 30th and therefore did not close on the second phase of the strategic investment by that date. On June 30, 2011, USEC entered into a standstill agreement with Toshiba and B&W whereby each of the parties agreed not to exercise its right to terminate prior to August 15, 2011.

USEC is continuing discussions with Toshiba and B&W with respect to the status and timing of the DOE loan guarantee process and its impact on closing of the next phase of the Toshiba and B&W investment and on the current standstill agreement. However, USEC has no assurance that a structuring option to address DOE's remaining concerns or a strategic alternative transaction will be achieved or the timing thereof, that any extension or other modifications to the standstill agreement will be agreed, that the terms USEC has negotiated with the DOE Loan Guarantee Program Office will be approved or that the credit subsidy cost will be reasonable. After obtaining a conditional commitment, USEC will need to conclude final documentation and satisfy any technical, financial and other conditions to funding in order to close on financing. Funding under a DOE loan guarantee will only occur following conditional commitment, final documentation and satisfaction of conditions to funding, which are subject to uncertainty.

To complete the project, USEC will require additional capital beyond the $2 billion DOE loan guarantee, proceeds from the $200 million investment from Toshiba and B&W and internally generated cash flow.

USEC also continues discussions with Japanese export credit agencies regarding financing $1 billion of the cost of completing the ACP. However, USEC has no assurance that it will be successful in obtaining any or all of the financing it is seeking or that it will not need additional capital.

Milestones under the 2002 DOE-USEC Agreement

In 2002, USEC and DOE signed an agreement (such agreement, as amended, the "2002 DOE-USEC Agreement") in which USEC and DOE made long-term commitments directed at resolving issues related to the stability and security of the domestic uranium enrichment industry. The 2002 DOE-USEC Agreement contains specific project milestones relating to the ACP. In February 2011, USEC and DOE amended the 2002 DOE-USEC Agreement to revise the remaining four milestones relating to the financing and operation of the ACP. The amendment extended by one year to November 2011 the financing milestone that required that USEC secure firm financing commitment(s) for the construction of the commercial American Centrifuge Plant with an annual capacity of approximately 3.5 million SWU per year. The remaining three milestones were also adjusted by the February 2011 amendment. In addition, DOE and USEC agreed to discuss adjustment of the remaining three milestones as may be appropriate based on a revised deployment plan to be submitted to DOE by USEC by January 30, 2012 following the completion of the November 2011 financing milestone. In the February 2011 amendment to the 2002 DOE-USEC Agreement, DOE and USEC re-iterated their acknowledgment that USEC's obligations with respect to the ACP milestones under the 2002 DOE-USEC Agreement are not dependent on the issuance by DOE of a loan guarantee to USEC. However, USEC communicated to DOE that its ability to meet the remaining milestones is dependent on its obtaining a timely commitment and funding for a loan guarantee from DOE. USEC will also need additional financing commitments beyond a DOE loan guarantee to meet the November 2011 financing milestone.

The 2002 DOE-USEC Agreement provides DOE with specific remedies if USEC fails to meet a milestone that would materially impact USEC's ability to begin commercial operations of the American Centrifuge Plant on schedule and such delay was within USEC's control or was due to USEC's fault or negligence. These remedies could include terminating the 2002 DOE-USEC Agreement, revoking USEC's access to DOE's U.S. centrifuge technology that USEC requires for the success of the American Centrifuge project and requiring USEC to transfer certain of its rights in the American Centrifuge technology and facilities to DOE, and to reimburse DOE for certain costs associated with the American Centrifuge project. DOE could also recommend that USEC be removed as the sole U.S. Executive Agent under the nonproliferation program between the United States and the Russian Federation known as "Megatons to Megawatts". As the U.S. Executive Agent, USEC signed a commercial agreement ("Russian Contract") in 1994 with a Russian government entity known as Techsnabexport ("TENEX") to implement the program. USEC currently purchases about one-half of its SWU supply from Russia under the Russian Contract. The 20-year Russian Contract expires at the end of 2013. Under the terms of a 1997 memorandum of agreement between USEC and the U.S. government, USEC can be terminated, or resign as the U.S. Executive Agent, or one or more additional executive agents may be named. If USEC were removed as the sole U.S. Executive Agent, it could reduce or terminate USEC's access to Russian LEU under the Megatons to Megawatts program in future years. However, under the 1997 memorandum of agreement, USEC has the right and obligation to pay for and take delivery of LEU that is to be delivered in the year of the date of termination and in the following year if USEC and TENEX have agreed on a price and quantity. Any of these remedies under the 2002 DOE-USEC Agreement could have a material adverse impact on USEC's business.

The 2002 DOE-USEC Agreement provides that if a delaying event beyond the control and without the fault or negligence of USEC occurs which would affect USEC's ability to meet an ACP milestone, DOE and USEC will jointly meet to discuss in good faith possible adjustments to the milestones as appropriate to accommodate the delaying event.

USEC's right to continue operating the Paducah GDP under its lease with DOE is not subject to meeting the ACP milestones. In addition, the new Russian Supply Agreement described below is not subject to any of the remedies related to the ACP under the 2002 DOE-USEC Agreement.
 
Russian Supply Agreement

On March 23, 2011, USEC signed a new multi-year contract with TENEX for the 10-year supply of Russian LEU beginning in 2013.  Under the terms of the new contract, the supply of LEU to USEC will begin in 2013 and increase until it reaches a level in 2015 that includes a quantity of SWU equal to approximately one-half the level currently supplied by TENEX to USEC under the Megatons to Megawatts program. TENEX and USEC also may mutually agree to increase the purchases and sales of SWU by certain additional optional quantities of SWU up to an amount beginning in 2015 equal to the amount USEC now purchases each year under the Megatons to Megawatts program. Unlike the Megatons to Megawatts program, the quantities supplied under the new contract will come from Russia's commercial enrichment activities rather than from downblending of excess Russian weapons material. As this new agreement is separate from the Megatons to Megawatts program, remedies provided to DOE under the 2002 DOE-USEC Agreement related to USEC's role under the Megatons to Megawatts program do not apply to the new purchase agreement.  However, the LEU USEC obtains from TENEX under the new agreement will be subject to quotas and other restrictions applicable to commercial Russian LEU that do not apply to LEU supplied to USEC under the Megatons to Megawatts program.

Deliveries under the new supply contract are expected to continue through 2022.  USEC will purchase the SWU component of the LEU and deliver natural uranium to TENEX for the LEU's uranium component.  The pricing terms for SWU under the contract are based on a mix of market-related price points and other factors. 

The new supply contract between TENEX and USEC was approved by the Russian State Atomic Energy Corporation ("Rosatom") on May 11, 2011.  The effectiveness of the new contract is subject to completion of administrative arrangements between the U.S. and Russian governments under the agreement for cooperation in nuclear energy between the United States and the Russian Federation which, among other things, provides the framework for the return to Russia of natural uranium delivered by USEC to TENEX. 

Legal Matters

USEC is subject to various legal proceedings and claims, either asserted or unasserted, which arise in the ordinary course of business. While the outcome of these claims cannot be predicted with certainty, USEC does not believe that the outcome of any of these legal matters will have a material adverse effect on its results of operations or financial condition.

        In June 2011, a complaint was filed in Federal court against USEC by a current Portsmouth GDP employee claiming that USEC owes or will owe severance benefits to him and other similarly situated employees that have transitioned or will transition to the DOE decommissioning and decontamination contractor.  USEC believes it has meritorious defenses against the suit and has not accrued any amounts for this matter. An estimate of the possible loss or range of loss from the litigation cannot be made because, among other things, (i) the plaintiff has failed to state the amount of damages sought, (ii) the plaintiff purports to represent a class of claimants the size and composition of which remains unknown and (iii) the certification of the class is uncertain. As disclosed in its Annual Report on Form 10-K for the year ended December 31, 2010,  USEC's severance liability could have been up to $25 million if severance was required to be paid to all employees ceasing employment with USEC as a result of the transition to the DOE D&D contractor.  In such an event, DOE would have owed a portion of this amount, estimated at $18.5 million.  As employees have transitioned or are currently expected to transition, the potential severance liability associated with the transition of services at the Portsmouth site is currently estimated to be less than $2 million, but due to continued uncertainty no costs have been accrued for severance liability as of June 30, 2011. This $2 million estimate is an estimate of potential severance liability associated with the transition of services at the Portsmouth site and is not an estimate of the possible loss or range of loss from the litigation which cannot be made at this time for the reasons listed above.