Commitments and Contingencies
3 Months Ended
Mar. 31, 2012
Commitments and Contingencies  
Commitments and Contingencies
12. COMMITMENTS AND CONTINGENCIES

American Centrifuge Plant

Project Funding

USEC needs significant additional financing in order to complete the American Centrifuge Plant ("ACP"). USEC believes a loan guarantee under the DOE Loan Guarantee Program, which was established by the Energy Policy Act of 2005, is essential to obtaining the funding needed to complete the ACP. In July 2008, USEC applied under the DOE Loan Guarantee Program for $2 billion in U.S. government guaranteed debt financing for the ACP.  Instead of moving forward with a conditional commitment for a loan guarantee, in the fall of 2011, DOE proposed a two-year cost share research, development and demonstration ("RD&D") program for the project to enhance the technical and financial readiness of the centrifuge technology for commercialization. Under the cost-sharing arrangement, DOE's total contribution would be capped at $300 million. DOE indicated that USEC's application for a DOE loan guarantee would remain pending during the RD&D program. In the first quarter of 2012, USEC's American Centrifuge project efforts focused on the planning and implementation of the RD&D program and efforts that are currently underway in Piketon, Ohio and Oak Ridge, Tennessee are based upon the proposed program scope. USEC is currently building machines and parts that would be part of the complete demonstration cascade that would be built and operated as part of the RD&D program. In parallel, USEC has been working with DOE and Congress to secure funding for the RD&D program. However, DOE's share of funding for the program has not yet been provided and the source for such funding is uncertain. Due to constraints on USEC's ability to continue to spend on the project, on March 13, 2012, USEC and DOE entered into an agreement that enables USEC to provide interim funding of $44 million. This funding was provided by DOE acquiring from USEC U.S. origin LEU in exchange for the transfer of quantities of USEC's depleted uranium ("tails") to DOE. This enables USEC to release encumbered funds of approximately $44 million that were previously provided as financial assurance for the disposition of such depleted uranium.  In consideration for accepting title to USEC's tails, USEC transferred to DOE title to LEU containing SWU of equal value.  This LEU acquired by DOE could be returned to USEC as part of DOE's cost share under the RD&D program if government funding is provided for the RD&D program in government fiscal year 2012.

USEC expects to continue funding project activities that support the RD&D program through May 31, 2012 as it continues to work with DOE and Congress on securing the government cost-share for the RD&D program.  Due to restrictions in USEC's credit facility, funding can only continue beyond May 31, 2012 if government funding for the RD&D program is secured. USEC continues to pursue both legislative and non-legislative paths to the federal cost share of the funding for the RD&D program for the balance of government fiscal year 2012. Funding for the RD&D program beyond government fiscal year 2012 would be subject to future appropriations. USEC has no assurance that it will be able to reach agreement with DOE regarding the RD&D program or that any funding will be provided or that the LEU will be returned. USEC also has no assurance that it will ultimately be able to obtain a loan guarantee and the timing thereof. Any agreement for the RD&D program would likely require restructuring of the project and of USEC's investment. In light of USEC's inability to obtain a conditional commitment for a DOE loan guarantee to date, and given the significant uncertainty surrounding USEC's prospects for finalizing an agreement and obtaining funding from DOE for the RD&D program and the timing thereof, USEC continues to evaluate its options concerning the American Centrifuge project. If USEC is unable to secure funding for the RD&D program beyond May 31, 2012, USEC would expect to begin demobilizing the project.

If conditions change and deployment becomes no longer probable or becomes delayed significantly from USEC's current expectations, USEC could expense up to the full amount of previously capitalized costs related to the ACP of up to $1.1 billion as early as the second quarter of 2012. Events that could impact USEC's views as to the probability of deployment or USEC's projections include a failure to successfully enter into an agreement with DOE for the RD&D program by May 31, 2012, or an unfavorable determination in any phase of the RD&D program regarding the restructuring of the project.

Milestones under the 2002 DOE-USEC Agreement

In 2002, USEC and DOE signed an agreement (such agreement, as amended, the "2002 DOE-USEC Agreement") in which USEC and DOE made long-term commitments directed at resolving issues related to the stability and security of the domestic uranium enrichment industry. The 2002 DOE-USEC Agreement contains specific project milestones relating to the ACP. Four milestones remain relating to the financing and operation of the ACP, including a November 2011 financing milestone that required that USEC secure firm financing commitment(s) for the construction of the commercial American Centrifuge Plant with an annual capacity of approximately 3.5 million SWU per year. Following the completion of the November 2011 financing milestone, USEC was to have submitted a revised deployment plan to DOE by January 30, 2012 as the basis for discussion of adjustment of the remaining three milestones. Due to DOE's deferral of a decision on the loan guarantee until after completion of the RD&D program, USEC did not meet the November 2011 financing milestone or submit a revised deployment plan to DOE.  In connection with discussions regarding the RD&D program described above, USEC has engaged in discussions with DOE regarding modification of the remaining milestones and other provisions of the 2002 DOE-USEC Agreement.  DOE has acknowledged that since DOE and USEC are working in good faith toward the RD&D program and the adjustment of the milestones in the 2002 DOE-USEC Agreement is currently a part of the proposed terms of the RD&D program, it does not see the need at the present time for USEC to present its position on the missed November 2011 milestone to DOE or to provide a revised deployment plan by the specified time.  However, USEC has no assurances that the RD&D program will move forward and/or that DOE will agree to an adjustment of the milestones or other provisions of the 2002 DOE-USEC Agreement. 

The 2002 DOE-USEC Agreement provides DOE with specific remedies if USEC fails to meet a milestone that would materially impact USEC's ability to begin commercial operations of the American Centrifuge Plant on schedule and such delay was within USEC's control or was due to USEC's fault or negligence. These remedies could include terminating the 2002 DOE-USEC Agreement, revoking USEC's access to DOE's U.S. centrifuge technology that USEC requires for the success of the American Centrifuge project and requiring USEC to transfer certain of its rights in the American Centrifuge technology and facilities to DOE, and to reimburse DOE for certain costs associated with the American Centrifuge project. DOE could also recommend that USEC be removed as the sole U.S. Executive Agent under the nonproliferation program between the United States and the Russian Federation known as "Megatons to Megawatts, " which could affect USEC's access to Russian LEU under the Megatons to Megawatts program in 2013.  Any of these remedies under the 2002 DOE-USEC Agreement could have a material adverse impact on USEC's business.

The 2002 DOE-USEC Agreement provides that if a delaying event beyond the control and without the fault or negligence of USEC occurs which would affect USEC's ability to meet an ACP milestone, DOE and USEC will jointly meet to discuss in good faith possible adjustments to the milestones as appropriate to accommodate the delaying event.

USEC's right to continue operating the Paducah GDP under its lease with DOE is not subject to meeting the ACP milestones. In addition, the new 10-year commercial supply agreement entered into on March 23, 2011 with TENEX is not subject to any of the remedies related to the ACP under the 2002 DOE-USEC Agreement.
 
Legal Matters

USEC is subject to various legal proceedings and claims, either asserted or unasserted, which arise in the ordinary course of business. While the outcome of these claims cannot be predicted with certainty, USEC does not believe that the outcome of any of these legal matters will have a material adverse effect on its results of operations, cash flows or financial condition.

On June 27, 2011, a complaint was filed in the United States District Court for the Southern District of Ohio, Eastern Division, against USEC by a former Portsmouth GDP employee claiming that USEC owes severance benefits to him and other similarly situated employees that have transitioned or will transition to the DOE decontamination and decommissioning ("D&D") contractor. The plaintiff amended its complaint on August 31, 2011 and February 10, 2012, among other things, to limit the purported class of similarly situated employees to salaried employees at the Portsmouth site who transitioned to the D&D contractor and are allegedly eligible for or owed benefits. USEC believes it has meritorious defenses against the suit and has not accrued any amounts for this matter. An estimate of the possible loss or range of loss from the litigation is difficult to make because, among other things, (i) the plaintiff has failed to state the amount of damages sought, (ii) the plaintiff purports to represent a class of claimants the size and composition of which remains unknown and (iii) the certification of the class is uncertain. However, USEC estimates that the total severance liability for the approximately 400 salaried employees at the Portsmouth site that transitioned to the DOE D&D contractor would have been approximately $14 million if severance was required to be paid to all of these employees. In such an event, DOE would have owed a portion of this amount, estimated at approximately $9 million, assuming DOE was responsible for periods both during which it operated the facility and under which USEC was a direct contractor to DOE.