Property, Plant and Equipment
6 Months Ended
Jun. 30, 2012
Property, Plant and Equipment  
Property, Plant and Equipment
4. PROPERTY, PLANT AND EQUIPMENT

A summary of changes in property, plant and equipment follows (in millions):

   
December 31,
2011
   
Capital Expenditures
(Depreciation)
   
Transfers
and
Retirements
   
June 30,
2012
 
Construction work in progress
  $ 1,111.2     $ 1.0     $ (47.0 )   $ 1,065.2  
Leasehold improvements                                          
    182.9       -       0.6       183.5  
Machinery and equipment
    251.2       0.9       (5.1 )     247.0  
      1,545.3       1.9       (51.5 )     1,495.7  
Accumulated depreciation and amortization
     (358.2 )     (13.8 )      6.9        (365.1 )
    $ 1,187.1     $ (11.9 )   $ (44.6 )   $ 1,130.6  

Capital expenditures include items in accounts payable and accrued liabilities at June 30, 2012 for which cash is paid in subsequent periods.

USEC is working to deploy the American Centrifuge technology at the American Centrifuge Plant ("ACP") in Piketon, Ohio. Capital expenditures related to the ACP, which are primarily included in the construction work in progress balance, totaled $1.1 billion at June 30, 2012 and December 31, 2011. Capitalized asset retirement obligations included in construction work in progress totaled $19.3 million at June 30, 2012 and December 31, 2011.

Instead of moving forward with a conditional commitment for a loan guarantee for the American Centrifuge project through the DOE Loan Guarantee Program, in the fall of 2011, DOE proposed a two-year cost share research, development and demonstration ("RD&D") program for the American Centrifuge project. Additional details are provided in Note 12 under "American Centrifuge Plant – Project Funding." As a result of the shift in focus of the American Centrifuge project, beginning in the fourth quarter of 2011, USEC began spending on the American Centrifuge technology at reduced levels with activities concentrating on development and demonstration. As a result, all project costs incurred since the fourth quarter of 2011 have been expensed, including interest expense that previously would have been capitalized. Capitalization of expenditures related to the ACP has ceased until commercial plant deployment resumes.

On June 12, 2012, USEC through its subsidiary entered into a contract with DOE to transfer to DOE title to the centrifuge machines and equipment produced or acquired under the RD&D program. The transferred property for research, development and demonstration activities include specified existing machines and equipment having a cost of $44.6 million that were transferred in the second quarter of 2012.

USEC believes that future cash flows from the ACP will exceed its capital investment. Since USEC believes its capital investment is fully recoverable, no impairment of the balance of capitalized costs is anticipated at this time. USEC will continue to evaluate this assessment as conditions change, including as a result of activities conducted as part of the RD&D program.