EX-99.1 2 d675939dex991.htm EX-99.1 EX-99.1

Exhibit 99.1

NI 43-101

Feasibility Study of the Rainy River Project,

Ontario, Canada

 

LOGO

Prepared for:

 

LOGO

Suite 1800, Two Bentall Centre

555 Burrard Street

Vancouver, BC

Report Date: February 14, 2014

Effective Date: January 16, 2014

3098007-AD0000-30-AET-0001-00

Colin Hardie, P. Eng., BBA Inc.

David Runnels, Eng., BBA Inc.

Patrice Live, Eng., BBA Inc.

Sheila E. Daniel, M.Sc., P. Geo, AMEC

David G. Ritchie, P. Eng., AMEC

Adam Coulson, PhD., P. Eng., AMEC

Glen Cole, P.Geo. SRK Consulting (Canada) Inc.

Dorota El-Rassi, P. Eng., SRK Consulting (Canada) Inc.

Colm Keogh, P. Eng., AMC Mining Consultants (Canada), Ltd.

Mo Molavi, P. Eng., AMC Mining Consultants (Canada), Ltd.

 

 

Prepared by:   In Collaboration with:    
LOGO          LOGO              LOGO   LOGO


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

DATE AND SIGNATURE PAGE

This Report is effective as of the 16th day of January 2014.

 

Original Signed

   

February 14, 2014

Colin Hardie, P.Eng.     Date
Department Manager, Mining and Metals    
BBA Inc.    

Original Signed

   

February 14, 2014

David Runnels, Eng.     Date
Project Manager, Mining and Metals    
BBA Inc.    

Original Signed

   

February 14, 2014

Patrice Live, Eng.     Date
Manager of Mining    
BBA Inc.    

Original Signed

   

February 14, 2014

Sheila E. Daniel, M.Sc., P.Geo.     Date
Head Environmental Management    
Senior Associate Geoscientist    
AMEC – Environment & Infrastructure    

Original Signed

   

February 14, 2014

David G. Ritchie, P.Eng.     Date
Geotechnical Engineering Group Manager    
Senior Associate Geotechnical Engineer    
AMEC – Environment & Infrastructure    

Original Signed

   

February 14, 2014

Adam Coulson, PhD., P.Eng.     Date
Rock Engineering Group Manager    
Senior Associate Rock Mechanics Engineer    
AMEC – Environment & Infrastructure    

Original Signed

   

February 14, 2014

Glen Cole, P.Geo.     Date
Principal Consultant (Resource Geology)    
SRK Consulting (Canada) Inc.    

 

 

i


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Original Signed

   

February 14, 2014

Dorota El-Rassi, P.Eng.     Date
Senior Consultant (Resource Geology)    
SRK Consulting (Canada) Inc.    

Original Signed

   

February 14, 2014

Colm Keogh, P.Eng.     Date
Principal Mining Engineer    
AMC Mining Consultants (Canada) Ltd.    

Original Signed

   

February 14, 2014

Mo Molavi, P.Eng.     Date
Principal Mining Engineer    
Mining Services Manager    
AMC Mining Consultants (Canada) Ltd.    

 

 

ii


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

CERTIFICATE OF QUALIFIED PERSON

This certificate applies to the technical report prepared for New Gold Inc. (“New Gold”) entitled: “Feasibility Study of the Rainy River Project, Ontario, Canada” signed on February 14, 2014 (the “Technical Report”) and effective January 16, 2014.

I, Colin Hardie, P. Eng., as a co-author of the Technical Report, do hereby certify that:

 

  1) I am currently employed as a Department Manager and Metallurgist in the consulting firm BBA Inc.:

630 René-Lévesque Boulevard West

Suite 1900

Montreal, Quebec H3B 4V5 Canada

 

  2) I graduated from the University of Toronto in 1996 with a BASc in Geological and Mineral Engineering. In 1999, I graduated from McGill University of Montreal with an M.Eng in Metallurgical Engineering and in 2008 obtained a Master of Business Administration (MBA) degree from the University of Montreal (HEC).

 

  3) I am a member in good standing of the Professional Engineers of Ontario (Member Number: 90512500) and of the Canadian Institute of Mining, Metallurgy, and Petroleum (Member Number: 140556). I have practiced my profession continuously since my graduation. I have been employed in mining operations, consulting engineering and applied metallurgical research for over 15 years;

 

  4) I visited the Rainy River Project site on June 16, 2011;

 

  5) I have read the definition of “qualified person” set out in the National Instrument 43-101 - Standards of Disclosure for Mineral Projects (“NI 43-101”) and certify that, by reason of my education, affiliation with a professional association, and past relevant work experience, I fulfill the requirements to be an independent qualified person for the purposes of NI 43-101;

 

  6) I am independent of the issuer as independence is described in Section 1.5 of NI 43-101;

 

  7) I am responsible for Sections 1, 2, 3, 4, 19, 21 (except 21.4.4, 21.4.5, 21.5.2, 21.5.5, 21.6.4, and 21.6.5), 22, 23, 25, 26, 27 and Appendices A and B of the Technical Report;

 

  8) I have had prior involvement with the subject property having co-authored a previous technical report entitled “Preliminary Economic Assessment of the Rainy River Gold Property” prepared by BBA in December 2011; the “Preliminary Economic Assessment Update of the Rainy River Gold Property” prepared by BBA in October 2012 and the “Feasibility Study of the Rainy River Gold Project” prepared by BBA in May 2013 and re- addressed to New Gold in July 2013;

 

  9) I have read NI 43-101 and the sections of the Technical Report under my responsibility have been prepared in compliance therewith; and

 

  10) That, as of the effective date of the Technical Report, to the best of my knowledge, information and belief, the sections of the Technical Report under my responsibility contain all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.

 

Montreal, Quebec      

Colin Hardie [“signed and sealed”]

  
February 14, 2014       Colin Hardie, P. Eng.   
      Department Manager –Mining and Metallurgy   

 

 

iii


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

CERTIFICATE OF QUALIFIED PERSON

This certificate applies to the technical report prepared for New Gold Inc. (“New Gold”) entitled: “Feasibility Study of the Rainy River Project, Ontario, Canada” signed on February 14, 2014 (the “Technical Report”) and effective January 16, 2014.

I, David Runnels, Eng., as a co-author of the Technical Report, do hereby certify that:

 

  1) I am the Project Manager – Mining and Metals with the firm BBA Inc. with an office at 630 René-Lévesque Blvd. West, Suite 1900, Montréal, Quebec, H3B 4V5 Canada;

 

  2) I am a graduate of the Queen’s University, Kingston Ontario, Canada with a B. Sc. In Metallurgy in 1971. I have practiced my profession continuously since my graduation from university;

 

  3) I am a registered member in good standing of the Order of Engineers of Québec (#22450) and I am a member of the Canadian Institute of Mining;

 

  4) I visited the Rainy River Project site on October 11, 2012;

 

  5) I have read the definition of “qualified person” set out in the NI 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”) and certify that, by reason of my education, affiliation with a professional association, and past relevant work experience, I fulfill the requirements to be an independent qualified person for the purposes of NI 43-101;

 

  6) I am independent of the issuer as independence is described in Section 1.5 of NI 43-101;

 

  7) I am responsible for Sections 13, 17, 18 (except 18.1.3, 18.8, 18.9 and 18.10), 24 and Appendix F of the Technical Report;

 

  8) I have had prior involvement with the subject property having co-authored a previous technical report entitled “Preliminary Economic Assessment of the Rainy River Gold Property” prepared by BBA in December 2011; the “Preliminary Economic Assessment Update of the Rainy River Gold Property” prepared by BBA in October 2012 and the “Feasibility Study of the Rainy River Gold Project” prepared by BBA in May 2013 and re- addressed to New Gold in July 2013;

 

  9) I have read NI 43-101 and the sections of the Technical Report I am responsible for and confirm that the sections under my responsibility in the Technical Report has been prepared in compliance therewith; and

 

  10) That, as of the effective date of the Technical Report, to the best of my knowledge, information and belief, the sections of the Technical Report under my responsibility contain all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.

 

Montreal, Quebec      

David Runnels [“signed and sealed”]

  
February 14, 2014       David Runnels, Eng.   
      Project Manager – Mining and Metals   

 

 

iv


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

CERTIFICATE OF QUALIFIED PERSON

This certificate applies to the technical report prepared for New Gold Inc. (“New Gold”) entitled: “Feasibility Study of the Rainy River Project, Ontario, Canada” signed on February 14, 2014 (the “Technical Report”) and effective January 16, 2014.

I, Patrice Live, Eng., as a co-author of the Technical Report, do hereby certify that:

 

  1) I am currently employed as Manager of Mining in the consulting firm BBA Inc.: 630 René-Lévesque Boulevard West, Suite 1900, Montreal, Quebec H3B 4V5 Canada;

 

  2) I graduated from the University of Laval (Québec City) in 1976 with a BASc in Mining Engineering. I have worked as a mining engineer continuously since my graduation from university;

 

  3) I am a member in good standing of the Order of Engineers of Québec (#38991) and I am a member of the Canadian Institute of Mining. Experience includes a full range of studies from: preliminary economic assessments, prefeasibility studies and feasibility studies, as well as due diligence audits and technical reviews, ore reserves estimation, mining methods, mine design and development, production scheduling and planning, equipment sizing, capital and operating cost estimates with cash flow models, and financial analysis;

 

  4) I visited the Rainy River Project site on October 11, 2012;

 

  5) I have read the definition of “qualified person” set out in the National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”) and certify that, by reason of my education, affiliation with a professional association, and past relevant work experience, I fulfill the requirements to be an independent qualified person for the purposes of NI 43-101;

 

  6) I am independent of the issuer as independence is described in Section 1.5 of NI 43-101;

 

  7) I am responsible for Sections 15 (except 15.3), 16 (except 16.2.1, 16.3, 16.4 and 16.5), 21.4.4, 21.4.5, 21.5.2 and 21.6.4 and contributed to Sections 1, 25 and 26 of the Technical Report;

 

  8) I have had prior involvement with the subject property having co-authored a previous technical report entitled “Preliminary Economic Assessment of the Rainy River Gold Property” prepared by BBA in December 2011; the “Preliminary Economic Assessment Update of the Rainy River Gold Property” prepared by BBA in October 2012 and the “Feasibility Study of the Rainy River Gold Project” prepared by BBA in May 2013 and re- addressed to New Gold in July 2013;

 

  9) I have read NI 43-101 and the sections of the Technical Report under my responsibility have been prepared in compliance therewith; and

 

  10) That, as of the effective date of the Technical Report, to the best of my knowledge, information and belief, the sections of the Technical Report under my responsibility contain all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.

 

Montreal, Quebec      

Patrice Live [“signed and sealed”]

  
February 14, 2013       Patrice Live, Eng.   
      Manager of Mining   

 

 

v


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

CERTIFICATE OF QUALIFIED PERSON

This certificate applies to the technical report prepared for New Gold Inc. (“New Gold”) entitled: “Feasibility Study of the Rainy River Project, Ontario, Canada” signed on February 14, 2014 (the “Technical Report”) and effective January 16, 2014.

I, Sheila Ellen Daniel, M.Sc., P.Geo. do hereby certify that:

 

  1) I am Head Environmental Management, Senior Associate Geoscientist, in the consulting firm:

AMEC Environment & Infrastructure, a Division of AMEC Americas Limited

160 Traders Blvd. East, Suite 110

Mississauga, ON

Canada L4Z 3K7;

 

  2) I graduated from McMaster University in 1990 with a M.Sc. and University of Western Ontario with a B.Sc. (Honours); I have practiced my profession for twenty-two years since my graduation from university;

 

  3) I am Professional Geoscientist in the Province of Ontario (Reg. # 0151);

 

  4) I visited the Rainy River Project site on May 19, 2011;

 

  5) I have read the definition of “qualified person” set out in the National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”) and certify that, by reason of my education, affiliation with a professional association, and past relevant work experience, I fulfill the requirements to be an independent qualified person for the purposes of NI 43-101;

 

  6) I am independent of the issuer as independence is described in Section 1.5 of NI 43-101;

 

  7) I am responsible for Section 20 and 18.10 and contributed to Sections 1, 25 and 26 of the Technical Report;

 

  8) I have had prior involvement with the subject property having co-authored a previous technical report entitled “Preliminary Economic Assessment of the Rainy River Gold Property” prepared by BBA in December 2011; the “Preliminary Economic Assessment Update of the Rainy River Gold Property” prepared by BBA in October 2012 and the “Feasibility Study of the Rainy River Gold Project” prepared by BBA in May 2013 and re- addressed to New Gold in July 2013;

 

  9) I have read NI 43-101 and confirm that the sections of the Technical Report under my responsibility have been prepared in compliance therewith; and

 

  10) That, as of the effective date of the Technical Report, to the best of my knowledge, information and belief, the sections of the Technical Report under my responsibility contain all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.

 

Mississauga, Ontario      

Sheila E. Daniel[“signed and sealed”]

  
February 14, 2014       Sheila E. Daniel, M.Sc., P. Geo.   
      Head Environmental Management   
      Senior Associate Geoscientist   

 

 

vi


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

CERTIFICATE OF QUALIFIED PERSON

This certificate applies to the technical report prepared for New Gold Inc. (“New Gold”) entitled: “Feasibility Study of the Rainy River Project, Ontario, Canada” signed on February 14, 2014 (the “Technical Report”) and effective January 16, 2014.

I, David G. Ritchie, P.Eng. do hereby certify that:

 

  1) I am a Senior Associate Geotechnical Engineer and Geotechnical Engineering Group Manager in the consulting firm:

AMEC Environment & Infrastructure, a Division of AMEC Americas Limited

160 Traders Blvd. East, Suite 110

Mississauga, ON L4Z 3K7

Canada

 

  2) I graduated from Ryerson Polytechnic University in 1995 with a B.Eng. in Civil Engineering and in 2000 from the University of Western Ontario with a M.Eng.

 

  3) I am Professional Engineer in the Province of Ontario (Reg. # 90488198). I have practiced my profession for eighteen years since my graduation from university;

 

  4) I visited the Rainy River Project site on September 4, 2013;

 

  5) I have read the definition of “qualified person” set out in the National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”) and certify that, by reason of my education, affiliation with a professional association, and past relevant work experience, I fulfill the requirements to be an independent qualified person for the purposes of NI 43-101;

 

  6) I am independent of the issuer as independence is described in Section 1.5 of NI 43-101;

 

  7) I am responsible for Sections 16.2.1.2, 18.1.3, 18.8 and 18.9 and contributed to Sections 1, 25 and 26 of the Technical Report;

 

  8) I have had prior involvement with the subject property having co-authored a previous technical report entitled “Preliminary Economic Assessment of the Rainy River Gold Property” prepared by BBA in December 2011; the “Preliminary Economic Assessment Update of the Rainy River Gold Property” prepared by BBA in October 2012 and the “Feasibility Study of the Rainy River Gold Project” prepared by BBA in May 2013 and re-addressed to New Gold in July 2013;

 

  9) I have read NI 43-101 and the parts of the Technical Report under my responsibility have been prepared in compliance therewith; and

 

  10) That, as of the date of the Technical Report, to the best of my knowledge, information and belief, the sections of the Technical Report under my responsibility contain all scientific and technical information that is required to be disclosed to make the technical report not misleading.

 

Mississauga, Ontario     

David G. Ritchie [“signed and sealed”]

  
February 14, 2014      David G. Ritchie, P. Eng.   
     Geotechnical Engineering Group Manager   
     Senior Associate Geotechnical Engineer   

 

 

vii


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

CERTIFICATE OF QUALIFIED PERSON

This certificate applies to the technical report prepared for New Gold Inc. (“New Gold”) entitled: “Feasibility Study of the Rainy River Project, Ontario, Canada” signed on February 14, 2014 (the “Technical Report”) and effective January 16, 2014.

I, Adam Coulson, Ph.D., P. Eng., as a co-author of the Technical Report, do hereby certify that:

 

  1) I am currently employed as a Senior Associate Rock Mechanics Engineer in the consulting firm AMEC Earth & Infrastructure, a division of AMEC Americas Ltd.:

160 Traders Blvd. E.,

Suite 110

Mississauga, Ontario L4Z 3K7 Canada

 

  2) I graduated with a B.Eng, from Camborne School of Mines, UK in 1990; obtained a MSc. (Eng) from Queens University, Canada in 1996; and a Ph.D. from the University of Toronto, Canada in 2009;

 

  3) I am a member in good standing of the Professional Engineers of Ontario (Member No. 100049242) and of the Canadian Institute of Mining, Metallurgy, and Petroleum (Member No. 146473). I have practiced my profession continuously since my graduation. I have been employed in mining operations, consulting engineering and rock mechanics research for over 22 years;

 

  4) I visited the Rainy River Project site on September 25 to 27, 2013;

 

  5) I have read the definition of “qualified person” set out in the NI 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”) and certify that, by reason of my education, affiliation with a professional association, and past relevant work experience, I fulfill the requirements to be an independent qualified person for the purposes of NI 43-101;

 

  6) I am independent of the issuer as independence is described in Section 1.5 of NI 43-101;

 

  7) I am responsible for Sections 16.2.1.1 and 16.3.6 and contributed to Sections 1, 25 and 26 of the Technical Report;

 

  8) I have had prior involvement with the subject property having co-authored a previous technical report entitled “Feasibility Study of the Rainy River Gold Project” prepared by BBA in May 2013 and re-addressed to New Gold in July 2013;

 

  9) I have read NI 43-101 and the sections of the Technical Report under my responsibility have been prepared in compliance therewith; and

 

  10) That, as of the effective date of the Technical Report, to the best of my knowledge, information and belief, the sections of the Technical Report under my responsibility contain all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.

 

Mississauga, Ontario     

Adam Coulson [“signed and sealed”]

  
February 14, 2014      Adam Coulson, Ph.D., P.Eng.   
     Rock Engineering Group Manager   
     Senior Associate Rock Mechanics Engineer (AMEC)   

 

 

viii


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

CERTIFICATE OF QUALIFIED PERSON

This certificate applies to the technical report prepared for New Gold Inc. (“New Gold”) entitled: “Feasibility Study of the Rainy River Project, Ontario, Canada” signed on February 14, 2014 (the “Technical Report”) and effective January 16, 2014.

I, Glen Cole residing at 15 Langmaid Court, Whitby, Ontario do hereby certify that:

 

  1) I am a Principal Consultant (Resource Geology) with the firm of SRK Consulting (Canada) Inc. (SRK) with an office at Suite 1300, 151 Yonge Street, Toronto, Ontario, Canada;

 

  2) I am a graduate of the University of Cape Town in South Africa with a B.Sc (Hons) in Geology in 1983; I obtained an M.Sc (Geology) from the University of Johannesburg in South Africa in 1995 and an M.Eng in Mineral Economics from the University of the Witwatersrand in South Africa in 1999. I have practiced my profession continuously since 1986. Since 2006, I have estimated and audited mineral resources for a variety of early and advanced base and precious metals projects in Africa, Canada, Chile and Mexico. Between 1989 and 2005 I have worked for Goldfields Ltd at several underground and open pit mining operations in Africa and held positions of Mineral Resources Manager, Chief Mine Geologist and Chief Evaluation Geologist, with the responsibility for estimation of mineral resources and mineral reserves for development projects and operating mines;

 

  3) I am a Professional Geoscientist registered with the Association of Professional Geoscientists of the Province of Ontario (APGO#1416) and am also registered as a Professional Natural Scientist with the South African Council for Scientific Professions (Reg#400070/02);

 

  4) I have personally inspected the Rainy River Project site and surrounding areas on a few occasions, most recently from April 30 to May 2, 2013;

 

  5) I have read the definition of “qualified person” set out in National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”) and certify that by virtue of my education, affiliation to a professional association and past relevant work experience, I fulfill the requirements to be a “qualified person” for the purposes of NI 43- 101;

 

  6) I am independent of the issuer as independence is described in Section 1.5 of NI 43-101;

 

  7) I am responsible for sections 5, 6, 7, 8, 9, 10, 11, 12 and Appendices C to E and contributed to Sections 1, 25 and 26 of the Technical Report;

 

  8) I have had prior involvement with the subject property having co-authored previous technical reports prepared by SRK in April 2009, April 2011 and April 9, 2012 (amended June 4, 2012) and a mineral resource model in February 2010. I also contributed to a technical report entitled: “Preliminary Economic Assessment of the Rainy River Gold Property” prepared by BBA in December 2011; the “Preliminary Economic Assessment Update of the Rainy River Gold Property” prepared by BBA in October 2012 and the “Feasibility Study of the Rainy River Gold Project” prepared by BBA in May 2013 and re-addressed to New Gold in July 2013;

 

  9) I have read NI 43-101 and the sections of the Technical Report under my responsibility have been prepared in compliance therewith; and

 

  10) That, as of the effective date of the Technical Report, to the best of my knowledge, information and belief, the sections of the Technical Report for which I am responsible for contain all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.

 

Toronto Ontario,     

Glen Cole [“signed and sealed”]

  
February 14, 2014      Glen Cole, P.Geo. P.Eng.   
     Principal Resource Geologist   

 

 

ix


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

CERTIFICATE OF QUALIFIED PERSON

This certificate applies to the technical report prepared for New Gold Inc. (“New Gold”) entitled: “Feasibility Study of the Rainy River Project, Ontario, Canada” signed on February 14, 2014 (the “Technical Report”) and effective January 16, 2014.

I, Dorota El-Rassi, residing at 70 Portsdown Road, Scarborough, Ontario do hereby certify that:

 

  1) I am a Senior Consultant (Resource Geology) with the firm of SRK Consulting (Canada) Inc. with an office at Suite 1300, 151 Yonge Street, Toronto, Ontario, Canada;

 

  2) I am a graduate of the University of Toronto with a BA.Sc (Hons) in 1997 and a MSc. in Geology in 2000. I have practiced my profession continuously since 1997. I have over 10 years’ experience in mineral exploration, resource estimation and consulting. Prior to joining SRK, I worked for Watts, Griffis and McOuat as a resource geologist. As a Resource Engineer, I estimated and audited projects in North America, South America, Asia and Africa. My experience includes gold, silver, copper, nickel, zinc, PGE and industrial mineral deposits. Areas of expertise are resource estimation, geological modelling and exploration project management;

 

  3) I am a Professional Engineer registered with the Association of Professional Engineers of the province of Ontario (Licence: 100012348) and a fellow with the Geological Association of Canada;

 

  4) I have not personally visited the Rainy River Project site but relied on a site visit completed by Mr. Glen Cole, P.Geo, a co-author of the Technical Report;

 

  5) I have read the definition of “qualified person” set out in National Instrument 43-101- Standards of Disclosure for Mineral Projects (“NI 43-101”) and certify that by virtue of my education, affiliation to a professional association and past relevant work experience, I fulfill the requirements to be a “qualified person” for the purposes of NI 43- 101;

 

  6) I am independent of the issuer as independence is described in Section 1.5 of NI 43-101;

 

  7) I contributed towards Section 14 of the Technical Report and I accept professional responsibility that section of the Technical Report;

 

  8) I have had prior involvement with the subject property having co-authored a previous technical reports prepared by SRK in April 2009, April 2011 and April 9, 2012 (amended June 4, 2012) and a mineral resource model in February 2010. I contributed to a previous technical report entitled “Preliminary Economic Assessment of the Rainy River Gold Property” prepared by BBA in December 2011; and the “Preliminary Economic Assessment Update of the Rainy River Gold Property” prepared by BBA in October 2012 and the “Feasibility Study of the Rainy River Gold Project” prepared by BBA in May 2013 and re-addressed to New Gold in July 2013;

 

  9) I have read NI 43-101 and the section of the Technical Report I am responsible for and confirm that the Technical Report has been prepared in compliance therewith; and

 

  10) That, as of the effective date of the Technical Report, to the best of my knowledge, information and belief, the section of the Technical Report under my responsibility contains all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.

 

Toronto, Ontario     

Dorota El-Rassi [“signed and sealed”]

  
February 14, 2014      Dorota El-Rassi, P.Eng. (# 100012348)   
     Senior Resource Geologist   

 

 

x


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

CERTIFICATE OF QUALIFIED PERSON

This certificate applies to the technical report prepared for New Gold Inc. (“New Gold”) entitled: “Feasibility Study of the Rainy River Project, Ontario, Canada” signed on February 14, 2014 (the “Technical Report”) and effective January 16, 2014.

I, Colm Keogh, P. Eng., as a co-author of the Technical Report, do hereby certify that:

 

  1) I am currently employed as a Principal Mining Engineer in the consulting firm AMC Mining Consultants (Canada) Inc. with a business address at Suite 202, 200 Granville Street, Vancouver, British Columbia, V6C 1S4.

 

  2) I graduated with a Bachelor of Applied Science degree (Mining) from the University of British Columbia in Vancouver, British Columbia in 1988;

 

  3) I am a chartered member of the Association of Professional Engineers and Geoscientists of British Columbia. I have practiced my profession continuously since 1988 in a range of operational, technical and consulting roles;

 

  4) I visited the Rainy River Project site on September 26, 2013;

 

  5) I have read the definition of “qualified person” set out in the National Instrument 43-101—Standards of Disclosure for Mineral Projects (“NI 43-101”) and certify that, by reason of my education, affiliation with a professional association, and past relevant work experience, I fulfill the requirements to be an independent qualified person for the purposes of NI 43-101;

 

  6) I am independent of the issuer as independence is described in Section 1.5 of NI 43-101;

 

  7) I am responsible for Sections 15.3, 16.3 (except 16.3.6), 21.5.5 and 21.6.5 and contributed to sections 1.15.2, 1.15.3, 1.16.4, 1.16.5, 25.5, 26 and 26.2 of the Technical Report;

 

  8) I have no prior involvement with the Property that is the subject of the Technical Report;

 

  9) I have read NI 43-101 and the sections of the Technical Report under my responsibility have been prepared in compliance therewith; and

 

  10) That, as of the effective date of the Technical Report, to the best of my knowledge, information and belief, the sections of the Technical Report under my responsibility contain all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.

 

Vancouver,     

Colm Keogh [signed and sealed]

  
British Columbia      Colm Keogh, P. Eng.   
February 14, 2014      Principal Mining Engineer   
     AMC Mining Consultants (Canada) Ltd   

 

 

xi


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

CERTIFICATE OF QUALIFIED PERSON

This certificate applies to the technical report prepared for New Gold Inc. (“New Gold”) entitled: “Feasibility Study of the Rainy River Project, Ontario, Canada” signed on February 14, 2014 (the “Technical Report”) and effective January 16, 2014.

I, Mo Molavi, P. Eng., as a co-author of the Technical Report, do hereby certify that:

 

  1) I am a Principal Mining Engineer with AMC Mining Consultants (Canada) Ltd with a business address at Suite 202, 200 Granville Street, Vancouver, British Columbia, V6C 1S4.

 

  2) I am a graduate Laurentian University (B. Eng. in Mining Engineering, 1979) and McGill University (M. Eng. in Mining Engineering specializing in Rock Mechanics and Mining Methods, 1987).

 

  3) I am a member in good standing of the Association of Professional Engineers and Geoscientists of British Columbia, License #37594 and a member of the Canadian Institute of Mining, Metallurgy and Petroleum. I have worked as a Mining Engineer for a total of 34 years since my graduation from university and have relevant experience in project management, feasibility studies and technical report preparations for mining projects in North America. I am a “Qualified Person” for the purposes of National Instrument 43-101 (the “Instrument”).

 

  4) I did not complete a personal inspection of the Rainy River Project site but relied on a site visit completed by Mr. Colm Keogh, P.Eng., a co-author of the Technical Report;

 

  5) I have read the definition of “qualified person” set out in the National Instrument 43-101—Standards of Disclosure for Mineral Projects (“NI 43-101”) and certify that, by reason of my education, affiliation with a professional association, and past relevant work experience, I fulfill the requirements to be an independent qualified person for the purposes of NI 43-101;

 

  6) I am independent of the issuer as independence is described in Section 1.5 of NI 43-101;

 

  7) I am responsible for Sections 16.4 and 16.5 and contributed to section 1.16.3 of the Technical Report;

 

  8) I have no prior involvement with the Property that is the subject of the Technical Report.

 

  9) I have read NI 43-101 and the sections of the Technical Report under my responsibility have been prepared in compliance therewith; and

 

  10) That, as of the effective date of the Technical Report, to the best of my knowledge, information and belief, the sections of the Technical Report under my responsibility contain all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.

 

Vancouver,     

Mo Molavi [“signed and sealed”]

  
British Columbia      Mo Molavi, P. Eng.   
February 14, 2014      Principal Mining Engineer   
     Mining Services Manager   
     AMC Mining Consultants (Canada) Ltd   

 

 

 

xii


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

CAUTIONARY NOTE WITH RESPECT TO FORWARD LOOKING INFORMATION

Certain information and statements contained in this report are “forward looking” in nature. All information and statements in this report, other than statements of historical fact, that address events, results, outcomes or developments that New Gold and/or the Qualified Persons who authored this report expect to occur are “forward-looking statements”. Forward-looking statements are statements that are not historical facts and are generally, but not always, identified by the use of forward-looking terminology such as “plans”, “expects”, is “expected”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates”, “projects”, “potential”, “believes” or variations of such words and phrases or statements that certain actions, events or results “may”, “could”, “would”, “should”, “might” or will be “taken”, “occur” or “be achieved” or the negative connotation of such terms. Forward-looking statements include, but are not limited to, statements with respect to the economic and feasibility parameters of the Rainy River project: the cost and timing of the development of the project; the proposed mine plan and mining method, stripping ratio, processing method and rates and production rates; grades; projected metallurgical recovery rates; infrastructure, capital, operating and sustaining costs; the projected life of mine and other expected attributes of the Rainy River project; the NPV and IRR and payback period of capital; cash costs and all-in sustaining costs; the success and continuation of exploration activities; estimates of mineral reserves and resources; the future price of gold; the timing of the environmental assessment process; government regulations and permitting timelines; estimates of reclamation obligations that may be assumed; requirements for additional capital; environmental risks; and general business and economic conditions.

All forward-looking statements in this report are necessarily based on opinions and estimates made as of the date such statements are made and are subject to important risk factors and uncertainties, many of which cannot be controlled or predicted. Material assumptions regarding forward-looking statements are discussed in this report, where applicable. In addition to, and subject to, such specific assumptions discussed in more detail elsewhere in this report, the forward-looking statements in this report are subject to the following assumptions: (1) there being no signification disruptions affecting the development and operation of the project; (2) the exchange rate between the Canadian dollar and U.S. dollar being approximately consistent with current levels; (3) the availability of certain consumables and services and the prices for diesel, natural gas, fuel oil, electricity and other key supplies being approximately consistent with current levels; (4) labour and materials costs increasing on a basis consistent with current expectations; (5) permitting and arrangements with First Nations and other Aboriginal groups being consistent with current expectations; (6) that all environmental approvals, required permits, licenses and authorizations will be obtained from the relevant

 

 

xiii


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

governments and other relevant stakeholders within the expected timelines; (7) certain tax rates, including the allocation of certain tax attributes to the project; (8) the availability of financing for New Gold’s development activities; (9) the timelines for exploration and development activities on the project; and (10) assumptions made in mineral resource and reserve estimates, including geological interpretation grade, recovery rates, gold price assumption, and operational costs; and general business and economic conditions.

Forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements to be materially different from any of the future results, performance or achievements expressed or implied by forward-looking statements. These risks, uncertainties and other factors include, but are not limited to, the assumptions underlying the feasibility study and economic parameters discussed herein not being realized; decrease of future gold prices; cost of labour, supplies, fuel and equipment rising; actual results of current exploration; adverse changes in project parameters including discrepancies between actual and estimated production, reserves, resources and recoveries; exchange rate fluctuations; delays and costs inherent in consulting and accommodating rights of First Nations and other Aboriginal groups; title risks; regulatory risks, and political or economic developments in Canada; changes to tax rates; changes to New Afton’s mine plan or profitability or to New Gold’s asset profile that might alter the allocation of tax attributes to Rainy River; risks and uncertainties with respect to obtaining necessary permits and necessary surface rights, land use rights and other tenure from the Crown and private landowners or delays in obtaining same; risks associated with maintaining and renewing permits and complying with permitting requirements, including without limitation approval of the environmental assessment and receipt of all related permits, authorizations or other rights, including under the Endangered Species Act and Public Lands Act; and other risks involved in the gold exploration and development industry; as well as those risk factors discussed elsewhere in this report, in New Gold’s latest Annual Information Form, Management’s Discussion and Analysis and its other SEDAR filings from time to time. All forward-looking statements herein are qualified by this cautionary statement. Accordingly, readers should not place undue reliance on forward-looking statements. New Gold and the Qualified Persons who authored of this report undertake no obligation to update publicly or otherwise revise any forward-looking statements whether as a result of new information or future events or otherwise, except as may be required by law.

 

 

xiv


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

CAUTIONARY NOTE TO U.S. READERS CONCERNING ESTIMATES OF MINERAL RESERVES

AND MINERAL RESOURCES

Information concerning the Rainy River Project has been prepared in accordance with Canadian standards under applicable Canadian securities laws, and may not be comparable to similar information for United States companies. The terms “Mineral Resource”, “Measured Mineral Resource”, “Indicated Mineral Resource” and “Inferred Mineral Resource” used in this Report are Canadian mining terms as defined in the Canadian Institute of Mining, Metallurgy and Petroleum (“CIM”) Definition Standards for Mineral Resources and Mineral Reserves adopted by CIM Council on November 27, 2010 and incorporated by reference in National Instrument 43-101 (“NI 43-101”). While the terms “Mineral Resource”, “Measured Mineral Resource”, “Indicated Mineral Resource” and “Inferred Mineral Resource” are recognized and required by Canadian securities regulations, they are not defined terms under standards of the United States Securities and Exchange Commission. As such, certain information contained in this Report concerning descriptions of mineralization and resources under Canadian standards is not comparable to similar information made public by United States companies subject to the reporting and disclosure requirements of the United States Securities and Exchange Commission.

An “Inferred Mineral Resource” has a greater amount of uncertainty as to its existence and as to its economic and legal feasibility. It cannot be assumed that all or any part of an “Inferred Mineral Resource” will ever be upgraded to a higher confidence category.Readers are cautioned not to assume that all or any part of an “Inferred Mineral Resource” exists or is economically or legally mineable.

Under United States standards, mineralization may not be classified as a “Reserve” unless the determination has been made that the mineralization could be economically and legally produced or extracted at the time the Reserve estimation is made. Readers are cautioned not to assume that all or any part of the Measured or Indicated Mineral Resources that are not Mineral Reserves will ever be converted into Mineral Reserves. In addition, the definitions of “Proven Mineral Reserves” and “Probable Mineral Reserves” under CIM standards differ in certain respects from the standards of the United States Securities and Exchange Commission.

 

 

xv


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

TABLE OF CONTENTS

 

1.

  

EXECUTIVE SUMMARY

     1-1   

1.1

  

Introduction

     1-1   

1.2

  

Contributors and Qualified Persons

     1-2   

1.3

  

Key Outcomes

     1-2   

1.4

  

Property Description

     1-4   

1.5

  

Accessibility, Climate, Local Resources, Infrastructure and Physiography

     1-5   

1.6

  

Project History

     1-5   

1.7

  

Geological Setting and Mineralization

     1-7   

1.8

  

Deposit Types

     1-7   

1.9

  

Exploration

     1-8   

1.10

  

Drilling

     1-8   

1.11

  

Sampling Method, Approach and Analyses

     1-9   

1.12

  

Data Verification

     1-9   

1.13

  

Metallurgical Test work

     1-10   
   1.13.1   

Historical Test work

     1-10   
   1.13.2   

Mineralogy

     1-10   
   1.13.3   

Flowsheet Determination Test work

     1-11   
   1.13.4   

Comminution Tests

     1-12   
   1.13.5   

Gravity Separation

     1-13   
   1.13.6   

Cyanide Leaching

     1-13   
   1.13.7   

Cyanide Destruction Test work

     1-14   
   1.13.8   

Environmental Test work

     1-14   
   1.13.9   

Test work Interpretation

     1-15   

1.14

  

Mineral Resource Estimate

     1-16   

1.15

  

Open Pit and Underground Mine Design

     1-19   
   1.15.1   

Open Pit Mine

     1-19   
   1.15.2   

Underground Mine

     1-21   
   1.15.3   

Open Pit and Underground Reserves

     1-22   

1.16

  

Mining Methods

     1-24   
   1.16.1   

Open Pit Operations

     1-25   
   1.16.2   

Open Pit Production Schedule

     1-26   
   1.16.3   

Underground Mine Infrastructure

     1-27   
  

1.16.4

  

Underground Operations

     1-28   
  

1.16.5

  

Underground Development and Production Schedule

     1-30   
   1.16.6   

Proposed Overall Mine Plan (Open Pit and Underground)

     1-31   

 

 

xvi


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

1.17

  

Process Plant

     1-33   

1.18

  

Project Infrastructure

     1-36   
  

1.18.1

  

Site Water Management

     1-39   
  

1.18.2

  

Tailings Management Area

     1-40   

1.19

  

Market Studies and Contracts

     1-40   

1.20

  

Environmental and Permitting

     1-40   

1.21

  

Capital and Operating Costs

     1-42   
  

1.21.1

  

Capital Costs

     1-42   
  

1.21.2

  

Operating Costs

     1-45   

1.22

  

Economic Analysis

     1-51   

1.23

  

Adjacent Properties

     1-56   

1.24

  

Other Relevant Data and Information

     1-57   

1.25

  

Conclusions

     1-57   

1.26

  

Recommendations and Future Work Program

     1-58   

2.

  

INTRODUCTION

     2-1   

2.1

  

Scope of Study

     2-1   

2.2

  

Effective Dates and Declaration

     2-2   

2.3

  

Sources of Information

     2-3   

2.4

  

Terms of Reference

     2-4   

2.5

  

Site Visit

     2-5   

2.6

  

Acknowledgement

     2-5   

3.

  

RELIANCE ON OTHER EXPERTS

     3-1   

3.1

  

Report Responsibility and Qualified Persons

     3-1   

3.2

  

Other Study Contributors

     3-4   

4.

  

PROPERTY DESCRIPTION AND LOCATION

     4-1   

4.1

  

Mineral Tenure

     4-1   

4.2

  

Underlying Agreements

     4-6   

4.3

  

Environmental Considerations

     4-6   

4.4

  

Environmental Approvals in Ontario

     4-9   

5.

  

ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE AND PHYSIOGRAPHY

     5-1   

5.1

  

Accessibility

     5-1   

5.2

  

Local Resources and Infrastructure

     5-1   

5.3

  

Climate

     5-2   

5.4

  

Physiography

     5-2   

 

 

xvii


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

6.

  

HISTORY

     6-1   

6.1

  

Previous Exploration Work

     6-1   
  

6.1.1

  

Period 1967 to 1989 by Various Companies

     6-1   
  

6.1.2

  

Period 1990 to 2004 by Nuinsco

     6-2   
  

6.1.3

  

Previous Mineral Resource Estimates

     6-3   

7.

  

GEOLOGICAL SETTING AND MINERALIZATION

     7-1   

7.1

  

Regional Geology

     7-1   

7.2

  

Property Geology

     7-4   
  

7.2.1

  

Lithology

     7-6   
  

7.2.2

  

Structural Geology

     7-8   

7.3

  

Mineralization

     7-15   
  

7.3.1

  

Auriferous Sulphide and Quartz-Sulphide Stringers and Veins in Felsic Quartz-Phyric Rocks

     7-16   
  

7.3.2

  

Deformed Quartz-Ankerite-Pyrite Shear Veins in Mafic Volcanic Rocks

     7-19   
  

7.3.3

  

Silver-Rich Deformed Sulphide-Quartz Veins within Tuffaceous Rocks

     7-20   
  

7.3.4

  

Nickel-Copper-PGE Mineralization

     7-21   

8.

  

DEPOSIT TYPES

     8-1   

9.

  

EXPLORATION

     9-1   

9.1

  

Period 1967-1989

     9-1   

9.2

  

Nuinsco Exploration Work (1990-2004)

     9-1   

9.3

  

Rainy River Exploration Work (2005-2013)

     9-1   

10.

  

DRILLING

     10-1   

10.1

  

Drilling from 2004 to 2013

     10-1   
  

10.1.1

  

Introduction

     10-1   
  

10.1.2

  

Drilling Procedures

     10-3   

10.2

  

Drilling Pattern and Density

     10-5   

10.3

  

SRK Comments

     10-5   

11.

  

SAMPLE PREPARATION, ANALYSES, AND SECURITY

     11-1   

11.1

  

Sampling Method and Approach

     11-1   

11.2

  

Sample Preparation and Analyses

     11-2   
  

11.2.1

  

Nuinsco Samples

     11-2   
  

11.2.2

  

Rainy River Samples

     11-2   
  

11.2.3

  

Metallurgical Testing

     11-6   

 

 

xviii


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

11.3

  

Specific Gravity Data

     11-7   

11.4

  

Quality Assurance and Quality Control Programs

     11-10   

11.5

  

SRK Comments

     11-11   

12.

  

DATA VERIFICATION

     12-1   

12.1

  

Verification of Nuinsco Data

     12-1   

12.2

  

Verifications by Rainy River

     12-1   

12.3

  

Verifications by SRK

     12-2   
   12.3.1   

Site Visit

     12-2   
   12.3.2   

Verifications of Analytical Quality Control Data

     12-2   
   12.3.3   

Verification of Electronic Data

     12-5   

13.

  

MINERAL PROCESSING AND METALLURGICAL TESTING

     13-1   

13.1

  

Historical Metallurgy

     13-1   
   13.1.1   

Sample Selection

     13-1   
   13.1.2   

Historical Testwork

     13-1   

13.2

  

Composite and Sample Selection

     13-2   
   13.2.1   

Variability Sample Selection

     13-3   
   13.2.2   

Sample Characterization

     13-5   

13.3

  

Mineralogy

     13-7   

13.4

  

Flowsheet Selection Testwork

     13-8   
   13.4.1   

Flotation Option

     13-9   
   13.4.2   

Gravity and Gravity Tailings Whole Rock Leach

     13-16   
  

13.4.3

  

Flowsheet Selection

     13-18   

13.5

  

Comminution Tests

     13-18   
   13.5.1   

Crusher Work Index

     13-18   
   13.5.2   

Unconfined Compressive Strength

     13-19   
   13.5.3   

JK Drop Weight and SAG Mill Comminution

     13-19   
   13.5.4   

SAGDesign

     13-22   
   13.5.5   

Bond Work Index

     13-24   
   13.5.6   

ModBond and A x b

     13-27   
   13.5.7   

Bond Abrasion Index

     13-28   
   13.5.8   

Grinding Circuit Design

     13-29   

13.6

  

Gravity Separation

     13-31   
   13.6.1   

Gravity Recoverable Gold

     13-31   
   13.6.2   

Gravity Variability Testwork

     13-32   

13.7

  

Heap Leaching

     13-34   

 

 

xix


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

13.8

  

Cyanide Leaching

     13-35   
   13.8.1   

Gravity Tailings Leaching

     13-35   
   13.8.2   

Cyanide Concentration

     13-38   
   13.8.3   

Pre-Conditioning

     13-39   
   13.8.4   

Oxygen (O2) vs. Air

     13-40   
   13.8.5   

Lead Nitrate Addition

     13-40   
   13.8.6   

Intrepid Zone Leaching Kinetics

     13-41   
   13.8.7   

Grade Recovery Variability Tests

     13-43   
   13.8.8   

Diagnostic Leach Testwork

     13-46   
   13.8.9   

Mercury Assays

     13-47   

13.9

  

Cyanide Destruction Testwork

     13-47   

13.10

  

Carbon-in-Pulp Modelling

     13-48   

13.11

  

Thickener Sizing Testwork

     13-50   
   13.11.1   

Flocculant Screening

     13-50   
   13.11.2   

Sedimentation Testwork

     13-51   

13.12

  

Rheology

     13-52   

13.13

  

Linear Screen Sizing Testwork

     13-53   

13.14

  

Environmental Testwork

     13-54   

13.15

  

Gold and Silver Recovery Curves

     13-55   

13.16

  

Testwork Interpretation

     13-57   

14.

  

MINERAL RESOURCE ESTIMATION

     14-1   

14.1

  

Introduction

     14-1   

14.2

  

Resource Estimation Procedures

     14-2   

14.1

  

Resource Database

     14-2   

14.3

  

Solid Body Modelling

     14-4   
   14.3.1   

Introduction

     14-4   
   14.1.1   

The ODM/17 Zone

     14-7   
   14.1.2   

The 433, HS and New Zones

     14-8   

14.4

  

Compositing

     14-10   

14.5

  

Evaluation of Outliers

     14-11   

14.6

  

Statistical Analysis and Variography

     14-14   
   14.6.1   

Statistical Analysis

     14-14   
   14.6.2   

Variography

     14-24   

14.7

  

Block Model and Grade Estimation

     14-30   
   14.7.1   

Block Model Definition

     14-30   
   14.7.2   

Grade and Specific Gravity Estimation

     14-30   

 

 

xx


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

14.8

  

Model Validation and Sensitivity

     14-38   

14.9

  

Mineral Resource Classification

     14-39   

14.10

  

Mineral Resource Statement

     14-40   

14.11

  

Grade Sensitivity Analysis

     14-48   

14.12

  

Previous Mineral Resource Estimates

     14-51   

15.

  

MINERAL RESERVE ESTIMATE

     15-1   

15.1

  

Introduction

     15-1   

15.2

  

Open Pit Mining

     15-1   
   15.2.1   

Resource Block Model

     15-1   
   15.2.2   

Open Pit Optimization

     15-4   
   15.2.3   

Detailed Mine Design

     15-8   
   15.2.4   

In-Pit Dilution and Mine Recovery

     15-20   
   15.2.5   

Open Pit Mineral Reserves

     15-21   

15.3

  

Underground Mining

     15-22   
   15.3.1   

Underground Mineral Reserves

     15-22   
   15.3.2   

Mining Shapes

     15-27   
   15.3.3   

Dilution and Recovery Estimates

     15-27   
   15.3.4   

Recovery Factors

     15-30   
   15.3.5   

Mineral Reserves

     15-30   

15.4

  

Open Pit and Underground Mineral Reserves

     15-30   

16.

  

MINING METHODS

     16-1   

16.1

  

Introduction

     16-1   

16.2

  

Open Pit Mining Methods

     16-2   
   16.2.1   

Open Pit and Stockpiles Geotechnical Designs

     16-2   
   16.2.2   

Open Pit Mine Planning

     16-5   
   16.2.3   

Material Management

     16-15   
   16.2.4   

Open Pit Mine Equipment and Operations

     16-21   
   16.2.5   

Open Pit Mine Personnel Requirements

     16-33   

16.3

  

Underground Mining Methods

     16-37   
   16.3.1   

Mine Design

     16-38   
   16.3.2   

Stope Design

     16-44   
   16.3.3   

Mining Method and Sequence

     16-46   
   16.3.4   

Waste Management and Stope Filling

     16-51   
   16.3.5   

Development and Production Schedule

     16-54   
   16.3.6   

Geotechnical

     16-58   

 

 

xxi


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

   16.3.7   

Drill and Blast

     16-63   
   16.3.8   

Mobile Equipment Requirements

     16-65   
   16.3.9   

Ventilation

     16-70   
   16.3.10   

Emergency Preparedness

     16-78   

16.4

  

Underground infrastructure

     16-80   
   16.4.1   

Refuge Stations

     16-80   
   16.4.2   

Mine Dewatering

     16-81   
   16.4.3   

Compressed Air

     16-83   
   16.4.4   

Mine Water Supply

     16-83   
   16.4.5   

Fuelling and Lubrication

     16-84   
   16.4.6   

Workshop Facility

     16-85   
   16.4.7   

Explosives Magazine

     16-86   
   16.4.8   

Underground (CAF Loading Station)

     16-87   
   16.4.9   

Communications and Automation

     16-88   
   16.4.10   

Electrical Distribution

     16-90   

16.5

  

Underground Manpower Requirements

     16-92   
   16.5.1   

Manpower

     16-92   
   16.5.2   

Schedule

     16-92   
   16.5.3   

Organization

     16-92   

16.6

  

Combined Production Schedule

     16-94   

17.

  

RECOVERY METHODS

     17-1   

17.1

  

Proposed Process Flowsheet

     17-1   

17.2

  

Process and Plant Facilities Description and Design Characteristics

     17-4   
   17.2.1   

Primary Crushing

     17-6   
   17.2.2   

Crushed Rock Handling and Storage

     17-7   
   17.2.3   

Processing Plant and Tailings Handling

     17-7   
   17.2.4   

Primary and Secondary Grinding

     17-9   
   17.2.5   

Gravity Circuit

     17-10   
   17.2.6   

Cyanide Leaching Circuit

     17-10   
   17.2.7   

Carbon-in-Pulp Circuit, Carbon Stripping and Reactivation

     17-11   
   17.2.8   

Tailings Management and Cyanide Destruction

     17-12   
   17.2.9   

Refining Area and Gold Room

     17-13   
   17.2.10   

Reagent Areas

     17-13   
   17.2.11   

Control Room and Maintenance Shop

     17-13   
   17.2.12   

Offices and Change House

     17-14   
   17.2.13   

Metallurgical Laboratory

     17-14   

 

 

xxii


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

17.3

  

Energy, Water and Consumable Requirements

     17-14   
   17.3.1   

Energy

     17-14   
   17.3.2   

Water

     17-14   
   17.3.3   

Consumables

     17-16   

18.

  

PROJECT INFRASTRUCTURE

     18-1   

18.1

  

General Site Works

     18-1   
   18.1.1   

Primary Site and Access Roads

     18-1   
   18.1.2   

Mine Haul Roads

     18-2   
   18.1.3   

Geotechnical

     18-2   

18.2

  

Mine Services Facilities

     18-3   

18.3

  

General Offices and Assay Laboratory

     18-4   
   18.3.1   

Main Administration Building

     18-5   
   18.3.2   

Mine Office and Dry

     18-5   
   18.3.3   

Plant Office

     18-5   

18.4

  

Parking Area

     18-6   

18.5

  

Assay Lab

     18-6   

18.6

  

Fuel Storage and Dispensing

     18-6   

18.7

  

Electrical and Communication

     18-7   
  

18.7.1

  

Emergency Power

     18-8   
  

18.7.2

  

Communication

     18-9   

18.8

  

Tailings Management Area

     18-10   
   18.8.1   

Tailings Deposition Plan

     18-10   
   18.8.2   

Dam Design

     18-11   
   18.8.3   

Construction and Operational Considerations

     18-13   
   18.8.4   

Site Water Management

     18-16   
   18.8.5   

Water Management Structures

     18-17   
   18.8.6   

Runoff and Seepage Collection

     18-18   
  

18.8.7

  

Process Plant Water Supply - Preparations for Start-up

     18-21   
  

18.8.8

  

Process Plant Water Supply - Operations

     18-22   

18.9

  

Water Treatment Design Basis and Operation

     18-23   
  

18.9.1

  

Water Treatment Design and Operation

     18-24   
  

18.9.2

  

Water Treatment Plant Opportunities

     18-26   

18.10

  

Fish Compensation Works

     18-27   
  

18.10.1 Background

     18-27   
  

18.10.2 Proposed Offset Measures

     18-29   

 

 

xxiii


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

19.

  

MARKET STUDIES AND CONTRACTS

     19-1   

19.1

  

Market Studies

     19-1   

19.2

  

Commodity Price Projections

     19-1   

19.3

  

Contracts

     19-1   

20.

  

ENVIRONMENTAL STUDIES, PERMITTING AND SOCIAL OR COMMUNITY IMPACT

     20-1   

20.1

  

General Approach

     20-1   

20.2

  

Consultation Activities

     20-1   
  

20.2.1

  

Community and Government Communications

     20-1   
  

20.2.2

  

Aboriginal Communications

     20-2   
  

20.2.3

  

Comments on the Project

     20-7   

20.3

  

Environmental Studies

     20-10   
  

20.3.1

  

Overview

     20-10   
  

20.3.2

  

Climate, Air Quality and Sound

     20-12   
  

20.3.3

  

Physiography, Soils and Geology

     20-13   
  

20.3.4

  

Hydrology and Hydrogeology

     20-15   
  

20.3.5

  

Surface Water, Sediment and Groundwater Quality

     20-17   
  

20.3.6

  

Biological Environment - Existing Conditions

     20-19   
  

20.3.7

  

Human Environment

     20-22   

20.4

  

Traditional Knowledge (“TK”) and Traditional Land Use (“TLU”)

     20-24   

20.5

  

Cultural Heritage Resources

     20-25   

20.6

  

Environmental Sensitivities

     20-26   

20.7

  

Regulatory Context

     20-27   
  

20.7.1

  

Current Regulatory Status

     20-27   
  

20.7.2

  

Environmental Approvals Required for Proposed Operations

     20-27   

20.8

  

Preliminary Environmental Impact

     20-32   

20.9

  

Effects Analysis

     20-33   
  

20.9.1

  

Air Quality and Sound

     20-33   
  

20.9.2

  

Streamflow, Aquatic Habitats and Species

     20-34   
  

20.9.3

  

Groundwater

     20-36   
  

20.9.4

  

Vegetation and Terrestrial Habitat

     20-36   
  

20.9.5

  

Terrestrial and Avian Species

     20-37   
  

20.9.6

  

Species at Risk

     20-37   
  

20.9.7

  

Traditional Land Use

     20-38   
  

20.9.8

  

Socio-economic

     20-38   
  

20.9.9

  

Human Health

     20-38   
  

20.9.10 Cultural Heritage Resources

     20-38   

 

 

xxiv


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

20.10

  

Reclamation Approach

     20-39   
   20.10.1   

Open Pit and Underground Mine

     20-39   
   20.10.2   

Stockpiles

     20-40   
   20.10.3   

Tailings Management Area

     20-41   
   20.10.4   

Aggregate Sources

     20-41   
   20.10.5   

Buildings, Machinery, Equipment and Infrastructure

     20-42   
   20.10.6   

Petroleum Products, Chemicals and Explosives

     20-42   
   20.10.7   

Roads, Pipelines and Power Distribution

     20-42   
   20.10.8   

Site Drainage and Water Structures

     20-43   
   20.10.9   

Waste Management

     20-43   
   20.10.10   

Offsite Facilities

     20-43   

21.

  

CAPITAL AND OPERATING COSTS

     21-1   

21.1

  

Capital Costs - Introduction

     21-1   
  

21.1.1

  

Assumptions

     21-1   
  

21.1.2

  

Exclusions

     21-2   

21.2

  

Capital Cost Summary

     21-2   

21.3

  

Basis of Estimate

     21-4   

21.4

  

Pre-Production Capital Costs

     21-11   
  

21.4.1

  

Introduction

     21-11   
  

21.4.2

  

Overhead Power Line

     21-11   
  

21.4.3

  

Highway 600 Re-alignment

     21-11   
  

21.4.4

  

Open Pit Overburden Pre-Stripping, Waste Removal and Ore Stockpiling

     21-12   
  

21.4.5

  

Open Pit Mining Equipment

     21-12   
  

21.4.6

  

Site Development and Process Facilities

     21-14   
  

21.4.7

  

Tailings, Water Management and Treatment

     21-15   
  

21.4.8

  

Indirect Costs

     21-16   
  

21.4.9

  

Owner’s Costs

     21-19   
  

21.4.10

  

Contingency

     21-19   

21.5

  

Sustaining Capital Costs

     21-20   
  

21.5.1

  

Introduction

     21-20   
  

21.5.2

  

Open Pit Mine Equipment

     21-20   
  

21.5.3

  

Mobile Equipment

     21-21   
  

21.5.4

  

Site Development

     21-22   
  

21.5.5

  

Underground Mine

     21-22   
  

21.5.6

  

Tailings Water Management and Treatment

     21-27   
  

21.5.7

  

Fish Habitat Compensation Costs

     21-28   

 

 

xxv


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

  

21.5.8

  

Chapple Township Compensation Costs

     21-28   
  

21.5.9

  

Salvage Value

     21-28   
  

21.5.10 Reclamation and Closure Costs

     21-28   

21.6

  

Operating Costs

     21-29   
  

21.6.1

  

Introduction

     21-29   
  

21.6.2

  

Power and Fuel

     21-32   
  

21.6.3

  

Total Employees

     21-32   
  

21.6.4

  

Open Pit Operating Costs

     21-33   
  

21.6.5

  

Underground Operating Costs

     21-36   
  

21.6.6

  

Process Plant

     21-38   
  

21.6.7

  

G&A Costs

     21-42   
  

21.6.8

  

Royalties

     21-43   
  

21.6.9

  

Transportation and Refining

     21-43   

22.

  

ECONOMIC ANALYSIS

     22-1   

22.1

  

Introduction

     22-1   

22.2

  

Methods, Assumptions and Basis

     22-1   

22.3

  

Royalties

     22-4   

22.4

  

Salvage Value

     22-4   

22.5

  

Taxation

     22-4   

22.6

  

Financial Analysis Summary

     22-6   

22.7

  

Sensitivity Analysis

     22-8   

23.

  

ADJACENT PROPERTIES

     23-1   

23.1

  

Introduction

     23-1   

24.

  

OTHER RELEVANT DATA AND INFORMATION

     24-1   

24.1

  

Project Execution

     24-1   

24.2

  

Health, Safety, Environmental and Security

     24-1   

24.3

  

Hazardous Waste Management

     24-1   

24.4

  

Execution Strategy

     24-2   

24.5

  

Management Procedures

     24-2   

24.6

  

EPCM Project Controls and Reporting

     24-4   

24.7

  

Project Scheduling

     24-5   

24.8

  

Procurement and Contracts

     24-7   

24.9

  

Site Development

     24-7   

24.10

  

Construction

     24-7   
  

24.10.1 Construction Management Responsibilities

     24-7   

 

 

xxvi


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

  

24.10.2

  

Construction Power

     24-8   
  

24.10.3

  

Construction Labour Requirement

     24-8   

24.11

  

Process Facilities

     24-9   
  

24.11.1

  

Critical Path and Installation Methodology

     24-9   

24.12

  

Tailings Management Area (‘‘TMA’’) Earthworks

     24-10   

24.13

  

Commissioning

     24-10   

24.14

  

Mechanical Completion

     24-11   

24.15

  

Risk Management

     24-11   

25.

  

INTERPRETATION AND CONCLUSIONS

     25-1   

25.1

  

Sampling Method, Approach and Analyses

     25-1   

25.2

  

Data Verification

     25-1   

25.3

  

Mineral Resources

     25-2   

25.4

  

Sampling Preparation, Analysis and Security

     25-4   

25.5

  

Mining Methods and Reserves

     25-4   

25.6

  

Metallurgy, Processing and General & Administrative

     25-7   

25.7

  

Infrastructure

     25-9   

25.8

  

Environmental Permitting

     25-10   

25.9

  

Financial Analysis

     25-10   

25.10

  

Conclusion

     25-11   

26.

  

RECOMMENDATIONS

     26-1   

26.1

  

Proposed 2014 Work Program Budget

     26-1   

26.2

  

2014 Detailed Recommendations

     26-2   

27.

  

REFERENCES

     27-1   

 

APPENDIX A –

  Rainy River Resources Title Opinion (November 27, 2013)

APPENDIX B –

  Rainy River Resources Patented, Leasehold and Mining Claims (November 22, 2013)

APPENDIX C –

  Nuinsco Exploration Activities (1993 to 2002)

APPENDIX D –

  Analytical Quality Control Data and Relative Precision Charts (December 2011 - July 2013)

APPENDIX E –

  Domain Variograms

APPENDIX F –

  Rainy River Project Site Plan

 

 

xxvii


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LIST OF FIGURES

 

Figure 1-1:

 

Phase I, Phase II and Final Pit

     1-27   

Figure 1-2:

 

Isometric View of the Rainy River Underground Mine

     1-28   

Figure 1-3:

 

Typical Stope Long Section and Cross Sections

     1-29   

Figure 1-4:

 

Combined Gold and Silver Production

     1-32   

Figure 1-5:

 

Schematic Process Flowsheet

     1-35   

Figure 1-6:

 

General Site Layout

     1-37   

Figure 1-7:

 

Annual Operating Cash Costs (USD/oz. Au) with Silver Credit

     1-50   

Figure 1-8:

 

Life-of-Mine Cash Flow Projections

     1-54   

Figure 1-9:

 

Pre-Tax Net Present Value (NPV) Sensitivity Analysis at 5% Discount Rate

     1-55   

Figure 4-1:

 

Location of Rainy River Project (as of November 22, 2013)

     4-3   

Figure 4-2:

 

Land Tenure Map of the Rainy River Gold Project (as of November 22, 2013)

     4-5   

Figure 5-1:

 

Typical Landscape in the Rainy River Project Area

     5-3   

Figure 7-1:

 

Regional Bedrock Geology of the Area West of Fort Frances (modified from Percival and Easton, 2007)

     7-3   

Figure 7-2:

 

Bedrock Geological Interpretation for the Area Surrounding the Rainy River Project (from Rainy River, 2013)

     7-5   

Figure 7-3:

 

Regional Structural Trends on the Rainy River Gold Project, Interpreted from Aeromagnetics (Rankin, 2013)

     7-9   

Figure 7-4:

 

Structural Fabrics Affecting Rock Types

     7-11   

Figure 7-5:

 

Evidence for Strike-Slip Kinematics of Late Brittle Faulting (SRK, 2011)

     7-12   

Figure 7-6:

 

Pressure Shadows Around Rigid Objects in Dacitic Rock

     7-13   

Figure 7-7:

 

Sulphide Mineralization Deformed by Folding in Core from the Rainy River Project (SRK, 2011)

     7-14   

Figure 7-8:

 

Structural Control of the Plunge of the Gold Mineralization at the Rainy River Project

     7-15   

Figure 7-9:

 

ODM/17 Zone Gold Mineralization (SRK, 2011)

     7-17   

Figure 7-10:

 

ODM/17 High-Grade Gold Mineralization (SRK, 2011)

     7-17   

Figure 7-11:

 

433 High-Grade Gold Mineralization (SRK, 2011)

     7-18   

Figure 7-12:

 

Higher Grade Gold Mineralization - Borehole NR10-474 from 188.0 to 234.0 m. (SRK, 2011)

     7-20   

Figure 7-13:

 

Intrepid Zone Gold Mineralization. Deformed Pyrite-Sphalerite Veins and Stringers Borehole NR131542 (Rainy River, 2013)

     7-21   

Figure 8-1:

 

Idealized Sketch Showing Relative Timing of Auriferous Features and illustrating Protracted Deformation Affecting Initial Gold-rich Volcanogenic Mineralization and Subsequently Overprinted by Mesothermal Gold Mineralization (SRK, 2011)

     8-2   

Figure 8-2:

 

Schematic Geological Setting and Hydrothermal Alteration Associated with Gold-rich Volcanogenic Hydrothermal Systems (after Hannington et al., 1999)

     8-4   

Figure 8-3:

 

Schematic Section and Hydrothermal Alteration Associated with the Rainy River Project (Sparkes & Wartman, 2012)

     8-5   

 

 

xxiii


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Figure 9-1:

 

Section Showing the Footwall Silver Zone below the Previous PEA Starter Pit (December 23, 2011) (from Rainy River

     9-3   

Figure 9-2:

 

Section through the Intrepid Zone

     9-4   

Figure 10-1:

 

Core Drilling Data by Period (1994 to August 16th, 2013)

     10-2   

Figure 10-2:

 

Drill Collar Plan in Relation to Resource Domains within the Main Rainy River Area and Showing Conceptual Pit Outline

     10-2   

Figure 11-1:

 

Summary of Specific Gravity Composite Data. Top: All Resource Domains; Middle: ODM/17 Zone Sub-Domains; and Bottom: Other Domains (600 Domains)

     11-8   

Figure 13-1:

 

Sample Locations for Comminution Variability Testwork

     13-3   

Figure 13-2:

 

Sample Locations for Metallurgical Variability Testwork

     13-4   

Figure 13-3:

 

Sample Locations for Comminution (Left) and Leaching (Right) Variability Testwork (Cross- Section View, Looking West)

     13-4   

Figure 13-4:

 

Specific Energy vs. Particle Size for IsaMill Testing

     13-14   

Figure 13-5:

 

Specific Energy vs. Particle Size for SMD Testing

     13-16   

Figure 13-6:

 

SMC Data Distribution with JK DWT Calibration Points

     13-21   

Figure 13-7:

 

Full Bond Ball Mill Work Indices vs. ModBond Work Indices (200 Mesh)

     13-25   

Figure 13-8:

 

Distribution of ModBond Indices (200 Mesh) by Zone

     13-27   

Figure 13-9:

 

ModBond Wi vs. A x b

     13-28   

Figure 13-10:

 

Gold Gravity Recovery vs. Head Grade

     13-33   

Figure 13-11:

 

Silver Gravity Recovery vs. Head Grade

     13-33   

Figure 13-12:

 

Heap Leach Gold Recovery Curve

     13-34   

Figure 13-13:

 

Gravity Tailings Leach Residue vs. Grind Size

     13-36   

Figure 13-14:

 

Cost and Revenue Analysis by Grind Size

     13-37   

Figure 13-15:

 

Gold Recovery vs. Time at Different NaCN Concentrations

     13-38   

Figure 13-16:

 

Gold and Silver Cyanide Leaching Kinetics (Intrepid Zone)

     13-42   

Figure 13-17:

 

Gold Residue vs. Head Grade (Variability Tests)

     13-45   

Figure 13-18:

 

Silver Residue vs. Head Grade (Variability Tests)

     13-46   

Figure 13-19:

 

CIP Modeling Isotherms

     13-49   

Figure 13-20:

 

Initial Pit Composite Yield Stress vs. Solids Density

     13-52   

Figure 13-21:

 

Remaining-Life-of-Mine Composite Yield Stress vs. Solids Density

     13-53   

Figure 14-1:

 

Location of New Boreholes Drilled on the Main Rainy River Deposit

     14-5   

Figure 14-2:

 

Location of Drill Collars and High Grade Subdomain for the Intrepid Zone

     14-6   

Figure 14-3:

 

Isometric View of the Rainy River Mineralization Wireframes Modelled by SRK with Borehole Data (View looking towards the West)

     14-6   

Figure 14-4:

 

Histogram Distribution of Raw Sample Lengths

     14-11   

Figure 14-5:

 

Cumulative Frequency Plot for Gold Composites

     14-13   

Figure 14-6:

 

Examples of Variogram Models for Rainy River Deposit

     14-25   

 

 

xxix


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Figure 14-7:

 

Cross-Section 425,775E Comparing Blocks Populated with Gold Grades and Informing Data

     14-38   

Figure 14-8:

 

Cross-Section 425, 335E Comparing Blocks Populated With Gold Grades and Informing Data in the Intrepid Zone

     14-39   

Figure 14-9:

 

Schematic Vertical Section Illustrating Criteria Considered for Preparing the Mineral Resource Statement for the Rainy River Project (View Looking East)

     14-43   

Figure 14-10:

 

Rainy River Project Global Grade Tonnage Curves (Open Pit and Underground Material Combined)

     14-48   

Figure 14-11:

 

Distribution of Open Pit Mineral Resources Relative to the Conceptual Pit Outline

     14-51   

Figure 15-1:

 

Isopach Mapping of Overburden Thickness

     15-3   

Figure 15-2:

 

Rainy River Theoretical Pit Shell and Bayfield constraint (Plan View)

     15-7   

Figure 15-3:

 

Detailed Open Pit Mine Design (Plan View)

     15-10   

Figure 15-4:

 

Final Pit Design and LG Optimization - Isometric View

     15-11   

Figure 15-5:

 

Final Pit Design and LG Optimization - Elevation 290 masl

     15-12   

Figure 15-6:

 

Final Pit Design and LG Optimization - Elevation 160 masl

     15-13   

Figure 15-7:

 

Final Pit Design and LG Optimization - Elevation 10 masl

     15-14   

Figure 15-8:

 

Final Pit Design and LG Optimization - Cross Section (East 425 400, looking West)

     15-15   

Figure 15-9:

 

Final Pit Design and LG Optimization - Cross Section (East 425 500, looking West)

     15-16   

Figure 15-10:

 

Final Pit Design and LG Optimization - Cross Section (East 425 600, looking West)

     15-17   

Figure 15-11:

 

Final Pit Design and LG Optimization - Cross Section (East 425 700, looking West)

     15-18   

Figure 15-12:

 

Final Pit Design and LG Optimization - Cross Section (East 425 800, looking West)

     15-19   

Figure 15-13:

 

Isometric View of the Rainy River Underground Mine

     15-23   

Figure 15-14:

 

Typical ODM Main Zone Cross-Section

     15-23   

Figure 15-15:

 

Typical Intrepid Zone Cross-Sections

     15-24   

Figure 15-16:

 

Unplanned Dilution from Hangingwall and Footwall Rock

     15-28   

Figure 15-17:

 

Backfill Dilution

     15-29   

Figure 16-1:

 

Isometric View of the Rainy River Open Pit and Underground Mine, Looking North

     16-1   

Figure 16-2:

 

Open Pit Design Zones & Recommendations (AMEC, 2013F)

     16-4   

Figure 16-3-

 

Phase 1, Phase 2 and Final Pit - 3D View

     16-7   

Figure 16-4:

 

Phase 1, Phase 2 and Final Pit - Cross-section (East 425 500, Looking West)

     16-7   

Figure 16-5:

 

Phase 1, Phase 2 and Final Pit - Cross-section (East 425 700, Looking West)

     16-8   

Figure 16-6:

 

Open Pit Mine Planning - End of 2015 (Year -2)

     16-9   

Figure 16-7:

 

Open Pit Mine Planning - End of 2016 (Year -1)

     16-10   

Figure 16-8:

 

Open Pit Mine Planning - End of 2017 (Year 1)

     16-11   

Figure 16-9:

 

Open Pit Mine Planning - End of 2018 (Year 2)

     16-11   

Figure 16-10:

 

Open Pit Mine Planning - End of 2020 (Year 4)

     16-12   

Figure 16-11:

 

Open Pit Mine Planning - End of 2022 (Year 6)

     16-12   

 

 

xxx


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Figure 16-12:

 

Final Pit Contour - End of 2025 (Year 9)

     16-13   

Figure 16-13:

 

Open Pit Material Movement over the Life-of-Mine

     16-14   

Figure 16-14:

 

Site Plan Showing West and East Mine Rock Stockpiles

     16-16   

Figure 16-15:

 

East Mine Rock Stockpile Area

     16-16   

Figure 16-16:

 

West Mine Rock Stockpile Area

     16-17   

Figure 16-17:

 

In-Pit Dumping Area and Dumping Sequence

     16-20   

Figure 16-18:

 

Cycle Time Trend over LOM

     16-28   

Figure 16-19:

 

LOM Haul Truck Fleet

     16-29   

Figure 16-20:

 

Sublevel Arrangement in Cross-section

     16-40   

Figure 16-21:

 

Typical Level Plan

     16-40   

Figure 16-22:

 

Standard Design - Ore Drive

     16-43   

Figure 16-23:

 

Standard Design - Main Decline, Internal Ramps and Level Accesses

     16-43   

Figure 16-24:

 

Mineable Stope Shape - Intrepid Zone

     16-45   

Figure 16-25:

 

Mineable Stope Shape - ODM and 17 East Zones

     16-45   

Figure 16-26:

 

Mining Zones

     16-46   

Figure 16-27:

 

Typical Stope Long Section

     16-48   

Figure 16-28:

 

Typical Stope Cross-sections

     16-48   

Figure 16-29:

 

CAF System Schematic

     16-51   

Figure 16-30:

 

Extent of Mine Development at the Onset of Production (April 2019)

     16-55   

Figure 16-31:

 

Underground Production Profile

     16-57   

Figure 16-32:

 

Production by Activity

     16-57   

Figure 16-33:

 

View North West of the Underground Mine Geometry Developed for the Map3D Numerical Stress Modelling, Indicating Zones and Main Underground Boreholes (AMEC, 2013G)

     16-58   

Figure 16-34:

 

Modified Stability Graph for ODM West Zone above 500 m depth Indicating Stability of Stope Surfaces Based on Potential Design Limits and Actual Final Stope Dimensions

     16-60   

Figure 16-35:

 

Empirical Estimation of Wall Slough (ELOS) for Varying HW Dip Cases for the 4 Main Underground Design Zones Above 500 m Depth in which LHOS Was Applied (AMEC, 2013G)

     16-62   

Figure 16-36:

 

Longitudinal Downhole Stope Long Section

     16-64   

Figure 16-37:

 

Drop Raise Drillhole Pattern for the Longitudinal Downhole Stope (Section View)

     16-64   

Figure 16-38:

 

Rainy River Ventilation System

     16-72   

Figure 16-39:

 

General Arrangement Refuge Station Plan

     16-81   

Figure 16-40:

 

Typical Sump Flow Diagram

     16-82   

Figure 16-41:

 

Dewatering Level Sump and Pumping

     16-82   

Figure 16-42:

 

General Arrangement Underground Main Sump Layout

     16-83   

Figure 16-43:

 

Typical Pressure Reducing Valve (‘‘PRV”) Station

     16-84   

Figure 16-44:

 

Underground Fuel Consumption Profile

     16-85   

 

 

xxxi


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Figure 16-45:

 

General Arrangement - Underground Fuel Station

     16-85   

Figure 16-46:

 

Underground Maintenance Workshops Layout

     16-86   

Figure 16-47:

 

ANFO Storage Plan and Sections

     16-87   

Figure 16-48:

 

Cap & Powder Magazine Plan and Sections

     16-87   

Figure 16-49:

 

Underground Cemented Rock Fill Loading Station

     16-88   

Figure 16-50:

 

Underground Power Requirement Profile

     16-91   

Figure 16-51:

 

Manpower Loading By Year

     16-94   

Figure 16-52:

 

Annual Concentrator Feed

     16-95   

Figure 16-53:

 

Annual Concentrator Feed

     16-96   

Figure 17-1:

 

Whole Rock Leach Process Schematic Diagram

     17-2   

Figure 17-2:

 

General Processing Area and Buildings Site Layout

     17-5   

Figure 17-3:

 

Process Plant General Arrangement Drawing (Including Primary Electrical Substation)

     17-8   

Figure 17-4:

 

Process Plant and Tailings Pond Water Balance

     17-16   

Figure 18-1:

 

Typical Cross Section - TMA South Dam Section (Refer to Table 18-8 for the construction fill material descriptions)

     18-14   

Figure 18-2:

 

Typical Cross Section - TMA West and North Sections (Refer to Table 18-8 for the construction fill material descriptions)

     18-15   

Figure 18-3:

 

Altered/Displaced Waters Frequented by Fish

     18-28   

Figure 21-1:

 

Project Operating Costs

     21-29   

Figure 21-2:

 

Annual Operating Cash Costs (USD/oz. Au) with Silver Credit

     21-32   

Figure 21-3:

 

Total Personnel

     21-33   

Figure 22-1:

 

Life-of-Mine Cash Flow Projection

     22-7   

Figure 22-2:

 

Life-of-Mine Cash Flow Projection (Pre-tax and After-tax, discount rate: 5%)

     22-8   

Figure 22-3:

 

Sensitivity of the Net Present Value (Pre-tax) to Selected Financial Variables

     22-10   

Figure 24-1:

 

Project Management Organization Chart

     24-3   

Figure 24-2:

 

Project Milestones

     24-6   

Figure 24-3:

 

Monthly Construction Manpower Graph

     24-9   

 

 

xxxii


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LIST OF TABLES

 

Table 1-1:

  

Feasibility Study Qualified Persons

     1-2   

Table 1-2:

  

Key Outcomes - Gold Production1

     1-3   

Table 1-3:

  

Key Outcomes - Silver Production1

     1-3   

Table 1-4:

  

Key Outcomes - Capital Expenses and Financial Results1

     1-4   

Table 1-5:

  

Consolidated Mineral Resource Statement, Rainy River Gold Project, SRK Consulting (Canada) Inc., November 2, 20131,2,3,4,5

     1-18   

Table 1-6:

  

Pit Optimization Parameters1

     1-20   

Table 1-7:

  

Open Pit and Underground Proven and Probable Mineral Reserves1,2,3,4,5,6

     1-23   

Table 1-8:

  

Open Pit Mine Schedule

     1-26   

Table 1-9:

  

Underground Production Schedule

     1-31   

Table 1-10:

  

Total Milled from OP and UG

     1-33   

Table 1-11:

  

Overall Project Capital Cost Summary

     1-43   

Table 1-12:

  

Key Project Operating Costs

     1-45   

Table 1-13:

  

Open Pit Operating Costs

     1-46   

Table 1-14:

  

LOM Underground Operating Costs by Activity

     1-48   

Table 1-15:

  

LOM Underground Mine General Cost Breakdown

     1-48   

Table 1-16:

  

Total and All-in Sustaining Cash Costs

     1-50   

Table 1-17:

  

Financial Analysis Summary5

     1-53   

Table 1-18:

  

Selected Sensitivities, Pre-Tax NPV at 5% Discount Rate (CAD $M)

     1-55   

Table 1-19:

  

Sensitivity Results for Metal Price and Exchange Rate Variations, $CAD

     1-56   

Table 1-20:

  

Sensitivity Results for Metal Price and Exchange Rate Variations, $USD

     1-56   

Table 1-21:

  

Rainy River Project Development Activities

     1-57   

Table 1-22:

  

Proven and Probable Reserves (November 2, 2013)

     1-58   

Table 1-23:

  

Budget for 2014 (US Dollars)

     1-59   

Table 2-1:

  

Major Study Contributors

     2-2   

Table 3-1:

  

Qualified Persons and Areas of Report Responsibility

     3-2   

Table 6-1:

  

Mineral Resource Statement1 for the Rainy River Project, Ontario, Mackie et al., December 23, 2003.

     6-3   

Table 6-2:

  

Mineral Resource Statement for the Rainy River Project, Ontario, Caracle Creek International Consulting Inc., April 30, 2008

     6-4   

Table 6-3:

  

Mineral Resource Statement1 for the Rainy River Project, Ontario, SRK Consulting (Canada) Inc., April 28, 2009

     6-5   

Table 6-4:

  

Mineral Resource Statement1, Rainy River Project, Ontario, SRK Consulting (Canada) Inc., February 26, 2010

     6-6   

Table 6-5:

  

Mineral Resource Statement1, Rainy River Project, Ontario, SRK Consulting (Canada) Inc., February 24, 2011

     6-7   

 

 

xxxiii


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 6-6:

  

Mineral Resource Statement1, Rainy River Project, Ontario, SRK Consulting (Canada) Inc., June, 29 2011

     6-8   

Table 6-7:

  

Mineral Resource Statement1, Rainy River Project, Ontario,SRK Consulting (Canada) Inc., February, 24 2012

     6-9   

Table 6-8:

  

Consolidated Mineral Resource Statement1, Rainy River Project, Ontario SRK Consulting (Canada) Inc., October 10, 2012

     6-10   

Table 9-1:

  

Summary of Exploration Work by Rainy River on the Rainy River Project between 2005 and 2013

     9-6   

Table 10-1:

  

Core Drilling Completed on the Rainy River Project (1994-2013)1

     10-1   

Table 11-1:

  

Specific Gravity Assigned to Gold Zones

     11-9   

Table 11-2:

  

Summary Statistics of Specific Gravity Data for the Intrepid Zone

     11-9   

Table 12-1:

  

Summary of Analytical Quality Control Data Produced between December 2011 and July 2012 for the Main Rainy River Deposit

     12-3   

Table 12-2:

  

Summary of Analytical Quality Control Data Produced between January 2012 to June 2013 for the Intrepid Zone

     12-4   

Table 13-1:

  

Master Composite Proportions

     13-1   

Table 13-2:

  

Weight Percentages by Zone for Initial Pit, RLOM Composites and Overall Pit

     13-3   

Table 13-3:

  

Testwork Sample Head Grades

     13-6   

Table 13-4:

  

Rougher Flotation Results

     13-9   

Table 13-5:

  

Cleaner Flotation Results

     13-10   

Table 13-6:

  

Flotation Concentrate Leaching Results (Gold Assays)

     13-11   

Table 13-7:

  

Flotation Concentrate Leaching Results (Silver Assays)

     13-11   

Table 13-8:

  

Flotation Tailings Leaching Results

     13-12   

Table 13-9:

  

IsaMill Testwork Results

     13-13   

Table 13-10:

  

Stirred Media Detritor Testwork Results

     13-15   

Table 13-11:

  

Gravity Tailings Leach Results (Gold)

     13-17   

Table 13-12:

  

Gravity Tailings Leach Results (Silver)

     13-17   

`Table 13-13:

  

Crusher Work Index Results

     13-18   

Table 13-14:

  

JK Drop Weight and Corresponding SMC Results

     13-20   

Table 13-15:

  

SAG Mill Comminution SMC and Mia Values

     13-22   

Table 13-16:

  

SAGDesign Testwork Results

     13-23   

Table 13-17:

  

Comparison between SAGDesign and JK DWT Results

     13-24   

Table 13-18:

  

Bond and ModBond Results

     13-26   

Table 13-19:

  

Abrasion Index Results

     13-28   

Table 13-20:

  

SAG and Ball Mill Simulation Results1

     13-30   

Table 13-21:

  

Gravity Recoverable Gold Results

     13-32   

Table 13-22:

  

Additional Gravity Tailings Leaching Results (Gold Assays)

     13-35   

Table 13-23:

  

Additional Gravity Tailings Leaching Results (Silver Assays)

     13-36   

 

 

xxxiv


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 13-24:

  

Cyanide Concentration Testwork Results

     13-38   

Table 13-25:

  

Pre-Conditioning vs. No Pre-Conditioning Testwork Results

     13-39   

Table 13-26:

  

O2 vs. Air and Lead Nitrate Addition Testwork Results

     13-40   

Table 13-27:

  

Intrepid Zone Leaching Kinetics Tests (Gold)

     13-41   

Table 13-28:

  

Intrepid Zone Leaching Kinetics Tests (Silver)

     13-42   

Table 13-29:

  

Gold Leaching Variability Testwork Average Results

     13-43   

Table 13-30:

  

Silver Leaching Variability Testwork Average Results

     13-44   

Table 13-31:

  

Cyanide Destruction Testwork Results

     13-48   

Table 13-32:

  

Flocculant Description

     13-50   

Table 13-33:

  

Sedimentation Testwork Results

     13-51   

Table 13-34:

  

Linear Screen Sizing Testwork Results

     13-53   

Table 13-35:

  

Summary of Geochemical Environmental Testing

     13-54   

Table 13-36:

  

Residue and Gravity Recovery Curves

     13-56   

Table 13-37:

  

Simplified Gold and Silver Recovery Curves

     13-56   

Table 13-38:

  

Gold and Silver Recoveries vs. Head Grade

     13-57   

Table 13-39:

  

Average Yearly Gold and Silver Recoveries

     13-59   

Table 14-1:

  

Rock Codes in the Rainy River Project Block Model

     14-5   

Table 14-2:

  

Summary of Metal Capping Levels Applied to each Resource Domain

     14-12   

Table 14-3:

  

Basic Statistics for Gold Composites for All Resource Domains

     14-15   

Table 14-4:

  

Basic Statistics for Capped Gold Composites for All Resource Domains

     14-16   

Table 14-5:

  

Basic Statistics for Silver Composites for All Resource Domains

     14-17   

Table 14-6:

  

Basic Statistics for Capped Silver Composites for All Resource Domains

     14-18   

Table 14-7:

  

Basic Statistics of Composites for Domain 200 (Zone 34)

     14-19   

Table 14-8:

  

Basic Statistics for Calcium Uncapped Composites for All Resource Domains

     14-20   

Table 14-9:

  

Basic Statistics for Calcium Capped Composites for All Resource Domains

     14-21   

Table 14-10:

  

Basic Statistics for Sulphur Uncapped Composites for All Resource Domains

     14-22   

Table 14-11:

  

Basic Statistics for Sulphur Capped Composites for All Resource Domains

     14-23   

Table 14-12:

  

Modeled Gold Variogram Parameters for All Resource Domains Grade Interpolation

     14-26   

Table 14-13:

  

Modeled Silver Variogram Parameters for All Resource Domains Grade Interpolation

     14-27   

Table 14-14:

  

Modeled Calcium Variogram Parameters for All Resource Domains Grade Interpolation

     14-28   

Table 14-15:

  

Modeled Sulphur Variogram Considered for All Resource Domains Grade Interpolation

     14-29   

Table 14-16:

  

Rainy River Project Block Model Parameters

     14-30   

Table 14-17:

  

Resource Estimation Parameters for Part of the Main Rainy River Deposit Amenable to Open Pit Mining

     14-32   

Table 14-18:

  

Resource Estimation Parameters for the Part of the Main Rainy River Deposit Amenable to Underground Mining

     14-33   

Table 14-19:

  

Resource Estimation Parameters for the Intrepid Zone

     14-34   

 

 

xxxv


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-20:

  

Search Neighbourhoods Used for Gold and Silver Estimation in Main Rainy River

     14-34   

Table 14-21:

  

Search Neighbourhoods Used for Gold and Silver Estimation in Intrepid Zone

     14-35   

Table 14-22:

  

Search Neighbourhoods Used for Calcium

     14-36   

Table 14-23:

  

Search Neighbourhoods Used for Sulphur

     14-37   

Table 14-24:

  

Search Neighbourhoods Used for Grade Estimation in Zone 34

     14-38   

Table 14-25:

  

Search Parameters Used to Code the Measured Blocks

     14-40   

Table 14-26:

  

Conceptual Assumptions Considered for Open Pit Resource Reporting

     14-41   

Table 14-27:

  

Conceptual Assumptions Considered for Underground Resource Reporting

     14-42   

Table 14-28:

  

Consolidated Mineral Resource Statement*, Rainy River Project, Ontario, SRK Consulting (Canada) Inc., November 2, 20131,2,3,4,5

     14-45   

Table 14-29:

  

Mineral Resources1 for Zone 34 (Domain 200), Rainy River Project, Ontario, SRK Consulting (Canada) Inc., November 2, 2013

     14-46   

Table 14-30:

  

Mineral Resources1 for the Silver Zone (Domain 901), Rainy River Project, SRK Consulting (Canada) Inc., November 2, 2013

     14-46   

Table 14-31:

  

Open Pit Mineral Resources1, Rainy River Project, Ontario, SRK Consulting (Canada) Inc., November 2, 2013

     14-47   

Table 14-32:

  

Underground Mineral Resources1, Rainy River Project, Ontario, SRK Consulting (Canada) Inc., November 2, 2013

     14-47   

Table 14-33:

  

Global Block Model Quantities and Grade Estimates1 at Various Cut-Off Grades

     14-49   

Table 14-34:

  

Block Model Quantities and Grade Estimates1 at Selective Cut-off Grades - Potential Open Pit Mining Material

     14-50   

Table 14-35:

  

Block Model Quantities and Grade Estimates1 at Selected Cut-off Grades Potential Underground Mining Material

     14-50   

Table 14-36:

  

Comparison of the October 2012 and November 2013 Mineral Resource Statements

     14-52   

Table 15-1:

  

Pit Optimization Parameters

     15-5   

Table 15-2:

  

Mill COG Calculated at Various % Dilution and Gold Prices1

     15-8   

Table 15-3:

  

Detailed Open Pit Mine Design Parameters

     15-8   

Table 15-4:

  

Estimation of In-pit Dilution and Mine Recovery

     15-21   

Table 15-5:

  

Open Pit Mineral Reserves Statement1,2

     15-21   

Table 15-6:

  

Preliminary Estimation of Operating Costs and Breakeven Cut-off Grade

     15-25   

Table 15-7:

  

Updated Estimation of Breakeven Cost and COG

     15-26   

Table 15-8:

  

Au eq Calculation Parameters

     15-27   

Table 15-9:

  

Dilution Estimate for Hangingwall Slough and Blasting Over-break

     15-29   

Table 15-10:

  

Dilution Estimate from Backfill Sources

     15-30   

Table 15-11:

  

Underground Mineral Reserves Statement1

     15-30   

Table 15-12:

  

Open Pit and Underground Proven and Probable Mineral Reserves1,2,3,4,5,6

     15-31   

Table 16-1:

  

Recommended Overall Slope Geometry by Sector (AMEC, 2013F)

     16-3   

Table 16-2:

  

Waste Mine Rock and Low-Grade Ore Stockpile Design Parameters

     16-18   

 

 

xxxvi


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 16-3:

  

Waste Mine Rock Stockpile Characteristics

     16-18   

Table 16-4:

  

Low-Grade Ore Stockpile Characteristics

     16-19   

Table 16-5:

  

Overburden Stockpile Design Parameters

     16-19   

Table 16-6:

  

Overburden Stockpile Design Summary

     16-20   

Table 16-7:

  

Operating Shift Parameters

     16-22   

Table 16-8:

  

Equipment and Worker Operating Time

     16-23   

Table 16-9:

  

Major Equipment Availability and Utilization

     16-24   

Table 16-10:

  

Major Equipment Operator Skill

     16-24   

Table 16-11:

  

Drill and Blast Specifications

     16-26   

Table 16-12:

  

Truck Speed and Fuel Consumption (Loaded and Empty)

     16-27   

Table 16-13:

  

Annual Open Pit Mine Equipment Requirements

     16-31   

Table 16-14:

  

Annual Hourly Personnel Requirements

     16-34   

Table 16-15:

  

Salaried Open Pit Personnel Requirements

     16-35   

Table 16-16:

  

Lateral Development Design Parameters

     16-42   

Table 16-17:

  

Vertical Development Design Parameters

     16-42   

Table 16-18:

  

Stope Design Parameters

     16-44   

Table 16-19:

  

Life of Mine Backfilling Waste Rock

     16-53   

Table 16-20:

  

Ground Support Recommendations

     16-61   

Table 16-21:

  

Mobile Equipment Requirements - Contract Mining Phase

     16-66   

Table 16-22:

  

Underground Development and Production Equipment List

     16-67   

Table 16-23:

  

Support Equipment

     16-67   

Table 16-24:

  

Total Airflow Requirements

     16-74   

Table 16-25:

  

Estimated Heating Consumption

     16-77   

Table 16-26:

  

Underground Manpower Loading At Full Production

     16-92   

Table 16-27:

  

Open Pit and Underground Mine Production Schedule

     16-97   

Table 17-1:

  

General Process Design Criteria

     17-3   

Table 17-2:

  

Process Plant Power Demand by Area

     17-14   

Table 17-3:

  

Process Plant Reagent Consumption

     17-21   

Table 17-4:

  

Grinding Media Consumptions by Mill Type

     17-21   

Table 18-1:

  

Mining Vehicle Dimensions

     18-3   

Table 18-2:

  

Mining Vehicle Repair Bay Specifications

     18-4   

Table 18-3:

  

Staff Requirements

     18-5   

Table 18-4:

  

Estimated Total Project Power Demand

     18-7   

Table 18-5:

  

Proposed Emergency Generators

     18-9   

Table 18-6:

  

Tailings Dam Sizing

     18-11   

Table 18-7:

  

Construction Fill Materials (Figures 18-1 and 18-2)

     18-16   

 

 

xxxvii


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 18-8:

  

Summary of Water Management Ponds

     18-20   

Table 18-9:

  

Water Availability from the Pinewood River below the McCallum Creek Inflow

     18-21   

Table 18-10:

  

Summary of WTP Design Criteria

     18-25   

Table 18-11:

  

Expected Production of Sludge at Design Flow

     18-26   

Table 18-12:

  

Summary of Proposed Habitat Offset Balance for Schedule 2 Amendment Waterbodies

     18-31   

Table 18-13:

  

Summary of Proposed Habitat Offset Balance for Section 35(2) Authorization Waterbodies

     18-31   

Table 20-1:

  

Local Aboriginal Groups Engaged as Instructed by MNDM, December 2011

     20-3   

Table 20-2:

  

Aboriginal Groups Identified by the Provincial Government to be Consulted or Notified, May 2012

     20-4   

Table 20-3:

  

Aboriginal Groups Identified by the Federal Government through the Results of Preliminary Depth of Consultation, September 2012

     20-6   

Table 20-4:

  

Summary of Concerns and Proposed Approach to Resolve

     20-8   

Table 20-5:

  

Species at Risk Known to Occur in the Rainy River Project Environs

     20-22   

Table 20-6:

  

Anticipated Federal Environmental Approvals

     20-30   

Table 20-7:

  

Anticipated Provincial Environmental Approvals

     20-31   

Table 21-1:

  

Project Capital Cost Summary

     21-3   

Table 21-2:

  

Direct Costs by Discipline

     21-4   

Table 21-3:

  

Civil/Earthwork Quantities

     21-5   

Table 21-4:

  

Concrete Quantities

     21-5   

Table 21-5:

  

Structural Quantities

     21-5   

Table 21-6:

  

Architectural Quantities

     21-6   

Table 21-7:

  

Piping Quantities

     21-7   

Table 21-8:

  

Electrical Quantities

     21-7   

Table 21-9:

  

Labour Productivity Factors

     21-10   

Table 21-10:

  

Open Pit Mine Equipment Capital Cost

     21-13   

Table 21-11:

  

Site Development and Process Facilities Direct Costs

     21-14   

Table 21-12:

  

Indirect Costs

     21-16   

Table 21-13:

  

Sustaining Open Pit Mine Equipment

     21-21   

Table 21-14:

  

Life of Mine Underground Capital Costs

     21-23   

Table 21-15:

  

Underground Capital Cost Breakdown

     21-24   

Table 21-16:

  

Underground Capital Development Costs

     21-24   

Table 21-17:

  

Underground Equipment Purchases - Mobile

     21-25   

Table 21-18:

  

Underground Equipment Purchases - Fixed Plant

     21-26   

Table 21-19:

  

Contracted Construction Costs

     21-27   

Table 21-20:

  

Annual Project Operating Cost Summary ($ /t milled)

     21-30   

Table 21-21:

  

Annual Project Operating Cost Summary ($ M)

     21-30   

 

 

xxxviii


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 21-22:

  

Project Cash Cost Summary

     21-31   

Table 21-23:

  

Project Peak Personnel

     21-33   

Table 21-24:

  

Open-Pit Mining Cost Summary Per Period

     21-34   

Table 21-25:

  

Open Pit Mine Operating Cost Breakdown

     21-34   

Table 21-26:

  

LOM Underground Operating Costs by Activity

     21-37   

Table 21-27:

  

Underground Operating Costs Mine General Area

     21-38   

Table 21-28:

  

Processing Operating Cost Breakdown

     21-39   

Table 21-29:

  

Average General and Administrative Costs

     21-43   

Table 22-1:

  

Financial Model Criteria and Production Summary1,2

     22-3   

Table 22-2:

  

Operating Costs and Cash Costs over the LOM

     22-3   

Table 22-3:

  

Capital Costs over the LOM (M $CAD)

     22-4   

Table 22-4:

  

Financial Analysis Summary (Pre-tax and After-tax)

     22-6   

Table 22-5:

  

Rainy River Financial Model Summary (CAD$)

     22-6   

Table 22-6:

  

Sensitivity Results for Metal Price and Exchange Rate Variations (CAD $M)

     22-9   

Table 22-7:

  

Sensitivity Results for Metal Price and Exchange Rate Variations (USD $M)

     22-9   

Table 22-8:

  

Selected Sensitivities, Pre-Tax NPV at 5% Discount Rate (CAD $M)

     22-9   

Table 25-1:

  

Mineral Resource Statement, Rainy River Gold Project, Ontario,

     25-3   

Table 25-2:

  

Comparison of October 2012 and November 2013 Mineral Resource Statements

     25-4   

Table 25-3:

  

Open Pit and Underground Proven and Probable Mineral Reserves1,2,3,4,5,6

     25-5   

Table 26-1:

  

Budget for 2014 (US dollars)

     26-1   

 

 

xxxix


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LIST OF ABBREVIATIONS

 

$

  

Dollar sign

%

  

Percent sign

¢/kWh

  

Cent per kilowatt hour

°

  

Degrees

°C

  

Degrees Celsius

3D

  

3 Dimensional

a

  

Acres

AACE

  

American Association of Cost Engineers

AAS

  

Atomic Absorption Spectroscopy

Actlabs

  

Activation Laboratories

AF

  

Aggregate Fill

AI

  

Abrasion Index

ALS

  

ALS Minerals Laboratories

AMT

  

Audio Magneto-Telluric

ANFO

  

Ammonium Nitrate and Fuel Oil

APEGBC

  

Professional Engineers and Geoscientists of British Columbia

APEO

  

Association of Professional Engineers of Ontario

APGO

  

Association of Professional Geoscientists of Ontario

Au

  

Gold

bank

  

Bank cubic metre - volume in-situ

BFA

  

Bench Face Angles

BWI

  

Bond Ball Mill Work Index

C&F

  

Cut and Fill

CAD

  

Canadian Dollar

CAF

  

Cemented Aggregate Fill

CAPEX

  

Capital Expense Estimate

CDE

  

Canadian Development Expenses

CDN

  

CDN Resource Laboratories Ltd.

CEE

  

Canadian Exploration Expenditures

CHF

  

Cemented Hydraulic Fill

CICC

   Caracle Creek International Consulting Inc.

CIL

   Carbon-in-Leach

 

 

xl


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LIST OF ABBREVIATIONS

 

CIM

  

Canadian Institute of Mining, Metallurgy and Petroleum

CIP

  

Carbon-in-Pulp

CLRA

  

Construction Labour Relations Association

CM

  

Construction Management

CMT

  

Corporate Minimum Tax

COG

  

Cut off Grade

CRF

  

Cemented Rock Fill

CSA

  

Canadian Standards Assocation

CWI

  

Crusher Work Index

D2

  

Second generation of deformation

D3

  

Third generation of deformation

D4

  

Fourth generation of deformation

DDH

  

Diamond Drill Hole

DGPS

  

Differential Global Positioning System

DWI

  

Drop Weight Index

DWT

  

Drop Weight Test

DXF

  

Drawing Interchange Format

E

  

East

EA

  

Environmental Assessment

EAC

  

Estimate at Completion

EDF

  

Environmental Design Flood

ELC

  

Extended Life Coolants

ELOS

  

Equivalent Linear Overbreak/Slough

EO

  

Enterprise Optimization

EP

  

Engineering and Procurement

EPCM

  

Engineering, Procurement and Construction Management

FAR

  

Fresh Air Raise

FFCS

  

Fort Frances Chiefs Secretariat

FOS

  

Factor of Safety

FS

  

Feasibility Study

fw

   Footwall

G

   Grams

 

 

xli


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LIST OF ABBREVIATIONS

 

g/t

   Grams per tonne

Ga

   Billion years

gal.

   Gallons

G&A

   General and Administrative

GA

   General Arrangement

GIS

   Gas Insulated Switchgear

GRG

   Gravity Reconverable Gold

GSI

   Geological Strength Index

h

   Hour

ha

   Hectare

HAZOP

   Hazard and Operability

HBED

   Hudson’s Bay Exploration and Development

HF

   Hydraulic Fill

HP

   Horsepower

HPDE

   High-density polyethylene

HQ

   Drill core size (6.4 cm diameter)

HS

   High Strain (zone)

HSE

   Health Safety and Environmental

HVAC

   Heating, Ventilation and Air-Conditioning

HW

   Hangingwall

IESO

   Independent Electricity System Operator

IFRS

   International Financial Reporting Standards

INCO

   International Nickel Corporation of Canada

IRA

   Inter-ramp Angles

IRR

   Internal Rate of Return

IT

   Information Technology

JEF

   Job Efficiency Factor

KCB

   Klohn Crippen Berger Ltd.

kPa

   Kilopascal

kV

   Kilovolt

kW

   kilowatt

kWh

   kilowatt-hour

 

 

xlii


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LIST OF ABBREVIATIONS

 

LG

  

Lerchs-Grossmann

LH

  

Longhole

LHD

  

Longhole Drill

LHD trucks

  

Load, Haul, Dump trucks

LHOS

  

Longhole Open Stoping

LIMS

  

Local Information Management System

LOA

  

Living out Allowance

LOM

  

Life-of-Mine

M

  

Million

m/h

  

Metres/hour

Ma

  

Million years

masl

  

Meters above sea level

MFL

  

Manpower Forecasting and Leveling

Mm3

  

Million cubic metres

MMBtu/h

  

1 Million British Thermal Units Per Hour

MMI

  

Mobile Metal Ion

MNO

  

Métis Nation of Ontario

MNDM

  

Ministry of Northern Development and Mines

MNR

  

Ministry of Natural Resources

MOE

  

Ministry of Environment

MOT

  

Ministry of Transportation of Ontario

MOU

  

Memorandum of Understanding

MPC

  

Mine Power Centre

MRC

  

Mechanized Raise Climber

MRP

  

Mine Rock Pond

MSE

  

Mechanically Stabilized Earth

MSO

  

Mineable Shape Optimizer

Mt

  

Million tonnes

Mtpa

  

Million tonnes per annum

MTO

  

Material Take-Offs

MW

  

Megawatt

N

  

North

 

 

xliii


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LIST OF ABBREVIATIONS

 

NAG

  

Non-Acid Generating

Nb

  

Number

NECA

  

National Electrical Contractors Association

NI

  

National Instrument

NOH

  

Net Operating Hours

NP

  

Acid Neutralizing Capacity

NPAG

  

Not Potentially Acid-Generating

NPI

  

Net Profits Interest

NPR

  

Neutralization Potential Ratio

NPV

  

Net Present Value

NQ

  

Drill core size (4.8 cm diameter)

NSR

  

Net Smelter Return

OB

  

Overburden

OIQ

  

Ordre des ingénieurs du Québec

OGS

  

Ontario Geological Survey

OMC

  

Orway Mineral Consultants

OMT

  

Ontario Mining Tax

OP

  

Open pit

OPA

  

Official Planning Amendment

OPEX

  

Operational Expenditure

OSA

  

Overall Slope Angles

Owner

  

Rainy River Resources Ltd.

oz.

  

ounce

oz./t

  

ounce per tonne

PA

  

Participation Agreement

PAAC

  

Participation Agreement Advisory Committee

PAG

  

Potential Acid-Generating

PEA

  

Preliminary Economic Assessment

PEO

  

Professional Engineers Ontario

PEP

  

Project Execution Plan

PF

  

Paste Fill

PGA

  

Peak Ground Acceleration

 

 

xliv


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LIST OF ABBREVIATIONS

 

pH

  

percentage hydrogen

PLC

  

Programmable Logic Controller

POF

  

Probability of Failure

POV

  

Pre-Operation Verification

ppb

  

part per billion

ppm

  

part per million

PRV

  

Pressure Reducing Valve

Q1

  

First Quarter

Q2

  

Second Quarter

Q3

  

Third Quarter

Q4

  

Fourth Quarter

QA/QC

  

Quality Assurance/Quality Control

QP

  

Qualified Person

RF

  

Unconsolidated Rock Fill

RLOM

  

Remaining-Life-of-Mine

RPM

  

Revolutions Per Minute

RQD

  

Rock Quality Designation

RRGB

  

Rainy River Green Belt

RRR

  

Rainy River Resources Ltd.

RRU

  

Rainy River Underground

RWI

  

Bond Rod Mill Work Index

S

  

South

SAG

  

Semi-Autogenous Grinding

SCIM

  

Squirrel Cage Induction Motor

SEDAR

  

System for Electronic Document Analysis and Retrieval

SG

  

Specific Gravity

SMC

  

SAG Mill Comminution

SMD

  

Stirred Mill Detritor

SP

  

Stockpile Pond

t/h

  

Tonnes per hour

tpa

  

Tonnes per annum

tpd

  

Tonnes per day

 

 

xlv


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LIST OF ABBREVIATIONS

 

TMA

  

Tailings Management Area

TMAP

  

Tailings Management Area Pond

TSX

  

Toronto Stock Exchange

UCS

  

Uniaxial Compressive Strength

UG

  

Underground

USD

  

United States Dollar

UTM

  

Universal Transverse Mercator

VCR

  

Vacuum Recloser

VFD

  

Variable Frequency Drive

VMS

  

Volcanogenic Massive Sulphide

VOD

  

Ventilation on Demand

VOIP

  

Voice Over Internet Protocol

VPSA

  

Vacuum Pressure Swing Adsorption

W

  

West

WBS

  

Work Breakdown Structure

WCP

  

West Creek Pond

WDP

  

Water Discharge Pond

WMP

  

Water Management Pond

XRD

  

X-ray diffraction

X

  

X coordinate (E-W)

mm

  

Microns

Y

  

Y coordinate (N-S)

Z

  

Z coordinate (depth or elevation)

ZBLA

  

Zoning by-law Amendment

 

 

xlvi


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

1. EXECUTIVE SUMMARY

 

1.1 Introduction

The Rainy River Project (the “Project”) is an advanced gold exploration project located 50 km northwest of Fort Frances, in northwestern Ontario. A takeover bid for Rainy River Resources Ltd. (“Rainy River” or “RRR”) by New Gold Inc. (“New Gold”) commenced on June 18th, 2013 and following completion of the bid and subsequent compulsory acquisition resulted in New Gold acquiring ownership of 100% of Rainy River’s outstanding shares. The compulsory acquisition was completed as of October 15th, 2013. Rainy River continues to exist as a separate legal entity from New Gold and is a wholly-owned subsidiary of New Gold.

In August 2013, New Gold requested that BBA Inc. (“BBA”) prepare an updated Feasibility Study (the “Feasibility Study” or “the Study”) from the original 2013 Feasibility Study issued on May 23, 2013. This Feasibility Study was prepared and compiled by BBA in a collaborative effort with New Gold and a number of specialized consultants. This Technical Report was prepared according to the guidelines set out under the requirements of National Instrument 43-101 Standards of Disclosure for Mineral Projects (“NI 43-101”) and to support a feasibility study on the Project as disclosed in New Golds press release entitled “New Gold Announces Its Rainy River Feasibility Study Results”, dated January 16, 2014.

The main intent of the updated Feasibility Study was to ensure that the key inputs and assumptions used for the Project were consistent with those used for New Gold’s other projects and operations as well as provide a technical and economic review of the potential mining operations, based on the Company’s most recent mineral resource estimate (November 2, 2013) and other recent project definition activities such as metallurgical test work. The mineral resources used in the Feasibility Study are based on updated drilling database and block model information as of August 16, 2013 (including the Intrepid Zone). The Feasibility Study is based on the development of a combined open pit (19,500 tpd) and underground mining operation (1,500 tpd), feeding a conventional process plant to recover gold and silver mineralization. The process plant will have a capacity of 21,000 tonnes per day.

All monetary units in the Report are in Canadian dollars (“CAD”), unless otherwise specified. Costs are based on fourth quarter (“Q4”) 2013 dollars.

 

 

1-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

1.2 Contributors and Qualified Persons

This Technical Report has been prepared for New Gold based on work prepared by a number of independent consultants. A summary of the Qualified Persons and Study contributors, their areas of responsibility and site visit dates are listed in Table 1-1.

Table 1-1: Feasibility Study Qualified Persons

 

Consulting Firm or Entity

  

Area of Responsibility

   Qualified
Person(s)
  

Last Site Visit

SRK Consulting (Canada) Inc.    Geological modelling and resource definition.    Glen Cole

Dorota El-Rassi

  

April 30-May 2, 2013

No site visit

BBA Inc.    Open pit mine design, production scheduling, processing plant design, site infrastructure, capital costs, operating costs, financial analysis and overall integration.    David Runnels

Patrice Live

Colin Hardie

  

October 11, 2012 October 11, 2012

June 16, 2011

AMC Mining Consultants (Canada), Ltd.    Underground mine design, production scheduling, capital cost and operating costs.    Colm Keogh

Mo Molavi

  

September 26, 2013

No site visit

AMEC Environment & Infrastructure    Tailings, waste rock and water management, environmental baseline, closure plan. Open pit and underground geomechanics and geotechnical investigations.    David Ritchie

Sheila Daniel

Adam Coulson

  

September 4, 2013

May 19, 2011

September 25-27, 2013

Other Study contributors included Merit Consultants Inc., who provided the schedule, support for the capital cost estimate and constructability. Wayne Clark, of SanZoe Consulting Inc., provided consulting for applications to IESO (Independent Electricity System Operator) and Hydro One Network, energy costs and technical assistance for the high voltage transmission line. Rob Frenette of TBT Engineering Ltd. provided consulting for the Highway 600 reroute and the East Access Road construction.

 

1.3 Key Outcomes

Key outcomes from the Feasibility Study are summarized in Table 1-2, Table 1-3 and Table 1-4, and include the following:

 

 

Direct processing Proven and Probable Mineral Reserves for the combined open pit and underground operations total 66.9 Mt grading 1.54 g/t Au and 3.26 g/t Ag. Total stockpile Proven and Probable Mineral Reserves total 37.4 Mt grading 0.38 g/t Au and 1.99 g/t Ag;

 

 

1-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

Planned processing rate is 21,000 tpd, and a mine life of 14 years (not including two (2) years of pre-production) or 16 years including pre-production years;

 

 

Commissioning starts in Q4 2016. Full production will be reached by the end of Q1 2017;

 

 

Planned overburden removal of 74 M tonnes over a period of seven (7) years;

 

 

The operational open pit stripping ratio, excluding waste and overburden stripping during the development phase is 3.5:1.0;

 

 

The overall open pit stripping ratio (LOM) is 3.91 (waste and overburden to ore ratio); and

 

 

Low-grade ore stockpiles created during the first 8 years will be processed in Years 9 to 14;

Table 1-2: Key Outcomes - Gold Production1

 

Parameter

   Units    Outcome         

Total Average Gold Grade (Years 1 – 9)

   g/t      1.44         ILLEGIBLE   

Total Average Gold Grade (LOM)

   g/t      1.12      

Average Open Pit Gold Grade (LOM)

   g/t      0.96      

Average Underground Gold Grade (LOM)

   g/t      4.96      

Total Gold Production from Open Pit (LOM)

   koz.      2,797      

Total Gold Production from Underground (LOM)

   koz.      605      

Total Gold Production (LOM)

   koz.      3,402      

Average Annual Gold Production (LOM)

   koz.      243      

Average Process Plant Gold Recovery (LOM)

   %      90.6      

 

  1.  Total gold production after mining and processing. Table excludes 0.4 Mt of material milled in the preproduction period.

Table 1-3: Key Outcomes - Silver Production1

 

Parameter

   Units    Outcome         

Total Average Silver Grade (Years 1 – 9)

   g/t      3.07         ILLEGIBLE   

Total Average Silver Grade (LOM)

   g/t      2.80      

Average Open Pit Silver Grade (LOM)

   g/t      2.48      

Average Underground Silver Grade (LOM)

   g/t      10.31      

Total Silver Production from Open Pit (LOM)

   koz.      5,115      

Total Silver Production from Underground (LOM)

   koz.      889      

Total Silver Production (LOM)

   koz.      6,004      

Average Annual Silver Production (LOM)

   koz.      429      

Average Process Plant Silver Recovery (LOM)

   %      64.1      

 

  1.  Total silver production after mining and processing. Table excludes 0.4 Mt of material milled in the preproduction period.

 

 

1-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 1-4: Key Outcomes – Capital Expenses and Financial Results1

 

Parameter

   Units    Outcome         

Open Pit Initial Project Capital (incl. Process Plant and Infrastructure)

   $M      931         ILLEGIBLE   

Total Sustaining Capital3

   $M      366      

Total Royalty Payments

   $M      43      

LOM Average Total Cash Cost2

   USD/oz. Au      663      

LOM Average All-in Sustaining Cost2,4

   USD/oz. Au      765      

Pre-tax Net Present Value @ 0% discount rate

   $M      983      

Pre-tax Net Present Value @ 5% discount rate

   $M      462      

Pre-tax Internal Rate of Return

   %      13.1      

Pre-tax Payback Period

   Years      5.4      

After-tax Net Present Value @ 0% discount rate

   $M      774      

After-tax Net Present Value @ 5% discount rate

   $M      330      

After-tax Internal Rate of Return

   %      11.3      

After-tax Payback Period

   Years      5.5      

 

  1. 

The financial analysis was conducted using long term consensus averages of USD $1,300/oz. Au and USD $22/oz. Ag. The United States to Canadian dollar exchange rate was assumed to be CAD $0.95:USD $1.00 during pre-production and operations. A discount rate of 5% was used.

  2. 

Includes silver credits and royalty payments.

  3. 

Funded by internal cash flows.

  4. 

All in sustaining costs accounts for operating expenditures and sustaining capital expenditures.

 

1.4 Property Description

The Rainy River Project is situated in the southern half of Richardson Township, part of the larger Township of Chapple, approximately 50 km northwest of Fort Frances in northwestern Ontario, Canada. The village of Emo is located approximately 25 km to the south on Highway 11. The Project property is approximately 160 km south of Kenora and 420 km west of Thunder Bay.

The Rainy River Project property comprises a portfolio of 162 patented mining rights and surface rights land claims, including three (3) leasehold interest mining rights land claims, and 81 unpatented mining claims covering an aggregate area of 17,018 hectares in the townships of Fleming, Mather, Menary, Pattullo, Potts, Richardson, Senn, Sifton, and Tait. All unpatented mining claims are in good standing and have sufficient work assessment credits available to maintain this good standing for several years. Assessment work of at least $400 per year is required to maintain interest in the staked claims and keep unpatented mining claims valid.

 

 

1-4


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The Rainy River Project property is divided into two (2) main physiographical regions separated by a distinct northwest to southeast divide, locally termed the Rainy Lake - Lake of the Woods Moraine. The bedrock is overlain by glacial till, which is in turn overlain by silts and clays. The Rainy River Project area is sparsely populated.

 

1.5 Accessibility, Climate, Local Resources, Infrastructure and Physiography

The climate is typically continental, with temperatures ranging from plus 35°C to minus 40°C. Average rainfall in the region is approximately 60 cm, while approximately 150 cm of snowfall is recorded annually.

The Project site is easily accessible by a network of secondary all-weather roads that branch off the well-maintained Trans-Canada Highways 11 and 71. Access roads are serviced, allowing year-round access. The Canadian National Railway is located 21 km to the south and runs east-west, immediately north of the Minnesota border. The nearby towns and villages of Fort Frances, Emo and Rainy River are located along this railway line.

 

1.6 Project History

The Rainy River Project has attracted exploration interest since 1967. Various companies, including Noranda, International Nickel Corporation of Canada, Hudson’s Bay Exploration and Development and Mingold Resources, operated in the area centered on the Project between 1967 and 1989.

The Ontario Geological Survey undertook geological mapping in 1971, and again from 1987 to 1988, in conjunction with a rotasonic overburden drilling program. Nuinsco Resources Limited (“Nuinsco”) undertook exploration activities between 1990 and 2004, with Rainy River continuing from 2005 onwards.

Nuinsco drilled a series of widely spaced reverse circulation drill holes from 1994 to 1998, defining a 15 km long “gold-grains-in-till” dispersal train emanating from a thickly overburden-covered, 6 km2 “gold-in-bedrock” anomaly. Nuinsco completed a series of diamond drilling programs to assess the mineral potential of the above anomalies that led to the initial discovery of the 17 Zone in 1994. Nuinsco subsequently discovered the 34 Zone in 1995 and the 433 Zone in 1997. Between 1994 and 1998, Nuinsco drilled 597 reverse circulation holes and 217 diamond drill core holes (49,515 m); these were mostly in the Richardson area. The 34 Zone was further drill-tested between 1999 and 2004.

 

 

1-5


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

In June 2005, Rainy River completed the acquisition of a 100% interest in the Project from Nuinsco. That same year, Rainy River relogged key sections of the historical core drilled on the Project property and then inputted all data into a GIS database. Rainy River subsequently drilled in excess of 100 reverse circulation holes in three (3) phases to better define the “gold-in-till” and “gold-in-bedrock” anomalies.

Between 2005 and 2007, 209 diamond drill holes, totalling 95,340 m, were drilled. In April 2008, a mineral resource estimate was completed by Caracle Creek International Consulting. In 2009, SRK prepared a mineral resource statement incorporating information from an additional 112 core holes (59,719 m), drilled during 2008. In early 2010, SRK Consulting (Canada) Inc. (“SRK”) prepared a revised mineral resource statement to incorporate information from an additional 124 core holes (68,453 m), drilled on the Project during 2009.

On February 24, 2011, SRK updated the mineral resource statement to incorporate information from an additional 163 core holes (84,648 m), drilled on the Project during 2010. A subsequent update, dated June 29, 2011, was prepared by SRK to consider additional drilling (50 core holes, 26,509 m) completed on the Project between December 2010 and February 27, 2011. This resource update was the basis for the Preliminary Economic Assessment (“PEA”) announced in Rainy River’s November 9, 2011 press release and filed by Rainy River on SEDAR on December 23, 2011. A complete summary of drilling on the Rainy River Project between 1994 and 2013 is presented in Chapter 10, in Table 10-1.

A PEA Update was announced in Rainy River’s August 29, 2012 press release and filed by Rainy River on SEDAR on October 12, 2012. A Feasibility Study technical report for the project was filed by Rainy River on SEDAR on May 17, 2013. The mineral resources used in the original 2013 Feasibility Study are based on updated information issued in a press release by Rainy River on October 10, 2012,

In June 2013, New Gold began acquiring ownership of RRR shares pursuant to a takeover bid. Following the completion of a compulsory acquisition as of October 15, 2013, New Gold owns 100% of Rainy River’s outstanding shares. RRR continues to exist as a separate legal entity from New Gold and is a wholly-owned subsidiary of New Gold.

 

 

1-6


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

This Feasibility Report is based on drilling data for the main Rainy River deposit comprising 1,435 core holes (662,849 m) and additional drilling data from 230 core holes (79,575 metres) for the adjacent Intrepid Zone.

 

1.7 Geological Setting and Mineralization

The Rainy River Project falls within the 2.7 billion year old Rainy River Greenstone Belt that forms part of the Wabigoon Subprovince. The Wabigoon Subprovince is a 900 km long east-west trending area of komaiitic to calc-alkaline metavolcanics that are in turn succeeded by clastics and chemical sediments. Granitoid batholiths have intruded into these rocks, forming synformal structures in the supracrustals that often have shear zones along their axial planes.

The Wabigoon basement rocks and remnant Mesozoic cover sediments are overlain by Labradorian till of northeastern provenance. This till has been found to contain anomalous concentrations of gold grains, auriferous pyrite and copper-zinc sulphides. It is overlain by a glaciolacustrine clay and silt horizon and by argillaceous and calcareous Keewatin till of western provenance.

The Rainy River Project is primarily underlain by a series of tholeiitic mafic rocks that are structurally overlain by calc-alkalic intermediate to felsic metavolcanic rocks. Intermediate dacitic rocks host most of the gold mineralization. At a regional scale, the strongest and earliest deformation event produced a well-defined penetrative fabric. This foliation is approximately parallel to the trend of the metavolcanic rocks that strike at approximately 120 degrees and dip 50 to 70 degrees to the south.

Structural geology studies by SRK suggest that the current geometry and westerly plunge of the gold mineralization is the result of high strain deformation features associated with gold mineralization and rotating the mineralization plunge parallel to the stretching direction.

 

1.8 Deposit Types

Four (4) main styles of mineralization have been identified on the Rainy River Project:

 

 

Moderately to strongly deformed, auriferous sulphide and quartz-sulphide stringers and veins in felsic quartz-phyric rocks (e.g., ODM/17, Beaver Pond, 433 and HS Zones);

 

 

Deformed quartz-ankerite-pyrite shear veins in mafic volcanic rocks (e.g., CAP/South Zone);

 

 

1-7


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

Deformed sulphide-bearing quartz veinlets in dacitic tuffs/breccias hosting enriched silver grades (e.g., Intrepid Zone); and

 

 

Copper-nickel-platinum group metals mineralization hosted in a younger mafic-ultramafic intrusion (e.g., 34 Zone).

The gold mineralization is interpreted as a hybrid deposit type, consisting of an early gold-rich volcanogenic sulphide mineralization overprinted by shear-hosted mesothermal gold mineralization. Magmatic-hydrothermal copper-nickel-platinum mineralization occurs within the main auriferous zones and crosscuts the volcanogenic sulphide mineralization and the later mesothermal gold mineralization associated with the regional deformation.

 

1.9 Exploration

In August 2012, exploration drilling discovered a significant new gold and silver zone approximately 1 km east of the proposed Open Pit boundary of the Rainy River Project. Drill hole NR121258 intersected 2.2 g/t gold and 38.5 g/t silver over 18.5 m, including 6.0 g/t gold and 83.9 g/t silver over 3.0 m at a vertical depth of 210 m. This new zone, named the Intrepid Zone, clearly demonstrates the potential for new discoveries along strike and the greater area surrounding the known zones of mineralization. The new zone was discovered after Mobile Metal Ion (“MMI”) geochemistry identified areas of anomalous gold over the prominent magnetic low trend that hosts the majority of the Rainy River Project deposits. The new zone contains disseminated and fracture-related mineralization, including 2-3% pyrite and variable amounts of sphalerite, galena and chalcopyrite. Both electrum and visible gold have also been identified in drill core. A total of 230 core holes have been completed to delineate the Intrepid Zone over a 410 m strike length, tracing the mineralization down dip to a depth of 450 m below surface. The Intrepid Zone has been included in all aspects of this Study.

 

1.10 Drilling

Nuinsco and Rainy River drilled a combined total of 1,435 core holes (662,849 m) on the main Rainy River deposit between 1994 and 2012. Prior to 1999, Nuinsco also drilled several reverse circulation holes to sample basal till and bedrock for exploration targeting. Reverse circulation drilling data was not used for resource estimation. An additional 230 core holes (79,575 metres) were drilled in the Intrepid Zone since 1996, with the majority of core holes being drilled by Rainy River between August 2012 and June 2013 (225 core holes: 77,969 metres).

 

 

1-8


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

SRK is of the opinion that the drilling procedures adopted by Rainy River are consistent with industry best practices and the resulting drilling pattern is sufficiently dense to interpret with confidence the geometry and boundaries of the gold mineralization.

 

1.11 Sampling Method, Approach and Analyses

There are no records describing the sampling method and approach used by Nuinsco during their 1994 to 2004 drilling program. Previously unsampled intervals within mineralized parts of the Nuinsco drill core have been identified and selectively sampled by Rainy River. This additional sampling was incorporated into the drill hole database used for mineral resource estimation.

Rainy River used industry best practices to collect, handle and assay core samples collected during the 2005 to 2012 period. All drilling and sampling were conducted by appropriately qualified personnel under the direct supervision of appropriately qualified geologists.

From early 2005 to late 2006, Rainy River used the accredited ALS Minerals Laboratories (“ALS”) in North Vancouver, British Columbia for sample preparation and analyses. From late 2006 to January 2011, samples were sent primarily to the accredited Accurassay Laboratory (“Accurassay”) facility in Thunder Bay, Ontario. Accurassay used industry standard preparation procedures and standard fire assay procedures for precious metals analysis and aqua regia digestion and atomic absorption spectrometry for metal analysis. In February 2011, Rainy River began using ALS as the primary laboratory for the Project. ALS is accredited by the Standards Council of Canada and its quality management system is accredited to ISO 9001:2008.

Rainy River has relied partly on the internal quality control measures of the accredited laboratory; however, they have also implemented external analytical quality control measures, consisting of inserting control samples (blanks and certified reference material, and field duplicates) with each batch of drill core samples submitted for assaying. In the opinion of SRK, the field sampling and assaying procedures used by Rainy River meet industry best practices.

 

1.12 Data Verification

In accordance with National Instrument 43-101 guidelines, Glen Cole, P.Geo. from SRK has visited the Project property on numerous occasions since 2008. His last visit to the site was from April 30 to May 2, 2013. SRK was given full access to all relevant project data during the mineral resource estimation process.

 

 

1-9


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

SRK conducted a series of routine verifications to ensure the reliability of the electronic data provided by Rainy River. SRK ensured the validation of all tables using Gemcom® validation tools that check for gaps, overlaps and out of sequence intervals. SRK has summarized the assay results for the external quality control samples on time series, plots bias charts, quantile-quantile and relative precision plots.

Since Rainy River commissioned ALS in February 2011, there has been an overall improvement in the performance of quality control samples. It is SRK’s opinion that gold grades can be reasonably reproduced, suggesting that the assay results reported by the primary assay laboratories are generally sufficiently reliable for the resource estimation used in this Feasibility Study.

 

1.13 Metallurgical Test work

 

1.13.1 Historical Test work

Initial metallurgical test work was carried out at SGS Canada Inc. (“SGS”) in Lakefield, Ontario from 2008 to 2011 and was the basis for the PEA Update issued publicly on October 12, 2012. The test work included mineralization, comminution, gravity separation, flotation, flotation concentrate leaching, and whole ore leaching. Results from the test work indicated that the material was moderately hard. The recovery for a flotation concentrate circuit was estimated at 88.5% with the flotation feed ground to 150 µm and the flotation concentrate ground to 15 µm. The recovery for the whole ore leach circuit was estimated at 91.0% when ground to 60 µm.

 

1.13.2 Mineralogy

Gold deportment studies were performed at SGS on samples from each zone from 2011 and 2012, including: five ODM, two 433, one CAP, one HS and one NZ sample.

 

 

The samples were composed mainly of non-opaque minerals, with minor amounts of pyrite present;

 

 

The gold occurs mainly as native gold, electrum and kustelite. Small amounts of Petzite (Ag3AuTe2) were also noted;

 

 

1-10


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

The gold occurs as liberated, attached and locked particles in most of the samples at a grind size of 150 µm, except for the CAP zone sample;

 

 

The gold grain size was relatively fine in all samples, with coarse gold (>100 µm) noted only in two (2) of the composites (HS and one of the 433 zone samples); and

 

 

Trace amounts of pyrrhotite were noted in approximately half the samples.

 

1.13.3 Flowsheet Determination Test work

The majority of flowsheet testwork for the Feasibility Study was conducted at SGS between 2011 and 2013. Various tests, such as grindability, were conducted by suppliers.

Gravity Tailings Leaching

Leaching tests were performed on gravity tailings to compare with a flotation concentrate leach option. The tests were done at grind sizes ranging from 50 to 120 µm. The results from the tests showed gold recoveries of approximately 92% (1% higher than historical test work) could be achieved. Low reagent consumptions during the tests were also noted.

Flotation Concentrate Leaching

The use of a flotation circuit prior to leaching was investigated. In this processing option, the concentrate from the flotation circuit is leached while the flotation tailings are discarded. The results indicated that an overall circuit gold recovery of approximately 87.5% (1% lower than historical test work) could be achieved by grinding the flotation concentrate to 15 µm. This ultrafine grind had a high energy requirement and the flotation concentrate leach had high reagent consumptions. As such, this process was not further evaluated.

Flowsheet Selection

The gravity tailings leach option was selected in favour of the flotation concentrate option based on the testwork results and is therefore the basis for this Feasibility Study. The main reason for this selection was the significant amount of energy associated with regrinding the flotation concentrate and the high cyanide consumption in flotation concentrate leaching, as well as the additional risk associated with ultrafine grinding of this material. All testwork following this decision was based on the cyanide leaching of gravity tailings.

 

 

1-11


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

1.13.4 Comminution Tests

A larger than average scale comminution test work program, providing a high level of confidence in the result interpretation, was undertaken to determine the sizing of the semi-autogenous (“SAG”) mill and ball mill. The larger than average testwork program provided a high level of confidence in the interpretation of the results. The tests included 21 crushing work index tests (seven (7) at three (3) separate testing facilities), 16 Bond Ball Mill Work Index (“BWi”), 160 ModBond Ball Mill Work Index, 13 JK Drop Weight tests and 175 SAG Mill Comminution tests (“SMC”). In addition, seven (7) samples were sent to Starkey and Associates for SAGDesign testing.

Results from the test work indicated that the Rainy River material is considered to be hard and relatively resistant to breakage. Based on the test work results, the following design parameters were determined for the Feasibility Study: Crusher Work Index of 25.0 kWh/t; A x b of 24.2; Bond Ball Work Index (200 mesh open side setting) of 15.0 kWh/t; Bond Abrasion Index of 0.25 g. All design parameters were based on the 80th percentile of test work results.

The large test work campaign provides confidence that the values obtained are representative of the deposit.

Grinding Circuit Design

Four (4) methods and a consultant were used to size the grinding circuit based on the test work results: Morrell’s Equation, JK SimMet with Bond Equation, JK SimMet with Phantom Cyclone, SAGDesign and Orway Mineral Consultants (“OMC”) as an outside consultant.

All methods yielded similar grinding circuit energy requirements. The lowest overall circuit energy requirement was estimated using SAGDesign at 25.45 kWh/t, while Morrell’s Equation yielded the highest circuit energy requirement at 28.64 kWh/t. The combined JK SimMet and Bond Equation method is the recommended design, resulting in a 26.63 kWh/t circuit energy requirement, including 13.2 kWh/t for the SAG mill and 13.0 kWh/t for the ball mill. This matches well with the energy requirement calculated by OMC.

Recent test work performed on the Intrepid Zone material indicates that the material is more variable than the main pit; however, it should not impact the grinding circuit design if blended at low percentages.

 

 

1-12


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

1.13.5 Gravity Separation

Two (2) Gravity Recoverable Gold (“GRG”) tests were performed on Zone composites representing the ODM and 433 Zones. The GRG numbers from these tests were 51.2 and 59.3, respectively, indicating that the ore responds to gravity separation and that the addition of a gravity circuit is beneficial to the process.

 

1.13.6 Cyanide Leaching

Additional Gravity Tailings Leaching

Additional gravity tailings leaching tests were performed to determine the retention time and grind size for the variability test work campaign. Based on these results, a grind size of 75 µm and a retention time of 36 h (with sub-sampling at 30 h) were selected for the variability test program.

Additional test work was performed to verify the effect of cyanide concentration, preconditioning, use of oxygen versus air and lead nitrate. The variability leaching test work was developed based on results from these tests.

Variability Tests

Cyanide leaching was performed on 208 samples (along with 37 repeats) and the results were used to develop grade-recovery curves for both gold and silver. The average residue value for all the samples was 0.10 g/t Au for the zones other than CAP and 0.16 g/t for the CAP Zone. These residues corresponded to a recalculated gold recovery of approximately 90-91% and 66-67% silver recovery.

The following gold residue (“Au res”) and silver residue (“Ag res”) versus head grade equations (exponential based) were developed using the variability test work results:

 

Non-CAP Zones

  

CAP Zone

Au res = 0.0937 • xAu0.4223    Au res = 0.2497 • xAu1.015
Ag res = 0.0148 • xAu2 + 0.294 xAg    Ag res = 0.0363 • xAu2 + 0.245 xAg

 

 

1-13


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The large leaching test work campaign has provided significant information regarding the metallurgical response of the material throughout the deposit. This level of test work reduces the risk that design production levels will not be achieved in operation.

Test work performed on 30 samples from the Intrepid Zone indicated that this material performed comparably to material from the Non-CAP zones. This material has to be blended due to high silver content.

 

1.13.7 Cyanide Destruction Test work

The SO2/air cyanide destruction process was investigated on three (3) composites: initial pit, remaining life-of-mine and Intrepid Zone. The results showed that this process is effective at lowering the weak acid dissociable cyanide (“CNWAD”) levels to well below 5 ppm. The average reagent consumptions for the main pit samples were 4.7, 3.5 and 0.1 g/gCNWAD for SO2, lime and copper, respectively.

Cyanide destruction test work was also performed on a sample from the Intrepid Zone. The first test yielded high residual cyanide values, however a repeat of the test showed results in line with the main pit.

 

1.13.8 Environmental Test work

AMEC Environment & Infrastructure is conducting environmental geochemical characterizations of selected samples, representative of the mine rock and overburden in the vicinity of the proposed Rainy River Project open pit, and tailings produced in metallurgical test work. To date, testing has been carried out on three (3) simulated tailings materials, and a total of 659 deposit-wide mine rock samples, of which 366 represent in-pit non-ore mine rock.

Geochemical studies to date on the mine rock indicate that approximately half the samples may have the potential to produce acid rock drainage. A block model was developed to refine the estimated tonnage of potentially acid generating rock. Generally, metal contents in mine rock materials are typical for their rock types and the risk for metal leaching under neutral conditions appears to be low. Humidity cell analysis is ongoing on the mine rock to evaluate the long term metal leaching characteristics of these materials. Preliminary results have identified a potential risk of short term neutral metal leaching (cadmium and zinc) from the tailings. These results suggest that a simple lime treatment system may be required for the Tailings Management Area (“TMA”) discharge to the water management pond during operations, but not post-closure.

 

 

1-14


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The results of the mine rock and tailings analyses indicate a risk for acid rock drainage from a portion of the Rainy River Project mineral waste in the future, if not appropriately managed. The Rainy River Project design has taken this into account in the operation and closure of the east mine rock stockpile and TMA.

 

1.13.9 Test work Interpretation

Results from the SGS test work are the basis for the mineral reserve estimate and Feasibility Study. Based on a trade-off study performed in 2012, it was determined that the whole rock leaching option with gravity separation was the most economical alternative compared to the flotation option, and was therefore used as the basis for the Feasibility Study. The main reason for this selection was the significant amount of energy associated with regrinding the flotation concentrate and the high cyanide consumption in the flotation concentrate leaching, in addition to risk associated with ultrafine grinding of this material. All subsequent test work was based on cyanide leaching of the gravity tailings.

The extensive grinding test work campaign has allowed for definition of the overall hardness of each zone and indicated that there are a number of portions of the deposit that will have high energy requirements and this will be reflected in the design of the process plant. The strong correlation between the five (5) methods used to size the grinding circuit provides a good level of confidence in the sizing of the SAG and ball mill.

Test work performed on the Intrepid Zone indicates that the material should not impact design if blended at low tonnage rates. Given the high silver grade of this material, it is not recommended to be blended at high tonnage due to downstream effects on carbon-in-pulp (“CIP”) and elution.

The process is expected to yield an overall gold recovery of approximately 90-91% and a silver recovery of approximately 66-67% over the life-of-mine without considering solution losses. When considering solution losses, the gold recovery decreases by an average of 0.6% while the silver recovery drops to approximately 64%. The grind size chosen for this study was 75 µm, based on a cost versus revenue study performed by BBA. Eight (8) agitated leach tanks will be used in a series arrangement, allowing for a 30 hour retention time. Seven (7) CIP tanks will be required with a total circuit retention time of 117 minutes. The gold recovery varies significantly throughout the deposit and the CAP Zone has considerably lower gold recoveries than the other zones. As such, the mine plan is based on stockpiling most of the CAP Zone material and processing it at the end of the mine life.

 

 

1-15


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

1.14 Mineral Resource Estimate

The mineral resource estimate presented herein represents the ninth resource evaluation for the Rainy River Project since 2008. The resource estimate was completed by Dorota El-Rassi, P.Eng. (APEO #100012348) and Glen Cole, P.Geo. (APGO #1416) from SRK, both independent Qualified Persons as defined by Canadian National Instrument 43-101. The effective date of the Mineral Resource Statement is November 2, 2013.

The Rainy River database comprises data from 1,665 core holes (743 km), drilled by Nuinsco and Rainy River up to August 16, 2013. All exploration information is located using a UTM grid (NAD 83 datum, 15 Zone). Resource modelling and grade estimation were conducted in this UTM coordinate space. SRK updated a series of previously constructed 3D wireframes used to constrain the extent of the gold mineralization, considering structural features, lithology, alteration, geochemical indices, as well as grade trends. For the main Rainy River deposit, 13 distinct mineralized zones with further domains within these were constructed and used as hard boundaries for estimating the mineral resource. An additional three mineralized zones were defined for estimating the Intrepid Zone mineral resource.

For geostatistical analysis, variography and grade estimation, raw assay data were composited to 1.5 m lengths. The impact of grade capping was analyzed - and capping levels were adjusted for each resource domain and each metal separately to constrain the influence of extreme high grade composite intervals. Capping was applied to the composited data. An unrotated block model was created to cover the entire extent of the Rainy River deposit area. An independent block model was created for the Intrepid Zone. Block sizes varied from 5 x 5 x 5 m for mineral resources amenable to underground extraction to 10 x 10 x 10 m for mineral resources amenable to open pit extraction.

Variography was undertaken to characterize the spatial continuity of gold and silver within each resource domain and to assist with the selection of estimation parameters. Metal grades were estimated separately using ordinary kriging as the principal estimator in each domain from capped composite data within that domain. Grades in domains 601 to 605 were estimated using

 

 

1-16


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

an inverse distance algorithm. Three (3) estimation passes, using search neighborhoods sized from variography results, were used to populate the block models. The first estimation pass generally considered search neighborhoods adjusted to half or full variogram ranges, with the search ellipse then doubled for the second and third estimation pass.

The mineral resources were classified as Measured, Indicated and Inferred, primarily determined on the basis of block distance from the nearest informing composites and on variography results. The classification strategy was based on gold data alone and also considered the geological setting of the project.

SRK considers that portions of the Rainy River gold mineralization are amenable for open pit extraction, while other parts of the deposits could be extracted using an underground mining methods. To assist with determining which portions of the modelled mineralization show “reasonable prospect for economic extraction” from an open pit, and to assist with selecting reasonable reporting assumptions, SRK used a Lerchs-Grossman 3D open pit optimizer to develop conceptual open pit shells to delimit the zones of mineralization reported in the mineral resource statement for the Project.

The block models were also reviewed to determine which portions of the gold mineralization have “reasonable prospects for economic extraction” from an underground mine. The mineral resource for the Rainy River Project is reported at two (2) cut-off grades (Table 1-5). The effective date of the Mineral Resource Statement is November 2, 2013. Open pit mineral resources are reported at a cut-off grade of 0.30 g/t gold, whereas underground mineral resources are reported at a cut-off grade of 2.5 g/t gold.

 

 

1-17


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 1-5 - Consolidated Mineral Resource Statement, Rainy River Gold Project,

SRK Consulting (Canada) Inc., November 2, 20131,2,3,4,5

 

            Grade      Metal  
     Quantity      Au      Ag      Au      Ag  

Category

   ‘000t      gpt      gpt      ‘000 oz      ‘000 oz  

Direct Processing Material

              

Open Pit2

              

Measured

     20,282         1.45         1.93         947         1,261   

Indicated

     80,411         1.35         2.55         3,486         6,584   

O/P Measured & Indicated

     100,693         1.37         2.42         4,433         7,846   

Inferred

     9,388         0.97         2.28         292         687   

Underground2

              

Measured

     89         4.95         2.75         14         8   

Indicated

     5,469         4.53         11.34         796         1,994   

Measured & Indicated

     5,558         4.53         11.20         810         2,002   

Inferred

     2,641         4.46         8.30         379         707   

Stockpile Material3

              

Open Pit

              

Measured

     6,294         0.37         1.29         74         262   

Indicated

     64,816         0.44         2.17         919         4,526   

Measured & Indicated

     71,110         0.43         2.09         993         4,788   

Inferred

     8,626         0.37         1.16         102         323   

Combined Direct Processing and Stockpile Mineral Resources

              

Measured

     26,665         1.21         1.79         1,035         1,531   

Indicated

     150,696         1.07         2.70         5,202         13,104   

Measured and Indicated

     177,361         1.09         2.57         6,236         14,635   

Inferred

     20,655         1.16         2.58         773         1,717   

 

1 

Mineral resources are reported in relation to conceptual pit shells which are limited to 150 m below sea level and are inclusive of the Intrepid Zone.

2 

Open pit mineral resources are reported at a cut-off grade of 0.30 g/t gold, underground mineral resources are reported at a cut-off grade of 2.50 g/t gold based on a gold price of US$1,400 per ounce, a silver price of US$24.00 per ounce, a foreign exchange rate of C$1.10 to US$1.00, gold recovery of 88% for open pit resources, 90% for underground resources and a silver recovery at 75% for all mineral resources.

3 

Direct processing material is defined as all mineralization above a cut-off of 0.45 g/t gold and likely to be mined and processed directly.

4 

Stockpile material includes all material within conceptual open pit shells above a cut-off of 0.30 g/t gold and below a 0.45 g/t gold cut-off as well as material within the CAP zone (code 500) that is suitable for stockpiling and future processing based on average metallurgical recoveries of 88% gold and 75% silver.

5 

Qualified Persons – The mineral resource statement was prepared by Dorota El-Rassi, P. Eng. (APEO #100012348) and Glen Cole (APGO #1416) from SRK Consulting (Canada) Inc, both independent “Qualified Persons” as that term is defined in Canadian National Instrument 43-101.

 

 

1-18


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

1.15 Open Pit and Underground Mine Design

The evaluation of the open pit reserves was carried out under the supervision of Patrice Live (BBA) and the underground reserves were evaluated by Colm Keogh (AMC). The open pit reserves were generated from the block model provided by SRK effective November 2nd, 2013 consisting of block sizes measuring 10 m x 10 m x 10 m. The original 2013 Feasibility Study used smaller sized blocks (previously 5 m x 5 m x 5 m). To better optimize the open pit and underground portions of the mineral resources for mine planning, two (2) further block models, covering the underground portion of the main ODM zone and Intrepid Zone were provided by SRK for the estimation of the underground reserves. The underground block models retained the 5 m x 5 m x 5 m block size used in the previous 2013 Feasibility Study.

This Feasibility Study assumes both open pit and underground mining methods will be used for reserve extraction. The milling throughput rate was established at 21,000 tpd (19,500 tpd from the open pit and 1,500 tpd from underground when full production is achieved). The open pit operations will deliver material to a gyratory crusher for primary size reduction and delivery to the processing plant. Ore from the underground operation will be fed to a portable crushing system for size reduction and tramp metal removal prior to being delivered to the gyratory crusher. New Gold’s mining equipment and personnel is expected to be used for the development of the open pit, as well as for the removal of overburden. In addition, a combination of New Gold personnel and various contractors will be used for the underground development and on-going production activities.

 

1.15.1 Open Pit Mine

Open Pit Mine Design

Surface mining at the Rainy River Project will follow the standard practice of an open pit operation, with conventional drill and blast, load and haul cycles using a drill/truck/shovel mining fleet.

In order to develop an optimal engineered pit design for the Rainy River deposit, BBA used the Lerchs-Grossman 3D (“LG 3D”) routine in MineSight. The pit optimizer searches for the pit shell with the highest undiscounted cash flow. It uses defined pit optimization parameters, including gold and silver prices, mining, processing and other indirect costs, Au and Ag recoveries for each ore type (as determined from metallurgical test work), pit slopes (by AMEC based on geotechnical pit slope study) and constraints. The main pit optimization parameters used in the LG 3D routine are listed in Table 1-6:

 

 

1-19


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 1-6: Pit Optimization Parameters1

 

Type of Activity

   Unit    Values     

Mining Cost of Rock

   $/t mined    1.95    ILLEGIBLE

Mining Cost of Overburden

   $/t mined    1.50   

Processing Cost

   $/t milled    8.65   

General and Administration Cost

   $/t milled    1.21   

Gold Recovery

   %    89.9   

Gold Recovery for CAP zone

   %    74.3   

Silver Recovery

   %    67.1   

Silver Recovery for CAP zone

   %    69.5   

Gold Selling Price

   USD/oz.    Intentionally varied
from 300 to 1100
  

Silver Selling Price

   USD/oz.    25   

Exchange Rate

   CAD/USD    1.05   

Overall Pit Slope Angle

   degree    Varies from 37 to 53
depending on zone
  

Overall Overburden Slope Angle

   degree    16   

Pit Limitation

      RRP Property   

Depth/elevation constraint

   masl    -50   

 

  1.

Pit optimization parameters differ from the final operating cost figures. The pit optimization parameters were taken as the initial iteration to determine the optimized pit shell.

Using the technical and economic parameters described previously, the MineSight LG 3D pit optimizer tool was run to produce a series of pit shells for a series of revenue factors. Once the series of pit shells was generated, the total material moved, total open pit resource and stripping ratios were evaluated to identify the optimum pit shell. The selected optimized mineral reserve pit shell for this Study is based on a gold price of USD $800/oz. The selection methodology was based on the stripping ratio and a mine life of approximately 15 years to maximize the NPV.

The optimum pit shell selected was used as a guide to carry out the detailed mine design using the design parameters discussed in Chapter 15. Access to the pit uses a 10% gradient ramp, 33 m wide, to accommodate large size trucks for double-traffic lane haulage. Overburden and rock slope configurations and angles were all based on geotechnical design recommendations provided by AMEC.

 

 

1-20


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

1.15.2 Underground Mine

The underground mine design supports the extraction of 1,500 tpd of ore by longitudinal, longhole open stoping (“LHOS”), a mining technique suitable for the geometry and ground conditions of the Rainy River underground resources. Backfilling with cemented aggregate fill (“CAF”) is a significant aspect of the Project with respect to maximization of both resource recovery and mining productivity.

Ore occurs in sub-vertical horizons in varying widths from approximately 3 m to 20 m. Widths over 15 m are rare, and the weighted average across all zones is approximately 8 m. The ore footwall and hanging wall generally dip at 60 degrees or more, but can flatten locally to as low as 45 degrees in some areas.

Ore-grade mineralization occurs in seven independent areas of differing geometry and grade. The spatial separation defines multiple working areas that support the projected 1,500 tpd production rate, and has afforded the flexibility in the production schedule to recover higher grade material earlier in the life of mine.

Rock mass conditions are projected to be generally very good and little water ingress is anticipated.

The underground Mineral Reserves include material from both longhole stopes and the development within mineralized horizons required to access those stopes.

A 3.5 g/t Au-Eq (gold equivalent) cut-off grade was applied for the purpose of delineating the stoping inventory based on a preliminary estimate of operating costs of $112/t, which implied a breakeven cut-off grade of approximately 3.2 g/t Au-Eq. A lower (1.5 g/t Au-Eq) cutoff grade was applied to development within mineralized horizons on the basis that the mining cost is effectively sunk, and the remaining costs to process this material as mill feed are marginal. A more detailed discussion of cut-off grade is presented in Chapter 15.

All underground Mineral Reserves have been classified within the Probable category, and have been estimated from Measured and Indicated Mineral Resources through an appropriate consideration of practical mining constraints, ore recovery estimates and dilution estimates. Inferred Mineral Resources that are contained within the design mining shapes were assigned zero grade values, consistent with the CIM definition for mineral reserves.

 

 

1-21


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

1.15.3 Open Pit and Underground Reserves

The combined open pit and underground mine mineral reserves are summarized in Table 1-7.

Open pit mine reserves are reported at a COG (cut-off grade) of 0.30 g/t Au-Eq, whereas underground reserves are reported at a COG of 3.5 g/t Au-Eq. The summary of mineral reserves includes both dilution and mining recovery factors. The Open Pit reserves are calculated using a mining dilution of 4% at a grade of 0.21 g/t Au and 1.19 g/t Ag. The Underground mineral reserves incorporate 8.3% dilution overall, projected to come from hanging-wall (hw) rock over-break and sloughing, and also from backfill dilution. Rock over-break is included in the stope volumes such that the over-break grade is not reported separately. Backfill dilution is assumed to carry no metal grades. Mining recoveries of 95% and 96.5% have been assumed for open pit and underground reserves, respectively.

 

 

1-22


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 1-7: Open Pit and Underground Proven and Probable Mineral Reserves1,2,3,4,5,6

 

Mineral Reserves Category

   Tonnage
(‘000 t)
     Au Grade
(g/t)
     Ag Grade
(g/t)
     Contained
Metal Au (koz)
     Contained
Metal Ag (koz)
 

Direct Processing Material

              

Open Pit

              

Proven

     15,839         1.47         2.04         746         1,038   

Probable

     46,866         1.26         3.05         1,896         4,594   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Underground

              

Proven

     —           —           —           —           —     

Probable

     4,187         4.96         10.31         668         1,388   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Total Direct Processing Material

     66,892         1.54         3.26         3,311         7,021   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Stockpile Material

              

Open Pit

              

Proven

     6,843         0.38         1.51         84         332   

Probable

     30,541         0.39         2.10         378         2,058   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Total Stockpile Material

     37,384         0.38         1.99         462         2,390   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Combined Direct Processing and Stockpile Material

              

Open Pit

              

Proven

     22,681         1.14         1.88         830         1,370   

Probable

     77,407         0.91         2.67         2,275         6,652   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Total

     100,088         0.96         2.49         3,105         8,022   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Underground

              

Proven

     —           —           —           —           —     

Probable

     4,187         4.96         10.31         668         1,388   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Total

     4,187         4.96         10.31         668         1,388   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Total Combined

              

Proven

     22,681         1.14         1.88         830         1,370   

Probable

     81,594         1.12         3.06         2,943         8,040   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

TOTAL

     104,275         1.13         2.81         3,773         9,410   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

 

1.

Open pit mineral reserves have been estimated using an optimized pit shell based on metal prices of USD $800 per ounce gold and USD $25 per ounce silver, a foreign exchange rate of CAD$1.05 to USD$1.00, gold recovery of 89.9% (non-CAP zone) and 74.3% (CAP zone) and a silver recovery of 67.1% (non-CAP zone) and 69.5% (CAP zone). The cut-off grade is based on a gold price of $USD 1,200. Underground reserves have been estimated from mining shapes generated using a cut-off grade of 3.5 g/t gold-equivalent. Development material from stope access drives above a cut-off grade of 1.5 g/t gold-equivalent and is also assumed to be sent to the mill for processing. Underground breakeven cut-off grade calculated at 2.75 g/t gold- equivalent based on metal prices of $USD 1,300 per ounce gold and $USD 22 per ounce silver, a foreign exchange rate of CAD$1.05 to USD$1.00, gold recovery of 95% and a silver recovery of 75%.

2.

Open pit reserves have been estimated using a dilution of 4% at 0.21 g/t Au and 1.19 g/t Ag. An average dilution of 11.7% for the underground stoping (8.3% total underground, inclusive of development ore), which includes dilution from both overbreak and backfill. Open pit and underground reserves have been estimated using a mining recovery of 95% and 96.5%, respectively.

3.

Open Pit direct processing material is defined as mineralization likely to be mined and processed directly and above a variable cut-off grade ranging from 0.3-0.7 g/t.

4.

Stockpile material includes all material within designed open pit between variable cut-offs described above in Note 3, as well as material within the CAP zone (code 500) that is suitable for stockpiling and future processing.

5.

Mineral Reserves for the open pit are derived from the August 6, 2013 resource model. Models for the underground reserves were derived from the August 2013 and September 2013 models for the main ODM zone and Intrepid Zone, respectively. Models were prepared by Dorota El-Rassi, P.Eng. (APEO #100012348) and Glen Cole, P.Geo. (APGO #1416), of SRK, both independent “Qualified Persons” as that term is defined in Canadian National Instrument 43-101. The combined mineral resource statement, including the Intrepid Zone was provided to BBA on November 2, 2013. Rainy River’s exploration program in Richardson Township is being supervised by Mark A. Petersen, (AIPG Certified Professional Geologist #10563), Vice President, Exploration for New Gold and a “Qualified Person” as defined in Canadian National Instrument 43-101. New Gold continues to implement a rigorous QA/QC program to ensure best practices in drill core sampling, analysis and data management.

6.

Qualified persons - The open pit portion of the mineral reserve statement was prepared under the supervision of Patrice Live (OIQ #38991) of BBA, and the underground portion of the mineral reserve statement was prepared by Colm Keogh, P.Eng. (APEGBC #37433) of AMC Mining Consultants (Canada) Ltd., both independent “Qualified Persons” as that term is defined in Canadian National Instrument 43-101.

 

 

1-23


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

1.16 Mining Methods

The Feasibility Study assumes both open pit and underground mining methods will be used for ore extraction. The mining methods and production capacity have been chosen to match a milling throughput rate of 21,000 tpd.

Open Pit and Underground Geotechnical Design

The feasibility level site investigation work, open pit slope design criteria for slope stability, underground mine design criteria for stope stability, sequencing, ground support and backfill, were performed by AMEC (AMEC 2012F, 2012G, 2013A, 2013B, 2013C, 2013D, 2013E, 2013F, 2013v) supervised by Adam Coulson (AMEC) and provided to BBA for open pit design and to AMC for underground mine design. This includes an updated review of the Intrepid Zone and a re-evaluation of the geomechanical mine design in the ODM/17 zones (AMEC 2014A).

During the 2012 AMEC geomechanical drilling campaign, assessment of various rock structural domains was based on the analysis, ten (10) NQ-sized core holes totaling 4,500 metres, with geomechanical logging of oriented core and packer testing down the holes to understand the hydrogeological characteristics. These drill holes were oriented in various azimuths, dipping on average at 65° in order to intersect potential open pit walls, known geological features and the three main underground zones of the ODM/17 (West, Central and East). This investigation work was supported with acoustic televiewer surveys by DGI Geoscience Inc. of ten (10) exploration core holes to confirm the orientation of the major joint sets at depth. Subsequent to this, further work was performed by New Gold with orientation of four (4) core holes for structure evaluation in the Intrepid Zone. These boreholes were further geomechanically logged by AMEC to provide design criteria for the Intrepid Zone (AMEC 2014A).

A total of 176 core samples were collected for laboratory strength testing by AMEC, with 268 test specimens prepared. From these, 117 specimens were tested for uniaxial compressive strength (“UCS”), 42 for triaxial strength, 100 for Brazilian tensile strength, and nine (9) for direct shear tests of open joints. Elastic properties (Young’s Modulus and Poisson’s ratio) were also assessed on 20 specimens. Additionally, for backfill strength assessment under various binder mixes by AMEC, two (2) bulk samples of potentially acid generating and potentially non-acid generating waste rock in excess of 1,000 kg each were sampled and crushed for short and long-term strength testing.

 

 

1-24


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Based on the field and laboratory investigations, open pit slope stability design criteria for optimized bench face angles, inter-ramp angles and overall slope angles was performed using probabilistic kinematic and limit equilibrium structural analyses, including numerical analyses. Similarly the underground stope dimensions, ground support requirements, backfill strength and effects of stope sequencing on development and ground support levels, were performed with a combination of numerical stress modeling and recognized empirical design tools.

 

1.16.1 Open Pit Operations

Conventional open pit mining has been chosen as the primary method to extract the Rainy River deposit because of the deposit’s geometry and proximity to the surface. The primary equipment fleet at the peak of operations consists of: three (3) hydraulic shovels (2 x 26 m3, 1 x 29 m3), one (1) wheel loader (18 m3), 22 haul trucks (220 t class), three (3) DTH drills (8.5”) and a fleet of support equipment. Operating bench heights of 10 m have been planned for mining operations. Over the life of the mine, a total of 318.2 Mt of waste rock and 73.6 Mt of overburden will be moved. It is anticipated that all overburden will be removed within the first seven (7) years of mine operation. At the peak of open pit mining, a workforce of 318 persons (staff and hourly employees) will be required. Mined waste and overburden will be stored in nearby stockpiles or used in dam construction activities associated with the Tailings Management Area (“TMA”) or blended in cement and used as backfill material for the underground mine.

 

 

1-25


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

1.16.2 Open Pit Production Schedule

The open pit mine schedule is shown in Table 1-8.

Table 1-8: Open Pit Mine Schedule

 

Year

(Period)

  OP Stripping
Ratio
(excluding
Stockpile)
    OP Stripping
Ratio
(including
Stockpile)
    Open Pit Direct                                                  
      Processing
(Mine to Mill)
    Mine to Stockpile     Stockpile to Mill     Waste
Rock
    Overburden  
      Mt     Au
(g/t)
    Ag
(g/t)
    Mt     Au
(g/t)
    Ag
(g/t)
    Mt     Au
(g/t)
    Ag
(g/t)
    Mt     Mt  

2015 (Y-2)

              0.16        0.71        1.84              8.82        13.40   

2016 (Y-1)

        0.38        1.50        3.00        0.75        0.45        1.76              12.71        11.88   

2017 (Y1)

    5.15        6.06        7.54        1.44        2.13        6.83        0.42        1.56              26.70        12.13   

2018 (Y2)

    6.95        7.51        7.65        1.48        1.95        4.30        0.41        1.46              42.72        10.44   

2019 (Y3)

    7.29        8.13        7.47        1.37        3.03        6.31        0.37        1.91              45.39        9.01   

2020 (Y4)

    7.63        8.25        7.43        1.31        2.65        4.61        0.41        1.93              44.90        11.80   

2021 (Y5)

    7.25        7.95        7.24        1.14        4.59        5.03        0.38        2.94              47.63        4.90   

2022 (Y6)

    6.23        7.06        7.11        1.17        4.18        5.91        0.35        2.43              44.33     

2023 (Y7)

    4.20        4.63        7.11        1.21        2.59        3.09        0.34        1.78              29.84     

2024 (Y8)

    1.77        1.84        7.11        1.30        1.88        0.48        0.30        1.20              12.60     

2025 (Y9)

    0.36        0.71        3.58        1.41        1.59              3.54        0.42        1.50        2.54     

2026 (Y10)

                    7.12        0.39        1.45       

2027 (Y11)

                    7.21        0.37        1.88       

2028 (Y12)

                    7.52        0.34        2.54       

2029 (Y13)

                    7.66        0.33        2.11       

2030 (Y14)

                    4.41        0.55        2.33       
 

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

 

Grand Total

    3.91        6.85        62.62        1.31        2.79        37.46        0.39        1.99        37.46        0.39        1.99        318.18        73.57   
 

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

 

Figure 1-1 shows the various stages of the open pit. Phase I is indicated by the pink outline. Phase II is indicated by the green outline and the final pit is outlined in purple.

 

 

1-26


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 1-1: Phase I, Phase II and Final Pit

 

1.16.3 Underground Mine Infrastructure

Key mine infrastructure includes a 4 km main access decline from a surface portal located to the east of the open pit, internal production ramps servicing each mining zone, ventilation intake shafts equipped with surface heating plant, ventilation exhaust raises, a backfill delivery raise that terminates at an underground truck loading station, a cement storage and grout mixing facility, two main dewatering stations, an equipment maintenance facility, electrical substations, and other smaller, ancillary installations.

Development dedicated to definition drilling activities has been incorporated into the overall design where required.

Figure 1-2 illustrates the geometry of development infrastructure and mining areas against the backdrop of the open pit.

 

 

1-27


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 1-2: Isometric View of the Rainy River Underground Mine

 

1.16.4 Underground Operations

Longitudinal LHOS proceeds along the strike of the orebody in increments (stopes) of dimensions that consider ground quality, support requirements and other practical considerations.

Stopes that are typically 20 m in length along strike and 20 m high underpin the life of mine plan, associated development requirements and mining costs, and the projected productivity of the underground mine. Actual mining experience, particularly with respect to ground conditions, will test the performance of this basic unit, and both height and length can eventually be optimized.

At the Rainy River Project, LHOS in each zone will proceed in a retreating pattern from the strike extent of ore to a common access point on all levels. Mining proceeds upwards from the lowest level of the zone or from an adopted sill elevation, with backfill providing the working platform for each successive lift.

Once mucking of blasted ore is complete, backfilling commences with the placement of a sufficient volume of CAF to provide stability of the backfill that is re-exposed during the extraction of the next stope in sequence. Once this volume of CAF has been placed, un-cemented waste from underground development or from surface is used to fill the remaining void – see Figure 1-3.

 

 

1-28


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 1-3: Typical Stope Long Section and Cross Sections

Trackless mobile equipment will be used for the majority of mining activities.

Ore handling from the underground workings to surface will be accomplished by a modern fleet of 7 m3 loaders and 45t haulage trucks. Loading will occur in close proximity to the stoping areas and will be hauled directly to a surface coarse ore stockpile adjacent to the portal. Primary crushing will be performed on surface in a dedicated jaw crusher as an essential measure to capture tramp steel before the underground ore stream is rehandled into the gyratory crusher that also services the open pit.

 

 

1-29


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

1.16.5 Underground Development and Production Schedule

Underground mine development will commence in 2017 after production from the open pit has started, leading to the projected recovery of 4.2 Mt of ore grading 4.96 g/t Au and 10.31 g/t Ag over a 12 year LOM.

An extensive underground development program that attains a peak of 560 m/month of jumbo advance is required to develop and maintain access to adequate resources to sustain 1,500 tpd of ore production. The ramp-up period to full production from the underground operation will require five years from the onset of underground mine development in 2017. Full production will be achieved in 2022. Waste generated through infrastructure development will be disposed of in underground stopes whenever operationally practical, however, an estimated excess of 1.80 Mt must be hauled to the surface waste stockpile over the life of mine.

Significant vertical raising is required to establish the primary ventilation circuit, and to provide backfill to the underground mine. Infrastructure development, including vertical raising and the construction of underground installations, will largely be accomplished by contractors.

Table 1-9 presents the annual underground ore production schedule.

 

 

1-30


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 1-9: Underground Production Schedule

 

     Longhole Stoping      Ore Development      Total  

Year

   (kt)      Au (g/t)      Ag (g/t)      (kt)      Au (g/t)      Ag (g/t)      (kt)      Au (g/t)      Ag (g/t)  

2017 (Year 1)

     0         0         0         0         0         0         0         0         0   

2018 (Year 2)

     0         0         0         17         4.65         24.79         17         4.65         24.79   

2019 (Year 3)

     106         4.75         31.05         92         4.18         34.58         198         4.48         32.69   

2020 (Year 4)

     185         5.43         39.63         51         4.05         4.22         237         5.13         31.94   

2021 (Year 5)

     290         5.87         13.85         135         4.57         3.75         425         5.46         10.65   

2022 (Year 6)

     373         5.24         6.68         178         5.48         2.77         551         5.31         5.41   

2023 (Year 7)

     387         5.86         3.78         165         3.77         6.64         552         5.23         4.63   

2024 (Year 8)

     444         5.56         2.58         109         3.32         17.78         554         5.12         5.58   

2025 (Year 9)

     461         5.19         7.77         89         3.58         12.35         550         4.93         8.51   

2026 (Year 10)

     401         4.54         4.55         142         4.65         3.28         543         4.57         4.21   

2027 (Year 11)

     436         4.35         14.17         8         5.59         10.89         443         4.37         14.12   

2028 (Year 12)

     119         4.29         19.94         0         0         0         119         4.29         19.94   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Total

     3,201         5.16         10.52         986         4.33         9.64         4,187         4.96         10.31   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

 

1.16.6 Proposed Overall Mine Plan (Open Pit and Underground)

The proposed Project will be a combined open pit (19,500 tpd) / underground (1,500 tpd) operation with approximately 104 Mt of material being processed over the life-of-mine at a nominal mill daily throughput of 21,000 tpd (7.67 Mtpa). The open pit mine production rate is planned to be approximately 21,000 tpd of mill feed material initially (2017). Development of the underground mine will start in 2017. The underground mine will come on line in 2019 and the open pit production rate will gradually decrease to 19,500 tpd when the underground operation reaches full production (2022). The mine schedule contains two (2) years of pre-production and envisions a mine operating life of 14 years, exclusive of the pre-production period.

The open pit mine schedule is based on pushback designs by BBA and has followed recommendations as presented in Whittle Consulting’s Enterprise Optimization (“EO”) report. The EO process is an integrated approach to maximizing the Net Present Value (“NPV”) of a mining business using methods described in Whittle’s EO report. It was conducted to support the PEA Update, the original 2013 Feasibility Study and this Feasibility Study.

Production is based on an elevated cut-off grade strategy, whereby low-grade material will be stockpiled near the primary crusher for future processing. The objective of this strategy is to obtain a higher average milling grade of the open pit direct processing material in the early years to maximize the Project’s cash flow and economics. The low-grade stockpiles will be reclaimed gradually at the end of the mine life or on an as-needed basis.

 

 

1-31


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Figure 1-4 presents the total gold and silver production based on the mill feed source of ore: open pit (“OP”)direct processing, underground (“UG”) direct processing and stockpile reclaim. The gold and silver production are based on the project’s recovery curves.

Over the life-of-mine, 2,814 koz. of gold and 5,139 koz. of silver will be recovered after processing from the open pit operation (average open pit LOM grade, including lower grade stockpile: 0.96 g/t Au and 2.49 g/t Ag) and 605 koz. of gold and 889 koz. of silver will be recovered from the underground operation with an average underground LOM grade: 4.96 g/t Au and 10.31 g/t Ag. Total production (including gold and silver produced during the pre-production period) of 3,419 koz. of gold and 6,028 koz. of silver is expected from the Rainy River Project.

 

LOGO

Figure 1-4: Combined Gold and Silver Production

The combined open pit and underground mine schedule is presented in Table 1-10.

 

 

1-32


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 1-10: Total Milled from OP and UG

 

     Total Milled UG and OP  

Year

   (Mt)      Au (g/t)      Ag (g/t)  

2014 (Year - 3)

     —           —           —     

2015 (Year - 2)

     —           —           —     

2016 (Year - 1)

     0.38         1.50         3.00   

2017 (Year 1)

     7.54         1.44         2.13   

2018 (Year 2)

     7.67         1.48         2.00   

2019 (Year 3)

     7.67         1.45         3.80   

2020 (Year 4)

     7.66         1.43         3.56   

2021 (Year 5)

     7.67         1.38         4.92   

2022 (Year 6)

     7.67         1.46         4.27   

2023 (Year 7)

     7.66         1.50         2.74   

2024 (Year 8)

     7.66         1.57         2.15   

2025 (Year 9)

     7.67         1.21         2.04   

2026 (Year 10)

     7.66         0.68         1.64   

2027 (Year 11)

     7.66         0.60         2.59   

2028 (Year 12)

     7.64         0.40         2.81   

2029 (Year 13)

     7.66         0.33         2.11   

2030 (Year 14)

     4.41         0.55         2.33   
  

 

 

    

 

 

    

 

 

 

TOTAL

     104.3         1.13         2.81   
  

 

 

    

 

 

    

 

 

 

 

1.17 Process Plant

The process plant facility is designed to have an availability of 92% and a capacity of 21,000 tpd (7.67 Mtpa). This includes an ultimate contribution of 1,500 tpd from the underground mine. Average head grade for the plant is 1.13 g/t Au while the design grade is 2.5 g/t Au, in order to accommodate periods of higher grade feed in the early years of the mine life. The average silver head grade is 2.81 g/t Ag while the design grade is 6.0 g/t Ag.

Run-of-mine material will be crushed to 165 mm in a 1,372 mm x 1,905 mm (54" x 75") gyratory crusher (596 kW) and then stockpiled. The primary crusher building houses the gyratory crusher and the tail-end of the stockpile feed conveyor.

 

 

1-33


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The crushed rock will be withdrawn from beneath the stockpile, conveyed and ground to approximately 2,800 µm in an 11.0 m x 6.1 m (36' x 20'), 15,000 kW SAG mill, in closed circuit with a scalping screen and a pebble crusher. The 448 kW pebble crusher will crush the scalping screen oversize to 13 mm. The undersize from the scalping screen will be combined with the ball mill discharge and pumped to the cyclone cluster. The underflow from the cyclone cluster will feed the 7.9 m x 12.3 m (26' x 40.5') 15,000 kW ball mill. A portion of the ball mill discharge will be treated by a gravity circuit, which includes an intensive cyanidation unit and dedicated electrowinning cell. The gravity tailings will be returned to the ball mill pump box.

The cyclone overflow will be thickened in a pre-leach thickener. The pre-leach thickener underflow will be pumped to the cyanide leaching circuit with one (1) series of eight (8) 18 m diameter tanks. The leach circuit has been designed for approximately 30 hours retention time. The discharge from the leach circuit will flow by gravity to a carousel-style CIP circuit with seven (7) tanks, where the leached gold and silver will be adsorbed onto the carbon. The slurry containing the loaded carbon will be pumped from the CIP circuit and then screened, and the oversized material (loaded carbon) will be sent to the carbon stripping circuit. The pregnant solution from carbon stripping will be cooled in a heat exchanger and discharged into two (2) series of electrowinning cells. The gold and silver will be recovered as sludge in the electrowinning cells, filtered, dried and then smelted into a doré bar. The coarse spent carbon from the stripping circuit will be reactivated in a kiln, while the fine carbon will be bagged and sold for silver and gold credit.

The tailings from the CIP circuit will be sent to the pre-detox tailings thickener. The objective of the pre-detox thickener is to recycle residual cyanide from the CIP tailings. Cyanide bearing water is recovered in the thickener underflow and is used to dilute the leach feed. The underflow from the thickener will be diluted with non-cyanide bearing process water prior to being pumped to cyanide destruction. The SO2/air process will be used to lower the cyanide level in the tailings to an acceptable level.

A schematic flowsheet of the process is presented in Figure 1-5.

 

 

1-34


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 1-5: Schematic Process Flowsheet

 

 

 

LOGO

 

1-35


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

A steel building will house the grinding area and the gold refinery. Mill reagents, grinding steel and maintenance supplies will be delivered to the site by transport truck and stored in the mill, as required.

In order to minimize fresh water use, a portion of the process water for the mill facility will be made-up using reclaim water from the tailings pond area. Additional make-up water will also come from the mine rock pond.

Overall gold recovery of the proposed circuit will be approximately 90.6% for the LOM (life-of-mine) and silver recovery will be approximately 64.1%. It is estimated that 91 people (staff and hourly employees) will be required for the process plant operations.

 

1.18 Project Infrastructure

A general site layout including the open pit, processing area, tailings management area (“TMA”), emulsion plant, truck shop and various stockpiles is shown in Figure 1-6. Details of the site are described in the following sections.

Site Access

The Project is very well situated where it can benefit from its proximity to existing infrastructure. Ontario Provincial Highway 600 currently runs directly through the Project site. The deviation of the road will require existing roads to be upgraded to provincial highway standards and a section of new highway will need to be built.

Site access roads to the TMA and to the explosives plant are pre-existing roads. The road widths will be enlarged to allow space for tailings and reclaim water pipes, as well as light traffic (emulsion tankers and pickup trucks). Existing roads will be resurfaced with crushed stone.

Mine haul roads will be built to connect the open pit to the overburden and waste rock stockpiles. These haul roads will also connect the pit to the crusher pad, mine facilities (truck shop and truck wash) and tailings dam.

 

 

 

LOGO

 

1-36


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 1-6: General Site Layout

 

 

1-37


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Buildings

The main administration building will be located at the entrance of the mine site and will house the administration and safety/security staff.

The mine office will be located next to the truck shop and will house the mine, maintenance and engineering office staff. The building will also have dry facilities with lockers.

The plant office will be located on the west side of the process building between the leach tanks and the pre-leach thickener and will be connected to the main building via a short corridor. The building will house the process operations/maintenance office staff, and a dry facility.

The assay laboratory is a separate building and will be equipped for all process plant and mine assaying requirements.

The mine truck shop, for both the open pit and underground operations, will have six (6) maintenance bays, including two (2) bays for auxiliary vehicles and one (1) bay dedicated for welding. The building will include a 1,400 m2 warehouse and a mechanical workshop which will also serve as a maintenance area for small vehicles.

The truck wash facility will be located approximately 80 m south of the mine truck shop.

Heating, ventilation and air conditioning (“HVAC”) will be provided for all buildings based on the required working temperatures.

The mine fleet fuel island will be located close to the crusher on the main haul road to the plant and facilities. The tank farm will be located on the service road between the crusher and stockpile. The light vehicle fleet fuel island will be located on the main access road near the warehouse.

Site Utilities

The total power demand of the Project is estimated at 58 MW. Electricity will be supplied by a new 17 km long 230 kV power line, to be built and subsequently connected to the existing 230 kV Hydro One line currently connecting Fort Frances and Kenora. The main 230–27.6 kV substation will be located near the concentrator building. The electrical distribution to the site infrastructure will consist of a dedicated 27.6 kV overhead line distribution network, equipped with 4/0 ACSR conductors.

 

 

1-38


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Underground sanitary sewers, underground fire protection and potable water pipes, as well as sewage and potable water treatment plants will be constructed according to local requirements. Potable water will be distributed to the process plant area and the mine truck shop. Potable water will be obtained from the West Creek Pond.

Fresh water will be obtained from the Water Management Pond and will be used for reagent preparation, surface utilities and for dust suppression. The total fresh water requirement is estimated to be approximately 75 m3/h.

Geotechnical

AMEC carried out a series of geotechnical drilling campaigns at the open pit, tailings and water dam sites, mineral waste stockpiles and critical areas between the open pit and Pinewood River, to characterize the site conditions and the subsurface stratigraphy, and to determine the soil and rock characteristics relevant to design of the facilities.

The geotechnical site investigations for the purposes of slope and dam design included 16 boreholes for the tailings dams, five (5) boreholes for the overburden stockpile and five (5) boreholes at the mine rock stockpiles. An additional 26 boreholes were drilled to allow for the design of the open pit overburden slopes to obtain samples for characterization of the mine waste overburden for use as dam construction material, and to determine hydrogeologic conditions between the pit and the Pinewood River.

The geotechnical investigations for the process plant, carried out under BBA’s specifications and requirements, included a comprehensive drilling and bedrock depth probing program consisting of two (2) drilling campaigns comprising 34 geotechnical boreholes, 38 test pits and 73 dynamic cone penetration tests. An iterative process between AMEC and BBA was followed in order to locate the process plant facilities on bedrock. The foundation design recommendations for the plant facilities were incorporated into the design of the facilities by BBA.

 

1.18.1 Site Water Management

The water management system developed by AMEC is designed to generate a reliable water source for mill operations and ancillary uses, while optimizing the quantity and quality of site effluents released to the environment. Water will be recycled from various man-made ponds for mill process water in order to minimize the volume of fresh water to be taken from local watercourses. The system has been designed to ensure a reliable water supply at all times of the year and to allow for contingencies, such as dry years.

 

 

1-39


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The system includes five (5) constructed ponds for water management in addition to sediment control ponds and a primary freshwater source. A constructed wetland is proposed downstream of the TMA and can act as part of the site effluent treatment system.

 

1.18.2 Tailings Management Area

The TMA has been designed by AMEC to store the process plant tailings. The tailings are assumed to be Potentially Acid Generating (“PAG”) and are therefore deposited in an area that allows for maintenance of a permanent water cover for closure. The total capacity for tailings produced over the mine life will be approximately 82 Mm3 at a deposited dry density of 1.4 t/m3.

The TMA location to the northwest of the open pit was selected in consideration of the topography, location of the pit and watershed boundaries, availability of dam construction materials and suitability for a flooded water cover for closure.

The geometry of the dams allows for a significant portion of the construction using haul trucks from the mine fleet. The dams have relatively flat slopes and are constructed largely using mine waste rock placed by the mine fleet, with the dam core, filter, and drain zones constructed by a qualified earthworks contractor.

 

1.19 Market Studies and Contracts

Neither BBA, nor New Gold, has conducted a market study related to the gold and silver doré that will be produced by the Rainy River Project. Gold and silver are freely traded commodities on the world market for which there is a steady demand from numerous buyers.

There are no refining agreements or sales contracts currently in place that are relevant to this Technical Report.

 

1.20 Environmental and Permitting

Rainy River is an active member of the local community with offices in both Emo and Thunder Bay that offer residents easily accessible locations to learn about the Rainy River Project. Rainy River has engaged the local communities, as well as local First Nations and Métis community members, in its Project planning activities.

 

 

1-40


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Environmental aspects have figured prominently in the development of the preliminary layouts and designs for the Rainy River Project described in this Study. These include consideration of the implications of design alternatives from an environmental management and approvals perspective, related to mineral waste management, and the siting and location of facilities and infrastructure. From an environmental perspective, the Rainy River Project is unique in that there are no lakes located within, or adjacent to, the main site. Based on multiple years of aquatics baseline investigations, while limited bait fishing does occur within certain area streams, the area does not support a significant commercial or recreational fishery.

There is considerable environmental baseline information currently available regarding the site and the surrounding area, compiled through extensive field investigations conducted over a four-year period. This information is being augmented as appropriate to support the progressing engineering design. Based on the information available to date and our understanding of the proposed development, there are no environmental aspects that are considered limiting to the Project development.

The Rainy River Project is being reviewed through a coordinated Federal Environmental Assessment (“EA”)/Provincial Individual EA. Draft EA Reports were submitted for review by local Aboriginal Groups, and government and stakeholder review. All comments received have been responded to. A Final EA Report was submitted on December 3, 2013 for Federal conformity review. New Gold was informed on December 11, 2013 that the document had passed the conformity review and the report will be issued for a stakeholder and Aboriginal group review period starting in January 2014.

A small number of Federal environmental approvals are likely necessary, as well as an anticipated requirement for a Schedule 2 listing for mineral waste management. The required supporting document for the Schedule 2 listing is included with the Final EA Report. Draft Fisheries Compensation Plans are also included with the Final EA Report. A number of Provincial environmental approvals will also be needed, focused on water taking, effluent and emission management, and closure planning.

The objective of final reclamation for the Rainy River Project is to return the site to a productive condition on completion of mining activities. A closure plan must be filed and financial assurance provided to the Province before construction of the Project is initiated. A conceptual closure plan consistent with regulatory requirements was part of the Draft EA Reports issued for comment and is included with the Final EA Report. As much as possible, reclamation will be completed progressively during operations, an industry best management practice. The financial model for the Project includes consideration of these costs.

 

 

1-41


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

1.21 Capital and Operating Costs

 

1.21.1 Capital Costs

The Capital Cost Estimate for the Project was developed by BBA, with input from various consultants according to their scope of work. The Capital Cost Estimate is based on a combination of equipment supplier quotes, supplier pricing, construction contractor input and experience with similar sized operations. This Project estimate meets AACE Class 3 requirements and is prepared to form the basis for budget authorization, appropriation and/or funding purposes. It has an expected accuracy range of -10 %/+15 %. This capital cost estimate assumes contracts will be awarded to reputable contractors on a lump sum basis in an open shop environment. Both hourly labour rates were combined in the 80% : 20% ratio (non-building trade workers : building trade union workers) to obtain an average of $132/hour.

The projected pre-production capital cost for the Project is estimated to be $931M, including a $73M contingency allocation (based on 12% of the direct and indirect costs). Total sustaining capital costs for the open pit mine and process facilities are $117.3M, while underground mine development and sustaining capital costs are estimated to be $110M and $138M, respectively. Any working capital requirements for the period between commissioning and first metal sales are assumed to be covered by New Gold’s operating mines. The Project capital summary is outlined in Table 1-11, as follows:

 

 

1-42


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

Table 1-11: Overall Project Capital Cost Summary

 

Area Description

   Pre-Production
Capital Costs ($M)
     Sustaining
Capital Costs ($M)
     

Overhead Power Line

     10.2         ILLEGIBLE

Highway 600 Realignment

     12.4        

Open Pit Overburden Pre-Stripping

     39.3        

Open Pit Mine Equipment

     85.1         74.1     

Mobile Equipment

        5.2     

Open Pit Waste Removal

     45.1        

Underground Mine Development Capital1

        110.5     

Underground Mine Sustaining Capital2

        138.5     

Site Development

     117.2         4.0     

Process Facilities

     312.8        

Tailings, Water Management and Treatment

     50.0         40.5     

Fish Compensation Costs

        2.0     

Chapple Township Compensation

        2.1     

Equipment Salvage Value

        (60.5  

Reclamation and Closure Costs

        49.9     
  

 

 

    

 

 

   

Direct Costs Subtotal

     672.1        
  

 

 

    

 

 

   

Indirect Costs (excluding Owner’s Cost)

     106.3        

Owner’s Cost

     79.7        
  

 

 

    

 

 

   

Indirect Costs Subtotal

     186.0        
  

 

 

    

 

 

   

Contingency

     73.3        
  

 

 

    

 

 

   

Total Capital

     931.4         366.3     
  

 

 

    

 

 

   

 

  1.

Funded through internal cash flows, this is the capital required in the development phase of the underground mine, consisting of equipment and infrastructure, as well as vertical and horizontal development.

  2.

Funded through internal cash flows, this is the sustaining capital required for the underground mine, consisting of equipment and infrastructure, as well as vertical and horizontal development.

Mining equipment quantities and costs have been developed based on the mine plan. Mining equipment costs are based on quotes requested during this study and from BBA’s recently updated database of supplier pricing. Mining equipment, including 10% down payment for 2017, are assumed to be purchased and not leased.

The average unit rate used for overburden removal is $1.53/t, based on using the open pit mining equipment fleet.

 

 

1-43


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Owner’s costs were provided by New Gold and include capital and operating costs until commercial production is achieved (60% production over a period of 30 days).

The site plan and General Arrangement (“GA”) drawings developed in this Study have been used to estimate quantities and generate Material Take-Offs (“MTOs”) for all commodities. Full specifications were issued and firm price quotations were obtained from suppliers for the following major equipment: gyratory crusher, apron feeders, SAG mill, ball mill, scalping screen, pebble crusher. For process and mechanical equipment packages, equipment datasheets and summary specifications were prepared and budget pricing obtained from suppliers. For packages of low monetary value, pricing was obtained from BBA’s recent project database. A detailed equipment list was developed with equipment sizes, capacities, motor power, etc. Related infrastructure costs were estimated by BBA based on the site plan developed.

Underground mine capital costs of a total $249M were provided by AMC and are included in the sustaining capital as the open pit operation will have already commenced.

During life of the operation, an estimated sustaining capital of $40.4M is required for necessary expansions, additions or improvements to the tailings management area. This includes $12.7M for the water treatment plant. The main components of sustaining capital related to the TMA and water management include:

 

 

Phased construction of TMA dams based on the tailings management strategy developed by AMEC;

 

 

The construction of an artificial wetland; and

 

 

A tailings pump booster station and tailings pipeline expansion during operation.

Progressive rehabilitation and mine closure quantities have been estimated by AMEC. BBA has estimated unit costs for the material handling requirements based on local contractor estimates and the use of the New Gold mine equipment.

 

 

1-44


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

1.21.2 Operating Costs

Introduction

For operating cost estimate purposes, the Project has been divided into six (6) areas: open pit mining, underground mining, processing, royalties, general and administrative, and refining. All costs are expressed in Q4 2013 Canadian dollars with no allowance for contingency The cost of electrical power was taken to be $0.065/kWh, which includes a $0.02/kWh reduction for the current Northern Ontario Industrial Rebate Program and other potential future government programs. The price of propane and diesel used in calculations were $0.50/L and $0.95/L, respectively. Overall peak operations personnel on site will consist of approximately 606 persons in Year 5 (2021), including 91 employees in the process plant, 29 employees in Administration (G&A), 318 employees in the open pit mine, and 168 employees in the underground mine. Project operating costs by area are summarized in Table 1-12.

Table 1-12: Key Project Operating Costs

 

Area

   LOM Total
(CAD$ M)
     CAD $ per
tonne milled
(LOM)
     USD $ per
gold ounce
produced
(LOM)
 

Open Pit Mining (Waste + Rock + Stockpile)1,2

     958         9.22         373   

Underground Mining (Cut & Fill)

     377         3.63      

Processing

     961         9.25         268   

General &Administration

     160         1.54         45   

Refining and Transportation3

     14         0.14         4   

Royalty Payments

     43         0.41         12   
  

 

 

    

 

 

    

 

 

 

Subtotal Costs

     2,514         24.19         702   
  

 

 

    

 

 

    

 

 

 

Silver by-Product Sales

     -139         -1.34         -39   
  

 

 

    

 

 

    

 

 

 

Total Costs Net Silver

     2,375         22.86         663   
  

 

 

    

 

 

    

 

 

 

Sustaining Capital

     366         3.53         102   
  

 

 

    

 

 

    

 

 

 

All-in Sustaining Cash Costs

     2,741         26.38         765   
  

 

 

    

 

 

    

 

 

 

 

  1.

Equivalent to $1.99 /tonne mined, including stockpile rehandling.

  2.

Stockpile rehandling costs of $0.50 per tonne milled are included in the open pit mining costs.

  3.

Equivalent to $90.10/tonne mined.

 

 

1-45


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Open Pit Mining

Open pit mining operating costs were developed for the production period (Years 1-9) and include operating costs for the fleet of primary, support and auxiliary equipment, maintenance, electricity and fuel costs, hourly labour and salaried personnel, blasting costs and services. The mine mobile fleet unit operating cost is based on both suppliers data requested during the Feasibility Study and from BBA’s recently updated database. The LOM mining cost is $2.02/t mined (including waste, ore, overburden and capitalized pre-production costs). The breakdown of operating costs for the open pit is shown in Table 1-13.

Table 1-13: Open Pit Operating Costs

 

Opex Summary

   Total Mine
Operating Costs
($M)
     Cost ($)
per  Tonne
Mined1
 

Hauling

     314.4         0.64   

Auxiliary Equipment

     185.0         0.38   

Blasting

     152.5         0.31   

Loading

     149.2         0.30   

Maintenance Personnel

     79.1         0.16   

Salaried Personnel

     60.0         0.12   

Drilling

     49.2         0.10   

Services

     5.0         0.01   
  

 

 

    

 

 

 

Total Mine Opex2

     994.4         2.02   
  

 

 

    

 

 

 

Stockpile Rehandling Cost

     50.4         1.34   

 

  1.

Cost per tonne mined includes mining cost for rock ($2.11/t) and overburden ($1.53/t)

  2.

Total Mine Opex includes capitalized pre-production costs. Mine opex during production years is $2.04/t mined and $1.81/t mined during pre-production years.

Stockpile Rehandling

Stockpile rehandling operating costs were developed for the last five (5) years of production (Years 9-14). The costs use the same basis as the mine operating costs and represent the primary and support fleet, fuel and labour required during the reclamation of the low grade ore stockpile. During the stockpile rehandling period, 7.2 Mt to 7.6 Mt of ore per year at an average rehandling cost of $1.34/tonne mined ($0.5/tonne milled) will be trucked to the primary crusher.

 

 

1-46


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Underground Mining

The operating costs for the Rainy River Underground operation were estimated based on first principle workups of all key mining activities and using a detailed cost model developed by AMC.

Equipment selection and associated operating costs were based on projections for mine activities and workups of required operating hours, productivity and cycle times (hrs/m and hrs/tonne), availability / utilization, and fuel consumption. The operating costs of all major mobile equipment were estimated using supplier quotes and benchmarked against AMC’s database of costs for similar recent projects. Ancillary equipment utilization and costs were calculated based on projected usage to complete general mine tasks.

The unit costs of all major consumables including explosives, ground support, pipes and ventilation ducting were estimated using supplier quotes. The unit costs of power, propane, cement, and diesel were provided by New Gold.

Mine General costs include mine power, heating, technical services consumables, definition drilling, communications and supplies, personal protective equipment and support equipment costs.

Mine maintenance costs include fixed plant and electrical maintenance, maintenance overheads and shop consumables. The mine general and mine maintenance costs were developed based on industry experience and benchmarking against similar projects in the region.

Manpower requirements and labour rates (including benefits and burdens) were developed in consultation with New Gold.

The LOM average underground operating cost has been estimated to be $90.10 /t ore mined. Table 1-14 provides the breakdown by activity. Estimated Mine General costs are further broken down by activity in Table 1-15.

 

 

1-47


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 1-14: LOM Underground Operating Costs by Activity

 

Operating Costs

   Total Cost
($M)
     Total Cost
($/t ore mined)
 

Labour

     164.8         39.36   

Mine General

     57.0         13.61   

LH Stoping

     48.8         11.65   

Ore Development

     35.9         8.57   

Waste Development

     28.9         6.90   

Backfill

     27.2         6.49   

Mine Maintenance

     14.7         3.51   
  

 

 

    

 

 

 

Total

     377.2         90.10   
  

 

 

    

 

 

 

Table 1-15: LOM Underground Mine General Cost Breakdown

 

Mine General

   Total Cost
($M)
     Total Cost
($/t ore mined)
 

Power

     23.2         5.53   

Heating

     13.0         3.11   

Definition Drilling

     8.7         2.08   

Support Equipment

     6.4         1.52   

Mine General Consumables

     2.1         0.50   

Freight

     1.8         0.42   

Technical Services Consumables

     1.3         0.30   

Personnel Safety Equipment

     0.6         0.15   
  

 

 

    

 

 

 

Total

     57.0         13.61   
  

 

 

    

 

 

 

Process Plant

Process plant operating costs were calculated for 14 years of operation. The operating costs are based on metallurgical test work, the mine plan, New Gold salary compensation/benefit guidelines, and recent supplier quotations. The average life-of-mine processing operating costs were determined to be $9.25 per tonne milled at approximately 21,000 tpd. The yearly tonnages from the mine plan vary and were used to obtain the operating costs. The operating cost includes reagents, consumables, personnel (including contractors), electrical power and propane. The consumables accounted for in the operating costs include spare parts, grinding media and liner and screen components. Gold/silver production and operating costs incurred during Q4 2016 are capitalized under the New Gold Owner’s costs until 60% production is achieved in Q1 2017 (commercial production).

 

 

1-48


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

General and Administrative

General and Administrative (“G&A”) costs are expenses not directly related to the production of goods and encompass items not included in mining, processing, refining and transportation costs. These costs are based on New Gold’s recommendations, similar sized operations, and BBA’s in-house database.

The G&A costs were calculated for 14 years of operation and are estimated to average $1.54 per tonne milled. This cost includes:

 

 

Human Resources;

 

 

Site Administration, Management and Insurance;

 

 

Infrastructure Power;

 

 

Health and Safety Supplies;

 

 

First Nations Participation Agreement Payments;

 

 

Security and Paramedic Services;

 

 

Environmental Costs;

 

 

G&A Personnel;

 

 

Information Technology (“IT”); and

 

 

Training.

Royalties, Refining and Transport

Annual royalty costs (claim blocks and First Nation payments) were provided by New Gold and are based on the conceptual mine design and production profile, along with the terms of the individual royalty agreements. The total estimated LOM royalty cost is USD$ 11/oz Au. Refining and transportation costs are based on a quotation from a North American gold refinery. The total royalty payments are equivalent to $0.41 /tonne milled.

Cash Costs

Table 1-16 provides a summary of average operating cash costs per ounce of gold over the first 9 years and life-of-mine. The operating cash costs include silver credits and royalties.

 

 

1-49


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 1-16: Total and All-in Sustaining Cash Costs

 

Area

   Units      Processing
(Years 1 - 9)
     LOM      

Open Pit Mining (Waste + Rock + Stockpile)

     USD/oz         389.70         372.79      ILLEGIBLE

Underground Mining (Cut & Fill)

     USD/oz           

Processing

     USD/oz         206.58         268.35     

General &Administration

     USD/oz         35.78         44.68     

Royalty Payments

     USD/oz         3.65         4.03     

Refining and Transportation

     USD/oz         10.29         12.03     

Cash Costs

     USD/oz         645.99         701.89     

Silver by-Product Sales

     USD/oz         -32.54         -38.83     

Total Cash Costs1

     USD/oz         613.46         663.06     

Sustaining Capital

     USD/oz         122.55         102.30     

All-in Sustaining Cash Costs

     USD/oz         736.00         765.36     

 

  1. Includes silver credits and royalty payments

The cash costs per ounce of gold vary significantly, depending on the feed grade, mine strip ratio and the amount of stockpiling. The annual fluctuation of operating costs per ounce of gold produced can be seen in Figure 1-7. It should be noted that the overall costs per ounce increase quite substantially during the later years due to the processing of stockpile material (with gold grades ranging from 0.3 to 0.6 g/t Au).

 

LOGO

Figure 1-7: Annual Operating Cash Costs (USD/oz. Au) with Silver Credit

 

 

1-50


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The average all-in sustaining cash cost was calculated to be USD $736/oz. Au over the first 9 years and USD $765/oz. Au over the LOM.

 

1.22 Economic Analysis

A financial analysis for the Rainy River Project was carried out using a discounted cash flow approach. The internal rate of return (“IRR”) on total investment was calculated based on 100% equity financing even though New Gold may decide in the future to finance part of the Project using alternative sources of capital. The Net Present Value (“NPV”) was calculated from the cash flow generated by the project based on a discount rate of 5%. The payback period based on the undiscounted annual cash flow of the project was also indicated as a financial measure. The Financial Analysis was performed using the following assumptions and basis:

 

 

The base case gold and silver prices are USD $1,300/oz. and USD $22/oz., respectively;

 

 

Cash flows are assumed to occur mid-period.

 

 

The Project value was determined on a pre-tax and after-tax basis and was discounted to the start of Year -2 (2015) which marks the first year of Project construction;

 

 

Commercial production will begin in January 2017;

 

 

During the pre-production period and during operations, the United States to Canadian dollar exchange rate was assumed to be CAD $0.95:USD $1.00.

 

 

All cost and sales estimates are in constant Q4 2013 Canadian dollars with no inflation or escalation factors taken into account;

 

 

All gold and silver is sold in the same year of production;

 

 

All project related payments and disbursements incurred prior to the effective date of this Study are considered as sunk costs. Disbursements projected for after the effective date of this Study but before the start of construction are considered to take place in the pre- production period;

 

 

All values shown are post payment of royalties. Total royalty payments over the LOM are $28.6M NPI/NSR (net profit interest / net smelter return) and $14.5M other; and

 

 

After tax figures assume a combined income tax rate of 25% with 2.7% corporate minimum tax, a mining tax of 10% of taxable mining profits over $500,000 and an allocation of corporate tax attributes among New Gold’s operations.

 

 

After-tax results were provided by New Gold. BBA has not verified this work.

 

 

1-51


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The after-tax economic for the Rainy River Project evaluation considered the following taxes:

 

 

15% federal income taxes on taxable income

 

 

10% Ontario provincial income tax on taxable income

 

 

10% Ontario mining taxes on mining income

 

 

2.7% Ontario Corporate Minimum Tax

Deductions, allowances, and credits were applied to the taxation model where applicable. The most notable of these deductions are Canadian Exploration Expenditures (“CEE”), Canadian Development Expenses (“CDE”), and capital costs eligible for Class 41 of the capital cost allowance system.

The results of the economic analysis summarized below represent forward–looking information as defined under Canadian securities law. Actual results may differ materially from those expressed or implied by forward-looking information. The reader should refer to the Cautionary Note with respect to Forward Looking Information at the front of this Report for more information regarding forward-looking statements, including material assumptions (in addition to those discussed in this section and elsewhere in the Report) and risks, uncertainties and other factors that could cause actual results to differ material from those expressed or implied in this section (and elsewhere in the Report).

The base case general economic results are summarized in Table 1-17.

 

 

1-52


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 1-17: Financial Analysis Summary5

 

Description

  

Base Case

   Units      

Ore Milled (LOM)6

   Million Tonnes      103.9      ILLEGIBLE

Waste Mined (LOM)

   Million Tonnes      318.2     

Average Gold Grade (Years 1-9)

   g/t Au      1.44     

Average Gold Grade (LOM)

   g/t Au      1.12     

Average Silver Grade (Years 1-9)

   g/t Ag      3.07     

Average Silver Grade (LOM)

   g/t Ag      2.80     

Open Pit Mining (waste, ore and stockpiling)1

   $/t milled (LOM)      9.22     

Stockpile Rehandling

   $/t milled (LOM)      0.50     

Underground Mining2

   $/t milled (LOM)      3.63     

Processing

   $/t milled (LOM)      9.25     

General and Administration

   $/t milled (LOM)      1.54     

Refining and Transportation Expenses

   $/t milled (LOM)      0.14     

Royalties

   $/t milled (LOM)      0.41     

Gold Recovery

   % (LOM)      90.6     

Silver Recovery

   % (LOM)      64.1     

Gold Recovered (LOM)6

   koz. Au      3,402     

Silver Recovered (LOM)6

   koz. Ag      6,004     

Initial Project Capital Cost

   $M      931     

Total Sustaining Capital Cost (including UG development)

   $M      366     

Total Cash Cost (Years 1 – 9)

   USD/oz.      613     

Total Cash Cost3 (LOM)

   USD/oz.      663     

All-in Sustaining Cost (Years 1 – 9)

   USD/oz.      736     

All-in Sustaining Cost4 (LOM)

   USD/oz.      765     

Net Present Value (0% disc) (Pre-Tax)

   $M      983     

Net Present Value (5% disc) (Pre-Tax)

   $M      462     

Internal Rate of Return (Pre-Tax)

   %      13.1     

Payback Period (Pre-Tax)

   Years      5.4     

Net Present Value (0% disc) (After-Tax)

   $M      774     

Net Present Value (5% disc) (After-Tax)

   $M      330     

Internal Rate of Return (After-Tax)

   %      11.3     

Payback Period (After-Tax)

   Years      5.5     

 

  1.

Equivalent to $1.99/tonne mined, including stockpile rehandling costs. Stockpile rehandling costs of $0.50 per tonne milled is included in the $9.22/tonne milled open pit mining costs.

  2.

Equivalent to $90.10/tonne mined.

  3.

Operating cash costs calculated using the total LOM operating expenditures include silver credits and royalty payments.

  4.

All in sustaining costs are calculated using the total LOM operating expenditures and the total LOM sustaining capital expenditures. Costs include silver credits and royalty payments.

  5. 

All values are in Canadian currency unless otherwise noted.

  6. 

Excludes 0.4 Mt of material milled from the preproduction period.

 

 

1-53


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

As part of the financial results, the Life-of-Mine Cash Flow Projection has been calculated and is shown in Figure 1-8. The graph includes cumulative cash flow projections (non-discounted) as well as discounted (5%) cumulative cash flow projections on a pre-tax and after-tax basis.

 

LOGO

Figure 1-8: Life-of-Mine Cash Flow Projections

A pre-tax sensitivity analysis was also performed to ascertain the impact of changes in metal price, capital costs, operating costs and foreign exchange rates. For the purposes of this sensitivity analysis it has been assumed that the royalties remain constant as per the base case. The results the Net Present Value using a discount rate of 5% are shown in Figure 1-9.

 

 

1-54


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 1-9: Pre-Tax Net Present Value (NPV) Sensitivity Analysis at 5% Discount Rate

The effect on the pre-tax NPV’s are shown in Table 1-18 when the CAPEX, OPEX, gold price, silver prices, exchange rate, mining costs and operating costs vary between -30% to +30%. As illustrated in Figure 1-9, the pre-tax NPV is most sensitive to the gold price and the exchange rate.

Table 1-18: Selected Sensitivities, Pre-Tax NPV at 5% Discount Rate (CAD $M)

 

     Sensitivities  

Description

   -30%     -20%     -10%      0%      10%      20%     30%  

LOM Capital Expenditures

     818        699        581         462         343         225        106   

LOM Operating Expenditures

     975        804        633         462         291         120        (51

Gold Price

     (525     (196     133         462         791         1,120        1,449   

Silver Price

     434        443        453         462         471         481        490   

USD Foreign Exchange Rate

     1,477        1,139        800         462         124         (215     (553

Open Pit Mining Costs

     742        649        555         462         369         275        182   

Under Ground Mining Costs

     594        550        506         462         418         374        330   

Processing Costs

     656        591        527         462         397         333        268   

 

 

1-55


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 1-19 shows the pre-tax and after-tax NPV (in $CAD) and IRR sensitivity to varying metal prices and exchange rates. The results are presented in $USD in Table 1-20.

Table 1-19: Sensitivity Results for Metal Price and Exchange Rate Variations, $CAD

 

Gold
Price
(USD/oz)
    Silver
Price
(USD/oz)
          NPV, 5%
Discount Rate
(CAD $M)
    IRR
(%)
    Payback Period
(Years)
 
    CAD/USD     Pre-Tax     After-
Tax
    Pre-Tax     After-
Tax
    Pre-Tax     After-
Tax
 
  1,150        20        0.93        147        107        7.8        7.1        6.8        6.8   
  1,300        22        0.95        462        330        13.1        11.3        5.4        5.5   
  1,450        24        0.97        763        536        17.6        14.9        4.3        4.4   
  1,600        26        1.00        1,013        706        21.1        17.8        3.6        3.8   

Table 1-20: Sensitivity Results for Metal Price and Exchange Rate Variations, $USD

 

Gold
Price
(USD/oz)
    Silver
Price
(USD/oz)
          NPV, 5%
Discount Rate
(USD $M)
    IRR
(%)
    Payback Period
(Years)
 
    CAD/USD     Pre-Tax     After-
Tax
    Pre-Tax     After-
Tax
    Pre-Tax     After-
Tax
 
  1,150        20        0.93        138        100        7.8        7.1        6.8        6.8   
  1,300        22        0.95        438        314        13.1        11.3        5.4        5.5   
  1,450        24        0.97        738        520        17.6        14.9        4.3        4.4   
  1,600        26        1.00        1,009        706        21.1        17.8        3.6        3.8   

 

1.23 Adjacent Properties

Seven (7) properties in the exploration stage are located adjacent to or near the Rainy River Project property. Bayfield Ventures Corp. holds three (3) of the properties, known as the B Block, C Block and Burns Block. In 2012, Rainy River also purchased a 100% interest in the surface rights to the Burns Block. Bayfield Ventures Corp. issued a press release on January 14, 2014: “Bayfield Announces Maiden NI 43-101 Technical Report and Mineral Resource Estimate on Burns Block Rainy River Gold-Silver Project, NW Ontario”. Coventry Resources Inc. holds three (3) of the properties, known as the Pattullo, Nelles and Blue properties. King’s Bay Gold Corp. holds the seventh property, being a single continuous land package contiguous with the most northerly portion of the Rainy River Project property. The closest Canadian operating mine is the Lac des Iles, palladium, nickel, gold and copper mine, owned by North American Palladium Ltd., located 90 km northwest of Thunder Bay and nearly 400 km northeast of the Rainy River Project.

 

 

1-56


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

1.24 Other Relevant Data and Information

Project Development Schedule

A Project Development Schedule has been generated to commence production in Q4 of 2016. Full production is assumed to be achieved in Q1 2017. The schedule includes consideration of early work requirements, various studies, the Environmental Assessment process, engineering, procurement, and construction activities. It covers all required site infrastructure, crushing, mineral resource stockpiling, milling and tailings management. The direct on-site personnel requirement peaks at approximately 447 persons during the construction of the Project. The major Project activity durations and milestones are listed below in Table 1-21

Table 1-21: Rainy River Project Development Activities

 

Activity

   Start Date    Completion Date

Detailed Engineering

   Q1 2014    Q2 2015

Environmental Assessment, Receipt of Construction Permits

   Q2 2013    Q1 2015

Highway 600 Road and Realignment

   Q1 2015    Q2 2015

Power Line Construction and Activation

   Q1 2015    Q2 2015

Pre-Stripping and Bench Preparation

   Q1 2015    Q4 2016

Construction of plant site & infrastructure

   Q2 2015    Q4 2016

Commissioning

   Q3 2016    Q4 2016

Production

   Q1 2017    Q2 2030

Some of the most time-sensitive items within the scope of executing the Rainy River Project are: environmental permitting, realignment of Highway 600, electrical transmission line permitting, integration to the electrical grid and construction of the process plant.

The Project execution will be managed by an EPCM (engineering, procurement and construction management) contractor that will be contracted out to qualified firms, under the supervision of the New Gold Project team.

 

1.25 Conclusions

The Feasibility Study indicates that the Rainy River Project, based on the calculated Proven and Probable reserves (shown in Table 1-22) of 104.3 Mt grading 1.13 g/t Au and 2.81 g/t Ag, can support a 19,500 tpd open pit and 1,500 tpd underground mine.

 

 

1-57


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 1-22: Proven and Probable Reserves (November 2, 2013)

 

Resources Category

   Tonnage
(‘000)
     Au Grade
(g/t)
     Ag Grade
(g/t)
     Au
(In-Situ ‘000 oz.)
     Ag
(In-Situ ‘000 oz.)
 

Proven

     22,681         1.14         1.88         830         1,370   

Probable

     81,594         1.12         3.06         2,943         8,040   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

TOTAL (Combined)

     104,275         1.13         2.81         3,773         9,410   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Mineralized material will be sent to a process plant designed to achieve gold and silver recoveries of 90.6% and 64.1%, respectively. It is anticipated that, over a mine life of 14 years, approximately 3,402 koz. of gold and 6,004 koz. of silver will be produced excluding capitalized gold and silver produced during the pre-production period.

The initial capital cost of the Project is estimated to be $931M and the sustaining capital (including the development of the underground mine) is estimated to be $366M. The operating life-of-mine total cost is USD $663/oz. Au, including silver credits and royalty payments. The all in sustaining life-of-mine total cost is USD $765 /oz. Au, including silver credits and royalty payments. The Project NPV (pre-tax) is estimated to be $462M and the Project NPV (after-tax) is estimated to be $330M using a discount rate of 5%. The Project internal rate of return (pre-tax) is estimated at 13.1% and the Project internal rate of return (after-tax) is estimated to be 11.3%. The simple payback period (pre-tax) is 5.4 years and the simple payback period (after-tax) is 5.5 years.

The pre-tax sensitivity analyses indicates that positive Project returns can be achieved over the likely range of variation in gold prices (+ 30%/-14%), silver prices (± 30%), capital costs (± 30%) and operating costs (+ 27%/-30%).

Based on the assumptions made in this analysis, it is BBA’s opinion that the Rainy River Project is sufficiently robust to warrant advancing to the next stage of development, that being the start of construction and continuation of detailed engineering.

 

1.26 Recommendations and Future Work Program

BBA recommends that New Gold proceed with the detailed engineering phase based on the results of this updated Feasibility Study and the Project risks/opportunities identified. However the decision to proceed with a mining operation on the Rainy River Project is at the discretion of New Gold. The suggested work program includes the following components:

 

 

1-58


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

Continuation of open pit and underground mine design optimization;

 

 

Consideration of an underground mining test program within the Intrepid Zone;

 

 

Procurement of long lead time mining and process equipment;

 

 

Continuation of preparatory work to secure electrical power and procurement of long lead time electrical equipment;

 

 

Continuation of key personnel recruitment;

 

 

Continuation of coordinated environmental assessment process;

 

 

Continuation of First Nation, Métis and public consultations;

 

 

Continuation of hydrogeological studies in specific areas;

 

 

Secure required permits and authorizations from government and regulatory agencies;

 

 

Continuation of detailed engineering activities; and

 

 

Construction of the Project (following appropriate approvals).

The 2014 budgeted costs for initiation of key project activities are estimated at approximately US $ 104 M, as shown in Table 1-23.

Table 1-23: Budget for 2014 (US Dollars)

 

Activity

   Cost (US$ M)  

Capitalized exploration and condemnation drilling

     14.0   

Property, plant and equipment payments

     60.0   

Detailed engineering and studies

     20.0   

Permitting and environmental monitoring

     10.0   
  

 

 

 

Total

     104.0   
  

 

 

 

 

 

1-59


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

2. INTRODUCTION

The Rainy River Project is an advanced stage gold exploration project situated in the southern half of Richardson Township, approximately 50 km northwest of Fort Frances in northwestern Ontario, Canada. Richardson Township is one of several townships that comprise Chapple Township, the municipal organization in the area. The Project is located approximately 162 km south of Kenora and 418 km west of Thunder Bay. In June 2005, Rainy River Resources Ltd. (“Rainy River”) acquired the Project from Nuinsco. On June 18th, 2013 a takeover bid commenced resulting in New Gold Inc. (“New Gold”) acquiring ownership of 100% of Rainy River’s outstanding shares. The acquisition was completed as of October 15th, 2013.

 

2.1 Scope of Study

The following Technical Report (the “Report”) presents the results of the Feasibility Update Study for the development of the Rainy River Project. In August 2013, New Gold commissioned the engineering consulting group BBA to lead and perform the Study, based on contributions from a number of independent consulting firms. This Report was prepared at the request of Mr. Garett Macdonald, Rainy River Project Director. As of the date of this Report, New Gold is a Canadian publicly traded company listed on the Toronto Stock Exchange (“TSX”) under the trading symbol NGD, with its head office situated at:

Suite 1800, Two Bentall Centre

555 Burrard Street

Vancouver, BC

Tel: (604) 696-4100

This Report, titled “Feasibility Study of the Rainy River Project, Ontario, Canada”, was prepared by Qualified Persons following the guidelines of the NI 43-101, and in conformity with the guidelines of the Canadian Institute of Mining, Metallurgy and Petroleum (“CIM”) Standards on Mineral Resources and Reserves.

A summary of the Report contributors and their areas of responsibility are presented in Table 2-1.

 

 

2-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 2-1: Major Study Contributors

 

Consulting Firm or Entity

  

Area of Responsibility

SRK Consulting (Canada) Inc.    Geological modelling and resource definition.
BBA Inc.    Open pit mine design, production scheduling, processing plant design, site infrastructure, capital costs, operating costs, financial analysis and overall integration.
AMC Mining Consultants (Canada) Ltd.    Underground mine design, production scheduling, capital costs and operating costs.
AMEC Environment & Infrastructure    Tailings, waste rock and water management, environmental baseline, closure plan. Open pit and underground geomechanics and geotechnical investigations.

 

2.2 Effective Dates and Declaration

This Report is in support of the New Gold press release, dated January 16, 2014, entitled “New Gold Announces its Rainy River Feasibility Study Results”. This report is considered effective as of January 16, 2014. BBA’s opinion contained herein is based on information collected by BBA throughout the course of BBA’s investigations, which in turn reflects various technical and economic conditions at the time of writing. Given the nature of the mining business, these conditions can change significantly over relatively short periods of time. Consequently, actual results can be significantly more or less favourable.

This Report may include technical information that requires subsequent calculations to derive subtotals, totals and weighted averages. Such calculations inherently involve a degree of rounding and, consequently, introduce a margin of error. Where this occurs, BBA does not consider it to be material. The overall Study was collated and integrated by BBA personnel.

BBA is not an insider, associate or an affiliate of New Gold and neither BBA nor any affiliate has acted as Advisor to New Gold, Rainy River, its subsidiaries or its affiliates, in connection with this Project. The results of the technical review by BBA are not dependent on any prior agreements concerning the conclusions to be reached, nor are there any undisclosed understandings concerning any future business dealings.

 

 

 

2-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

This report was prepared as National Instrument 43-101 Technical Report for New Gold Inc. (New Gold) by BBA Inc. (BBA), AMEC Environment and Infrastructure (AMEC), AMC Mining Consultants (Canada) Ltd. (AMC) and SRK Consulting (Canada) Inc. (SRK), collectively the “Report Authors”. The quality of information, conclusions, and estimates contained herein is consistent with the level of effort involved in the Report Authors’ services, based on i) information available at the time of preparation, ii) data supplied by outside sources, and iii) the assumptions, conditions, and qualifications set forth in this report. This report is intended for use by New Gold subject to terms and conditions of its respective contracts with the Report Authors. Except for the purposes legislated under Canadian provincial and territorial securities law, any other uses of this report by any third party is at that party’s sole risk.

 

2.3 Sources of Information

This Report is based in part on internal company reports, maps, published government reports, company letters and memoranda, and public information, as listed in Section 27 “References” of this Report. Sections from reports authored by other consultants may have been directly quoted or summarized in this Report, and are so indicated, where appropriate.

It should be noted that the authors have made use of selected portions or updated excerpts from material contained in the following re-addressed NI 43-101 Compliant Technical Report: “Feasibility Study for the Rainy River Gold Project”, for New Gold NI 43-101 Technical Report, prepared by BBA Inc., dated July 31, 2013. This Report is publicly available on SEDAR (www.sedar.com).

This Feasibility Study has been completed using the previously mentioned Technical Report, as well as available information contained in, but not limited to, the following reports, documents and discussions:

 

 

Technical discussions with New Gold personnel;

 

 

Personal inspection of the Rainy River Project property;

 

 

Report of mineralogical, metallurgical and grindability characteristics of the Rainy River deposit, conducted by SGS Minerals Services and other firms on behalf of New Gold;

 

 

Resource Block Model provided by SRK;

 

 

A conceptual process flowsheet developed by BBA based on the testwork and similar operations;

 

 

Internal and commercially available databases and cost models;

 

 

2-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

Various reports produced by AMEC concerning environmental considerations for permitting, site hydrology, hydrogeology and geotechnical, tailings management, water treatment plant and site closure plan;

 

 

A memo from Merit Consultants Inc., providing construction labour rates and productivity factors;

 

 

A memo from SanZoe Consulting Inc., providing future electrical costs for industrial users in Ontario;

 

 

A Feasibility Study Report provided by TBT Engineering Ltd. to Rainy River Resources for the Highway 600 Realignment;

 

 

Internal unpublished reports received from New Gold staff; and

 

 

Additional information from public domain sources.

BBA believes that the basic assumptions contained in the information above are factual and accurate, and that the interpretations are reasonable. BBA has relied on this data and has no reason to believe that any material facts have been withheld. BBA also has no reason to doubt the reliability of the information used to evaluate the mineral resources presented herein.

 

2.4 Terms of Reference

Unless otherwise stated:

 

 

All units of measurement in the Report are in the metric system;

 

 

All currency amounts in this Report are stated in Canadian dollars (“CAD”), unless otherwise stated;

 

 

All ounce units are reported in troy ounces, unless otherwise stated; 1 oz. (troy) = 31.1 g = 1.1 oz. (imperial);

 

 

All metal prices are expressed in terms of US dollars (“USD”);

 

 

A foreign exchange rate of USD $0.95 = CAD $1.00 was used; and

 

 

All cost estimates have a base date of the fourth (“Q4”) quarter of 2013.

Grid coordinates for the Block Model are given in the UTM NAD 27 (Zone 19N) and latitude/longitude system; maps are either in UTM coordinates or in the latitude/longitude system.

 

 

2-4


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

2.5 Site Visit

BBA and Rainy River representatives conducted a site visit on October 11, 2012 and BBA was represented by Mr. David Runnels and Mr. Patrice Live. The purpose of the visit was to provide the Project team members with an overview of the Rainy River Project property and to review Project development milestones and planning. Rainy River geologists were available to discuss general geological conditions and to provide a tour of the core storage facility, with a presentation of select mineral material. To provide an overview of the Rainy River Project property terrain and potential locations for eventual Project infrastructure, Mr. Garett Macdonald led a visit of the Rainy River Project property using a company vehicle. Mr. Colin Hardie visited the site in June 2011; Ms. Sheila Daniel visited the site in May 2011; Mr. Glen Cole was present at the site from April 30 to May 2, 2013, Mr. Adam Coulson visited the site most recently from September 25-27, 2013 and David Ritchie most recently visited the site on September 4, 2013. Mr. Colm Keogh visited the site on September 26, 2013.

 

2.6 Acknowledgement

BBA would like to acknowledge the general support provided by New Gold personnel during this assignment. Their collaboration is greatly appreciated. The Project also benefitted from the inputs of Mr. Garett Macdonald, Rainy River Project Director, Mr. Paolo Toscano, Director of Engineering and Mr. Nolan Peterson, Project Engineer. Their contributions are gratefully acknowledged.

 

 

2-5


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

3. RELIANCE ON OTHER EXPERTS

BBA prepared this Feasibility Study using the reports and documents noted in Section 27 “References”. BBA has not performed an independent verification of land title and tenure as summarized in Section 4.1 of this Technical Report. BBA did not verify the legality of any underlying agreement(s) that may exist concerning the permits or other agreement(s) between third parties, but has relied upon the opinion of the client’s lawyers, Davis LLP of Toronto, for the land tenure information summarized in Section 4. An extract from the land title opinion provided by Davis LLP can be found in Appendix A. Any statements and opinions expressed in this document are given in good faith and in the belief that such statements and opinions are not false and misleading at the date of this Report. BBA is not aware of any known litigations potentially affecting the Rainy River Project.

It should be understood that the mineral reserves and resources presented in this Report are estimates of the size and grade of the deposits. The estimates are based on a certain number of drill holes and samples, and on assumptions and parameters currently available. The level of confidence in the estimates depends upon a number of uncertainties. These uncertainties include, but are not limited to: future changes in metal prices and/or production costs, differences in size, grade and recovery rates from those expected, and changes in Project parameters. In addition, there is no assurance that the Project implementation will be carried out. BBA’s responsibility was to assure that this Technical Report met the stipulated guidelines and standards, given that certain sections of this Report were contributed by SRK, AMC, AMEC or other New Gold consultants.

 

3.1 Report Responsibility and Qualified Persons

Table 3-1 outlines responsibility for the various sections of the Report and the name of the corresponding Qualified Person.

The authors of this Report consist of both BBA employees and various other consultants. Each author is a Qualified Person and is responsible for various sections of this Report, according to his or her expertise and scope of work. Each author has contributed figures, tables and portions of Sections 1 (Summary), 25 (Interpretation and Conclusions), and 26 (Recommendations).

 

 

3-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 3-1: Qualified Persons and Areas of Report Responsibility

 

Section

  

Description

  

Responsibility

  

Qualified
Person

  

Comments and Exceptions

1.    Summary    BBA    C. Hardie    All contributed based on their expertise and scope of work.
2.    Introduction    BBA    C. Hardie   
3.    Reliance on other Experts    BBA    C. Hardie   
4.    Project Property Description and Location   

BBA

AMEC E&I RRR

   C. Hardie    Mineral tenure and underlying agreements by NG (Sections 4.1 and 4.2) and environment considerations and mining rights (Sections 4.3 and 4.4) by AMEC.
5.    Accessibility, Climate, Local Resource, Infrastructure and Physiography    SRK    G. Cole   
6.    History    SRK    G. Cole   
7.    Geological Setting and Mineralization    SRK    G. Cole   
8.    Deposit Types    SRK    G. Cole   
9.    Exploration    SRK    G. Cole   
10.    Drilling    SRK    G. Cole   
11.    Sample Preparation, Analyses and Security    SRK    G. Cole   
12.    Data Verification    SRK    G. Cole   
13.    Mineral Processing and Metallurgical Testing    BBA    D. Runnels    Testwork by SGS, FLS, Metso, SAG Design and Outotec.
14.    Mineral Resource Estimate    SRK    D. El-Rassi   
15.    Mineral Reserve Estimates   

BBA

AMC

  

P. Live

C. Keogh

   Underground mineral resources estimate by AMC (Section 15.3)

 

 

3-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Section

  

Description

  

Responsibility

  

Qualified
Person

  

Comments and Exceptions

16.    Mining Methods   

BBA

AMC

AMEC E & I

  

P. Live

C. Keogh

M. Molavi

A. Coulson

   Open pit mining and reserves by BBA, underground mining and reserves by AMC (Section 16.3, 16.4 and 16.5). Geomechanical designs by AMEC (Section 16.2.1 and 16.3.6)
17.    Recovery Methods    BBA    D. Runnels   
18.    Project Infrastructure   

BBA

AMEC E & I

   D. Runnels D. Ritchie    Site infrastructure by BBA, tailings management area design, water management and fisheries compensation by AMEC (Section 18.8, 18.9 and 18.10) and Highway 600 realignment study conducted by TBT Engineering Consulting Group (part of Section 18.1.1). Geotechnical by AMEC (Section 18.1.3).
19.    Market Studies and Contracts    BBA    C. Hardie    No market study performed.
20.    Environmental Studies, Permitting, and Social or Community Impact    AMEC E & I    S. Daniel   
21.    Capital and Operating Costs   

BBA

AMC

  

C. Hardie

C. Keogh

   AMEC provided tailings area construction quantities, water treatment plant quantities and site closure plan, Merit Consultants provided construction labour rates and productivity factors, AMC provided CAPEX and OPEX for underground mining (Sections 21.5.5 and 21.6.5). New Gold provided royalty costs.
22.    Economic Analysis    BBA    C. Hardie    AMEC provided closure costs, New Gold calculated Project taxes and after-tax cash flow.
23.    Adjacent Properties    BBA    C. Hardie   

 

 

3-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Section

  

Description

  

Responsibility

  

Qualified
Person

  

Comments and Exceptions

24.    Other Relevant Data and Information    BBA    D. Runnels    Schedule developed by BBA, and Merit Consultants. AMEC provided permitting information.
25.    Interpretation and Conclusions    BBA    C. Hardie    All contributed based on their expertise and scope of work.
26.    Recommendations    BBA    C. Hardie    All contributed based on their expertise and scope of work.
27.    References    BBA    C. Hardie   

The following Qualified Persons (“QPs”) have contributed to the writing of this Report and have provided QP certificates, included at the beginning of this Report. All QPs have visited the Rainy River Project property with the exception of Dorota El-Rassi and Mo Molavi. The information contained in the certificates outline the sections in this Report for which each of the QPs is responsible.

 

•   Colin Hardie, P.Eng.

   BBA Inc.

•   David Runnels, Eng.

   BBA Inc.

•   Patrice Live, Eng.

   BBA Inc.

•   Sheila Daniel, M.Sc., P.Geo.

   AMEC Earth & Infrastructure

•   David Ritchie, P.Eng.

   AMEC Earth & Infrastructure

•   Adam Coulson, PhD., P.Eng.

   AMEC Earth & Infrastructure

•   Dorota El-Rassi, P.Eng.

   SRK Consulting (Canada) Inc.

•   Glen Cole, P.Geo.

   SRK Consulting (Canada) Inc.

•   Colm Keogh, P.Eng.

   AMC Mining Consultants (Canada) Ltd.

•   Mo Molavi, M.Eng., P.Eng.

   AMC Mining Consultants (Canada) Ltd.

 

3.2 Other Study Contributors

The individuals listed below have contributed to the Feasibility Study and to this Report, and have extensive experience in the mining and metals industry or in a supporting capacity in the industry. They are not considered as QPs for the purpose of this NI 43-101 Report.

 

 

3-4


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Jay Collins, P.Eng.    Construction Management    Merit Consultants Inc.
John Fletcher, C.Eng.    Construction Management    Merit Consultants Inc.
Wayne Clark, P.Eng.    Electrical Transmission Line    SanZoe Consulting Inc.
Rob Frenette, P.Eng.    Road Construction    TBT Engineering Consulting Group
Paolo Toscano, P.Eng.    Metallurgy & Processing    New Gold Inc.
Nick Kwong, P.Eng.    Mining Engineering    New Gold Inc.
Garett Macdonald, P.Eng.    Project Management    New Gold Inc.

Jay Collins, P.Eng., President of Merit Consultants Inc., and John Fletcher, C.Eng., provided construction labour rates and productivity factors. Wayne Clark, of SanZoe Consulting Inc., provided electricity pricing, consulting for applications to IESO and Hydro One and advice for the high voltage power transmission line. Rob Frenette provided road alignments and capital costs for the East Access Road and Highway 600.

Drill core samples for metallurgical testing were collected and prepared by Rainy River Resources and submitted to SGS Minerals Services (Lakefield, Ontario, Canada), which is an accredited laboratory. Although BBA has reviewed the testwork results generated by SGS and believes that they are generally accurate, BBA is relying on SGS as an independent expert.

 

 

3-5


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

4. PROPERTY DESCRIPTION AND LOCATION

The New Gold Inc. - Rainy River Project (the “Rainy River Project” or “RRP” or the “Project”) is located approximately 50 km to the northwest of Fort Frances, the nearest large town in Western Ontario; refer to Figure 4-1. The village of Emo is located approximately 25 km to the south on Highway 11.

The Rainy River Project property is comprised of a portfolio of unpatented mining claims located in the townships of Fleming, Menary, Potts, Richardson, Senn, Sifton and Tait, and leasehold interest mining rights land claims and patented mining rights and surface rights land claims located in Mather, Pattullo, Potts, Richardson, Senn, Sifton and Tait townships. All of the unpatented mining claims, leasehold mining rights lands, and patented mining rights and surface rights lands, within the above-mentioned townships, can be accessed by a network of secondary all-weather roads that branch off the well-maintained Trans-Canada Highways 11 and 71.

 

4.1 Mineral Tenure

The Rainy River Project is comprised of a portfolio of 243 patented mining rights and surface rights lands, including three (3) leasehold patented mining rights, and unpatented mining claims. The Rainy River Project property is collectively located in Fleming, Mather, Menary, Pattullo, Potts, Richardson, Senn, Sifton, and Tait townships. The Project property covers an aggregate area of 17,018.59 hectares.

In Ontario, Crown lands are available to licensed prospectors for the purposes of mineral exploration. Claim staking is governed by the Mining Act (Ontario) and is administered through the Provincial Mining Recorder and Mining Lands offices of the Ministry of Northern Development and Mines (“MNDM”).

The unpatented mining claims are comprised of a multiple of 16 ha (40 acres) square blocks. In Ontario, after staking, the unpatented mining claims are recorded within 31 days with the MNDM upon payment of an appropriate fee. In order to keep the unpatented mining claims valid, an approved expenditure per claim in excess of CAD $400 within two (2) years is required.

Patented lands do not have an assessment work obligation, but require maintaining both municipal realty and provincial mining land taxes.

 

 

4-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

In June 2005, Rainy River Resources Ltd. (“Rainy River”) completed the acquisition of a 100% interest in the Project from Nuinsco Resources Limited (“Nuinsco”). As of November 22, 2013, the Rainy River Project land package consists of:

 

 

A total of 162 patented mining rights and surface rights land claims, including three (3) leasehold patented mining rights land claims; and

 

 

A total of 81 unpatented mining claims.

An updated listing of the current Rainy River patented, leasehold and unpatented mining claims and leases was provided to BBA by Rainy River for review. These claims have not been legally surveyed by Rainy River.

The unpatented mining claims were independently verified by BBA on December 19, 2013, through the MNDM website (www.mndmf.gov.on.ca/mines/claimaps_e.asp).

 

 

4-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 4-1: Location of Rainy River Project (as of November 22, 2013)

 

 

4-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

A plan illustrating the distribution of the claims on the Rainy River Project is shown in Figure 4-1 and a title list is provided in Appendix B (claims as of November 22, 2013).

All unpatented mining claims are recorded in the name of Rainy River, save and except those unpatented mining claims set out within the ‘English Option’ and the ‘Roisin Option’ and the ‘Timberridge Option’, are described in more detail in Appendix B, and as of the effective date of this technical report are in good standing and have sufficient work assessment credits available for several years. SRK is not aware of any outstanding aboriginal land rights or aboriginal claims to this area.

The mineral resources reported herein occur within the patented claims former 4950, 5614, 5939, 25891, 25892 and 25894 (Figure 4-2).

 

 

4-4


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 4-2: Land Tenure Map of the Rainy River Gold Project (as of November 22, 2013)

 

 

4-5


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

4.2 Underlying Agreements

Rainy River, through direct ownership or option agreement, has a 100% interest in the lands forming the Rainy River Project.

Various option payments are due on certain patented land claims. Details of these option agreements, that include issuance of common shares and cash payments, are presented in Appendix B.

On March 3, 2010, Rainy River announced an option to acquire five (5) unpatented mining claims in the Tait Township (Figure 4-2) from Perry Vern English for Rubicon Minerals Corporation in consideration of cash payments of CAD $150,000, and the issuance of 60,000 shares over a period of five (5) years and a 2% net smelter return royalty. Rainy River may, at any time, re-purchase 1% of the royalty for CAD $1,000,000.

On December 16, 2011, Rainy River entered into an option to acquire three (3) unpatented mining claims in Richardson and Potts Townships (Figure 4-2) from Fred A. Roisin, in consideration of cash payments of CAD $100,000, and the issuance of 50,000 shares over a period of five (5) years and a 2% net smelter return royalty. Rainy River may, at any time, repurchase 1% of the royalty for CAD $1,000,000.

On March 29, 2012, Rainy River entered into an option to acquire one (1) unpatented mining claim in Sifton Township (Figure 4-2) from Timberridge Land & Forestry Services Inc. in consideration of cash payments of CAD $100,000 and the issuance of 50,000 shares over a period of five (5) years and a 2% net smelter return royalty. Rainy River may, at any time, repurchase 1% of the royalty for CAD $1,000,000.

 

4.3 Environmental Considerations

The RRP area exhibits variable, gently undulating terrain, and is drained principally by the Pinewood River and its associated minor tributaries. The RRP site is located in a low density rural area within the Township of Chapple (total population of 856 in 2006). There is some limited agriculture focused on cattle and fodder cropping, as well as logging activities in the area. Adjacent areas show mainly second growth poplar-dominated forests and wetlands. From an environmental perspective for northern Ontario, the RRP site is unique in that there are no lakes located within, or adjacent to, the RRP footprint. There are small lakes near the proposed transmission line routing.

 

 

 

4-6


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Rainy River initiated environmental studies of the Project area in 2008. Initial work from 2008 to 2010 was completed by Klohn Crippen Berger Ltd. (“KCB”). In 2011, Rainy River commissioned AMEC Environment & Infrastructure (“AMEC”) to conduct further environmental baseline investigations which continued into 2013; as well as anticipated mine environmental assessment and permitting stages. Five (5) years of comprehensive environmental baseline studies of the project and regional area have now been completed including:

 

 

Air quality;

 

 

Meteorology and climate;

 

 

Sound;

 

 

Aquatic resources (fish and benthic invertebrates) and habitat;

 

 

Wildlife and habitat;

 

 

Species-at-Risk;

 

 

Surface water quality and flows;

 

 

Groundwater quality and paths;

 

 

Sediment quality;

 

 

Geochemistry;

 

 

Socio-economics;

 

 

Heritage resources; and

 

 

Traditional knowledge and traditional land use.

While Rainy River Resources recognizes that the land on which the Rainy River Project is being planned is heavily impacted by historic and ongoing, farming and logging operations, the company feels that it is important that any oral history be properly documented and respected. Rainy River Resources is continuing to support preparation of Traditional Knowledge / Traditional Land Use studies to assess use of the local area by Aboriginal peoples. Rainy River Resources has taken a very proactive approach, and regular meetings are underway with First Nations and Métis to ensure communities are consulted with in a positive manner.

RRR is an active member of the local community with offices in both Emo and Thunder Bay, Ontario that offer residents easily accessible locations to learn about the RRP. RRR continues to engage and consult with the local communities, including First Nations and Métis community members. Through meetings, site tours and regular communications, RRR strives to ensure engagement with all members of the local communities.

 

 

 

4-7


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

RRR is actively involving local Aboriginal groups in the project planning and has negotiated agreements with First Nations as well as the Métis to set protocols and commitments for ongoing involvement for the life of the project and community benefits that would, in part, help mitigate any potential effects to Aboriginal or Treaty rights. Key issues and interests raised by Aboriginal groups to date are related to: environmental management; employment and benefits; fisheries and wildlife; project components and mining; TLU and culture; and water resources.

Through advice from the Provincial Crown, Aboriginal groups identified to be consulted regarding the RRP are:

 

 

Mishkosiminiziibiing (Big Grassy River) First Nation;

 

 

Anishinaabeg of Naongashiing First Nation (Big Island);

 

 

Naicatchewenin First Nation;

 

 

Naotkamegwanning (Whitefish Bay) First Nation;

 

 

Ojibways of Onigaming First Nation;

 

 

Rainy River First Nations;

 

 

Buffalo Point First Nation; and

 

 

Métis - Rainy River Lake of the Wood Regional Consultation Committee Region #1.

RRR will also continue to consult and involve the Fort Frances Chiefs Secretariat and Pwi-Di-Goo-Zing-Ne-Yaa-Zhing Advisory Services Tribal organizations.

Aboriginal groups identified by the Provincial Crown to be notified regarding the RRP are:

 

 

Anishinabe of Wauzhushk Onigum First Nation (Rat Portage);

 

 

Couchiching First Nation;

 

 

Lac La Croix First Nation;

 

 

Mitaanjigamiing (Stanjikoming) First Nation;

 

 

Nigigoonsiminikaaning (Nicickousemenecaning) First Nation;

 

 

Northwest Angle #33 First Nation;

 

 

Northwest Angle #37 First Nation; and

 

 

Seine River First Nation.

 

 

4-8


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

4.4 Environmental Approvals in Ontario

The Rainy River Project is located in Ontario; a province that has a well understood permitting process in place and one that is coordinated with the Federal regulatory agencies. As is the case for similar mine developments in Canada, the Project will be subject to a Federal and Provincial Environmental Assessment (the “EA”) process. The Rainy River Project will require completion of a Federal Environmental Assessment, pursuant to the Canadian Environmental Assessment Act, 2012. Rainy River entered into a Voluntary Agreement with the Ontario Ministry of the Environment to conduct a Provincial Individual Environmental Assessment that will meet the requirements of the Ontario Environmental Assessment Act. The same body of information will be used to inform the Provincial and Federal Environmental Assessment process, culminating in a single Environmental Assessment Report that meets both the Federal Environmental Impact Statement Guidelines and the Provincially-approved Amended Terms of Reference. A Final Environmental Assessment Report is currently under Federal and Provincial review.

After the Environmental Assessment process is completed, environmental approvals will be required to construct, operate and close the Rainy River Project. Due to the complexity and size of the project, various Federal and Provincial agencies will have jurisdiction to provide approvals that will enable project construction to proceed. A schedule has been developed to allow submission of approval applications in parallel with the Environmental Assessment process, such that construction will be able to start once first approvals are received shortly after Environmental Assessment sign-off is received. The Environmental Assessment process is expected to be completed in 2014 with the issuance of various environmental approvals over the ensuing approximate 12 months.

 

 

4-9


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

5. ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE AND PHYSIOGRAPHY

The Rainy River Project is located approximately 50 km to the northwest of Fort Frances, the nearest large town in western Ontario. Infrastructure in the area of the Project is satisfactory with numerous gravel/paved roads, power and water resources available within close proximity to the Project. In addition, Rainy River Resources has adequate surface rights for the Project requirements, as proposed in the site plan (Appendix F).

 

5.1 Accessibility

The Project is centred in Richardson Township (part of Chapple Township) in northwestern Ontario, approximately 162 km (Highway 17/Highway 71/Regional Road 600) south of Kenora, and 418 km (Highway 11/Highway 71/Regional Road 600) west of Thunder Bay. These access roads are sealed allowing year-round access. The final access to the deposit consists of a 540 m track from Regional Road 600 to the 17 Zone and there are drill tracks to other areas that are of exploration interest. Figure 4-2 in Chapter 4 indicates the location of the Project claims with respect to local roads in the area.

The Canadian National Railway is located 21 km to the south and runs east-west, immediately north of the Minnesota border. The nearby towns and villages of Fort Frances, Emo and Rainy River are located along this railway line.

 

5.2 Local Resources and Infrastructure

The towns within immediate driving distance of the Rainy River Project are:

 

 

Emo, with a population of 1,305 – 34 km (30-minute drive);

 

 

Rainy River, population 909 – 73 km (67-minute drive); and

 

 

Fort Frances, with a population of 8,103 – 63 km (1-hour drive).

Hydroelectricity is produced north of Kenora at various locations, as well as west and east of Thunder Bay. A medium-sized coal-powered thermal power station is located east of Fort Frances and another is located near Thunder Bay.

There is a ready supply of water in the area from lakes and rivers. Ground water is also likely to be in plenteous supply, given the abundance of standing water and rivers within the region. The major primary drainage system in the area includes Rainy Lake, which lies to the southeast and is drained by Rainy River which flows west along the Minnesota border to Lake of the Woods, which in turn feeds into the Lake Winnipeg watershed.

 

 

5-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

5.3 Climate

The climate is typically continental, with extremes in temperatures ranging from +35°C to -40°C, from summer to winter. Annual rainfall in the region averages about 60 cm, with heaviest rains expected from June to August, when an average of about 30 cm of rain is recorded. An average of 150 cm snowfall is recorded annually in the region.

 

5.4 Physiography

The Rainy River Project region is divided into two (2) main physiographical regions. These regions are separated by a distinct northwest to southeast divider, locally termed the Rainy Lake - Lake of the Woods Moraine, which traverses the countryside immediately to the north of the Richardson Township. To the north and east of this Rainy Lake - Lake of the Woods Moraine, there is a substantial amount of bedrock exposure and topographic relief can be up to 90 m. This relief contrast is controlled by the geology of the batholiths, which erode negatively in comparison to the supracrustals of the Canadian Shield. The area was subjected to the Whiteshell glacial event from the Labradorean ice centre to the northeast.

The region to the south and west of the Rainy Lake - Lake of the Woods Moraine, comprises of lowlands, which underwent peneplanation in the Cretaceous, eroding away most of the Mesozoic cover. Topographic relief in this region is lacking, the glacial overburden is typically twenty to forty metres thick, drainage is poor and outcrop is limited to less than one percent of the surface area. This area was exposed to successive glaciations from the northeast and west.

The bedrock is immediately overlain by Labradorean till that is geochemically responsive. This Labradorean till is in turn overlain by thick, highly conductive glaciolacustrine silts and clays of Glacial Lake Agassiz and easterly transported clay and carbonate-rich Keewatin till. Some poorly drained areas are also covered by a thick peat layer which further impedes exploration activities.

The Project area is sparsely populated. The vegetation falls within the northeastern hardwood region immediately adjacent to the southern margin of the boreal forest (Figure 5-1).

 

 

5-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 5-1: Typical Landscape in the Rainy River Project Area

 

A Landscape east of the open pit area, looking north towards the Intrepid Zone within the Project Area.
B View of the Rainy River Exploration facility. A new facility was constructed in 2013 a few kilometres east of the Project Area.

 

 

5-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

6. HISTORY

The bulk of this historical review is based upon the documentation of exploration in northwestern Ontario that is archived in the MNDM offices at Kenora. Exploration in the Rainy River Project area began in 1967. Various companies were active between 1967 and 1989. Nuinsco undertook exploration activities between 1990 and 2004, with Rainy River continuing from 2005 onwards.

 

6.1 Previous Exploration Work

A summary of the exploration activities undertaken on the Rainy River Project property from 1967 to 2004 is presented below.

 

6.1.1 Period 1967 to 1989 by Various Companies

1967

Anomalous copper was noted in the region.

1967

Noranda registered claims and performed geophysics.

1971

The Ontario Division of Mines, Ministry of Natural Resources, mapped the north-central part of the Rainy River Greenstone Belt (Blackburn, 1976).

1971

International Nickel Corporation of Canada (“INCO”) undertook follow-up ground geophysics. INCO drilled two (2) diamond drill holes in Richardson Township. Results are unknown.

1972

Hudson’s Bay Exploration and Development (“HBED”) undertook airborne and follow-up ground geophysics. In 1973, HBED drilled 54 core boreholes in the Rainy River Project region. There was insufficient encouragement to continue and exploration was curtailed.

1988

The Ontario Geological Survey (“OGS”) Map P.3140 was produced. It was based on the interpretation of aeromagnetic data and geological mapping carried out by Johns (1988). This mapping was supported by an OGS rotasonic drilling program on a 3 km drill grid completed between 1987 and 1988.

 

 

6-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The OGS program resulted in the discovery of a “gold grains-in-till” anomaly in Richardson Township.

1988

Mingold Resources followed up on this gold grains-in-till anomaly and staked 85 claims and optioned patented lands in Richardson and some neighbouring townships. Their use of various sampling methodologies on the till, including reverse circulation drilling, gave inconclusive results.

 

6.1.2 Period 1990 to 2004 by Nuinsco

A tabulated summary of the exploration work undertaken by Nuinsco is provided in Appendix C.

1992

Nuinsco optioned patented lands centred on Richardson Township and the Menary Township. Gold occurrences discovered by King’s Bay Gold Corporation optioned from Western Troy Resources in September 1992.

1993 to 1998

A total of 597 widely spaced reverse circulation drill boreholes define a 15 km long gold grains-in-till dispersal train emanating from a 6 km2 gold-in-bedrock” anomaly averaging 79 parts per million (“ppm”) gold.

1994 to 2004

Total of 217 core boreholes (49,515 m) drilled, mostly in Richardson Township.

1994

Investigation of gold grains-in-till and gold-in-bedrock anomalies with a series of core boreholes leading to the discovery of the 17 Zone.

1995

Discovery of 34 Zone (copper-nickel-platinum group metals) followed by intensive diamond drilling.

 

 

6-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

1997

The discovery of 433 Zone 500 m to the north of the 17 Zone.

1999

Core drilling targeting the 34 Zone and a magnetic anomaly in Tait Township.

2000

Audio magneto-telluric (“AMT”) geophysical survey. Several targets were defined and drilled, but these proved to be massive graphite, disseminated sulphides or massive but barren sulphides.

2004

Investigation of the depth continuity of the 34 Zone with eight (8) core boreholes (1,549 m).

 

6.1.3 Previous Mineral Resource Estimates

Eight (8) previous mineral resource evaluations were prepared for the Rainy River Project by Mackie et al. in 2003, Caracle Creek International Consulting Inc. (“CCIC”) in 2008 and by SRK in 2009, 2010, 2011 and 2012. Six (6) of these mineral resource statements are documented in previous technical reports prepared for the Project and are available from SEDAR.

The initial mineral resource statement prepared by Mackie et al. (2003) is presented in Table 6-1. The second mineral resource statement was prepared by CCIC in 2008 and is presented in Table 6-2. CCIC reported the mineral resources at three (3) gold cut-off grades.

Table 6-1: Mineral Resource Statement1 for the Rainy River Project, Ontario, Mackie et al., December 23, 2003.

 

     Quantity      Grade      Metal  

Category

   ‘000 t      Au
g/t
     Cu (%)      Zn (%)      Ag
g/t
     Au ‘000
oz.
 

Indicated

     1,736         1.56         0.03         0.21         4.0         87.1   

Inferred

     11,025         1.33         0.02         0.20         3.6         471.2   

 

1. 

Reported at a cut-off grade of 0.7 g/t gold.

 

 

6-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 6-2: Mineral Resource Statement for the Rainy River Project, Ontario, Caracle Creek International Consulting Inc., April 30, 2008

 

     Cut-off      Quantity      Grade      Metal  

Category

   Au
g/t
     ‘000 t      Au
g/t
     Ag
g/t
     Au
‘000 oz.
     Ag
‘000 oz.
 

Indicated

     0.3         37,761         1.18         2.60         1,436         3,159   

Inferred

     0.3         79,654         0.94         2.31         2,400         5,923   

Indicated

     0.5         34,238         1.26         2.63         1,386         2,896   

Inferred

     0.5         67,564         1.03         2.35         2,233         5,109   

Indicated

     0.7         24,959         1.50         2.63         1,206         2,106   

Inferred

     0.7         44,391         1.25         2.26         1,787         3,257   

In 2009, SRK prepared the third mineral resource statement incorporating information from an additional 112 core boreholes (59,719 m) drilled subsequent to the CCIC 2008 mineral resource statement. The third consolidated mineral resource statement prepared by SRK in April 2009 is presented in Table 6-3.

 

 

6-4


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 6-3: Mineral Resource Statement1 for the Rainy River Project, Ontario,

SRK Consulting (Canada) Inc., April 28, 2009

 

     Quantity      Grade      Metal  

Category

   ‘000 t      Au
g/t
     Ag
g/t
     Au
‘000 oz.
     Ag
‘000 oz.
 

Open Pit2

              

Indicated

              

Volcanic-hosted

              

Within shell

     55,027         1.21         1.89         2,135         3,350   

Mafic-hosted

              

Within shell

     57         1.37            3      

Inferred

              

Volcanic-hosted

              

Within shell

     12,491         0.95         2.36         382         950   

Outside shell

     50,637         0.79         2.19         1,278         3,562   

Underground2

              

Indicated

              

Volcanic-hosted

              

Below shell

     530         5.14         1.47         88         25   

Inferred

              

Volcanic-hosted

              

Below shell

     875         5.22         1.27         147         36   

Combined Mining

              

Indicated

     55,615         1.24         1.89         2,225         3,375   

Inferred

     64,003         0.88         2.21         1,807         4,548   

 

1. 

Mineral resources are reported in relation to optimized pit shells. Mineral resources are not mineral reserves and do not have demonstrated economic viability. All figures are rounded to reflect the relative accuracy of the estimate. All assays have been capped where appropriate. SRK also estimated zinc, lead and copper grades but these metals are not reported in the mineral resource statement because they reasonably do not contribute to the metal value of the gold mineralization. Nickel, copper and platinum group metals were also estimated for one small zone (34 Zone, Domain 201) and are reported separately. The consolidated resource statement above includes the gold mineralization in 34 Zone.

2. 

Open pit mineral resources are reported at a cut-off grade of 0.4 g/t gold; underground mineral resources are reported at cut-off grade of 3.0 g/t gold. Cut-off grades are based on a gold price of USD $800 per ounce gold and a gold metallurgical recovery of 85%, without considering revenues from other metals.

In early 2010, SRK prepared the fourth mineral resource statement to incorporate information from 124 core boreholes (68,453 m) drilled on the Project during 2009. The fourth consolidated mineral resource statement dated February 26, 2010, is represented in Table 6-4.

 

 

6-5


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 6-4: Mineral Resource Statement1, Rainy River Project, Ontario,

SRK Consulting (Canada) Inc., February 26, 2010

 

     Quantity      Grade      Metal  

Category

   ‘000 t      Au
g/t
     Ag
g/t
     Au
‘000 oz.
     Ag
‘000 oz.
 

Open Pit2

              

Indicated

              

Volcanic-hosted

              

Within shell

     55,657         1.20         1.76         2,153         3,151   

Mafic-hosted

              

Within shell

     57         1.37         5.10         3         9   

Inferred

              

Volcanic-hosted

              

Within shell

     6,252         1.26         2.66         252         535   

Outside shell

     58,339         0.90         2.81         1,688         5,270   

Underground2

              

Indicated

              

Volcanic-hosted

              

Below shell

     1,119         6.03         4.28         217         154   

Inferred

              

Volcanic-hosted

              

Below shell

     4,339         5.15         1.69         718         236   

Combined Mining

              

Indicated

     56,833         1.30         1.81         2,370         3,314   

Inferred

     68,930         1.20         2.73         2,659         6,041   

 

1. 

Mineral resources are reported in relation to optimized pit shells. Mineral resources are not mineral reserves and do not have demonstrated economic viability. All figures are rounded to reflect the relative accuracy of the estimate. All assays have been capped where appropriate. Nickel, copper and platinum group metals were also estimated for one small zone (Zone 34) and are reported separately. The consolidated resource statement above includes the gold mineralization in Zone 34.

2. 

Open pit mineral resources are reported at a cut-off grade of 0.4 g/t gold, underground mineral resources are reported at a cut-off grade of 3.0 g/t gold. Cut-off grades are based on a gold price of USD $850 per ounce gold and a gold metallurgical recovery of 85%, without considering revenues from other metals.

In early 2011, SRK prepared the fifth mineral resource statement to incorporate information from 163 core boreholes (84,648 m) drilled on the Project during 2010. The fifth consolidated mineral resource statement dated February 24, 2011 is represented in Table 6-5.

 

 

6-6


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 6-5: Mineral Resource Statement1, Rainy River Project, Ontario,

SRK Consulting (Canada) Inc., February 24, 2011

 

     Quantity      Grade      Metal  

Category

   ‘000 t      Au
g/t
     Ag
g/t
     Au
‘000 oz.
     Ag
‘000 oz.
 

Open Pit2

              

Measured

     14,707         1.21         1.84         572         869   

Indicated

     77,934         1.05         2.24         2,640         5,616   

Measured and Indicated

     92,641         1.08         2.18         3,212         6,485   

Inferred

     104,591         0.80         2.31         2,703         7,781   

Underground2

              

Measured

     39         5.66         2.38         7         3   

Indicated

     1,197         5.18         3.30         199         127   

Measured and Indicated

     1,236         5.20         3.27         206         130   

Inferred

     3,831         3.83         2.62         472         323   

Combined Mining

              

Measured

     14,746         1.22         1.84         579         872   

Indicated

     79,131         1.11         2.26         2,839         5,743   

Measured and Indicated

     93,877         1.13         2.19         3,418         6,615   

Inferred

     108,422         0.91         2.32         3,175         8,104   

 

1. 

Mineral resources are reported in relation to an elevation determined from optimized pit shells. Mineral resources are not mineral reserves and do not have demonstrated economic viability. All figures are rounded to reflect the relative accuracy of the estimate. All composites have been capped where appropriate.

2. 

Open pit mineral resources are reported at a cut-off grade of 0.35 g/t gold and underground mineral resources are reported at a cut-off grade of 2.50 g/t gold. Cut-off grades are based on a price of USD $1,025 per ounce of gold and gold recoveries of 88% and 90% for open pit and underground resources, without considering revenues from other metals.

In June 2011, SRK prepared a sixth mineral resource statement to incorporate information from an additional 50 core boreholes (26,509 m) drilled on the Project since the last resource model considering data up to February 27, 2011. The sixth consolidated mineral resource statement dated June 29, 2011 is represented in Table 6-6.

 

 

6-7


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 6-6: Mineral Resource Statement1, Rainy River Project, Ontario,

SRK Consulting (Canada) Inc., June, 29 2011

 

     Quantity      Grade      Metal  

Category

   ‘000 t      Au
g/t
     Ag
g/t
     Au
‘000 oz.
     Ag
‘000 oz.
 

Open Pit2

              

Measured

     15,660         1.26         1.93         636         973   

Indicated

     99,927         1.08         2.48         3,481         7,967   

Measured and Indicated

     115,587         1.11         2.41         4,117         8,940   

Inferred (inside pit shell)

     16,602         0.94         2.63         504         1,406   

Inferred (outside pit shell)

     57,211         0.75         2.82         1,380         5,184   

Underground2

              

Measured

     100         4.74         2.67         15         9   

Indicated

     1,775         4.83         3.10         276         177   

Measured and Indicated

     1,875         4.82         3.08         291         185   

Inferred

     3,628         3.82         3.84         445         448   

Combined Mining

              

Measured

     15,760         1.28         1.94         651         981   

Indicated

     101,702         1.15         2.49         3,757         8,144   

Measured and Indicated

     117,462         1.16         2.42         4,407         9,125   

Inferred

     77,442         0.94         2.83         2,330         7,038   

 

1. 

Mineral resources are reported in relation to an elevation determined from optimized pit shells. Mineral resources are not mineral reserves and do not have demonstrated economic viability. All figures are rounded to reflect the relative accuracy of the estimate. All composites have been capped where appropriate.

2. 

Open pit mineral resources are reported at a cut-off grade of 0.35 g/t gold and underground mineral resources are reported at a cut-off grade of 2.50 g/t gold. Cut-off grades are based on a price of USD $1,100 per ounce of gold and gold recoveries of 88% and 90% for open pit and underground resources, respectively, without considering revenues from other metals.

In February 2012, SRK prepared a seventh mineral resource statement to incorporate information from an additional 375 core boreholes (181,682 m) drilled on the project since the last resource model considering data up to January 9, 2012. The seventh consolidated mineral resource statement dated February 24, 2012 is represented in Table 6-7.

 

 

6-8


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 6-7: Mineral Resource Statement1, Rainy River Project, Ontario,

SRK Consulting (Canada) Inc., February, 24 2012

 

     Quantity      Grade      Metal  

Category

   ‘000 t      Au
g/t
     Ag
g/t
     Au
‘000 oz.
     Ag
‘000 oz.
 

Open Pit2

              

Measured

     23,154         1.29         2.00         960         1,491   

Indicated (in pit)

     112,778         1.09         2.39         3,963         8,673   

Indicated (ex. pit)

     11,476         0.81         3.37         298         1,242   

Measured & Indicated

     147,407         1.10         2.41         5,221         11,406   

Inferred (in pit)

     22,679         0.93         2.18         675         1,588   

Inferred (ex. pit)

     64,437         0.67         2.35         1,387         4,871   

Underground2

              

Measured3

     89         4.62         2.55         13         7   

Indicated3

     3,083         4.32         5.00         429         495   

Measured and Indicated3

     3,172         4.33         4.93         442         502   

Inferred3

     1,172         4.12         5.82         155         219   

Combined Mining

              

Measured3

     23,243         1.30         2.00         973         1,498   

Indicated3

     127,337         1.14         2.54         4,690         10,410   

Measured and Indicated3

     150,580         1.17         2.46         5,663         11,908   

Inferred3

     88,288         0.78         2.35         2,217         6,678   

 

1. 

Mineral resources are reported in relation to an elevation determined from optimized pit shells. Mineral resources are not mineral reserves and do not have demonstrated economic viability. All figures are rounded to reflect the relative accuracy of the estimate. All composites have been capped where appropriate.

2. 

Open pit mineral resources are reported at a cut-off grade of 0.35 g/t gold and underground mineral resources are reported at a cut-off grade of 2.5 g/t gold. Cut-off grades are based on a gold price of USD $1,100 per ounce, and a foreign exchange rate of CAD $1.10 to USD $1.00 and gold recoveries of 88% for open pit and 90% for open pit and underground mineral resources, respectively.

3. 

Due to a reporting discrepancy, the underground resources reported in the Press Release by Rainy River on February 24, 2012 differ nominally to that reported here.

In October 2012, SRK prepared an eighth mineral resource statement to consider new drilling data available up to July 10, 2012. The total database comprised 1,435 core boreholes (662,849 m). This consolidated mineral resource statement dated October 10, 2012 is represented in Table 6-8.

 

 

6-9


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 6-8: Consolidated Mineral Resource Statement1, Rainy River Project, Ontario

SRK Consulting (Canada) Inc., October 10, 2012

 

            Grade      Metal  

Category

   Quantity
‘000 t
     Au
g/t
     Ag
g/t
     Au
‘000 oz.
     Ag
‘000 oz.
 

In Pit Mineral Resources2

              

Measured

     27,550         1.32         1.90         1,168         1,681   

Indicated

     112,271         1.11         2.51         4,012         9,048   

Measured and Indicated

     139,821         1.15         2.39         5,180         10,728   

Inferred

     19,353         0.88         1.40         550         870   

Out of Pit Mineral Resources2

              

Indicated

     14,466         0.80         3.84         373         1,785   

Inferred

     73,555         0.68         2.53         1,610         5,980   

Underground Mineral Resources2

              

Measured

     88         4.97         2.76         14         8   

Indicated

     4,148         4.50         6.12         600         816   

Measured and Indicated

     4,236         4.50         6.05         614         824   

Inferred

     897         4.18         4.63         120         134   

Combined Mineral Resources: In Pit, Out of Pit and Underground2

              

Measured

     27,638         1.33         1.90         1,182         1,689   

Indicated

     130,885         1.18         2.46         4,985         11,649   

Measured and Indicated

     158,523         1.21         2.62         6,167         13,338   

Inferred

     93,805         0.75         2.32         2,280         6,984   

 

1. 

Mineral resources are reported by relative conceptual pit shells. On average, the open pit extends to an elevation of 500 m below surface. Mineral resources are not mineral reserves and do not have a demonstrated economic viability. All figures are rounded to reflect the relative accuracy of the estimate. Figures may not add due to rounding. All assays have been capped where appropriate.

2.** 

Open pit mineral resources are reported at a cut-off grade of 0.35 g/t gold, underground mineral resources are reported at a cut-off grade of 2.5 g/t gold based on a gold price of USD $1,100 per ounce, a silver price of USD $22.50 per ounce, a foreign exchange rate of CAD $1.10 to USD $1.00, gold recovery of 88% for open pit resources and 90% for underground resources with silver recovery at 75%.

 

 

6-10


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

7. GEOLOGICAL SETTING AND MINERALIZATION

 

7.1 Regional Geology

The Rainy River Project is located within the Late Archean Rainy River Greenstone Belt (“RRGB”) which formed approximately 2.7 billion years ago (“Ga”). The RRGB forms part of the western Wabigoon subprovince, located in the Superior Province of the Canadian Shield. The Wabigoon subprovince is a 900 km long, east-west trending composite volcanic and plutonic terrane comprising distinct eastern and western domains separated by rocks of Mesoarchean age (Percival et al. 2006).

The western Wabigoon domain is predominantly composed of mafic volcanic rocks intruded by tonalite-granodiorite intrusions. The volcanic rocks which were largely deposited between approximately 2.74 and 2.72 Ga, range from tholeiitic to calc-alkaline in composition, and are interpreted to represent oceanic crust and volcanic arcs, respectfully (Percival et al. 2006). These are succeeded by approximately 2.71 to 2.70 Ga volcano-sedimentary sequences and by locally deposited, unconformable, immature clastic sedimentary sequences.

The volcanic rocks have been intruded by a wide variety of plutonic rocks including synvolcanic tonalite-diorite-granodiorite batholiths, younger granodiorite batholiths, sanukitoid monzodiorite intrusions and monzogranite batholiths and plutons. The intrusions were emplaced over a large time span between approximately 2.74 to 2.66 Ga (Percival et al. 2006).

A regional map of the interpreted bedrock geology of the area west of Fort Frances is shown in Figure 7-1. In the region east of Fort Frances, the Wabigoon subprovince is bound to the south by the late Archean, dextral Seine River–Rainy Lake and Quetico faults. The Quetico Fault splays off the subprovince boundary and strikes west through the western Wabigoon domain just south of the Rainy River Project. The RRGB is bounded to the north by the Sabaskong Batholith and to the east by the Rainy Lake Batholithic Complex and is contiguous with the Kakagi-Rowan Lakes Greenstone Belt to the north.

The regional metamorphic grade of the Achaean rocks is greenschist to lower-middle amphibolite facies. Locally, adjacent to the intruding batholiths, upper amphibolite mineral assemblages are recognized.

 

 

7-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Significant metallic mineral deposits hosted in the western Wabigoon domain include the Cameron Lake gold deposit hosted in the adjacent Kakagi–Rowan Lakes Greenstone Belt, the Hammond Reef gold deposit 190 km to the east of the Rainy River Gold Project, and the Sturgeon Lake Volcanogenic Massive Sulphide (VMS) deposits 250 km to the northeast of the Rainy River Project.

Three (3) phases of the Quaternary Wisconsinan glaciation are recorded in the Rainy River Project (Barnett, 1992). The Archean basement rocks and locally preserved Mesozoic sediments are overlain by till deposited from the Labrador Sector of the Laurentide Ice Sheet. Its provenance area is the Archaen basement of the Canadian Shield to the northeast. In the area of the Rainy River Project, this till has been found to contain highly anomalous concentrations of gold grains, auriferous pyrite and copper-zinc sulphides. As the Labradorean ice sheet retreated, a thick, electrically conductive, geochemically unresponsive glaciolacustrine clay and silt horizon originating from glacial Lake Agassiz was deposited.

 

 

7-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 7-1: Regional Bedrock Geology of the Area West of Fort Frances

(modified from Percival and Easton, 2007)

 

 

7-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Abbreviations in Figure 7-1 are as follows:

 

 

BHS – Black Hawk Stock,

 

 

KFLGB – Kakagi-Rowan Lakes Greenstone Belt,

 

 

QF – Quetico Fault, RLBC–Rainy Lake Batholithic Complex,

 

 

RRGB – Rainy River Greenstone Belt, Rainy River Project,

 

 

SRRLF – Seine River–Rainy Lake Fault,

 

 

SB – Sabaskong Batholith.

The Keewatin Sector of the Laurentide Ice Sheet then advanced over the area and deposited an argillaceous till of western provenance on top of the clay and silt horizon. The Rainy River Project area was therefore successively covered by the Labradorean and Keewatin ice sheets.

 

7.2 Property Geology

The geology of the Rainy River Project is inferred from regional field mapping of limited rock exposures, extensive drilling by Nuinsco and Rainy River, OGS rotasonic drilling and airborne geophysics.

A bedrock geological interpretation produced by Rainy River for the area surrounding the Rainy River Project is shown in Figure 7-2.

The Rainy River Project is centred on Richardson Township. To the north of Richardson Township lies the Sabaskong granitoid batholith. The Black Hawk Stock lies to the east of Richardson Township. A package of metasedimentary rock is found south of Richardson Township. Wedged in between these lithologies are a series of tholeiitic mafic and structurally overlying calc-alkalic intermediate to felsic metavolcanic rocks, striking almost east-west and dipping to the south. Intermediate dacitic rocks host most of the Rainy River gold mineralization.

 

 

7-4


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 7-2: Bedrock Geological Interpretation for the Area Surrounding the Rainy River Project (from Rainy River, 2013)

 

 

7-5


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

7.2.1 Lithology

Lower Mafic Volcanic Succession

The Rainy River Project area is primarily underlain by tholeiitic metavolcanic rocks of the western Wabigoon subprovince – the Rainy River Greenstone Belt. Geochemically they are high-iron and high-magnesium basalts comprising coarse-grained massive lava flows, massive and pillow flows and flow breccia. Subordinate dacitic tuff and intrusive quartz-feldspar porphyry dikes and sills are commonly noted interbedded or intruding respectively throughout the mafic volcanic rock.

Intermediate-Felsic Porphyritic Intrusive Rock

Swarms of porphyritic intermediate to felsic dikes cut through the Lower Mafic volcanic succession. They range in thickness up to several tens of metres. It has been suggested that these dikes may have been the conduits that fed the overlying intermediate succession hosting the mineralization. They have been variably interpreted and often described as dacitic tuffs due to their similar composition and appearance to units noted within the overlying intermediate succession. Historically, these complex and strongly deformed units have been denoted as the Georgeson/Feeder Porphyries.

Upper Felsic Succession

The Upper Felsic Succession overlies the Intermediate Succession along the southern boundary of Richardson Township. The Upper Felsic Succession is a few hundred metres thick and has been traced for 4 km westwards from the Black Hawk Stock. It has been interpreted as a quartz-phyric rhyolite.

Pinewood Sediment Succession

The Pinewood sedimentary rock package is composed of predominantly clastic intermediate derived wacke and argillite. The sequence conformably overlies the upper diverse mafic volcanic rocks, and the contact is typically marked by a pyritic heavy metal-bearing graphitic horizon. The upper contact of the succession is interbedded with the Upper Felsic Succession.

 

 

7-6


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Pyritic Sediment Succession

Conformably overlying the Lower Mafic Volcanic Succession are a series of pyrite-bearing siliceous to chloritic wacke, interpreted as derived from intermediate to mafic volcanic sediments. These horizons are increasingly interbedded with homogenous and nondescript to quartz-eye dacite tuff horizons as the upper contact is approached, and these tuff horizons likely represent onset of the lateral equivalent of subsequent intermediate volcanism.

Ultramafic-Mafic Intrusion

Thin zones of ultramafic to mafic intrusions have been noted in drill core. They form dikes or sills intruding the volcanic stratigraphy at different times. Their sulphide content is typically below 2%. The 34 Zone is hosted in a late-stage mafic-ultramafic intrusion, crosscutting the 17 Zone. The main lithological units include dunite, pyroxenite, pyroxene-gabbro and gabbro. The lowermost units contain significant sulphide mineralization enriched in copper, nickel, gold and platinum group metals.

Intermediate Fragmental Volcanic Succession

The Intermediate Succession is complex. Immediately overlying the pyritic sediment horizon in Richardson Township, these volcaniclastic rocks are composed of fine-grained “quartz-eye” dacite and fine-grained ash horizons with subordinate interbedded coarse grained lapilli tuff and localized sedimentary and exhalative horizons. A high proportion of what appear to be coarse volcaniclastic rocks may in fact be massive flows or tuffs overprinted by strong, anastomosing foliation and sericite alteration. Geochemically these intermediate rocks have been interpreted as calc-alkaline dacite with subordinate rhyolite and andesite. Some blocks of tuff breccia have been observed juxtaposed against the Black Hawk Stock which intrudes and notably alters the volcaniclastic rocks to the east. The rocks of the intermediate succession dip 50° to 70° to the south in the Richardson area and are the principal host of the mineralization in the ODM/17, 433, Beaver Pond, Western, and HS Zones.

Black Hawk Stock

This quartz monzonitic to granodioritic stock consists of two (2) phases and represents a topographic high to the east. The early phase forms the rim of the stock, and is a weakly foliated, notably magnetic, massive to pegmatitic quartz monzonite with minor subordinate granodiorite. The late phase consists of equigranular coarse grained granodiorite, and forms the central core of the stock. Associated magnetic aplitic to pegmatitic dikes compositionally similar to the early phase intrude the surrounding metavolcanic rocks.

 

 

7-7


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Massive Lava Flows

Immediately overlying the intermediate fragmental volcanic rocks are a series of intermediate to mafic volcanic massive lava flows, ranging from fine-grained porphyritic quartz dacite, to massive magnetite-bearing mafic volcanic rocks, with localized pillowed mafic flows. These units are notably homogenous, and the intermediate volcanic units often show a diagnostic deformed sericitic net-textured compression fracture pattern. Upper and lower contacts display a centimetre scale shear fabric at the margins.

Upper Diverse Mafic Volcanics

The upper diverse mafic volcanic succession is composed of a series of mafic tuffs, massive to glomeroporphyritic mafic flows, localized pillowed flows, interflow sediment and hyaloclastite, and minor subordinate intermediate volcanic tuffs. The rocks of the upper diverse mafic volcanics are the principal host of the CAP Zone mineralization.

Proterozoic Diabase Dike

A northwest-striking, steeply dipping diabase dike cross-cuts the ODM/17 Zone and extends across the entire Project area.

 

7.2.2 Structural Geology

The volcano-sedimentary sequences of the Rainy River Project and regional greenstone belt were affected by at least five (5) main deformation episodes. See Figure 7-3.

All rock types within the Intrepid mineralized zone, with the exception of the late diabase dykes, have a well-developed, moderately south-dipping, penetrative foliation and a moderately southwest-plunging stretching lineation (Figure 7-4).

These fabrics commonly obliterate the original layering and a primary folding event (F1), consisting of large recumbent and low-plunging folds with a north-south axial plane parallel to the strike of a steep axial-plane foliation (S1). The folding event was also accompanied by localized T1 thrusts (potentially at regional scale) (Rankin 2013). The pre-D1 mineralized veins are strongly folded and commonly transposed into the S1 foliation.

 

 

7-8


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 7-3: Regional Structural Trends on the Rainy River Gold Project, Interpreted from Aeromagnetics (Rankin, 2013)

 

 

7-9


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

A second folding event (F2) consisting of east-southeast-trending upright to overturned shallow-plunging folds of variable intensity, refolded S1 and L1 with variable dips and plunges across the belt. The Rainy River Project auriferous zones lie within a moderate to steeply dipping F2 limb with So & S1 trending 110/55 (average) and L1 steep south-southwestern plunge (~down-dip). This forms the northern limb of a regional F2. F2 folding was possibly accompanied by T2 thrust to high angle reverse faults, partitioning subdomains with varying D2 strain. A weak F2 axial-planar foliation is locally visible in both drill core and outcrop. F2 fold axes are typically subhorizontal to shallowly plunging (Rankin 2013). Steep-plunging ore-shoots within the mineralized zones probably represent localized F1 fold hinges, forming thickened zones of early veins. Termination of ore shoots down-plunge may locally be due to refolding of F1 about local F2 folds at an oblique angle.

Broad-scale bends (D3) in the D1/D2 structural grain followed as kink folds in the greenstone belt. These trend north-northwest- to north-east (with some conjugate kink geometry evident). F3 folds are associated with subvertical S3 spaced fracture cleavages to small scale faults. See Figure 7-5.

A consistent sinistral displacement along these structures may be due to progressive rotation of the compressive stress direction from D3 to D4. Small-scale F3 kinks are common within the layered sequences in outcrop and drill core. Very localized remobilization of quartz-sulphide (as veinets) into the kink axial planes may have produced small zones of enriched mineralization. F3 fold axes are typically steeply plunging (where is folding steeply dipping So/S1 fabrics). Emplacement of ~north-trending granitoid stocks east of the Rainy River gold project is interpreted to have occurred along F3 kink axes (possible reactivated basement faults) (Rankin 2013).

D4 is represented by a late-stage NNW-SSE to N-S compressive episode causing broad warping of all pre-existing fabrics, including F3 mega-kink axial planes. D4 is interpreted to have also caused both flat-lying breccia bodies with late-stage kaolin-sericite alteration in the Intrepid area (subhorizontal tension gash structures), and a weak ESE-trending foliation in the Blackhawk granitoid stock.

The final deformation event; D5 is represented by late stage (Proterozoic) emplacement of NW-trending mafic dykes (NE-SW extension).

 

 

7-10


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 7-4: Structural Fabrics Affecting Rock Types

 

A. Strong, penetrative foliation in sericite-quartz-altered, quartz-phyric rocks. Photo is rotated to approximate dip of borehole (NR09399, 672.2 m).
B. Southwest raking stretching lineation (NR09402, 245.9 m).

 

 

7-11


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 7-5: Evidence for Strike-Slip Kinematics of Late Brittle Faulting (SRK, 2011)

 

A. Subhorizontal striations on calcite-filled, north-striking subvertical strike-slip faults (borehole NR0505, 150.6 m).
B. Outcrop (426255E/5409525N) showing set of 360° to 020°-striking, subvertical faults offsetting mafic dike predominantly with sinistral separation in this area.

Outcrop (426255E/5409525N) showing set of 360° to 020°-striking, subvertical faults offsetting mafic dyke predominantly with sinistral separation in this area.

A late-stage north-northwest to south-southeast to north-south compressive episode caused broad warping of all pre-existing fabrics, including F3 mega-kink axial planes (Figure 7-6). This D4 episode is interpreted to have also caused both flat-lying breccia bodies with late-stage kaolin-sericite alteration in the Intrepid Zone (subhorizontal tension gash structures) and a weak east-southeast trending foliation in the Blackhawk granitoid stock.

 

 

7-12


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 7-6: Pressure Shadows Around Rigid Objects in Dacitic Rock

SRK structural analyses (Siddorn, 2007; Hrabi and Vos, 2010) have noted that the gold mineralization is strongly overprinted by subsequent deformation.

Key observations in core and outcrop include:

 

 

Auriferous mineralization is aligned along the regional foliation;

 

 

Fold axes of auriferous quartz veins and sulphide stringers are rotated subparallel to the stretching lineation;

 

 

Fold axes, boudin necks and stretching lineation are subparallel to the plunge of the gold mineralization;

 

 

Early sulphide mineralization is deformed by folding (Figure 7-7); and

 

 

Later quartz-sulphide veins are variably deformed and overlap in time with the main regional deformation.

 

 

7-13


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 7-7: Sulphide Mineralization Deformed by Folding in Core from the Rainy River Project (SRK, 2011)

This strongly suggests that the current geometry and plunge of the gold mineralization at the Rainy River Project is the result of high strain deforming features associated with gold mineralization and rotating the ore plunge parallel to the stretching direction (Figure 7-8).

 

 

7-14


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 7-8: Structural Control of the Plunge of the Gold Mineralization at the Rainy River Project

 

A. Fold axis of pyrite stringer vein rotated parallel to mineral lineation (NR09408, 459.5 m).
B. Boudinaged quartz vein with boudin neck parallel to stretching lineation (NR09360, 766.4 m).
C. Diagram illustrating rotation of ore plunge in high strain deformation (modified from Robert and Poulsen, 2001).

 

7.3 Mineralization

Four (4) main styles of mineralization have been identified on the Rainy River Project:

 

1. Moderately to strongly deformed, auriferous sulphide and quartz-sulphide stringers and veins in felsic quartz-phyric rocks (ODM/17, Beaver Pond, 433 and HS Zones);

 

2. Deformed quartz-ankerite-pyrite shear veins in mafic volcanic rocks (CAP/South Zone);

 

3. Deformed sulphide-bearing quartz veinlets in dacitic tuffs/breccias hosting enriched silver grades (Intrepid Zone); and

 

4. Copper-nickel-platinum group metals mineralization hosted in a younger mafic-ultramafic intrusion (34 Zone).

 

 

7-15


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

7.3.1 Auriferous Sulphide and Quartz-Sulphide Stringers and Veins in Felsic Quartz-Phyric Rocks

The bulk of the gold mineralization at the Rainy River Project is contained in sulphide and quartz-sulphide stringers and veins hosted by felsic quartz-phyric rocks. Two (2) main zones are recognized (ODM/17 and 433 Zones) with subsidiary zones (HS and New), which are mostly bound by high strain zones.

ODM/17 Zone

Three (3) styles of gold mineralization can be observed in the ODM/17 Zone. Low-grade intervals are characterized by tightly folded pyrite stringer veins and disseminated pyrite in sericite-quartz-chlorite altered host rocks.

Low- to moderate-grade (up to approximately 10 g/t gold) intervals are characterized by tightly folded and foliation parallel pyrite-sphalerite and pyrite stringer veins, commonly associated with stronger silica and weak garnet alteration (Figure 7-9). High-grade gold mineralization in this zone is associated with deformed quartz-pyrite-gold veinlets (Figure 7-10) that overprint other mineralization styles.

The low-grade ODM/17 Zone is modelled over a strike length of approximately 1,600 m, over a vertical distance of approximately 975 m and over a true width of up to 200 m.

The medium-grade Beaver Pond subdomain (Subdomain 114) is located 300 m to the west of the ODM/17 Zone and is included within the larger ODM/17 low-grade domain. Mineralization is similar in style and character to the ODM/17 Zone, including the presence of deformed gold-rich quartz veinlets, although generally the widths of auriferous drill intercepts are narrower.

 

 

7-16


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 7-9: ODM/17 Zone Gold Mineralization (SRK, 2011)

Deformed pyrite-sphalerite veins and stringers parallel to, or obliquely to foliation in quartz-sericite-chlorite altered rocks (Borehole NR0651 at downhole interval, as indicated).

 

LOGO

Figure 7-10: ODM/17 High-Grade Gold Mineralization (SRK, 2011)

Deformed quartz-pyrite vein with visible gold emplaced along boudin neck (Borehole NR0651 at 251.1 m; 195.5 g/t gold over 1 m core length interval).

 

 

7-17


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The 433, HS and New Zones

The style of gold mineralization in the 433 Zone is comparable to that observed in the ODM/17 Zone, although some differences are apparent. These include an overall dominance of chlorite alteration (relative to dominant sericite in the ODM/17 Zone) of quartz-phyric host rocks, occurrences of chlorite-pyrite altered heterolithic conglomerates, and the occurrence of chalcopyrite and chlorite with high-grade quartz-pyrite-gold veinlets (Figure 7-11).

 

LOGO

Figure 7-11: 433 High-Grade Gold Mineralization (SRK, 2011)

Deformed quartz-pyrite-chalcopyrite-chlorite-gold veins cross-cutting foliation and disseminated pyrite in quartz-sericite altered quartz-phyric rock (Borehole NR07-218 at 305.2 m; 4,159 g/t gold over 1 m core length interval).

The modelled 433 low-grade Zone has a flattened oblate shape that plunges moderately to the southwest. The zone extends over a strike length of approximately 325 m, over a vertical distance of approximately 820 m and a true width of up to 125 m.

Several subsidiary zones of gold mineralization are identified at the Rainy River Project, including the HS and New Zones. The HS and New Zones are located north of and structurally beneath the ODM/17 Zone and slightly above the 433 Zone. The full extent of the HS Zone has not been defined by drilling to-date.

 

 

7-18


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The HS Zone defines a plunging, flattened oblate shape subparallel to the ODM/17 and 433 Zones which hosts discontinuous, irregular low-grade gold mineralization associated with chlorite-pyrite replacement of matrix in flattened, albitized heterolithic pebble conglomerates. The New Zone is more irregular in shape, comprising a number of small zones in the immediate hanging wall of the 433 Zone. The zones have a strike length of approximately 200 and 275 m respectively, and both extend a vertical distance of approximately 700 m.

The Western Zone

The Western Zone occurs near surface approximately 1 km northwest of the Beaver Pond Zone. It is composed of stockwork of discrete centimetre scale anastomosing, folded to linear quartz and quartz-carbonate veinlets, hosted predominantly by strongly deformed intermediate volcanic fragmental units, analogous to those that host the ODM/17 Zone, but also present in mafic volcanic flows in both the immediate footwall and hanging wall. The stratigraphy hosting the Western Zone shows a much higher degree of deformation than to the east and combined with intense sericitic alteration and foliation is often described as a pervasive shear fabric or approaching mylonitic texture. The veinlets are variably mineralized, with inclusions (in the order of frequency) of pyrite, anemic sphalerite, chalcopyrite, galena, native silver, electrum and native gold.

 

7.3.2 Deformed Quartz-Ankerite-Pyrite Shear Veins in Mafic Volcanic Rocks

The CAP Zone

The CAP Zone is located approximately 200 m to the south of the ODM/17 Zone and defines a southwest-plunging lens modelled over a strike length of approximately 400 m to a depth of approximately 400 m below surface. Higher-grade gold mineralization is associated with deformed quartz-ankerite-pyrite shear and extensional veins hosted by quartz-ankerite-pyrite altered mafic volcanic rocks. See Figure 7-12. Relative to ODM/17 and 433 Zones, the CAP Zone has a higher pyrite-chalcopyrite content.

 

 

7-19


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 7-12: Higher Grade Gold Mineralization—Borehole NR10-474 from 188.0 to 234.0 m. (SRK, 2011)

 

7.3.3 Silver-Rich Deformed Sulphide-Quartz Veins within Tuffaceous Rocks

The so-called “Footwall Silver Zone” occurs in altered dacitic tuffs/tuff breccias immediately adjacent to the high strain zone at the northern contact of the ODM/17 Zone. The zone plunges to the southwest in similar orientation to the ODM/17 Zone, and is hosted by centimetre scale sulphide bearing quartz veinlets, typically appearing as millimetre scale fracture filling to dendritic native silver inclusions. Associated sulphides within these veinlets in order of frequency are; pyrite, sphalerite, chalcopyrite, galena. Localized spessartine garnets have been noted. The presence of isoclinal folding of the veinlets gives the mineralization a relative timing of pre to syndeformational, and the zone is currently considered to be coeval with the ODM/17 Zone.

High-grade gold and silver mineralization in the Intrepid Zone is associated with deformed quartz-pyrite-gold, quartz-pyrite-silver, or quartz-pyrite-gold-silver veinlets that overprint other mineralization styles. See Figure 7-13. The gold-silver ratio is determined by their location within the base metal zonation controlling the low to moderate grade mineralization.

 

 

7-20


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 7-13: Intrepid Zone Gold Mineralization. Deformed Pyrite-Sphalerite Veins and Stringers Borehole NR131542 (Rainy River, 2013)

 

7.3.4 Nickel-Copper-PGE Mineralization

The 34 Zone

Magmatic nickel copper sulphide mineralization is found in the 34 Zone. It is associated with precious metals (gold, platinum group metals) and occurs within a tubular, late-stage pyroxenite-gabbro intrusion that crosscuts the ODM/17 Zone. The magmatic sulphides vary from massive to net-textured and disseminated. The host pyroxenite-gabbro intrusion is unmetamorphosed, but locally altered into serpentine and talc. The 34 Zone extends at least 350 m along strike. The host intrusion is approximately 100 m thick and plunges at 12° to the west. The limits of the 34 Zone are poorly constrained owing to the discontinuous nature of the mineralization and a lack of drilling data.

 

 

7-21


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

8. DEPOSIT TYPES

The origin of gold mineralization at the Rainy River Project remains enigmatic because it has been modified by deformation as highlighted in recent studies (Siddorn, 2007; Hrabi and Vos, 2010).

Early exploration work performed by Nuinsco was based on the premise that the gold mineralization encountered at Rainy River was shear-hosted and epigenetic in origin. Subsequent interpretations for the geology and genesis of the Rainy River Project gold mineralization involved an early, volcanogenic-associated caldera model, as proposed by Ayres (1997) and Averill (2008). Volcanic facies reconstruction studies by Wartman (2011) suggest the presence of a lobe-hyaloclastite dacite dome/flow complex fed and locally intruded by synvolcanic dacite hypabyssal intrusions. Despite the strong alteration overprint, primary textures indicate that the volcanic facies in the deposit include coherent dacitic flows and associated syn-volcanic intrusions with autoclastic breccias, hyaloclastites, peperites and syn- to post-depositional resedimented volcaniclastic deposits.

With the collection of additional data from exploration drilling, it was recognized that gold mineralization at the Rainy River Project is associated with strong sodium depletion, potassium enrichment, aluminous alteration, a strong gold-pyrite association, common sphalerite, chalcopyrite and manganiferous garnet (spessartine) and a very high ratio of silver to gold. These features suggest a volcanogenic sulphide origin. However, no significant base metal mineralization or stratiform sulphide lenses have been recognized.

Siddorn (2007) and Hrabi and Vos (2010) suggested that at least two (2) stages of gold mineralization occurred in the Rainy River Project:

 

 

Early (low- to moderate-grade) gold mineralization associated with the emplacement of sulphide (pyrite-sphalerite-chalcopyrite-galena) stringers and veins and disseminated pyrite in quartz-phyric volcaniclastic rocks and conglomerates; and

 

 

Late (high-grade) gold mineralization associated with the emplacement of quartz-pyrite-chalcopyrite-gold veins and veinlets.

Both styles of gold mineralization have been progressively overprinted by deformation, whereby auriferous quartz veins post-date the sulphide stringers and veins and were emplaced during active deformation (Figure 8-1).

 

 

8-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 8-1: Idealized Sketch Showing Relative Timing of Auriferous Features and illustrating

Protracted Deformation Affecting Initial Gold-rich Volcanogenic Mineralization and

Subsequently Overprinted by Mesothermal Gold Mineralization (SRK, 2011)

On this basis, the gold mineralization is interpreted as a hybrid deposit-type consisting of an early gold-rich volcanogenic sulphide mineralization overprinted by shear-hosted mesothermal gold mineralization.

Volcanogenic deposits refer to a large family of mainly copper-zinc (and subsidiary gold, silver and/or lead) deposit types that are typically related to the precipitation of metals from hydrothermal solutions circulating in volcanically active submarine environments. Volcanogenic deposits typically form during periods of active rifting along volcanic arcs, fore-arcs and in extensional back-arc basins. Gold-rich volcanogenic deposits form a sub-type as described by Dubé et al., (2007).

Dubé et al., (2007) indicate that their diagnostic features include stratabound to discordant massive sulphide lenses with associated discordant stockwork feeder zones in which gold is the main commodity. The gold-rich volcanogenic deposits are present in both recent seafloor and deformed and metamorphosed submarine volcanic settings. Several of the largest volcanogenic gold deposits are located in Canada, including the Horne, Bousquet 2-Dumagami, LaRonde Penna and Eskay Creek deposits.

 

 

8-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Dubé et al. (2007) proposed that there are two (2) genetic models for gold-rich volcanogenic deposits:

 

 

Conventional syngenetic volcanic-hosted gold-poor volcanogenic mineralization overprinted during regional deformation by gold mineralization; and

 

 

Syngenetic volcanogenic deposits characterized by an anomalous fluid chemistry (with magmatic input) and/or deposition within a shallow-water to subaerial volcanic setting equivalent to epithermal conditions, in which boiling may have had a major impact on the fluid chemistry.

The deformation and metamorphism that commonly overprint the sulphide mineralization in ancient terranes have obscured the original relationships and led to considerable debate about the syntectonic versus synvolcanic origin of gold-rich volcanogenic deposits, as is also the case at the Rainy River Project.

Gold-rich volcanogenic deposits are characterized by zoned alteration profiles with an outer propylitic (chlorite±sericite) zone surrounding a sericite-rich core representing the “feeder zone” (Figure 8-2). Wartman (2011) and Sparkes & Wartman (2012) have proposed a similar genetic model to the classic model by Hannington et al., 1999, placing the various Rainy River deposits into better context with respect to their stratigraphic position (Figure 8-3).

Although no lenses of massive sulphides have been identified at the Rainy River Project, early pyrite-sphalerite-chalcopyrite-galena stringers and veins may have formed as a stockwork system in the feeder zone (i.e., fault system) as part of a gold-rich volcanogenic deposit.

In addition to the gold mineralization discussed above, the Rainy River Project also contains nickel, copper and platinum group metals sulphide mineralization associated with a differentiated ultramafic-mafic intrusion. This magmatic-hydrothermal mineralization occurs within the main auriferous zones and crosscuts the volcanogenic sulphide mineralization and the later mesothermal gold mineralization associated with the regional deformation.

 

 

8-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 8-2: Schematic Geological Setting and Hydrothermal Alteration Associated with Gold-rich

Volcanogenic Hydrothermal Systems (after Hannington et al., 1999)

 

 

8-4


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 8-3: Schematic Section and Hydrothermal Alteration Associated with the

Rainy River Project (Sparkes & Wartman, 2012)

 

 

8-5


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

9. EXPLORATION

 

9.1 Period 1967-1989

A summary of the historical exploration work from 1967 to 1989 is discussed in Section 6.1.1.

 

9.2 Nuinsco Exploration Work (1990-2004)

A summary of the exploration work undertaken by Nuinsco on the Rainy River Project property during 1990 to 2004 is discussed in Section 6.1.2 (refer to Appendix C).

 

9.3 Rainy River Exploration Work (2005-2013)

In June 2005, Rainy River completed the acquisition of a 100% interest in the Project from Nuinsco.

In the same year, Rainy River re-logged key sections of the historical core drilled on the Project property and then input all of the data into a GIS database. Rainy River subsequently drilled in excess of 100 reverse circulation holes in four (4) phases to better define the gold-in-till and gold-in-bedrock anomalies.

Between 2005 and 2007, 218 core boreholes (119,729 m) were drilled. This drilling resulted in the discovery of both the ODM and CAP gold mineralized Zones. The ODM is correlated as being the western extension of the 17 Zone. The CAP is a mineralized zone which is located higher up in the stratigraphy.

In April 2008 CCIC were commissioned to evaluate the mineral resources and prepare a technical report for the Rainy River Project. In 2008, Rainy River drilled an additional 100 core boreholes (53,123 m) and performed a fifth phase of reverse circulation drilling, peripheral to the known gold zones.

In 2009, SRK prepared a mineral resource statement incorporating information from the core boreholes drilled during 2008.

In early 2010, SRK prepared a revised mineral resource statement to incorporate information from 128 core boreholes (72,164 m) drilled on the Project during 2009.

 

 

9-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

In early 2011, SRK updated the mineral resource statement to incorporate information from 165 core boreholes (84,134 m) drilled on the project during 2010. In addition, Rainy River Resources discovered the western area mineralization, and continued to delineate the new zone throughout the year. The western area is located approximately 800 m to the northwest of the ODM/Beaver Pond mineralization.

In May 2011, SRK was contracted to prepare a mineral resource statement with additional core boreholes completed on the project between December 2010 and February 2011. This mineral resource statement represented the sixth resource evaluation prepared for the Rainy River Project.

Three (3) new significant discoveries were made in 2011. The first was a deep higher-grade gold mineralized ‘shoot’ with a significant silver component, known as the 17 East Extension and represents a potential underground component of the 17 East Zone.

In late 2011, a new high-grade silver zone was discovered in the footwall of the ODM. This zone consists of disseminated to stringer galena mineralization and visible silver. The zone does not host any significant gold. See Figure 9-1.

The third discovery in 2011 was a high-grade nickel, copper, PGE discovery, located approximately 1.2 km south of the ODM. This represents the first new magmatic sulphide discovery since the 34 Zone was discovered in 1994.

 

 

9-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 9-1: Section Showing the Footwall Silver Zone below the Previous PEA Starter Pit

(December 23, 2011) (from Rainy River

In February 2012, SRK prepared and revised a mineral resource statement with an additional 388 core boreholes (188,588 m) considering data up to January 9, 2012. This mineral resource statement represents the seventh resource evaluation prepared for the Rainy River Project.

In August 2012, exploration drilling discovered a significant new gold and silver zone approximately 1 kilometre east of the proposed open pit boundary of the Rainy River Project. See Figure 9-2. Borehole NR121258 intersected 2.2 gpt gold and 38.5 gpt silver over 18.5 metres, including 6.0 gpt gold and 83.9 gpt silver over 3.0 metres at a vertical depth of 210 metres. This new zone, termed the Intrepid Zone, clearly demonstrates the potential for new discoveries along strike of known mineralization.

 

 

9-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

In October 2012, SRK prepared and revised a mineral resource statement with an additional 237 holes (95,760 m) considering data up to July 2012, and excluding the Intrepid discovery. This mineral resource statement represented the eighth resource evaluation prepared for the Rainy River Project.

 

LOGO

Figure 9-2: Section through the Intrepid Zone

The Intrepid Zone was covered by a mobile metal ion (MMI) soil survey and identified anomalous gold over a prominent magnetic low trend similar to the magnetic trend that hosts the majority of the Rainy River Project deposits. The new zone contains disseminated and fracture-related mineralization, including 2 – 3 percent pyrite and variable amounts of sphalerite, galena, and chalcopyrite. Both electrum and visible gold have also been identified in core. Up to August 16th, 2013, a total of 230 boreholes (79.575 m) have now penetrated the Intrepid Zone over 410 metres strike length, and have traced the mineralization down dip for 550 metres.

 

 

9-4


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Wide zones of near-surface gold mineralization continue to contribute to mineralization that has the potential to be exploitable via open pit mining, complemented by higher grade intersections that have the potential to be extracted by underground mining early in the mine life. Diamond drilling in the third and fourth quarters of 2013 has shifted away from resource drilling to test regional targets, infrastructure condemnation and, potential fold repetitions of the Intrepid Zone horizon elsewhere on the Rainy River Project property. The alteration envelope associated with the Intrepid Zone mineralization has been traced by widely spaced boreholes (400 metres) along strike on an interpreted fold limb.

Exploration drilling undertaken in 2013 after the drilling data cut-off of August 16th, 2013 includes 27 diamond drill holes for a total of 7,960.5 metres. As mentioned above, the majority of this drilling was conducted outside the main mineralized zones. None of the logging or analytical results from this drilling post the data cut-off date indicate any material changes to the results or conclusions contained in this report.

Additional exploration work post August 16th, 2013 includes a program of 2,085 MMI soil samples in five (5) discrete grids was undertaken in the second half of 2013 to detect geochemical anomalies through the overburden cover to assist in identifying Intrepid-like zones along these structural trends.

Further, a re-logging program was undertaken to update and re-interpret lithological units within the main ODM zone of the Rainy River Property with an ultimate goal of producing a set of improved, geologically consistent sections and plans for this zone. This in turn will help drive future drill planning and ultimately improve confidence in future resource definition. Phase 1 of the ODM re-logging Program was completed in November 2013 and a total of 56,000 m of core was re-logged. As of year-end 2013, sectional and level plan interpretation had begun and was progressing on schedule.

To date, the Rainy River Project hosts several significant gold mineralized zones stretching over a 3.5 km strike length comprising (from west to east): Western Area, Beaver Pond, ODM, 17, 17 East, 17 East Extension, 280 Zone and the recently discovered Intrepid Zone. The HS, New and 433 Zones are located north of the ODM, while the CAP Zone is to the south.

 

 

9-5


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The exploration activities undertaken by Rainy River between 2005 and 2013 are summarized in Table 9-1

Table 9-1: Summary of Exploration Work by Rainy River on the

Rainy River Project between 2005 and 2013

 

Activity

  

Date

  

Performed by

2005

     
Re-Log 13 Diamond Drill Holes    Feb 2005    L.D. Ayres
Summary of Structural Observations    Feb 2005    G. Zhang
Re-Log 8 Nuinsco Diamond Drill Holes    April 2005    L.D. Ayres
53 RC Holes - Phase 1 Drilling    April 2005    Overburden Drilling Management
Technical Report    April 2005    Clark Exploration Consulting
Re-Log 24 Nuinsco Diamond Drill Holes    June 2005    L.D. Ayres
31 RC Holes - Phase 2 Drilling    Aug 2005    Overburden Drilling Management
Petrography and Mineralogy    Aug 2005    R.P. Taylor
DD Drill 17 Holes (3,800 m) BP and W Zones    Sept-Dec 2005    C.J. Baker, N. Pettigrew
Structure and Geology of Caldera Model    Oct 2005    L.D. Ayres
Structure and Geology of Richardson Twp    Oct 2005    H. Paulsen
22 RC Holes - Phase 2 Drilling    Dec 2005    Overburden Drilling Management
2006      
Report of Re-Logging of Nuinsco DD Core    Jan 2006    L.D. Ayres
DD Drill 121 Holes (55,219 m)    Jan-Dec 2006    W. Rayner, B. Nelson, A. Tims
Vtem Airborne Geophys. Survey    March 2006    Geotech Limited
U-Pb Zircon Age Dating    June 2006    Geospec Consultants Limited
Petrographic and Mineralogical Report    June 2006    E. Schandl
Structure and Geology Review    July 2006    K. H. Paulsen
U-Pb Zircon Age Dating    Nov 2006    Geospec Consultants Limited
3D Borehole Pulse EM Survey    Nov-Dec 2006    Crone Geophysics and Exploration
2007      
DD 179 Holes in 17/ODM, 433 and BP Zones    Jan-Dec 2007    B. Nelson, A. Tims, R. Greenwood
Site Visit by Geologist    Jan 2007    Panterra Geoservices Inc., D. Rhys
IP Survey of 9 Holes, 3D Cond. Inv. Models    May 2007    JVX Limited
Line Cutting    Nov-Dec 2007    Archer Exploration Inc.
Ground Gravity and EM Survey    Dec 2007    Abitibi Geophysics

 

 

9-6


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Activity

  

Date

    

Performed by

2008

       
DD 102 Holes (53,733 m) 17/ODM and 433 Zone    Jan-Dec 2008      W. Rayner, B. Nelson, A. Tims, C. Hercun
Titan 24 Survey    Jan 2008      Quantec Geoscience
Airborne Magnetic Gradiometer Survey    Feb 2008      Fugro Airborne Surveys, Corp.
47 RC Holes - Phase 5 Drilling    Apr-Jun 2008      Overburden Drilling Management
Regional Geophysical Interpretation    May 2008      J. Siddorn - SRK
Socio-Economic Scoping Study Draft Report    Nov 2008      Klohn, Crippen and Berger Ltd.
Preliminary Pit Slope Design and Waste Management Assessment    Nov 2008      Klohn, Crippen and Berger Ltd.

2009

       
Preliminary Pit Slope Design and Waste Management Assessment    Nov 2008-Feb 2009      Klohn Crippen Berger Ltd.
Preliminary Pit Slope Stability Assessment    Nov 2008-March 2009      Klohn Crippen Berger Ltd.
DD 139 Holes (69,753 m) in 17/ODM, 433,    Jan-Dec 2009      W. Rayner, B. Nelson, A. Tims, C. Hercun,
CAP, South and BP Zones         A. Shute
Age Dating of Lithologies    Jan-Feb 2009      University of Toronto Geochronology Lab
Third Mineral Resource Statement    Apr 2009      SRK Consulting (Canada) Inc.
Surficial Drainage Project    Apr-Sept 2009      K. Smart Associates Limited
Socio-Environmental Baseline Assessment.    May-Oct 2009      Klohn Crippen Berger Ltd.
Phase 5, 28-Hole RC Program    Jun-Aug 2009      Overburden Drilling Management
Acid Leach Test    Jun-Aug 2009      Klohn Crippen Berger Ltd.
New Office Building    Jul-Oct 2009      W. Rayner, K. Schram, B. Burnell, R. Burnell
Lidar Survey    Sept 2009      Lidar Services International
Preliminary Metallurgical Testing    Sep-Nov 2010      SGS Canada Inc.

2010

       
DD 196 holes (88,61 m) in 17/ODM, 433,    Jan-Dec 2010      W. Rayner, B. Nelson, A. Tims, C. Hercun,
CAP, South and BP Zones         A. Shute, J. Pattison, H. Buck, K. Pedersen
Phase 6, 37-hole RC Program (1,066 m)    Jan-Feb 2010      Overburden Drilling Management
Metallurgical Testwork    Jan-Dec 2010      SGS Canada Inc.
Environmental Baseline Studies    Jan-Dec 2010      Klohn Crippen Berger
DD 4 Geotechnical Drill Holes (1,405 m)    Mar-May 2010      Klohn Crippen Berger Ltd.
Review of Pit Slope Design    Mar-May 2010      SRK Consulting (Canada) Inc.
Memorandum of Understanding with Fort Francis Chiefs Secretariat    May 2010      Rainy River Resources Ltd.
Structural Study    May-Sept 2010      SRK Consulting (Canada) Inc.

 

 

9-7


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Activity

  

Date

    

Performed by

Deepened 48 Holes (17,718 m) in the

17/ODM Zones

   May-Oct 2010      W. Rayner, B. Nelson, A. Tims, C. Hercun, A. Shute, J. Pattison, H. Buck, J. Wartman
M.Sc Thesis on Richardson Deposit    Jun-Sept 2010      J. Wartman - University of Minnesota
Pre-Feasibility Open Pit Slope Design    Jun-Dec 2010      Klohn Crippen Berger
Infill Sampling of Historical Drill Holes - 9504 Samples (13,660 m)    Jul-Aug 2010      A. Tims, C. Hercun, A. Shute, H. Buck, J. Pattison
New Core Logging Facility    Jul-Dec 2010      C. Hercun, True-line Construction
Phase 7, 34-Hole RC Program (762 m)    Sept-Nov 2010      Overburden Drilling Management
Line Cutting Geophysical Grid 33 km    Nov-Dec 2010      Archer Exploration Inc.
Titan Survey 33 km    Dec 2010      Quantec Geoscience
Application for Advanced Exploration Permit    Dec 2010      G. Macdonald, K. Stanfield
2011        
28 Overburden Holes (618 M) Over First 600 m of Proposed Ramp.    Jan-Feb 2011      A. Tims, C. Hercon, A. Shute,H. Buck, J. Pattison, K. Pederson, A. Philippe
88 km High-Sensitivity Potassium Magnetometer Ground Survey    Jan-Feb 2011      RDF Consulting
DD 157 holes (77,222 m) in 17/ODM, 17 East, 433, The Gap, South, Beaver Pond, District, Northern, and HS Zones    Jan-Jun 2011      A. Tims, C. Hercun, A. Shute, H. Buck, J. Pattison, K. Pedersen, A. Philippe, R. Montufar, M. Rousseau.
Fifth Mineral Resource Statement    April 2011      SRK Consulting (Canada) Inc.
Environmental Baseline Gap Analysis    Apr-May 2011      AMEC Earth and Environmental
First Quarter QA/QC Report    Apr-June 2011      Analytical Solutions Ltd.
Fugro AEM Survey    May 2011      Fugro Airborne Surveys Corp.
Sixth Mineral Resource Statement    June 2011      SRK Consulting (Canada) Inc.
Report on Ground Gravity Surveys    Sept-Oct 2011      Eastern Geophysics, Gerard Lambert
Report on Borehole Surveys    Sept-Oct 2011      Eastern Geophysics, Gerard Lambert
Preliminary Economic Assessment of the Rainy River Gold Property    December 2011      AMEC, BBA Inc., SRK Consulting, Golder Associates
2012        
2011 Rainy River Gold QC Report    Jan 2012      Analytical Solutions Ltd.
DD 237 Holes (95,760 m)    Jan-Jul 2012      Rainy River Resources Ltd.
DD 403 boreholes (141,987 m) in 17/ODM, 433, The Gap, South, Beaver Pond, District, Northern, and HS zones plus infrastructure condemnation drilling    Jan-Sept 2012      A. Tims, C. Hercun, A. Shute, H. Buck, J. Pattison, K. Pedersen, A. Philippe, R. Montufar, M. Rousseau, C.Shaw
Seventh Mineral Resource Statement    Feb 2012      SRK Consulting (Canada) Inc.
Mobile metal ion soil surveys - various    May-Oct 2012      Rainy River Resources Ltd.
Intrepid DD 102 boreholes (28,689 m)    May, July-Dec 2012      A. Tims, A. Shute, H. Buck, J. Pattison, M. Rousseau, C.Shaw, D.Hyde

 

 

9-8


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Activity

  

Date

    

Performed by

Report on 34 zone & Pinewood Ni, Cu & PGE mineralization    July 2012      Revelation Geoscience Ltd.
Eighth Mineral Resource Statement    Oct 2012      SRK Consulting (Canada) Inc.
Preliminary Economic Assessment Update of the Rainy River Gold Property    Oct 2012      AMEC, BBA Inc., SRK Consulting, Golder Associates
2013        
DDH gyro survey 53 boreholes    Jan-Feb 2013      Reflex Instrument North America
Intrepid specific gravity data    Jan-June 2013      ALS Chemex Laboratory
Intrepid DD 122 boreholes 2 geotechnical, 4 oriented core    Jan-June 2013      A. Tims, A. Shute, H. Buck, J. Pattison, M. Rousseau, C.Shaw, D.Hyde
Soil gas hydrocarbon orientation survey    April-May 2013      Rainy River Resources Ltd.
Feasibility study of the Rainy River Gold Project    May 2013      AMEC, BBA Inc., SRK Consulting, Golder Associates
MSc thesis - style, geometry, timing and structure    Jun-Sept 2013      M. Pelletier - Institut national de la recherche scientifique
Feasibility Study of the Rainy River Gold Project: Re-addressed to New Gold    July 2013      AMEC, BBA Inc., SRK Consulting, Golder Associates
2,085 MMI Sampling program across 5 grids    July-October 2013      Rainy River Geologists
56,000 m re-logging program within ODM    August-November 2013      Rainy River Geologists
Ninth Mineral Resource Statement - reported herein    November 2013      SRK Consulting (Canada) Inc.
Exploration drilling 27 boreholes, 7,960.5 m    August-December 2013      Rainy River Geologists

 

 

9-9


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

10. DRILLING

 

10.1 Drilling from 2004 to 2013

 

10.1.1 Introduction

Nuinsco and Rainy River Resources drilled a combined total of 1,435 core boreholes (662,849 m) on the main Rainy River deposit between 1994 and 2012 (refer to Table 10-1). Prior to 1999, Nuinsco also drilled several reverse circulation boreholes to sample basal till and bedrock for exploration targeting. Reverse circulation drilling data was not used for resource estimation. An additional 230 boreholes (79,575 metres) were drilled in the Intrepid Zone between 1996 and August 16, 2013. The majority of boreholes were drilled by Rainy River between August 2012 and June 2013 (225 boreholes: 77,969 metres). The mineral resources reported herein consider all drilling data available as of August 16, 2013.

The distribution of the core drilling in the area of the main Rainy River deposit is summarized in Table 10-1 illustrated in

Figure 10-1 and Figure 10-2. The Nuinsco data contributes about 7% of the total drilling information (measured by drill metres). Rainy River Resources drilling data represents 93% of the drilling data.

Table 10-1: Core Drilling Completed on the Rainy River Project (1994-2013)1

 

Company

   Period     Type      No. of
Holes
     Total Length
(m)
 

Nuinsco

     1994 - 2004        Core         199         49,351   

Rainy River Resources

     2005 - 2007        Core         218         119,729   
     2008        Core         100         53,123   
     2009        Core         128         72,164   
     2010        Core         165         84,134   
     2011 - 2012        Core         388         188,588   
     2012        Core         237         95,760   
     1996 - 2013 2      Core         230         79,575   
       

 

 

    

 

 

 

Total

     1994 - 2013 3      Core         1,665         742,424   
       

 

 

    

 

 

 

 

1. 

Table reflects all exploration drilling and will differ from the total meterage incorporated into resource calculations.

2. 

Drilling within the Intrepid Zone.

3. 

2013 represents the August 16th, 2013 drilling data cut-off date for the mineral resource calculation.

 

 

10-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 10-1: Core Drilling Data by Period (1994 to August 16th, 2013)

 

LOGO

Figure 10-2: Drill Collar Plan in Relation to Resource Domains within the Main Rainy River Area

and Showing Conceptual Pit Outline

 

 

10-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Exploration drilling undertaken in 2013, after the drilling data cut-off date (August 16th, 2013), includes 27 diamond drill holes for a total of 7,960.5 metres. The majority of this drilling was conducted outside the main mineralized zones. None of the logging or analytical results from this drilling post data cut-off indicates any material changes to the results or conclusions contained within this report.

 

10.1.2 Drilling Procedures

Rainy River drill programs are designed and conducted by an experienced exploration team under the supervision of a Project Manager and a Vice President, Exploration. The drill procedures used by Nuinsco are not well documented, therefore SRK cannot comment on the procedures used by Nuinsco.

Nuinsco drilling focused on the ODM/17 and 433 Zones, whereas Rainy River drilling focused on infill and step-out drilling in these two (2) zones and on the investigation of new zones (such as the CAP and HS Zones). The discussion below focuses on the drilling procedures adopted by Rainy River.

Most of the recent drilling on the main Rainy River deposit has been completed by Bradley Bros. Ltd, whereas drilling on the Intrepid Zone has been completed by Naicatchewenin Development Corporation (“NDC”) in partnership with C3 Drilling and Major Drilling Group International Inc. All drilling used NQ core tools from surface collars. Active drilling was taking place at the time of SRK’s site visits.

A hand-held GPS is used initially to locate and prepare drilling pads in the field. After each hole is complete, a Differential Global Positioning System (“DGPS”) is used to survey the casing with typical accuracy in the tens of centimetres range. The DGPS accuracy is validated using a known control station location.

The path of the core borehole is surveyed using a Reflex EZ-SHOT™ instrument, which is an electronic solid-state, single-shot drill hole survey tool, at downhole intervals of 50 m. Their path typically flattens up with depth and wanders off section on the deeper boreholes.

Borehole deviation is regarded as a critical issue, as the average borehole length is approximately 400 m. In late 2011, Rainy River started using Tech Directional Drilling to help steer the deeper holes for better control and targeting of the zones. This program was

 

 

10-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

successful and implemented for almost a year. At the Intrepid Zone, 60 out of the 230 boreholes have been resurveyed with a Reflex Gyro at 5-metre intervals. The initial orientation of the Gyro instrument was set using an azimuth pointing system (“APS”) at the collar location. In SRK’s opinion, the survey method used by Rainy River is appropriate.

Rainy River uses a well-designed procedure for logging the drill core and the subsequent integration of this information into the exploration database. Core logging is recorded directly onto laptop computers equipped with DHLogger logging software which ensures that all relevant information is consistently captured and transferred to the main database. Descriptive geological information is recorded with the appropriate validation procedures in place. After validation, logging information is transferred directly from the DHLogger database into Gemcom Project software for 3D visualization, interpretation and modeling.

Standardized logging procedures include the collection of lithological, structural, mineralization, and alteration features. Magnetic susceptibility readings are recorded every 3 metres. Core recovery is reported to be excellent, but was not measured until 2008 when procedures were upgraded to include core recovery and geotechnical parameters such as rock quality designation (“RQD”), joint/fracture analyses, material type, and rock strength. Structural and geotechnical logging is usually not based on orientated core. More recently, Rainy River submitted several samples per borehole for specific gravity analyses for both waste rock and mineralized zones.

Core was not routinely photographed, although significant intersections and features are photographically recorded. Diamond core is archived in secure, high quality storage facilities on the Rainy River Project site where it is under security watch 24 hours a day, seven days a week.

Following the drilling data cut-off date for the mineral resource calculation, minor changes to the drilling procedures were implemented to improve data confidence and usability. These include an increase in the sampling density for condemnation holes where these are being selectively sampled. The frequency of systematic insertion of certified reference standards and blanks into the sample batches to be shipped to the lab was increased slightly. The collection of routine geotechnical data such as RQD and the practice of core photography have been extended to all exploration drill holes.

 

 

10-4


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

10.2 Drilling Pattern and Density

Rainy River core boreholes are mostly angled boreholes drilled on northerly directed azimuths, predominantly at a dip angle of 50 to 55 degrees. The main zones of gold mineralization have been drilled on at least 60 m x 60 m centres (Figure 10-2). The ODM/17 Zone was investigated on a more detailed 30 m x 30 m grid pattern.

The Intrepid Zone boreholes were mostly drilled at a dip of 51 degrees and occasionally up to 61 degrees on north directed azimuths. The zone has been drilled on at least 25 x 25 metres centres; however, there can be significant deviation with depth. Before 2012, drilling was targeting geophysical conductors or was designed as stratigraphic fences. Early 2012 boreholes were spaced 200 metres apart to complete infrastructure condemnation. After the discovery at NR12-1258, the resource drilling began at 50-metre borehole spacing. By January 2013, the drilling pattern was reduced to 25 – 30 metres.

 

10.3 SRK Comments

SRK is of the opinion that the drilling procedures adopted by Rainy River are consistent with industry best practices and the resulting drilling pattern is sufficiently dense to interpret the geometry and boundaries of the gold mineralization with confidence.

 

 

10-5


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

11. SAMPLE PREPARATION, ANALYSES, AND SECURITY

 

11.1 Sampling Method and Approach

There are no records describing the sampling method and approach used by Nuinsco during their 1994 to 2004 drilling program. When SRK visited the Rainy River Project property on numerous occasions, and most recently from April 30 to May 2, 2013, drilling and sampling was active. The following information regarding Rainy River sampling procedures (2005 to 2013) is derived from direct observations, as well as from discussions with Rainy River personnel.

Standardized core sampling protocols are used by Rainy River. Initially, Rainy River selectively sampled each core borehole based on visible observation of mineralization and alteration. Core was marked for sampling at regular 1.5 m intervals and half core was cut and sampled. Since then, sampling is performed for the entire length of each hole. The maximum and most common sample interval is still 1.5 m. Shorter samples are collected to demarcate geological domains, however, a minimum sample interval of 1 m is maintained.

The sampling interval is the last item marked on the core and recorded in the log. A qualified geologist marks out sample intervals with a red grease pencil and places two (2) sample tags at the beginning of each sample interval. A third copy of the sample tag remains in the sample booklet, along with “from” and “to” information recorded by the geologist. These tags are kept in the main office and filed with each individual hole.

The core boxes with samples marked are then prepared for cutting. Once a sample is cut, one half of the core is rinsed and placed into a sample bag and the second half is returned to the core box. One of the sample tags is placed in the sample bag, while the other remains in the core box for reference. The sample bags are stapled closed by the core cutting technician and also individually marked with each sample number. Five (5) sample bags are normally placed into a labelled rice bag and stored in a secured area prior to dispatch to the assaying laboratory. Each hole is separated by placing the rice bags on separate wooden pallets, never combining holes on one pallet.

Sample shipments are typically coordinated two (2) days per week, to ensure the shipment is never left overnight or over weekends at the shipping yard. A photocopy of the sample submission form is placed inside the first rice bag of each hole. The rice bags are transported directly to Gardewine North Shipping, in Fort Frances. A typical dispatch contains approximately 400-600 samples. Rice bags requiring overnight storage are securely stored inside a designated building.

 

 

11-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Following completion of core cutting and sample packing, the core boxes containing the remaining half core are stored outdoors, on sheltered racks. Unsampled intervals in the Nuinsco boreholes were subsequently sampled by Rainy River and incorporated into the borehole database.

In the opinion of SRK, the sampling methodology and procedures used by Rainy River are appropriate. The core samples were collected by competent personnel using procedures meeting with the generally accepted industry best practices. SRK concludes that the samples are representative of the source materials and there is no evidence of bias.

 

11.2 Sample Preparation and Analyses

 

11.2.1 Nuinsco Samples

There are no records describing the sampling preparation, analyses and security approach adopted by Nuinsco in their 1994 to 2004 programs. It is not known if analytical quality control measures were implemented.

 

11.2.2 Rainy River Samples

Between 2005 and August 16th, 2013, Rainy River collected core samples from 1,236 core boreholes (613,498 m) from the main Rainy River deposit and from an additional 221 core boreholes (73,578 m) from the Intrepid Zone. The following sections describe the sample preparation, analyses and security during this period. Core samples were submitted to three (3) separate primary laboratories for preparation and assaying:

 

 

2005-2006 and since February 2011: ALS Minerals, North Vancouver, British Columbia;

 

 

2006-2011: Accurassay Laboratory, Thunder Bay, Ontario; and

 

 

2009: Activation Laboratories, Thunder Bay, Ontario.

From early 2005 to late 2006, Rainy River used the ALS Minerals Laboratories (“ALS”) in Thunder Bay, Ontario for sample preparation and ALS Minerals Laboratories (“ALS”) North Vancouver, British Columbia for analyses. The management system of the ALS Group Laboratories is accredited ISO 9001:2000 by QMI Management Systems Registration. The

 

 

11-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

North Vancouver Laboratory is accredited ISO/IEC 17025:2005 for certain testing procedures, including those used to assay samples submitted by Rainy River. ALS Laboratories also participated in international proficiency tests such as those managed by CANMET and Geostats Pty Ltd.

Between late 2006 and early 2011, Rainy River utilized, almost exclusively, the Accurassay Laboratory (“Accurassay”) facility in Thunder Bay as a primary laboratory. On February 27, 2002, the Standards Council of Canada accredited Accurassay Laboratories for certain testing procedures under ISO/IEC Guideline 17025. The scope of accreditation includes fire assay analyses with atomic absorption finish for gold, platinum and palladium, as well as aqua regia digestion with atomic absorption finish for copper, nickel and cobalt.

Rainy River used the ALS Minerals Laboratory in North Vancouver, British Columbia as an umpire laboratory to monitor the reliability of assaying results delivered by Accurassay during 2010.

In late 2009, Rainy River also used Activation Laboratories (“Actlabs”) in Thunder Bay, Ontario to accelerate the delivery of a small amount of sample batches prior to the resource estimate update of March 2010. Actlabs is also accredited ISO/IEC Guideline 17025:2005 by the Standards Council of Canada for certain testing procedures including gold and silver assaying using a fire assay procedure.

In February 2011, Rainy River reverted to ALS as the primary laboratory for the Project.

The general sample preparation and analyses procedures used by ALS during 2005 – 2006 are described in a previous Technical Report (CCIC, 2008). A description of the sample preparation and analyses procedures adopted by Accurassay (2006 – 2011) and ALS Minerals (2011 – 2013) is provided herein.

Accurassay Laboratory (2006 – 2011)

Sample Preparation

Samples are first entered into a local information management system (“LIMS”). The protocol for sample preparation at Accurassay involves drying, crushing, splitting, pulverizing and matting:

 

 

11-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

 

Drying: Prior to the preparation of drill core, the samples are placed in a drying oven, if necessary (approximately 50°C), until dry;

 

 

Crushing: The entire sample is crushed using a TM Engineering Rhino Jaw crusher to below 10 mesh;

 

 

Splitting: Approximately 500 g subsamples are split-off using a Jones Riffle Splitter;

 

 

Pulverizing: Samples are pulverized using a TM Engineering ring and puck pulverizer with 500 g bowls to 90% below 150 mesh (105 microns). The bowls are cleaned with silica sand between each sample; and

 

 

Matting: Pulverized samples are matted to ensure homogeneity.

The homogeneous sample is then sent to the fire assay laboratory or the wet chemistry laboratory, depending on the analysis required.

Precious Metal Analyses

Precious metal analyses (gold, platinum, palladium and/or rhodium) require that the sample is mixed with a lead-based flux and fused for one (1) hour and 15 minutes. Each sample has a silver solution added to it prior to fusion, which allows each sample to produce a precious metal bead after cupellation. The fusing process produces lead buttons that contain all of the precious metals from the sample as well as the silver that was added.

The button is then placed in a cupelling furnace where all of the lead is absorbed by the cupel and a silver bead, which contains any gold, platinum and palladium, is left in the cupel. The cupel is removed from the furnace and allowed to cool. Once the cupel has cooled sufficiently, the silver bead is placed in an appropriately labelled test tube and digested using aqua regia. The samples are bulked up with 1.0 mL of distilled de-ionized water and 1.0 mL of 1% digested lanthanum solution. The samples are allowed to cool and are mixed to ensure proper homogeneity of the solution.

Once the samples have settled, they are analyzed for gold, platinum and palladium using atomic absorption spectroscopy. The atomic absorption spectroscopy unit is calibrated for each element using the appropriate ISO 9002 certified standards in an air-acetylene flame. The results for the atomic absorption are checked by the technician and then forwarded to data entry by means of electronic transfer and a certificate is produced. The laboratory manager checks the data, validates the certificates and issues the results in the format requested by Rainy River.

 

 

11-4


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Base Metal Analyses

Base metal samples (copper, nickel, cobalt, lead, zinc, and silver) are weighed for a geochemical analysis and digested using aqua regia. The samples are bulked to a final volume and mixed. Once the samples have settled, they are analyzed for copper, nickel and cobalt using atomic absorption spectroscopy. The atomic absorption spectroscopy unit is calibrated for each element using the appropriate ISO 9002 certified standards in an air-acetylene flame. The results for the atomic absorption are checked by the technician and then forwarded to data entry by means of electronic transfer and a certificate is produced. The laboratory manager checks the data and validates the certificates and issues the results in the format requested by Rainy River.

Analytical Quality Control Measures

Accurassay employs an internal quality control system that tracks certified reference materials and in-house quality assurance standards. Accurassay uses a combination of reference materials, including reference materials purchased from CANMET, standards created in-house by Accurassay and tested by round robin with laboratories across Canada, and ISO certified calibration standards purchased from suppliers.

Should any of the standards fall outside the warning limits (± two (2) standard deviations); re-assays will be performed on 10% of the samples analyzed in the same batch and the re-assay values are compared with the original values. If the values from the re-assays match original assays, the data is certified, if they do not match, the entire batch is re-assayed. Should any of the standards fall outside the control limit (± three (3) standard deviations), all assay values are rejected and all of the samples in that batch will be re-assayed.

ALS Minerals (2011 – 2013)

ALS Minerals undertakes precious metal analyses by fire assay with an atomic absorption spectroscopy (“AAS”) finish.

Sample Preparation

The sample is logged in the tracking system, weighed, dried and finely crushed to better than 70% passing a 2 mm (Tyler 9 mesh, US Std. No.10) screen. A split of up to 250 g is taken and pulverized to better than 85% passing a 75 micron (Tyler 200 mesh, US Std. No. 200) screen. This method is appropriate for rock chip or drill samples. ALS sample preparation method codes applied are: LOG-22, DRY-21, CRU-31, SPL-21 and PUL-31.

 

 

11-5


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Precious Metal Analyses

Sample decomposition is by fire assay fusion (ALS method codes FA-FUSO1 and FA-FUSO2); whereas the analytical method is Atomic Absorption Spectroscopy (ALS method codes Au-AA23 and Au-AA24).

A prepared sample is fused with a mixture of lead oxide, sodium carbonate, borax, silica and other reagents, as required, inquarted with 6 mg of gold-free silver and then cupelled to yield a precious metal bead. The bead is digested in 0.5 mL dilute nitric acid in the microwave oven, 0.5 mL concentrated hydrochloric acid is then added and the bead is further digested in the microwave at a lower power setting. The digested solution is cooled, diluted to a total volume of 4 mL with demineralized water, and analyzed by atomic absorption spectroscopy against matrix-matched standards.

Samples grading over 10 g/t gold were analyzed by gravimetric methods (ALS method codes Au-GRA21 and Au-GRA22).

Analyses of Other Metals

ALS also undertakes multi-element analyses by inductively coupled plasma with atomic emission spectroscopy (ICP-AES).

Sample decomposition is by HF-HNO3-HClO4 acid digestion, HCl leach (ALS method code GEO 4A01), whereas the analytical method is ICP-AES or inductively coupled plasma – mass spectrometry (ICP-MS).

A prepared sample (0.25 g) is digested with perchloric, nitric, hydrofluoric and hydrochloric acids. The residue is topped up with dilute hydrochloric acid and analyzed by ICP-AES. Following this analysis, the results are reviewed for high concentrations of bismuth, mercury, molybdenum, silver and tungsten and diluted accordingly. Samples meeting this criterion are then analyzed by ICP-MS. Results are corrected for spectral inter-element interferences.

 

11.2.3 Metallurgical Testing

Rainy River used the SGS Canada Minerals Services Lakefield Laboratory in Lakefield, Ontario (Lakefield) for metallurgical testwork. The Lakefield Laboratory is accredited ISO/IEC 17025:2005 for certain testing procedures, including those used to test and assay samples submitted by Rainy River. The Lakefield Laboratory also participated in international proficiency tests such as those managed by CANMET and Geostats Pty Ltd. The metallurgical testwork completed by Lakefield is discussed in more detail in Section 13.

 

 

11-6


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

11.3 Specific Gravity Data

The specific gravity database for the main Rainy River deposit (excluding the Intrepid Zone) contains 11,827 measurements completed by Accurassay Laboratory, and more recently ALS, by pycnometry on pulverized split core samples selected as representative of each modelled geological domain. SRK has composited the specific gravity data to 1.5 m length intervals. Figure 11-1 shows boxplots of the specific gravity composites in each domain.

There are sufficient data to use interpolation, a specific gravity field in the block model for the ODM/17, 433, HS and CAP domains. For all other domains, SRK assigned an average specific gravity value, as indicated in Table 11-1.

 

 

11-7


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 11-1: Summary of Specific Gravity Composite Data. Top: All Resource Domains;

Middle: ODM/17 Zone Sub-Domains; and Bottom: Other Domains (600 Domains)

 

 

11-8


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 11-1: Specific Gravity Assigned to Gold Zones

 

Zone

   Domain Code    Specific Gravity

ODM/17

   100, 110-115, 120-123    Interpolated

Zone 433

   300, 310,3 20    Interpolated

Zone 34

   200    2.99

HS Zone

   400    Interpolated

CAP Zone

   500    Interpolated

Intermediate Zones (600 Series)

   601    2.77
   602    2.78
   603    2.77
   604    2.84
   605    2.87

Western Zone

   800    2.88

Silver Zone 1

   901    2.84

Silver Zone 2

   902    2.87

Silver Zone 3

   903    2.81

Silver Zone 4

   904    2.70

The specific gravity database for the Intrepid Zone includes 661 measurements completed by ALS by pycnometry on pulverized core samples selected as representative of each modelled geological domain (Table 11-2).

Table 11-2: Summary Statistics of Specific Gravity Data for the Intrepid Zone

 

Zone

   Minimum      Maximum      Mean      Standard
Deviation
     Sample
Variance
     Count  

Low grade

     2.63         3.17         2.84         0.08         0.01         72   

Medium grade

     2.62         2.95         2.82         0.07         0.01         85   

High grade

     2.64         3.03         2.82         0.09         0.01         94   

All ore

     2.62         3.17         2.83         0.08         0.01         251   

Waste

     2.55         4.48         2.82         0.12         0.01         410   

There are insufficient specific gravity data to model the spatial variance of specific gravity across the deposit area. Accordingly, SRK assigned an average specific gravity value of 2.82 to all resource domains to convert volumes into tonnages.

 

 

11-9


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

11.4 Quality Assurance and Quality Control Programs

Quality control measures are typically set in place to ensure the reliability and trustworthiness of exploration data. These measures include written field procedures and independent verifications of aspects such as drilling, surveying, sampling and assaying, data management and database integrity. Appropriate documentation of quality control measures and regular analysis of quality control data are important as a safeguard for project data and form the basis for the quality assurance program implemented during exploration.

Analytical control measures typically involve internal and external laboratory control measures implemented to monitor the precision and accuracy of the sampling, preparation and assaying. They are also important to prevent sample mix-up and to monitor the voluntary or inadvertent contamination of samples. Assaying protocols typically involve the use of quality control samples (blank, duplicate samples, certified reference material) to monitor the reliability of assaying results delivered by the Assay Laboratory. Check assaying is normally performed as an additional test of the reliability of assaying results. This typically involves re-assaying a set number of sample rejects and pulps at a secondary umpire laboratory.

The review of analytical quality control measures implemented prior to December 2011 is discussed in previous Rainy River technical reports. This Technical Report reviews the analytical quality control measures implemented by Rainy River between December 2011 and June 2012 on the main Rainy River deposit and between January 2012 and June 2013 on the Intrepid Zone.

Between December 2011 and June 2013, Rainy River relied partly on the internal analytical quality control measures implemented by ALS Minerals. In addition, Rainy River implemented external analytical quality control measures on all sampling consisting of using control samples (blanks, certified reference material and field duplicates) inserted in all sample batches submitted for assaying at a rate of one (1) control sample every 25 samples.

Field blanks consisted of crushed rock material sourced locally from the local Black Hawk Stock and homogenized pulp prepared by Accurassay Laboratories and a second field blank which consisted of a mixture of finely pulverized feldspars and basalt, sourced from Rocklabs Ltd. (Rocklabs), New Zealand, named AuBlank36A and certified as less than 0.002 ppm gold. In May 2011, the field blanks were changed to a medium-hardness coarse marble garden stone sourced from Quali-Grow Garden Products Inc., Canada.

 

 

11-10


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Eight (8) commercial certified reference material control samples were used during this period, sourced from CDN Resource Laboratories Ltd. (“CDN”), Canada.

 

11.5 SRK Comments

In the opinion of SRK, Rainy River personnel used care in the collection and management of field and assaying exploration data. The analysis of the analytical quality control data is presented in Chapter 12.

 

 

11-11


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

12. DATA VERIFICATION

 

12.1 Verification of Nuinsco Data

Considering the lack of documented exploration procedures adopted during the Nuinsco exploration program, CCIC (2008) recommended that Rainy River re-sample Nuinsco cores for verification of the assays. According to CCIC (2008), these re-sampled core assays compare well with original assay results reported by Nuinsco.

 

12.2 Verifications by Rainy River

As outlined in Chapter 11, Section 11.3, Rainy River relied partly on the internal analytical quality control measures implemented by the accredited ALS Mineral, Accurassay and Actlabs Laboratories but also implemented external analytical quality control measures consisting of inserting control samples into all sample batches submitted for assaying and requesting replicate pulp assays every 12th sample.

During drilling, experienced Rainy River geologists implement industry standard measures designed to ensure the reliability and trustworthiness of the exploration data. During 2011, Rainy River strengthened the quality control measures partly in response to the recommendations of SRK (2011a). These measures designed by Analytical Solutions include protocols for drill core sampling, sample dispatch, insertion of quality control materials, assessment of incoming data for quality control failures, actions required to remediate quality control failures, regular submission of sample pulps for check assays and collection of core and preparation duplicates. Analytical Solutions also reviewed quality control data up to December 2011 and recommended procedures for ongoing monitoring of analytical results as submitted by the primary laboratory, investigations of dubious results and preparation of regular quarterly quality control reports. SRK considers that the improved procedures adequately address the deficiencies noted previously (e.g., SRK, 2011a) and note that the enhanced procedures have positively impacted the SRK’s analyses of the analytical quality control data.

 

 

12-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

12.3 Verifications by SRK

 

12.3.1 Site Visit

In accordance with the National Instrument 43-101 Guidelines, Glen Cole, P.Geo, visited the Project site on numerous occasions since 2008, most recently from April 30 to May 2, 2013. He was accompanied by various Rainy River staff. At the time of the site visits, active drilling was taking place. The purpose of the site visits was to ascertain the geological setting of the Rainy River Project, witness the extent of exploration work carried out on the Project property, and assess logistical aspects and other constraints relating to conducting exploration work in this area.

All aspects that could materially impact the integrity of the resource estimate (such as core logging, sampling and database management) were reviewed with Rainy River staff. SRK was given full access to all relevant project data. SRK was also able to interview exploration staff to ascertain exploration procedures and protocols.

The location of several borehole collars in the ODM/17, 433, CAP and Intrepid Zones were verified in the field by SRK. The collars are clearly marked by casings with caps inscribed with the borehole number. No discrepancies were found between the location, numbering or orientation of the holes verified in the field and on plans and the database examined by SRK.

Blair Hrabi, P.Geo, Dr. Ivo Vos, P.Geo, and Simon Craggs from SRK, examined cores from numerous boreholes during various site visits (drilled by Nuinsco and Rainy River) and found the logging information to accurately reflect core intervals. The lithology and gold mineralization contacts checked by SRK match the information reported in the drill logs. Generally, the boundaries of the auriferous zones examined in cores match the boundaries determined from assay results.

 

12.3.2 Verifications of Analytical Quality Control Data

The analysis of analytical quality control data produced by Rainy River prior to March 2011 was discussed in previous technical reports and is not reproduced here. Rainy River provided SRK with external analytical control data in the form of Microsoft Excel spreadsheets containing the assay results for the quality control samples for the period of December 2011 to July 2012 relating to the main Rainy deposit, as well as quality control samples for the period of January 2012 to June 2013 relating to the Intrepid Zone.

 

 

12-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

SRK aggregated the assay results of the external analytical control samples for further analysis. Control samples (field blanks and certified standards) were summarized on time series plots to highlight the performance of the control samples. Paired data (field duplicates and check assays) were analyzed using bias charts, quantile-quantile, and relative precision plots. These plots and charts are presented in Appendix D.

The external analytical quality control data produced by Rainy River from December 2011 to July 2012 for the main Rainy River deposit are summarized in Table 12-1. The external quality control data produced during 2011 and 2012 represents 7% of the total number of samples assayed for gold and 1% of the total number of samples assayed for silver.

Table 12-1: Summary of Analytical Quality Control Data Produced

between December 2011 and July 2012 for the Main Rainy River Deposit

 

      Au      Ag      Total      Au (%)     

Comment

Sample Count

           54,515         

Field Blanks

     640            640         1.2       Coarse marble

Certified Standards

     2,648            2,648         4.9      

P3B

     449            449          CDN (0.409 ± 0.042 g/t Au)

P4A

     241            241          CDN (0.438 ± 0.032 g/t Au)

IJ

     435            435          CDN (0.946 ± 0.102 g/t Au)

IH

     279            279          CDN (0.972 ± 0.108 g/t Au)

1P5D

     472            472          CDN (1.47 ± 0.15 g/t Au)

1P5E

     144            144          CDN (1.52 ± 0.11 g/t Au)

5G

     55         19         74          CDN (4.77 ± 0.40 g/t Au, 101.8 ± 72.5 g/t Ag)

5J

     573         475         1,048          CDN (4.96 ± 0.42 g/t Au, 7.0 ± 4.8 g/t Ag)

Field Duplicates

     524            524         1.0      

Pulp Duplicates

     —           —           —           —        

Total QC Samples

     3,812            3,812         7.0      

Check Assays

     —           —           —           —        

At ALS Chemex

     352            352         

The performance of the control samples is acceptable. For field blanks, assuming a threshold limit of five (5) times the detection limit, only one (1) sample performed above this threshold. The field blank chart does not show any evidence of sample contamination. For certified standards, the majority of samples performed as expected within two (2) standard deviations for both gold and silver. The certified standard charts do not show any evidence of analytical bias.

 

 

12-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Paired data for field duplicates show that gold grades can be reasonably reproduced by ALS Minerals. Rank half absolute difference (“HARD”) plots suggest that 62.8% of samples have HARD below 10%. This is consistent with results expected from gold mineralization from this deposit style. Quantile-quantile and mean-to-half relative deviation plots show no apparent bias between original and duplicate samples.

Paired data for check assays show that original gold assays produced by ALS Minerals can be reasonably reproduced by Actlabs. HARD plots suggest 77.3% of samples have HARD below 10%. Quantile-quantile and mean-to-half relative deviation plots show no apparent bias between original and check samples.

The external analytical quality control data produced by Rainy River for the Intrepid Zone are summarized in Table 12-2 and presented in graphical format in Appendix D. The external quality control data produced on this project represents approximately 4 percent of the total number of samples.

Table 12-2: Summary of Analytical Quality Control Data Produced

between January 2012 to June 2013 for the Intrepid Zone

 

     Total      (%)    

Comment

Sample count

     41,020        

Field blanks

     235         0.57   Coarse marble

Certified standards

     1,162         2.83  

26

     44         CDN (0.372 ± 0.048 gpt gold)

P3B

     248         CDN (0.409 ± 0.042 gpt gold)

P4A

     3         CDN (0.438 ± 0.032 gpt gold)

IJ

     203         CDN (0.946 ± 0.102 gpt gold)

IH

     4         CDN (0.972 ± 0.108 gpt gold)

1L

     48         CDN (1.16 ± 0.10 gpt gold)

1P5K

     11         CDN (1.44 ± 0.13 gpt gold)

1P5D

     4         CDN (1.47 ± 0.15 gpt gold)

1P5E

     281         CDN (1.52 ± 0.11 gpt gold)

5H

     51         CDN (3.88 ± 0.28 gpt gold, 50.4 ± 2.7 gpt silver)

5G

     2         CDN (4.77 ± 0.40 gpt gold, 101.8 ± 72.5 gpt silver)

5J

     263         CDN (4.96 ± 0.42 gpt gold, 7.0 ± 4.8 gpt silver)

Field duplicates

     224         0.55  

Total QC samples

     1,621         3.95  

Check assays

       

ALS Minerals vs. Actlabs

     317         0.77  

 

 

12-4


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

In the opinion of SRK, the results of the analytical quality control data produced from December 2011 to June 2013 are sufficiently reliable to support resource estimation.

 

12.3.3 Verification of Electronic Data

Rainy River made a Gemcom database available to SRK containing all electronic data accumulated on the Rainy River Project. SRK conducted a series of routine verifications to ensure the reliability of the electronic data provided by Rainy River. SRK validated all tables using Gemcom validation tools that check for gaps, overlaps and out of sequence intervals.

The Gemcom collar, survey, lithology and assay tables did not contain obvious errors. On completion of the validation procedures, SRK concludes that the digital database for the Rainy River Project is reliable for resource estimation.

 

 

12-5


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

13. MINERAL PROCESSING AND METALLURGICAL TESTING

 

13.1 Historical Metallurgy

Initial metallurgical testwork was carried out at SGS in Lakefield, Ontario from 2008 to 2011 and was the basis for the PEA Update Technical Report published in October 2012.

 

13.1.1 Sample Selection

The metallurgical samples for this testwork were selected to give an accurate representation of the different mineralization zones based on information available at the time.

A master composite sample was created by combining individual samples from each zone in the proportion indicated in Table 13-1.

Table 13-1: Master Composite Proportions

 

Zone Composite

   Zone Composite
Proportions
    Total
Proportion
 

CAP

     2.0     20.0

Z-433

     12.0  

HS

     1.0  

NZ

     5.0  

ODM-1

     35.1     80.0

ODM-2

     3.5  

ODM-3

     31.4  

ODM-4

     9.9  

Master

       100.0

 

13.1.2 Historical Testwork

The testwork included mineralogy, comminution, gravity separation, flotation, flotation concentrate leaching and whole rock leaching. The results from the testwork indicated that the material was moderately hard. Overall gold recovery for the flotation concentrate leach circuit was estimated at 88.5% with the flotation feed ground to a P80 of 150 µm and the flotation concentrate re-ground to a P80 of 15 µm. Recovery for the whole rock leach circuit was estimated at 91.0% when ground to a P80 of 60 µm. No optimization of the grind size was performed at the time.

 

 

13-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The flotation concentrate leach option was selected mainly due to the separation of the sulphides into a low mass stream that could be deposited separately from the flotation tailings that would be low in sulphide content and cyanide free. While this flowsheet was selected for the December 2011 PEA, there was no significant economic or environmental benefit to either option that justified a final flowsheet selection. For this reason, additional testwork was performed in 2012 to give the analysis more precision and allow for a more conclusive flowsheet selection.

 

13.2 Composite and Sample Selection

The results presented in Sections 13.2 to 13.14 were used as the basis for the Feasibility Update Study. The testwork was completed from October 2011 until November 2012 on the main pit and from November 2012 to November 2013 on the Intrepid Zone. The objective of the Intrepid Zone testwork program was to confirm that this material could be treated using the proposed flowsheet for the main pit and would not have a significant impact on the design of the plant when blended at low tonnages.

Composite Selection Three (3) composites were used for determining the flowsheet and the parameters for the variability testwork:

 

 

ODM Master;

 

 

Initial Pit;

 

 

Remaining-Life-of-Mine (“RLOM”).

The ODM master composite was developed as the ODM Zone is the most significant portion of the deposit and Initial Pit. The initial pit composites and RLOM composites were selected to develop a better understanding of the metallurgical responses for the early years of mining compared to the later years.

The tonnages by zone that were used to develop the composites are presented in Table 13-2. The values shown are those used for metallurgical testing and were determined in March 2012.

 

 

13-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 13-2: Weight Percentages by Zone for Initial Pit, RLOM Composites and Overall Pit

 

Zone

   Initial Pit
(%)
     RLOM
(%)
     Overall
Pit (%)
 

ODM

     86.4         60.4         68.0   

Z-433

     4.3         13.8         11.0   

HS

     0.4         5.5         4.0   

NZ

     4.4         5.2         5.0   

CAP

     4.6         15.1         12.0   

A master composite for the Intrepid Zone was also generated using the variability samples.

 

13.2.1 Variability Sample Selection

In order to provide a high level of confidence, 162 comminution and 208 leaching samples were selected for variability testwork for the main pit and another 30 comminution and leaching samples were selected for the Intrepid Zone. All samples selected for the comminution and leaching variability testwork were selected using a geometallurgical approach to provide good definition of the deposit.

The sample locations in the main pit are presented in Figure 13-1 and Figure 13-2.

 

LOGO

Figure 13-1: Sample Locations for Comminution Variability Testwork

 

 

13-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 13-2: Sample Locations for Metallurgical Variability Testwork

The sample selection provides a good representation of the entire proposed pit.

It should be noted that a number of samples are located outside of the proposed pit outline. This is due to the change in size of the engineered pit from the December 2011 PEA to the August 2012 updated PEA. The pit was reduced in size, however, the testwork campaign had already commenced at this stage. This is illustrated by a pit cross section shown in Figure 13-3, where the August 2012 pit outline is in purple and the December 2011 pit is in grey.

 

LOGO

Figure 13-3: Sample Locations for Comminution (Left) and Leaching (Right)

Variability Testwork (Cross-Section View, Looking West)

 

 

13-4


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

13.2.2 Sample Characterization

A large number of samples from each of the zones were selected and assayed for the variability testwork campaign, as described in Section 13.2.1. Three (3) master composites were also assayed: Initial Pit, Remaining Life of Mine and Intrepid Zone master composites.

The head grades and major impurities for the variability samples and Master Composite are presented in Table 13-3.

 

 

13-5


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

Table 13-3: Testwork Sample Head Grades

 

Sample

   # of
Samples
-
  

Au
(Screen Met.)

g/t

  

Ag

(Direct)

g/t

   Cu
%
   S
%
   Zn
%
  

Fe

%

Variability Samples1

                    

ODM

   117    1.04 +/- 1.59    4.04 +/- 4.18    0.010 +/- 0.012    2.07 +/- 0.88    0.13 +/- 0.15    2.74 +/- 0.87

Z433

   27    1.12 +/- 1.21    2.03 +/- 1.25    0.041 +/- 0.036    2.22 +/- 1.70    0.06 +/- 0.09    4.20 +/- 1.82

HS

   13    0.51 +/- 0.32    1.00 +/- 0.71    0.015 +/- 0.008    2.15 +/- 0.94    0.06 +/- 0.03    3.23 +/- 0.63

NZ

   22    0.79 +/- 0.84    1.99 +/- 0.92    0.019 +/- 0.020    2.25 +/- 0.90    0.07 +/- 0.11    3.54 +/- 0.79

CAP

   33    0.72 +/- 0.82    3.65 +/- 0.71    0.017 +/- 0.015    3.70 +/- 1.97    0.07 +/- 0.08    9.39 +/- 3.44

Intrepid Zone

   30    1.64 +/- 1.79    14.9 +/- 17.4    0.009 +/- 0.009    2.27 +/- 0.42    0.11 +/- 0.16    2.37 +/- 0.40

Master Composites

                    

Initial Pit

   —      0.90    2.57    0.016    2.05    0.15    3.13

Remaining Life of Mine

   —      0.71    2.86    0.010    2.54    0.07    4.05

Intrepid Zone Master

   —      1.45    13.8    0.009    2.19    0.10    2.34

 

1. 

Numbers shown are averages +/- one standard deviation (s).

 

 

13-6


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The samples from the CAP Zone have significantly higher levels of sulphur than any of the other zones. The iron levels in the CAP Zone are also considerably higher than any other zone. The Intrepid Zone has much higher silver levels than the other zones; however the copper, sulphur, zinc and iron levels seem to correspond well to the samples from the main pit (excluding the CAP Zone samples).

It can be also seen that the Master Composite for the Intrepid Zone corresponds well in terms of the elemental averages of the variability samples, and Initial Pit and Remaining Life of Mine composites correspond well to the averages of the zones of the main pit.

 

13.3 Mineralogy

Gold deportment studies have been performed on samples from each zone during the 2011 and 2012 testwork campaigns, including: five ODM, two 433, one CAP, one HS and one NZ sample:

 

 

The samples were composed mainly of non-opaque minerals, with minor amounts of pyrite present (ranging from 2.5% in one (1) of the 433 Composites to 9.5% in the CAP composite).

 

   

Gold associated with pyrite can be recovered and concentrated using froth flotation;

 

   

Gold encapsulated in pyrite is difficult to recover via cyanidation without a fine or ultra-fine grind;

 

   

Gold associated with the non-opaque minerals will be not be recovered by flotation but can be recovered by leaching of flotation tailings or by whole rock leach if the particle is not locked.

 

 

The gold occurs mainly as native gold, electrum and kustelite. Small amounts of Petzite (Ag3AuTe2) were also noted;

 

 

The gold occurs as liberated, attached and locked particles in most of the samples at a grind size of 150 µm except for the CAP sample;

 

   

Liberated and attached gold can be readily extracted with whole rock leaching at the grind size of 150 µm;

 

   

Locked gold will require finer grinding to be recovered by cyanide leaching. Locked gold represented the majority of the gold, indicating that these composites would require grinding finer than 150 µm prior to whole rock cyanidation to achieve a good gold recovery;

 

 

13-7


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

   

The CAP composite had gold occurring as locked inclusions in pyrite and non-opaque minerals only. This is an indication that the gold in the CAP composite will be difficult to recover by either flotation (due to gold being locked with non-opaque minerals) or whole rock leach (due to gold being locked in pyrite).

 

 

The gold grain size was relatively fine in all samples, with coarse gold (>100 µm) noted only in two (2) of the composites (HS and one of the Z-433 samples).

 

   

Overall, the two (2) Z-433 composites had the coarsest gold particles;

 

   

All other samples had fine gold grains, which the majority of the gold distribution falling into the <10 µm category;

 

   

The liberated gold tended to have the coarsest grain size whereas the locked gold tended to be the finest.

 

 

Trace amounts of pyrrhotite were noted in approximately half of the samples.

 

   

Pyrrhotite can have a negative impact on gold dissolution and can increase cyanide consumption.

 

13.4 Flowsheet Selection Testwork

Subsequent testwork was carried out from fall 2011 to spring 2012 to provide a better definition to the flowsheets and allow for a final flowsheet selection.

Two (2) flowsheet options were investigated:

 

 

Flotation Concentrate Leach: This flowsheet includes rougher and cleaner flotation in which the sulphides are separated from gangue. The flotation concentrate is reground and the gold and silver are then recovered from the flotation concentrate using conventional cyanide leaching and carbon-in-pulp (“CIP”);

 

 

Gravity Tailings Leach: This flowsheet is a whole rock cyanide leach process followed by CIP.

Testwork was performed to give a better definition of both flowsheets. Once testwork was completed, a techno-economic study was performed to determine which process had the best economic return. All testwork was performed on an ODM master composite. This composite was selected since the ODM represents the largest portion of the deposit and Initial Pit.

 

 

13-8


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

A gravity circuit is included in the grinding circuit for both flowsheets. The gravity circuit was included based on the moderately high gravity recoveries noted during historical testwork. Testwork for the gravity circuit for the flowsheet selection were 10 kg tests performed on the sample prior to flotation or leaching testwork. These tests were performed using a Knelson concentrator and the concentrate was upgraded with a Mozley separator. The results from the gravity separation testwork are presented along with the flotation and leach results.

 

13.4.1 Flotation Option

Flotation

The use of a flotation circuit prior to leaching was investigated. In this processing option, gravity gold is recovered in a gravity separation stage and the gravity tailings are subjected to froth flotation. The concentrate from the flotation circuit is reground and then leached while the tailings are discarded. The rougher flotation results are presented in Table 13-4.

Table 13-4: Rougher Flotation Results

 

                        Assays      % Distribution  
     Combined                                Au      Ag         

Test No.

   Products
K80, µm
    

Product

   Mass
%
     Au
(g/t)
     Ag
(g/t)
     S=
(%)
     Flot
(unit)
     Grav+
Flot
     Flot
(unit)
     Grav+
Flot
     S=  

1

      Ro Conc 1-5      14.6         4.33         18.3         12.9         91.9         94.3         77.6         78.7         97.4   
     163       Rougher Tail      85.4         0.07         0.9         0.06         8.1         5.7         22.4         21.3         2.6   
      Head (calc)      100.0         0.69         3.4         1.94         100.0         100.0         100.0         100.0         100.0   

2

      Ro Conc 1-5      14.6         4.03         19.5         13.0         92.0         94.3         78.7         79.7         97.8   
     101       Rougher Tail      85.4         0.06         0.9         <0.05         8.0         5.7         21.3         20.3         2.2   
      Head (calc)      100.0         0.64         3.6         1.94         100.0         100.0         100.0         100.0         100.0   

3

      Ro Conc 1-5      20.6         2.70         13.7         9.3         90.9         93.6         78.1         79.1         97.2   
     79       Rougher Tail      79.4         0.07         1.0         0.07         9.1         6.4         21.9         20.9         2.8   
      Head (calc)      100.0         0.61         3.6         1.98         100.0         100.0         100.0         100.0         100.0   

4

      Ro Conc 1-5      19.6         3.38         14.6         10.2         92.7         94.8         79.9         80.8         98.0   
     76       Rougher Tail      80.4         0.07         0.9         <0.05         7.3         5.2         20.1         19.2         2.0   
      Head (calc)      100.0         0.71         3.6         2.04         100.0         100.0         100.0         100.0         100.0   

The rougher flotation results yielded gold recoveries from the gravity tailings ranging from 90.9 to 92.7% with mass pulls ranging from 14-20%. The sulphide recoveries were high, ranging between 97-98%. The high sulphide recovery is an indication that the gold flotation recovery likely cannot be improved significantly from these results since the gold is recovered with the sulphides. The silver recoveries in flotation ranged from 78.7 to 80.8%.

 

 

13-9


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The use of a cleaner stage (to process the rougher concentrate) was investigated to reduce mass pull and increase gold grade in the feed to the cyanide leaching circuit. The results for the rougher and cleaner stages are presented in Table 13-5.

For the first test the concentrate was reground. In the second test, the concentrate was floated without regrinding.

Table 13-5: Cleaner Flotation Results

 

                 Assays      % Distribution  
    

Product

   Mass
%
     Au
(g/t)
     Ag
(g/t)
     S=
(%)
     Au      Ag         
                       

Feed Size P80, µm

                  Flot      Grav+
Flot
     Flot      Grav+
Flot
     S=  
                             

30

   1st Cleaner Conc      6.2         11.1         36.8         27.9         88.2         91.7         69.1         70.5         93.4   
   1st Cleaner Conc + Scav      7.1         9.88         33.3         25.1         88.9         92.2         70.8         72.1         95.2   
   Rougher Conc      17.2         4.15         15.0         10.4         91.0         93.6         77.5         78.6         96.4   
   Rougher Tail      82.8         0.09         0.9         0.08         9.0         6.4         22.5         21.4         3.6   
   Head (calc)      100         0.78         3.3         1.86         100         100         100         100         100   

59

   1st Cleaner Conc      6.7         8.91         36.3         0.8         81.7         87.1         66.7         68.2         2.1   
   1st Cleaner Conc + Scav      7.4         8.58         34.5         1.2         86.7         90.6         69.9         71.2         3.4   
   Rougher Conc      17.1         3.92         16.9         15.0         92.0         94.3         79.5         80.4         96.9   
   Rougher Tail      82.9         0.07         0.9         0.10         8.0         5.7         20.5         19.6         3.1   
   Head (calc)      100         0.73         3.6         2.65         100         100         100         100         100   

The results indicated that the mass pull could be decreased to below 10% with a drop in gold recovery between 2% and 10%. Also, regrinding appeared to improve the recovery with a slightly lower mass pull. Losses in the silver recoveries were slightly more pronounced, ranging from 8 to 10%.

Flotation Concentrate Leach Tests

Cyanide leaching was performed on the flotation concentrate to estimate the recovery of the entire circuit. The product from the flotation tests was reground to two (2) particle sizes (approximately 50 and 15 µm) to investigate the effect of grind size on the cyanidation recovery. Bulk gravity and flotation separations were performed to generate the flotation concentrate for these tests.

The flotation concentrate leach results are presented in Table 13-6 and Table 13-7.

 

 

13-10


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 13-6: Flotation Concentrate Leaching Results (Gold Assays)

 

     Test Parameters    Reagent
Consumptions
(kg/t)
     Au Recovery (%)      Au Assays  

Number

of tests

   P80
(µm)
     Pb(NO3)2
Addition
(g/t)
     O2 or
Air
   NaCN      CaO      24 h      36 h      48 h      Grav      Float      Grav +
Float +
Leach
     Residue
(g/t)
     Float
Head
Grade
(g/t)
     Calc.
Head
Grade
(g/t)
 
3      45         0       Air      2.8         1.2         87.4         86.0         87.7         36.6         54.7         84.6         0.51         4.2         1.12   
3      42         0       O2      0.6         1.6         88.5         87.7         88.8         36.6         54.7         85.2         0.50         4.3         1.14   
3      45         500       Air      2.7         1.3         88.1         89.0         86.7         36.6         54.7         84.0         0.55         4.2         1.12   
3      46         500       O2      0.6         1.4         87.7         86.9         87.5         36.6         54.7         84.5         0.51         4.1         1.10   
3      14         0       Air      3.8         3.9         96.2         95.1         94.9         36.6         54.7         88.5         0.21         4.1         1.11   
3      15         0       O2      1.8         1.6         94.9         94.8         93.1         36.6         54.7         87.5         0.30         4.1         1.11   
3      13         500       Air      4.4         3.5         95.8         94.8         94.1         36.6         54.7         88.1         0.21         3.9         1.06   
3      14         500       O2      2.3         1.9         95.9         94.9         94.4         36.6         54.7         88.3         0.21         4.1         1.11   

Table 13-7: Flotation Concentrate Leaching Results (Silver Assays)

 

     Test Parameters    Reagent
Consumptions
(kg/t)
     Ag Recovery (%)      Ag Assays  

Number

of tests

   P80
(µm)
     Pb(NO32
Addition
(g/t)
     O2 or
Air
   NaCN      CaO      24 h      36 h      48 h      Grav      Float      Grav +
Float +
Leach
     Residue
(g/t)
     Head
Grade
(g/t)
     Calc.
Head
Grade
(g/t)
 
3      45         0       Air      2.8         1.2         67.4         68.0         69.5         1.6         74.6         53.4         5.90         16.9         3.65   
3      42         0       O2      0.6         1.6         71.0         72.2         75.5         1.6         74.6         57.9         5.05         18.8         3.61   
3      45         500       Air      2.7         1.3         67.2         70.1         68.7         1.6         74.6         52.8         6.10         19.1         3.65   
3      46         500       O2      0.6         1.4         71.1         69.8         70.7         1.6         74.6         54.3         5.40         18.0         3.67   
3      14         0       Air      3.8         3.9         82.4         83.9         89.3         1.6         74.6         68.2         1.95         18.5         3.56   
3      15         0       O2      1.8         1.6         86.5         90.4         89.1         1.6         74.6         68.1         2.10         18.7         3.59   
3      13         500       Air      4.4         3.5         83.4         88.5         89.8         1.6         74.6         68.6         2.00         18.8         3.60   
3      14         500       O2      2.3         1.9         89.7         90.5         94.0         1.6         74.6         71.7         1.20         19.0         3.64   

 

 

13-11


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The results indicated that gold recoveries of 94 to 96% in the leaching circuit could be achieved by grinding the material down to around 15 µm. This gave overall recoveries ranging from 87.5 to 89.2% for the entire circuit. Silver recoveries were also higher when ground to around 15 µm, with recoveries ranging from 89.1 to 94.0%, compared to 68.7 to 75.5% when ground to approximately 45 µm.

High cyanide (NaCN) and lime (CaO) consumptions were noted when the samples were ground to 15 µm or below, ranging from 4.0 to 5.0 kgNaCN/t and 2.0 to 6.0 kgCaO/t. The cyanide and lime consumptions were considerably lower when ground to 40-50 µm, ranging from 1.2 to 4.9 kgNaCN/t and 0.8 to 1.8 kgCaO/t. The use of oxygen instead of air decreased the consumption of cyanide and lime to around 1.3 to 2.5 kgNaCN/t and 1.3 to 2.0 kgCaO/t for the samples ground to 15 µm. The use of lead nitrate was also investigated but it did not have any noticeable effect.

Flotation Tailings Leaching

Additional testwork was performed in an attempt to improve the recovery of the circuit by leaching the flotation tailings.

The results from the flotation tailings leaching tests are presented in Table 13-8.

Table 13-8: Flotation Tailings Leaching Results

 

     Feed    Feed      Reag.                                                   
     (Tails    Size      Consumption      % Au Recovery                       
     from    P80,      kg/t of CN Feed      CN Leach Time (h)             Residue      Head Au  

CN Test No.

   Test)    µm      NaCN      CaO      6      24      36      48      Rec.1      Au (g/t)      (g/t)  

CN-8

   F-1      181         0.08         0.35         66.6         66.8         67.0         67.3         3.9         0.02         0.06   

CN-9

   F-2      101         0.06         0.33         66.5         66.7         66.9         67.3         3.8         <0.02         0.06   

CN-10

   F-3      81         0.08         0.33         66.4         66.7         67.0         67.3         4.3         0.02         0.06   

CN-11

   F-4      82         0.08         0.43         66.5         66.7         66.9         67.2         3.5         0.02         0.06   

 

1. 

Recovery values indicate additional overall recovery.

Based on the results, it can be seen that close to an additional 4% overall recovery could likely be achieved by leaching the flotation tailings. The recoveries presented in Table 13-8 are artificially high as they do not include the flotation concentrate leaching recoveries. Regardless, this option was rejected due to the high capital and operating costs associated with leaching of the flotation tailings.

 

 

13-12


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Ultrafine Grinding

Ultrafine grinding tests were performed to simulate both an IsaMill and a stirred media detritor (“SMD”). The IsaMill tests were performed in a single unit to grind a flotation concentrate sample (S.G. of 3.06 t/m3) from an F80 of 127 µm to a target P80 of 10 µm. This target was selected prior to the completion of the flotation concentrate leach tests presented previously in Section 13.4.1. The tests were performed in a single IsaMill M4 test unit using 3.5 mm media. The results from the testwork are presented in Table 13-9.

Table 13-9: IsaMill Testwork Results

 

Pass #

   Gross kW      Net kW      Q (m3/h)      % Solids      M
(t/h)
     E (kWh/t)      Cumul. E
(kWh/t)
     P98
(µm)
     P80
(µm)
 

Feed

     —           —           0.158         44.6         0.101         —           0         459.8         127.5   

1

     1.76         1.00         0.138         44.7         0.088         11.3         11.3         97.6         26.0   

2

     1.69         0.92         0.138         45.8         0.092         10.0         21.3         52.0         22.3   

3

     1.69         0.93         0.138         46.9         0.095         9.7         31.0         41.8         19.5   

4

     1.68         0.92         0.138         45.9         0.092         10.0         41.0         37.9         18.4   

5

     1.67         0.90         0.136         45.9         0.092         10.0         51.0         35.4         17.5   

6

     1.69         0.93         0.14         45.9         0.093         10.0         61.0         33.9         16.8   

7

     1.68         0.92         0.138         45.9         0.091         10.0         71.0         32.9         16.3   

8

     1.70         0.93         0.091         45.5         0.059         15.7         86.7         30.9         15.4   

9

     1.60         0.83         0.095         40.9         0.054         15.5         102.2         29.7         14.8   

10

     1.60         0.83         0.098         41.1         0.056         15.0         117.2         28.9         14.3   

Target Size (µm):

        10         Est. kWh/t to Target:         472.4         Media Consumption (g/kWh):         21.6   

The results from the IsaMill tests indicated that between 80-100 kWh/t would be required to grind to 15 µm and the target grind size of 10 µm could not be achieved using the 3.5 mm media. An extrapolation of the results indicated that 472.4 kWh/t would be required to grind to 10 µm. Media consumption was estimated to be 21.6 g/kWh or 10.2 kg per tonne of flotation concentrate. The results are indicative of a material that is difficult to grind to 15 µm or below. The results from the test are plotted in Figure 13-4.

 

 

13-13


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 13-4: Specific Energy vs. Particle Size for IsaMill Testing

Testing at Metso was also performed to estimate the energy requirement of an SMD unit. The SMD tests were performed in a single unit to grind a flotation concentrate sample from an F80 of 34 µm to a target P80 of 10 µm. The tests were performed in a steel jar rotating at 76% critical speed using 19 mm steel balls. The particle sizes of the feed and products were analyzed using a Malvern Mastersizer 2000.

The results are presented in Table 13-10.

 

 

13-14


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 13-10: Stirred Media Detritor Testwork Results

 

     Pass # (% Passing)  

Particle Size (µm)

   Feed      1      2      3      4  

589

     100         100         100         100         100   

417

     99.2         99.7         100         100         100   

295

     97.6         99.5         100         100         100   

208

     95.5         99.4         100         100         100   

147

     93.3         99.4         100         100         100   

104

     90.4         98.4         99.4         100         100   

74

     87.4         97.0         98.5         100         100   

53

     84.9         96.0         98.2         100         100   

44

     83.4         95.4         98.2         100         100   

37

     81.6         94.4         98.1         100         100   

25

     74.4         88.6         95.0         99.6         100   

18

     64.2         78.4         87.0         95.8         98.9   

12.5

     49.6         62.0         71.5         84.7         91.3   

8.8

     35.2         44.6         53.2         67.7         77.1   

6.3

     23.5         30.1         36.6         49.6         59.5   

4.4

     15.0         19.5         23.9         33.7         42.0   

3.1

     9.4         12.5         15.4         22.1         28.0   

P98 (um)

     325.5         95.4         36.6         22.1         17.3   

P80 (um)

     34.1         19         15.4         11.4         9.5   

Specific Energy (kWh/t)

     0         20         40         80         120   

It was estimated that approximately 45 kWh/t would be required to grind to 15 µm and 110 kWh/t to grind to 10 µm. The results confirmed that the flotation concentrate is difficult to grind to below 20 µm. A graphical representation of the energy requirement is presented in Figure 13-5.

 

 

13-15


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 13-5: Specific Energy vs. Particle Size for SMD Testing

 

13.4.2 Gravity and Gravity Tailings Whole Rock Leach

A gravity circuit was included in the whole rock leach flowsheet. The gravity circuit is designed to remove and recover any gold nuggets that would not be completely leached in conventional cyanide leaching circuit. The use of a gravity circuit also allows for a more consistent head grade in the leach feed.

Leaching tests were performed on gravity tailings to compare a gravity tailings leaching circuit to the flotation concentrate leaching option. All tests were performed on an ODM master composite. The tests were done at grind sizes ranging from 50 to 120 µm.

The gravity tailings leaching results for gold and silver are presented in Table 13-11 and Table 13-12, respectively. Any results presented for grind sizes with more than one (1) test are averaged values.

 

 

13-16


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 13-11: Gravity Tailings Leach Results (Gold)

 

            Reagent      Au Recovery (%)      Au Assays  

Number of tests

   P80
(µm)
     Consumptions (kg/t)        
      NaCN      CaO      6 h      24 h      36 h      48 h      Grav      Grav. +
CN
     Residue
(g/t)
     Head Grade
(g/t)
 

1

     119         0.08         0.39         77.7         83.5         85.6         85.8         29.1         89.9         0.10         0.98   

1

     95         0.12         0.38         76.9         86.3         85.3         86.7         29.1         90.6         0.10         0.98   

3

     68         0.16         0.39         78.7         88.3         84.6         89.3         29.1         92.4         0.08         0.98   

1

     50         0.34         0.40         79.2         87.9         88.4         89.8         29.1         92.8         0.08         0.98   

3

     94         0.09         0.34         77.2         87.6         87.0         88.1         25.7         91.1         0.10         1.05   

2

     75         0.10         0.31         79.3         89.9         87.8         90.1         25.7         92.6         0.08         1.05   

4

     62         0.14         0.36         79.3         87.5         88.1         89.6         25.7         92.3         0.08         1.05   

3

     51         0.18         0.37         78.8         90.6         88.6         90.8         25.7         93.2         0.07         1.05   

Table 13-12: Gravity Tailings Leach Results (Silver)

 

            Reagent             Ag Assays  

Number of tests

          Consumptions (kg/t)      Ag Recovery (%)     
   P80
(µm)
     NaCN      CaO      6 h      24 h      36 h      48 h      Grav      Grav. +
CN
     Residue
(g/t)
     Head Grade
(g/t)
 

1

     119         0.08         0.39         53.4         61.5         64.7         66.5         4.6         68.0         1.20         3.80   

1

     95         0.12         0.38         54.5         64.5         67.3         68.9         4.6         70.3         1.10         3.80   

3

     68         0.16         0.39         54.4         64.4         63.2         68.8         4.6         70.2         1.13         3.80   

1

     50         0.34         0.40         52.9         63.5         65.7         68.0         4.6         69.5         1.20         3.80   

3

     94         0.09         0.34         60.8         70.6         73.0         74.7         6.7         76.4         0.87         3.80   

1*

     69         0.09         0.37         64.9         75.4         74.2         78.8         6.7         80.2         0.70         3.80   

4

     62         0.14         0.36         59.9         69.6         72.3         72.8         6.7         74.6         0.96         3.80   

3

     51         0.18         0.37         56.2         67.1         68.6         71.6         6.7         73.5         1.05         3.80   

 

* One test result not presented as silver residue levels were much lower than any other test.

Test results showed gold recoveries ranging from 89.2 to 93.5% (residues from 0.07 to 0.12 g/t) and silver recoveries ranged from 67.2 to 81.0% (residues of 0.7 to 1.2 g/t). Sodium cyanide consumptions averaged 0.10 kgNaCN/t, while lime consumptions averaged 0.36 kgCaO/t. It was also noted that cyanide consumption increased with decreasing grind size.

From these results, it was estimated that an overall gold recovery of approximately 92% (1% higher than historical testwork) could be achieved when the material was ground below 90 µm followed by gravity tailings leaching.

 

 

13-17


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

13.4.3 Flowsheet Selection

Based on a trade-off study comparison, it was determined that the whole rock leaching option with gravity separation was the most economically viable alternative and was therefore used as the basis for the Feasibility Study. The main reason for this selection was the significant amount of energy associated with regrinding the flotation concentrate and the high cyanide consumption in the flotation concentrate leaching, in addition to the risk associated with ultrafine grinding of this material. The gravity circuit was included due to relatively high gravity recovery (25-37%) noted during the testwork. All subsequent testwork was therefore based on cyanide leaching of the gravity tailings.

 

13.5 Comminution Tests

A large comminution testwork program was undertaken to establish the basis for the sizing of the crusher, SAG mill and ball mill. The tests included 21 crushing work index tests (seven (7) tests at three (3) separate testing facilities), 16 Bond Ball Mill Work index (“BWi”) tests, 160 ModBond Ball Mill Work index (“ModBWi”) tests, 13 JK Drop Weight tests (“DWT”), 175 SAG Mill Comminution (“SMC”) tests and eleven (11) SPI tests. In addition, seven (7) samples were sent to Starkey and Associates for SAGDesign testing.

 

13.5.1 Crusher Work Index

Crushing work index (“CWi”) tests were performed at three (3) testing facilities (SGS and two (2) suppliers). The results from the testwork are presented in Table 13-13.

Table 13-13: Crusher Work Index Results

 

Lab

   SGS/Phillips      Supplier A      Supplier B  

Zone

   ODM      Z-433      HS      NZ      CAP      ODM      Z-433      HS      CAP      ODM      Z-433      HS      CAP  

No. of Tests

     4         2         1         1         1         6         1         2         2         4         1         1         1   

No. of Specimens

     69         38         20         17         20         60         10         20         20         40         10         10         10   

Average

     19.7         34.8         25.0         19.4         10.9         20.9         18.7         18.8         14.0         11.6         10.3         10.3         7.3   

Minimum

     8.8         17.2         17.1         13.7         6.6         11.1         12.0         10.0         10.2         2.9         6.4         6.9         3.7   

Median

     17.7         35.9         24.5         17.4         10.1         20.9         18.2         17.3         14.3         10.3         10.1         9.8         6.7   

80th Percentile

     24.0         39.9         28.4         24.4         14.3         24.7         23.4         21.7         15.5         16.5         11.1         13.4         9.8   

Maximum

     52.1         50.3         30.9         27.6         18.3         36.6         27.8         39.4         20.0         30.2         20.9         15.1         11.6   

 

 

13-18


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The SGS results indicated that the crusher work indices ranged from 10.1 to 35.9 kWh/t and 14.3 to 39.9 kWh/t at the 50th and 80th percentiles, respectively. It was noted that the Z-433 samples had much higher values while the CAP Zone had lower CWi values. Supplier A produced CWi values ranging from 10.3 to 20.9 and 15.5 to 24.7 kWh/t at the 50th and 80th percentiles, respectively. The numbers provided by Supplier B were considerably lower, with values ranging from 6.7 to 14.3 kWh/t and 9.8 to 16.5 kWh/t at the 50th and 80th percentiles. The results from SGS and Supplier A are indicative of a hard material resistant to coarse breakage, while Supplier B indicated that the samples had average resistance to coarse breakage.

The results from Supplier A were used for the design as they were deemed the most reliable and consistent. An 80th percentile value of 25 kWh/t was chosen for the design.

 

13.5.2 Unconfined Compressive Strength

Unconfined compressive strength tests were performed at Queen’s University to determine competency of the selected rock samples. Seven (7) samples (four (4) ODM, one (1) Z-433, one (1) HS and one (1) CAP) were tested with one (1) repeat each.

Ten (10) of the 14 samples had partial failure occur along foliation lines, including all of the ODM samples. The values from all the tests ranged from 34.5 to 109.4 MPa with an average of 66.3 MPa. The average of the samples that did not have partial failures along the foliation lines was 87.2 MPa. As most of the samples suffered partial failures along foliation lines, the results are not considered to be reliable and were not used for the design.

 

13.5.3 JK Drop Weight and SAG Mill Comminution

A large SAG Mill sizing testwork campaign including 13 JK DWT tests and 175 SMC tests was undertaken at SGS on the main pit, along with an additional two samples from the Intrepid Zone. The JK DWT tests were performed on PQ core drilled specifically for the comminution program, while the SMC tests were performed on samples selected from the exploration drilling program. The SMC samples were selected using a geometallurgical approach to give a good definition of the deposit. The samples were selected by SGS geometallurgy group by dividing the deposit into one million tonne blocks (“domains”) and selecting a sample in each domain. Using this method, 162 total samples (from the main pit) were selected for SMC testing as described in section 13-3 in addition to the 13 samples that the JK DWT tests were performed on, for a total of 175 SMC tests.

 

 

13-19


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The JK DWT results consist of A and b factors (often referenced as A x b) that indicate the resistance to impact breakage and a ta value, which indicates the resistance to abrasion. A lower A x b value indicates a higher resistance to impact breakage while a higher ta value indicates a material that is more resistant to abrasion breakage. The JK Drop Weight test results were also used to calibrate the SMC results. The calibration was performed by zone (i.e., the HS Zone JK DWT was used to calibrate the HS SMC samples). The SMC tests generate A and b factors similar to the JK DWT, along with Mia, Mic, Mih and density values. The Mia value is the coarse grinding work index, Mic is the crushing work index and Mih is the HPGR work index. All SMC tests were performed on the -22.4 /+19.2 mm size fraction.

An SMC test was performed on the remaining portion of each sample that was first tested using JK DWT. The objective of this was to provide confidence in the results obtained from the SMC tests and to support the validity of using SMC testing for the variability testwork. The results from the JK DWT are presented alongside the corresponding SMC results for the same sample in Table 13-14.

Table 13-14: JK Drop Weight and Corresponding SMC Results

 

     JK DWT      SMC         

Zone

   A      B      A x b      ta      r
(g/cm3)
     A      b      A x b      A x b %
Difference
 

HS

     76.4         0.30         22.9         0.32         2.79         75.4         0.33         24.9         8.7   
     66.4         0.37         24.6         0.31         2.81         58.0         0.56         27.6         12.2   

ODM

     66.2         0.37         24.5         0.45         2.77         68.9         0.35         24.1         -1.6   
     50.8         0.61         31.0         0.46         2.82         55.0         0.60         33.0         6.4   
     54.9         0.55         30.2         0.48         2.83         54.2         0.64         34.7         12.9   
     53.2         0.59         31.4         0.47         2.83         54.9         0.57         31.3         -0.3   
     55.2         0.67         37.0         0.57         2.80         56.4         0.70         39.5         6.7   
     50.0         0.79         39.5         0.43         2.75         60.8         0.65         39.5         0.0   

CAP

     67.0         0.37         24.8         0.35         3.02         58.6         0.45         26.4         6.4   
     59.5         0.40         23.8         0.21         2.92         79.1         0.34         26.9         13.0   

Z-433

     60.6         0.41         24.8         0.44         2.81         69.5         0.35         24.3         -2.0   
     60.1         0.42         25.2         0.28         2.82         70.5         0.36         25.4         0.8   

NZ

     35.0         0.81         28.4         0.46         2.73         64.7         0.45         29.1         2.5   

Intrepid

     65.9         1.36         89.6         1.04         2.63         64.9         1.60         104         16.1   
     100         0.23         23.0         0.28         2.72         83.4         0.60         38.0         65.2   
                    

 

Average (Main pit)

  

     5.1   
              

 

Average (including Intrepid Zone)

  

     9.8   

 

 

13-20


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

It can be seen from Table 13-14 that the calibrated SMC test results are slightly higher than the JK DWT results for the same sample, indicating that for a given sample the SMC results will indicate slightly less resistant to impact breakage than the JK DWT. As the SMC test could only be performed once on the excess material, the minor difference confirmed that the SMC tests could be used for the variability analysis rather than performing a full JK DWT as a better distribution could be developed with multiple SMC tests.

The differences on the Intrepid Zone samples between the JK DWT and SMC tests were more significant than the other zones. One of the samples tested had a much higher A x b value than any other samples tested from the main pit. This is an indication that the ore hardness variability in the Intrepid Zone may be more significant than the zones from the main pit. However, this is not expected to have a significant impact on operations given the high blending ratio that will be used when introducing the Intrepid Zone material to the mill.

As can be seen in Figure 13-6, the JK DWT tests (indicated as diamonds) fall onto the curve generated by the multiple SMC tests, as expected.

 

 

LOGO

Figure 13-6: SMC Data Distribution with JK DWT Calibration Points

 

 

13-21


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The distributions for the Z-433, HS and CAP Zones are quite narrow and consistent throughout each respective zone, while there is a wider range of values for the ODM and NZ Zones.

The multiple SMC test results provide definition of the hardness profile of the deposit.

The SMC A x b and Mia results are presented in Table 13-15. It should be noted that a lower A x b or a higher Mia number is indicative of a harder material.

Table 13-15: SAG Mill Comminution SMC and Mia Values

 

Zone

   ODM      Z-433      HS      NZ      CAP      Waste  

A x b

                 

Number of Tests

     95         19         12         21         26         2   

Average

     32.9         23.7         22.0         28.3         23.2         21.6   

Minimum

     62.6         38.6         24.9         63.3         34.7         22.0   

Median

     32.4         22.7         22.1         26.0         22.3         21.6   

80th Percentile

     26.6         20.7         20.8         21.8         20.3         21.3   

Maximum

     20.7         19.0         19.0         20.0         18.0         21.1   

Mia (kWh/t)

                 

Average

     23.6         30.0         31.5         27.0         30.3         31.9   

Minimum

     13.8         19.9         28.5         13.5         21.6         31.4   

Median

     23.2         30.4         31.1         27.4         30.6         31.9   

80th Percentile

     27.0         32.5         33.0         31.4         33.2         32.1   

Maximum

     32.8         35.6         35.2         34.6         37.4         32.3   

Based on reference and industrial data, all zones tested are considered to be very hard. The ODM Zone is slightly less resistant to coarse breakage while the other zones and waste rock samples were considerably harder. This can be noted from both the A x b and Mia values. The hardest zone noted in the testwork was the CAP Zone, with an A x b of 20.3 and a Mia of 33.2 kWh/t at the 80th percentile.

A x b values of 25.7 and 24.0 at the 80th percentile were estimated from JK DWT and SMC tests for the Initial Pit and remaining-life-of-mine, respectively, using the proportions from Table 13-2. The A x b and ta values were used in the JKSimMet simulation program to estimate SAG mill sizing and energy requirements.

 

13.5.4 SAGDesign

Starkey and Associates (www.sagdesign.com) performed “SAGDesign” testwork on the PQ core samples that were tested using the JK DWT method. The testwork results are presented in Table 13-16.

 

 

13-22


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 13-16: SAGDesign Testwork Results

 

Sample

  

SAG Mill Data from SAGDesign Test

            Ball Mill Data from
SAGDesign Test
        

No.

  

Name

   Charge
Mass
(g)
     No.
of
Revs
     Bulk
SG
(g/cm3)
     SG
Solids

(g/cm3)
     Calc WSAG
to  1.7mm
(kWh/t)
     SAG
Dis.
Bond
BWI
(kWh/t)
     Calc
WBM
to P80
(kWh/t)
     Total
Wto
P80
(kWh/t)
 

1

   NR 11-935      6906         1541         1.53         2.76         11.4         11.1         10.1         21.5   

2

   NR 11-955      7016         1292         1.56         2.80         9.5         11.0         10.0         19.5   

3

   NR 11-956      7145         1333         1.59         2.86         9.7         13.5         12.3         22.0   

4

   NR 11-1003      7205         1512         1.60         2.79         10.9         11.5         10.5         21.4   

5

   NR 12-1176      7499         1658         1.67         2.97         11.6         14.4         13.2         24.8   

6

   NR 11-825      6759         1770         1.50         2.74         13.3         14.8         13.5         26.8   

7

   NR 12-1191      6827         1626         1.52         2.77         12.2         14.6         13.3         25.4   

Minimum

     6759         1292         1.50         2.74         9.5         11.0         10.0         19.5   

Median

     7016         1541         1.56         2.79         11.4         13.5         12.3         22.0   

Average

     7051         1533         1.57         2.81         11.2         13.0         11.8         23.1   

Maximum

     7499         1770         1.67         2.97         13.3         14.8         13.5         26.8   

Design Data (80th Percentile)

  

        2.81         12.2         14.6         13.3         25.4   

The WSAG values provided by SAG Design ranged from 9.5 to 13.3 kWh/t with an 80th percentile value of 12.2 kWh/t.

Bond Ball Mill Work index tests were performed on the discharge of the SAGDesign testwork at a closed side setting of 200 mesh. The design BWI value was determined to be 14.6 kWh/t.

The samples tested using the SAGDesign method were also tested by JKDWT, presented in Section 13.5.3. This allowed for a direct sample-by-sample analysis of the SAGDesign method compared to the JKDWT method.

A comparison of the SAGDesign and JK DWT test program results is presented in Table 13-17.

 

 

13-23


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 13-17: Comparison between SAGDesign and JK DWT Results

 

Sample Name

   SAGDesign
(kWh/t)
     JK DWT
(A x b)
     JKSimMet
(kWh/t)
 

NR 11-935

     11.4         24.5         13.6   

NR 11-955

     9.5         31.0         11.9   

NR 11-956

     9.7         30.2         12.1   

NR 11-1003

     10.9         31.4         11.8   

NR 12-1176

     11.6         24.8         13.4   

NR 11-825

     13.3         22.9         13.9   

NR 12-1191

     12.2         25.2         13.3   

The SAGDesign results confirmed the JK Drop Weight results and correlated well in terms of hardness. It can be seen that the softer samples according to the JK DWT (NR 11-955, NR 11-956 and NR 11-1003) had the lowest pinion power requirements according to SAGDesign (ranging from 9.5 to 10.9 kWh/t). Furthermore, the hardest sample from the JK DWT (NR 11-825) had the highest pinion power requirements (13.3 kWh/t). The overall results indicate that the SAGDesign method yielded pinion energy requirements that were approximately 1-2 kWh/t lower than the JKSimMet method. This good correlation between the two (2) methodologies provides confidence in the sizing of the SAG mill.

 

13.5.5 Bond Work Index

The ball mill sizing test program consisted of 160 Modified Bond Mill Work index (“ModBWi”) tests and 20 standard Bond Ball Mill index (“BWi”) tests on material from the main pit. The tests were performed on all five (5) zones of the deposit.

To validate the ModBond numbers, a comparison between the ModBond Ball Mill Work index and the full Bond Ball Mill Work index was performed. The average ModBond and Bond Ball Mill Work indices were identical for the two (2) tests, and overall the tests indicated that the ModBond results were representative of the results obtained by the full Bond Ball Mill tests.

A visual representation of the results was prepared to verify if the ModBWi were within 5% of the BWi. The results from the full BWi were plotted with a 5% error bar and the corresponding ModBWi results were also shown. The plot is presented in Figure 13-7.

 

 

13-24


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 13-7: Full Bond Ball Mill Work Indices vs. ModBond Work Indices (200 Mesh)

It can be seen that all but four (4) of the ModBWi results fell within 5% of the BWi. Since the majority of the results were within 5% of the BWi and the average for the two (2) datasets was identical, the ModBWi were deemed representative of the BWi and the full program was performed using the ModBond technique.

The tests were performed at a closed side setting of 200 mesh (75 µm). The results are presented in Table 13-18.

 

 

13-25


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 13-18: Bond and ModBond Results

 

Description

   Bond Work Index (200 mesh)
kWh/t
 

Zone

   ODM      Z-433      HS      NZ      CAP      Intrepid  

Bond Work Index, 200 mesh (kWh/t)

                 

Number of Tests

     5         4         2         2         3         8   

Average

     13.6         15.6         16.2         13.0         15.2         16.7   

Minimum

     12.6         15.2         16.1         12.1         14.8         13.2   

Median

     13.8         15.7         16.2         13.0         14.9         15.6   

80th Percentile

     14.2         15.9         16.2         13.5         15.6         19.0   

Maximum

     15.0         15.9         16.3         13.8         16.1         21.5   

ModBond Work Index, 200 mesh (kWh/t)

                 

Number of Tests

     89         17         10         20         24         30   

Average

     13.8         15.1         14.9         14.1         14.7         15.1   

Minimum

     11.6         12.9         14.1         11.1         13.0         13.4   

Median

     13.8         15.3         15.0         14.2         14.8         15.1   

80th Percentile

     14.7         15.4         15.2         15.0         15.5         15.7   

Maximum

     16.0         15.8         15.5         16.2         15.8         17.3   

It can be seen that at the 80th percentile all the zones are relatively similar in terms of ModBWi. A weighted average ModBWi value of 15.0 kWh/t (80th percentile) for the deposit was determined using the ModBond test results.

The results include results from testwork for the Intrepid Zone that was performed after completion of the testwork program for the main zone. It can be seen that for the Intrepid Zone, at the 80th percentile, the BWi and ModBWi are considerably different, with values of 19.0 and 15.7 kWh/t, respectively. This is due to two (2) samples that had considerably higher BWi values. When ignoring these two (2) results, the 80th percentile of the BWi tests is 15.7 kWh/t –identical to the ModBWi results. Overall the Intrepid Zone has slightly higher BWi and ModBWi values, indicating that the zone is harder than the zones from the main pit.

The distribution of the ModBond work indices can be seen in Figure 13-8.

 

 

13-26


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 13-8: Distribution of ModBond Indices (200 Mesh) by Zone

The ODM and NZ Zones were slightly softer than the other zones and also had a wider range of values, analogous to the SMC tests. However, at the 80th percentile the BWi values are much closer across all the zones ranging from 14.7 kWh/t to 15.7 kWh/t. A weighted average value of 15.0 kWh/t was used for design.

 

13.5.6 ModBond and A x b

Figure 13-9 shows an interesting behaviour between A x b and ModBond for the main pit. The linear trend indicates that the material grinding characteristics (impact and attrition) are very consistent (hard A x b with a hard BWi). This information may be useful in future production planning.

 

 

13-27


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 13-9: ModBond Wi vs. A x b

 

13.5.7 Bond Abrasion Index

Twenty-four abrasion index tests were performed and the results indicated a large amount of variability in the samples with values ranging from 0.050 to 0.663 (7th to 88th percentile hardness in the SGS database).

The results are presented in Table 13-19.

Table 13-19: Abrasion Index Results

 

Description

   ODM      Z-433      HS      NZ      CAP  

Number of Tests

     12         4         2         2         4   

Average (g)

     0.20         0.27         0.32         0.11         0.15   

Minimum (g)

     0.05         0.14         0.21         0.11         0.08   

Median (g)

     0.15         0.21         0.32         0.11         0.15   

80th Percentile (g)

     0.26         0.33         0.38         0.11         0.19   

Maximum (g)

     0.66         0.51         0.43         0.11         0.21   

Overall, the ore is considered moderately abrasive when compared to the SGS database.

 

 

13-28


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

13.5.8 Grinding Circuit Design

Several different design methods were used to size the SAG and ball mill circuit. The 80th percentile of the crushing and grinding testwork results was used for each of the tests to ensure that an appropriate safety factor was provided. The following estimation methods and consultants were used to estimate the size of the grinding circuit:

 

 

Morrell’s Equation: This method uses the Mia and Mic values from the SMC tests described in Section 13.5.3 and the Bond Ball Work index test results from Section 13.5.5 to estimate the total power required by the SABC circuit. While the power divided into the SAG mill, ball mill and pebble crusher, the total circuit energy is the recommended value to use.

 

 

JKSimMet with the Bond Equation: This method utilizes the A x b and Ta results from the JK DWT and SMC tests to estimate the power requirement for the SAG mill using the software JKSimMet. The JKSimMet simulation also indicates the transfer size (T80) that can then be used to size the ball mill according to the Bond Equation using standard efficiency factors and the BWI or ModBWi.

 

 

JKSimMet with the Phantom Cyclone: This method estimates the SAG mill power using the same method as previously described in the JKSimMet with the Bond Equation method. The SAG mill discharge is assuming that the SAG discharge is treated by a cyclone prior to feeding the ball mill circuit, with only the cyclone underflow being treated by the ball mill. The ball mill power is then calculated using the Bond Equation with no efficiency factors and the BWi or ModBWi. This method often yields a lower energy requirement than the standard Bond method with efficiency factors as it underestimates the hardness of the material in the cyclone underflow. It is BBA’s opinion that this method should not be used for design; however, it has been included in order to provide an additional reference.

 

 

SAGDesign: The testwork and interpretation performed by SAGDesign is described in Section 13.5.4.

 

 

Orway Mineral Consultants (OMC): A third party was asked to independently assess the power requirements for the grinding circuit using the data presented in Section 13.5 excluding the SAGDesign testwork.

 

 

13-29


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

To calculate the power requirement of the SAG and ball mill (at the pinion), the following design criteria were used:

 

 

Simulations performed at a nominal tonnage of 906 t/h or 20,000 tpd:

 

   

Energy requirements (operating work indices) were then used to determine the operating power and required installed power for the SAG mill and ball mill for a nominal tonnage of 21,000 tpd.

 

 

Variable transfer size (T80), depending on method;

 

 

Final circuit P80 of 75 µm;

 

 

A x b value of 24.2, ta value of 0.35;

 

 

BWi value of 15.0 kWh/t; and

 

 

Mia value of 29.3 kWh/t.

The results from the simulations are presented in Table 13-20.

Table 13-20: SAG and Ball Mill Simulation Results1

 

          Morrell’s
Equation
    JKSimMet +
Bond’s Equation
    JK SimMet +
Phantom Cy
    SAGDesign     OMC  

Method

  Units     80th Percentile     80th Percentile     80th Percentile     79th Percentile2     80th Percentile  

Parameters

           

F80

    µm        162 500        162 500        162 500        152 000        <150 000   

T80

    µm        750        2 400        2 400        1 300        Unknown   

Final P80

    µm        75        75        75        75        75   

Energy Requirements (Operating Work Indices)

           

SAG Mill

    kWh/t        15.26        13.23        13.23        12.56        13.70   

Ball Mill

    kWh/t        12.92        13.03        12.20        12.89        12.60   

Subtotal

    kWh/t        28.18        26.26        25.43        25.45        26.30   

Pebble Crusher

    kWh/t        0.46        0.37        0.37        —          0.57   

Total

    kWh/t        28.64        26.63        25.79        25.45        26.87   

Operating Power Required (21,000 tpd)

           

SAG Mill

    kW        14 510        12 580        12 580        11 948        13 033   

Ball Mill

    kW        12 289        12 395        11 603        12 262        12 143   

 

1. 

Simulations were performed at 20,000 tpd. Operating powers for 21,000 tpd were calculated using the same operating work index (kWh/t) as was used for the 20,000 tpd simulations. Note that particle sizes have not been adjusted for 21,000 tpd.

2. 

The 79th percentile used for the SAGDesign simulations was based on seven (7) samples only.

 

 

13-30


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

It can be seen that the JKSimMet simulation using the Phantom Cyclone method yielded the lowest power requirement for the ball mill, as expected. The lowest overall circuit (SAG mill + ball mill + crusher) energy requirement estimated was by SAGDesign at 25.45 kWh/t while Morrell’s Equation yielded the highest circuit energy requirement at 28.64 kWh/t. It can be seen that all the power requirements are relatively close, giving confidence to the calculation methods. The Feasibility Study design was based on the JKSimMet with the Bond Equation method, which estimated a circuit energy requirement of 26.63 kWh/t. This matches well with the energy requirement calculated by OMC.

Based on these results, 15 MW dual pinion drives were selected for both the SAG mill and ball mill for a mill fresh feed throughput of 951 t/h. The SAG mill and drive were sized with design factors to provide sufficient operating flexibility to achieve the plant throughput. The ball mill drive size was selected to match the SAG drive for a reduction in spares and to simplify operations. Based on the results, a 36’ x 20’ (18.25’ EGL) SAG mill and a 26’ x 40.5’ (40’ EGL) ball mill were selected based on equipment sizing software and discussions with mill suppliers. This design will allow for operational flexibility and provide confidence that the process plant throughput will be achieved.

Subsequent simulations performed at 21,000 tpd (951 tph) indicated that the T80 of the SAG Mill circuit would be 2,800 µm rather than 2,400 µm. This is not expected to have a significant impact on the design of the plant.

 

13.6 Gravity Separation

 

13.6.1 Gravity Recoverable Gold

Two (2) Gravity Recoverable Gold (“GRG”) tests were performed on zone composites representing the ODM and 433 Zones. The test results are presented in Table 13-21.

 

 

13-31


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 13-21: Gravity Recoverable Gold Results

 

     Grind Size         Mass     

Assay

Au

    

Au

grams

     Dist’n  

Sample

   P80 (µm)   

Product

   grams      %      (g/t)      (g)      %  
   650    Stage 1 Conc      79.1         0.4         46.7         3,691         18.8   
   542    Sampled Tails      188.8         1.0         0.62         118         0.6   
   275    Stage 2 Conc      76.0         0.4         48.7         2,698         18.8   

ODM Master

   211    Sampled Tails      205.7         1.1         0.72         149         0.8   
   141    Stage 3 Conc      98.6         0.5         27.1         2,676         13.6   
   90    Final Tails      18,339         96.6         0.51         9.311         47.7   
   Total (Head)         18,987         100         1.03         19,643         100   
   Final Conc         254         1.3         39.7         10,065         51.2   
   612    Stage 1 Conc      80.2         0.40         56         4,529         20.6   
   546    Sampled Tails      204.5         1.02         0.89         182         0.83   
   260    Stage 2 Conc      87.9         0.44         52         4,568         20.8   

Z433

   247    Sampled Tails      194.5         0.97         0.75         145         0.66   
   132    Stage 3 Conc      109.8         0.55         35.8         3,927         17.9   
   92    Final Tails      19,323         96.6         0.45         8,609         39.2   
   Total (Head)         20,000         100         1.10         21,960         100   
   Final Conc         277.9         1.39         46.9         13,024         59.3   

The GRG numbers from these tests were 51.2 and 59.3, respectively. A higher GRG number indicates that more gold can be recovered by gravity; however, this cannot be taken as an absolute number. The actual gold recovery by gravity will be dependent on grind size and material flow to the gravity circuit.

 

13.6.2 Gravity Variability Testwork

In addition to the GRG tests, gravity separation was also performed in the variability test program using 2 kg samples. The gravity recoveries of these tests ranged from 1% to 77% with an average of 27% for the non-CAP Zones excluding the Intrepid Zone. The gravity gold recovery from the CAP Zone was considerably lower with an average recovery of 9%. The Intrepid Zone also had considerably lower recoveries, averaging 16% gold recovery by gravity.

The gold and silver recoveries as a function of head grade are presented in Figure 13-10 and Figure 13-11.

 

 

13-32


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 13-10: Gold Gravity Recovery vs. Head Grade

 

LOGO

Figure 13-11: Silver Gravity Recovery vs. Head Grade

It can be seen that the gravity recovery of gold is sensitive to the head grade, with higher grades giving higher recoveries. The same trend was noted for the Non-CAP, CAP and Intrepid Zones; however, the CAP and Intrepid Zone gold recovery were lower than the Non-CAP Zones. No trend was noted for the silver and it was assumed that silver gravity recovery is independent from the head grade. The silver gravity recoveries for the CAP and Intrepid Zones were lower than the non-CAP Zones, analogous to the gold gravity recovery. The average silver gravity recovery for the CAP Zone was roughly 3%; the Intrepid Zone averaged 5% while the non-CAP Zones silver gravity recovery was approximately 10%.

 

 

13-33


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

13.7 Heap Leaching

Heap leaching was investigated as an alternative process to agitated tank leaching. The following conditions were used for the heap leaching tests:

 

 

Feed material: 12.7 mm (1/2 inch) material from ODM and Z-433 master composites;

 

 

50% pulp density;

 

 

0.5 g/L NaCN concentration; and

 

 

pH range: 10.5 – 11.

A visual representation of the results is presented in Figure 13-12.

 

LOGO

Figure 13-12: Heap Leach Gold Recovery Curve

The test results showed a 29.7% recovery after fourteen days with a plateau beginning around day five (5). Based on the low recovery, heap leaching was rejected as a processing option.

 

 

13-34


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

13.8 Cyanide Leaching

 

13.8.1 Gravity Tailings Leaching

Gravity tailings leaching tests were performed on the Initial Pit and the remaining-life-of-mine (“RLOM”) composites. The tests were performed as “stop tests” with residue assays measured for each time duration.

Thirty-six tests were performed for each composite to help determine leach time and final grind size using the following criteria:

 

 

Four (4) leach times (18, 24, 30 and 36 h for the Initial Pit and 12, 18, 24 and 30 h for the RLOM sample);

 

 

Three (3) grind sizes (110, 85 and 70 µm); and

 

 

Two (2) repeats (three (3) total tests) per leach time/grind size criteria.

The additional gravity tailings leaching test results are shown in Table 13-22 and Table 13-23 for gold and silver assays, respectively. The results are presented as averages of the 12 tests performed per grind size per composite.

Table 13-22: Additional Gravity Tailings Leaching Results (Gold Assays)

 

                   Reagent                                                                 
                   Consumptions                                                                 
                   (kg/t)      Reagent Consumptions (kg/t)      Ag Assays  
                                                                                          Head  
     Number      P80                                                              Grav +      Residue      Grade  

Comp Name

   of Tests      (µm)      NaCN      CaO      12h      18h      24h      30h      36h      Grav      CN      (g/t)      (g/t)  

Initial Pit

     12         110         0.03         0.32         —           82.6         83.8         82.6         83.9         33.1         89.2         0.12         1.07   
     12         85         0.04         0.33         —           84.8         86.1         85.2         86.4         33.1         90.9         0.10         1.07   
     12         70         0.05         0.35         —           85.8         86.6         86.7         86.5         33.1         90.9         0.10         1.07   

RLOM

     12         110         0.02         0.31         79.7         79.7         81.3         82.2         —           29.6         87.5         0.10         0.83   
     12         85         0.02         0.32         82.1         82.6         83.8         84.2         —           29.6         88.9         0.09         0.83   
     12         70         0.01         0.32         84.1         85.2         86.0         85.7         —           29.6         90.0         0.08         0.83   

 

 

13-35


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 13-23: Additional Gravity Tailings Leaching Results (Silver Assays)

 

                   Reagent                                                                 
                   Consumptions                                                                 
                   (kg/t)      Ag Recovery (%)      Ag Assays  
                                                                                          Head  
     Number      P80                                                              Grav +      Residu      Grade  

Comp Name

   of Tests      (µm)      NaCN      CaO      12h      18h      24h      30h      36h      Grav      CN      e (g/t)      (g/t)  

Initial Pit

     12         110         0.03         0.32         —           62.3         61.9         69.9         61.2         7.4         64.1         1.07         2.80   
     12         85         0.04         0.33         —           59.4         62.4         70.5         62.8         7.4         65.5         1.07         2.80   
     12         70         0.05         0.35         —           58.0         65.3         72.1         61.8         7.4         64.6         1.10         2.80   

RLOM

     12         110         0.02         0.31         61.1         66.4         68.1         68.9         —           6.1         70.8         0.80         2.80   
     12         85         0.02         0.32         65.1         68.9         70.8         71.3         —           6.1         73.1         0.77         2.80   
     12         70         0.01         0.32         66.2         72.1         70.7         70.8         —           6.1         72.6         0.80         2.80   

The test results showed that the recovery of gold is moderately sensitive to grind size, confirming trends that had previously been noted. No noticeable improvement in recovery was noted beyond 24 hours of leaching for the Initial Pit; however, slight increases in recovery were noted for the RLOM sample when leaching from 24 to 30 h.

The gravity tailings residue for all the tests presented in Sections 13.4.2 and 13.8.1 were plotted versus the grind size of the feed material, presented in Figure 13-13. The dotted lines represent the sensitivity of the assay technique (0.02 g/t).

 

LOGO

Figure 13-13: Gravity Tailings Leach Residue vs. Grind Size

 

 

13-36


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

To determine a final P80 for the variability test program, a cost versus revenue study was performed. The costs included cyanide consumption, grinding energy at a fixed tonnage and estimated media wear, while the revenue was calculated based on the residue equation from Figure 13-13. High and low cost scenarios were investigated in addition to the nominal costs. The cost of sodium cyanide, steel and energy were varied to generate the high and low cost scenarios.

To standardize the values, the marginal costs and marginal revenues were used, rather than absolute costs and revenues, to determine the P80 at which is it no longer economical to grind finer.

The results are presented in Figure 13-14.

 

LOGO

Figure 13-14: Cost and Revenue Analysis by Grind Size

The results show that for the average costs of the aforementioned parameters, grinding to 65 µm is still economical. However when using higher costs, it is only economical to grind to 75 µm.

Based on these results, a grind size of 75 µm and a retention time of 36 h (with subsampling at 30 h) were selected for the variability test program described in Section 13.8.7.

 

 

13-37


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

13.8.2 Cyanide Concentration

The effect of the concentration of sodium cyanide in the leach was investigated by varying the sodium cyanide concentration from 0.15 to 0.5 g/L. The testwork was based on 36-hour cyanide leaching tests with subsampling at different time intervals.

The results from the cyanide concentration testwork results are presented in Table 13-24.

Table 13-24: Cyanide Concentration Testwork Results

 

                   Reagent
Consumptions

(kg/t)
     Au Recovery (%)      Au Assays  

Comp Name

   P80
(µm)
     NaCN
Conc.
(g/L)
     NaCN      CaO      12 h      18 h      24 h      30 h      36 h      Grav      Grav
+ CN
     Residue
(g/t)
     Head
Grade
(g/t)
 

RLOM

     118         0.50         0.11         0.40         77         80         83         81         82.8         16.4         85.6         0.12         0.67   
     117         0.30         0.08         0.37         71         77         82         81         81.9         16.4         84.9         0.13         0.69   
     120         0.20         0.06         0.40         74         78         82         82         82.3         16.4         85.2         0.12         0.65   
     118         0.15         0.06         0.41         70         77         81         80         82.3         16.4         85.2         0.12         0.68   

The test results did not indicate that the gold or silver recoveries were sensitive to cyanide concentration. A consistent trend between cyanide concentration and gold/silver recovery was not observed.

The results are plotted in Figure 13-15.

 

LOGO

Figure 13-15: Gold Recovery vs. Time at Different NaCN Concentrations

 

 

13-38


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Based on these results, 0.5 g/L NaCN was selected for the variability tests as it did not appear that the cyanide level had any effect on overall recovery. This value was selected to ensure there was no cyanide starvation during variability testwork.

 

13.8.3 Pre-Conditioning

Pre-conditioning tests were performed on the sample to determine if aerating the sample prior to leaching had any effect on cyanide consumption. A short pre-conditioning was performed on the sample to raise the dissolved oxygen levels to approximately 5 ppm for four (4) tests while no pre-conditioning was performed for another four (4) tests. A level of 5 ppm dissolved oxygen is comparable to that of typical slurry after passing through the grinding circuit.

The pre-aeration results are presented in Table 13-25.

Table 13-25: Pre-Conditioning vs. No Pre-Conditioning Testwork Results

 

                 Reagent
Consumptions

(kg/t)
     Au Recovery (%)      Au Assays  

Comp Name

   Pre-
Aeration
   P80
(µm)
     NaCN      CaO      6 h      12 h      24 h      36 h      Grav      Grav
+ CN
     Residue
(g/t)
     Head
Grade
(g/t)
 

Initial Pit

   Y      100         0.07         0.36         79         83         83         83.5         31.4         88.7         0.12         0.73   
   Y      100         0.08         0.36         73         79         80         82.7         31.4         88.1         0.13         0.72   
   N      100         0.22         0.30         74         82         86         84.0         31.4         89.0         0.12         0.72   
   N      100         0.19         0.31         75         82         81         85.0         31.4         89.7         0.12         0.77   

RLOM

   Y      118         0.08         0.36         75         75         81         80.8         16.4         84.0         0.14         0.70   
   Y      118         0.07         0.36         76         82         83         82.1         16.4         85.0         0.13         0.70   
   N      118         0.18         0.33         72         77         80         81.5         16.4         84.5         0.13         0.70   
   N      118         0.25         0.29         70         70         77         78.8         16.4         82.3         0.15         0.71   

The cyanide consumption was increased from 0.07-0.08 kg/t in tests with pre-conditioning to 0.18-0.25 kg/t when no pre-aeration was performed. The residue levels when using pre-aeration were comparable to when pre-aeration was not used. Given the high consumptions when no-pre-conditioning was used, it was determined that cyanide would not be added to the grinding circuit. The use of a pre-conditioning tank is not required, as the minimum acceptable level of dissolved oxygen can be achieved through the grinding circuit.

Based on these results, it was decided that the variability tests would be performed with preconditioning prior to leaching.

 

 

13-39


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

13.8.4

Oxygen (O2) vs. Air

The use of oxygen in the cyanide leach was investigated. The results from the tests did not indicate that the use of oxygen decreased cyanide consumption or improved reaction kinetics significantly.

The results are presented in Table 13-26.

Table 13-26: O2 vs. Air and Lead Nitrate Addition Testwork Results

 

                        Reagent
Consumptions
(kg/t)
     Au Recovery (%)      Au Assays  

Comp Name

   Aeration      Lead
Nitrate
   P80
(µm)
     NaCN      CaO      6 h      12 h      24 h      36 h      Grav      Grav
+ CN
     Residue
(g/t)
     Head
Grade
(g/t)
 
     O2       N         0.04         0.37         82         —           —           —           29.0         87.1         0.12      
     O2       N      54         0.04         0.36         —           86         —           —           29.0         90.2         0.09      
     O2       N      52         0.11         0.41         —           —           89         —           29.0         92.2         0.07      
     O2       N      61         0.06         0.38         —           —           88         —           29.0         91.8         0.10      
     O2       N      55         0.12         0.38         —           —           —           87         29.0         91.0         0.09      
     O2       N      59         0.04         0.39         —           —           —           87         29.0         90.8         0.10         0.97   

Initial Pit

     O2       Y      59         0.16         0.50         —           —           —           88         29.0         91.5         0.08      
     O2       Y      45         0.05         0.52         —           —           —           87         29.0         90.9         0.08      
     Air       Y      48         0.14         0.56         —           —           —           88         29.0         91.3         0.08      
     Air       Y      59         0.06         0.51         —           —           —           87         29.0         90.9         0.09      
     O2       N      66         0.05         0.36         84         —           —           —           38.5         90.5         0.08      
     O2       N      59         0.05         0.41         —           87         —           —           38.5         91.9         0.07      
     O2       N      79         0.06         0.33         —           —           87         —           38.5         92.2         0.09      

RLOM

     O2       N      68         0.07         0.40         —           —           84         —           38.5         90.3         0.08      
     O2       N      57         0.08         0.41         —           —           —           85.3         38.5         91.0         0.08      
     O2       N      66         0.08         0.41         —           —           —           85.5         38.5         91.1         0.08         0.89   
     O2       Y      70         0.06         0.53         —           —           —           84.0         38.5         90.2         0.08      
     O2       Y      71         0.03         0.53         —           —           —           84.6         38.5         90.5         0.08      
     Air       Y      72         0.06         0.50         —           —           —           82.2         38.5         89.0         0.11      
     Air       Y      71         0.08         0.49         —           —           —           84.1         38.5         90.2         0.10      

Based on these results, it was decided that the variability tests would be performed with air.

13.8.5 Lead Nitrate Addition

The use of lead nitrate in the leaching circuit was also investigated. The results are presented in Table 13-26 in Section 13.8.4.

 

 

13-40


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The lead nitrate cyanide leach test results did not indicate that the use of lead nitrate decreased cyanide consumption or improved reaction kinetics significantly. Furthermore, the lime addition for the samples with lead nitrate addition was higher than those without.

Based on these results, it was decided that the variability tests would be done without lead nitrate.

 

13.8.6 Intrepid Zone Leaching Kinetics

Given the large amount of silver in the Intrepid Zone, the leaching kinetics for both gold and silver were investigated. To evaluate the silver leaching kinetics, the following conditions were considered:

 

 

Leach time of 96 hours with a sub-sample at 30, 36, 48 and 72 hours;

 

 

Target grind size (P80) of 75 µm;

 

 

Cyanide concentration of 0.5 g/L NaCN;

 

 

30-minute pre-conditioning;

 

 

pH of 10.5-11.

The first two (2) tests (as well as a repeat of the first test) were performed without gravity concentration, while the subsequent two (2) tests included gravity separation.

The cyanide leaching kinetics results are presented in Table 13-27 and Table 13-28.

Table 13-27: Intrepid Zone Leaching Kinetics Tests (Gold)

 

                   Reagent
Consumptions

(kg/t)
     Au Recovery (%)      Au Assays  

Test

   P80
(µm)
     NaCN
Conc.
(g/L)
     NaCN      CaO      30 h      36 h      48 h      72 h      96 h      Grav      Total      Residue
(g/t)
     Head
Grade
(g/t)
 

1

     78         0.5         0.19         0.36         88         89         90         88         89.3         n/a         89.3         0.17      

1R

     80         0.5         0.18         0.31         91         90         93         95         95.5         n/a         95.5         0.10      

2

     74         1.0         0.31         0.32         92         93         93         92         92.2         n/a         92.2         0.13         1.45   

3

     74         0.5         0.20         0.37         91         92         93         92         90.9         16.9         92.4         0.13      

4

     72         1.0         0.30         0.33         93         93         93         92         92.1         16.9         93.4         0.12      

 

 

13-41


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 13-28: Intrepid Zone Leaching Kinetics Tests (Silver)

 

                   Reagent
Consumptions
(kg/t)
     Ag Recovery (%)      Ag Assays  

Test

   P80
(µm)
     NaCN
Conc.
(g/L)
     NaCN      CaO      30 h      36 h      48 h      72 h      96 h      Grav      Total      Residue
(g/t)
     Head
Grade
(g/t)
 

1

     78         0.5         0.19         0.36         56         58         62         68         70.1         n/a         70.1         4.3      

1R

     80         0.5         0.18         0.31         52         55         60         67         69.7         n/a         69.7         4.6      

2

     74         1.0         0.31         0.32         58         61         64         70         72.5         n/a         72.5         4.1         13.8   

3

     74         0.5         0.20         0.37         50         52         56         64         67.5         3.8         68.7         4.5      

4

     72         1.0         0.30         0.33         60         61         65         73         74.5         3.8         75.5         3.6      

The average leaching extraction for gold and silver was plotted as a function of time to analyse the reaction kinetics. The standard deviations for each point were also shown. This data includes results with and without gravity separation.

This data can be seen in Figure 13-16.

 

LOGO

Figure 13-16: Gold and Silver Cyanide Leaching Kinetics (Intrepid Zone)

The silver kinetics for the Intrepid Zone are quite slow, with increases in silver extraction noticeable up to 96 hours, and possibly longer. The gold extraction kinetics are considerably faster, with little to no improvement noted from 30 hours to 96 hours. Based on this information, it was determined that material from the Intrepid Zone would be treated using the same leaching conditions as the main pit.

 

 

13-42


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

13.8.7 Grade Recovery Variability Tests

Cyanide leaching was performed on 208 samples (and 37 repeats) and the results were used to develop grade-recovery curves for both gold and silver for the main pit. An additional 30 samples from the Intrepid Zone were also tested.

All tests were performed at the following conditions:

 

 

Leach time of 36 hours with a subsample at 30 hours;

 

 

Target grind size (P80) of 75 µm;

 

Cyanide concentration of 0.5 g/L NaCN;

 

 

30-minute pre-conditioning; and

 

 

pH of 10.5-11.

The summary of the variability testwork is presented in Table 13-29 and Table 13-30.

Table 13-29: Gold Leaching Variability Testwork Average Results

 

                   Reag.
Consumption
     % Au Recovery                
     # of      P80      (kg/t)      CN (Unit)                    Overall      Residue      Direct Au  

Zone

   Tests      (µm)1      NaCN      CaO      30 h      36 h      Grav      Overall2      Recalculated3      Au (g/t)      Head (g/t)1  

ODM

     138         95 +/- 40         0.06         0.37         78.1         78.7         25.8         83.8         90.1         0.12         1.19 +/- 1.84   

Z-433

     30         82 +/- 32         0.10         0.41         82.8         84.4         35.6         89.5         93.8         0.08         1.21 +/- 1.21   

HS

     13         86 +/- 26         0.06         0.36         84.4         86.1         24.2         89.1         90.8         0.05         0.51 +/- 0.31   

NZ

     24         86 +/- 33         0.08         0.40         82.1         82.7         27.0         87.0         91.2         0.07         0.75 +/- 0.81   

Intrepid

     30         75 +/- 6         0.10         0.31         86.1         86.9         16.1         88.0         92.0         0.13         1.57 +/- 1.79   

Non-CAP Subtotal

     235         89 +/- 36         0.07         0.37         80.5         81.3         25.7         85.7         90.8         0.10         1.17 +/- 1.65   

CAP

     40         92 +/- 50         0.11         0.62         71.5         71.5         8.7         73.9         76.8         0.16         0.67 +/- 0.74   

TOTAL

     275         89 +/- 38         0.08         0.41         79.1         79.9         23.4         84.0         89.8         0.11         1.09 +/- 1.56   

 

1. 

Values shown are averages +/- the standard deviation (s) of the results.

2. 

The overall recovery numbers are artificially low as low grade samples have same weighting as high grade samples.

3. 

Gold recoveries recalculated using average direct head grade and average residue values.

 

 

13-43


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 13-30: Silver Leaching Variability Testwork Average Results

 

                   Reag. Consumption      % Ag Recovery                
     # of      P80      (kg/t)      CN (Unit)                    Overall      Residue      Direct Ag  

Zone

   Tests      (µm)1      NaCN      CaO      30 h      36 h      Grav      Overall2      Recalculated3      Ag (g/t)      Head (g/t)  

ODM

     138         95 +/- 40         0.06         0.37         57.4         58.8         10.0         62.7         67.1         1.24         3.77 +/-7.38   

Z-433

     30         82 +/- 32         0.10         0.41         49.1         51.4         12.8         57.6         55.2         0.60         1.34 +/-0.83   

HS

     13         86 +/- 26         0.06         0.36         47.8         48.2         8.5         52.8         51.1         0.51         1.04 +/-0.69   

NZ

     24         86 +/- 33         0.08         0.40         55.8         56.1         8.5         59.5         62.2         0.53         1.39 +/-0.72   

Intrepid

     30         75 +/- 6         0.10         0.31         58.5         60.2         5.3         60.5         55.5         6.6         14.9 +/-17.4   

Non-CAP Subtotal

     235         89 +/- 36         0.07         0.37         55.8         57.2         9.5         60.9         61.4         1.73         4.48 +/-9.32   

CAP

     40         92 +/- 50         0.11         0.62         63.8         65.1         3.0         66.4         67.5         0.86         2.65 +/-1.25   

TOTAL

     275         89 +/- 38         0.08         0.41         57.0         58.3         8.6         61.9         61.9         1.60         4.21 +/-8.65   

 

1. 

Values shown are averages +/- the standard deviation (s) of the results.

2. 

The overall recovery numbers are artificially low due as low grade samples have same weighting as high grade samples.

3. 

Silver recovery recalculated using average direct head grade and average residue values

The results indicated that there was significant variability in both the overall deposit and the individual zones. The average residue value for all the samples was 0.10 g/t Au for the Non-CAP zones (including the Intrepid Zone) and 0.16 g/t for the CAP Zone. It can be seen that the CAP Zone had lower gravity and overall recoveries for gold, and lower gravity recoveries for silver.

It should be noted that the average overall recoveries for both gold and silver are lower than the true average that would be expected in operation. This is because the average overall recovery is more influenced by the samples with low head grades than the samples with average or high head grades. As a result, the overall recovery was recalculated using the average head grade and residue values, which is a more representative average recovery.

It can also be seen that the average P80 of 89 µm was considerably coarser than the target P80 of 75 µm. The P80 also ranged from 30 to 260 µm, indicating that there were large variations in hardness of the material.

Filters were applied to the data to remove samples that did not conform to the process design criteria to generate the residue versus grade curves. Samples outside the proposed pit were removed, along with samples with a P80 less than 60 µm and greater than 120 µm and those with high head grades (above 4 g/t Au or 20 g/t Ag). Samples with silver residues below the detection level of 0.5 g/t (unless the recovery was above 70%) and samples with gold recoveries below 60% were also removed.

 

 

13-44


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The filtered gold and silver residues are plotted as a function of head grade in Figure 13-17 and Figure 13-18, respectively. The Non-CAP curves do not include data from the Intrepid Zone as the numbers of samples tested per tonne of material is considerably higher than the other zones and might influence the recovery curves. Given that Intrepid Zone will be blended at low tonnage rates and appears to behave similarly to Non-CAP material, it is not anticipated that the Intrepid Zone samples will have any impact on the Non-CAP recovery curve.

 

LOGO

Figure 13-17: Gold Residue vs. Head Grade (Variability Tests)

 

 

13-45


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 13-18: Silver Residue vs. Head Grade (Variability Tests)

Figure 13-17 shows that the CAP Zone has considerably higher gold residues than noted in the Non-CAP Zones at the same head grade. No noticeable difference in silver residues was noted between the CAP and Non-CAP Zones.

 

13.8.8 Diagnostic Leach Testwork

Due to the lower gold recovery observed in the CAP Zone samples, and a small percentage of the non-CAP Zones samples, diagnostic leaches were performed on tailings from three (3) ODM and three (3) CAP samples. The objective of the diagnostic leach is to determine the nature of the residual gold from leach tests.

The diagnostic leach is composed of three (3) leaches:

 

 

Intensive Cyanide Leach: Extraction of gold that is readily available and is an indication that more retention time was required to complete reaction;

 

 

Hydrochloric Acid (HCl) Leach followed by Intensive Cyanide Leach: Extraction of gold that is associated with pyrrhotite, calcite, ferrites, etc. This is done by leaching the tailings using hydrochloric acid to dissolve the pyrrhotite and other minerals, then performing the intensive cyanide leach to extract the liberated gold; and

 

 

13-46


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

Aqua Regia Leach: Extraction of gold associated with or encapsulated by sulphide minerals such as pyrite and arsenopyrite.

The final residue from these leaches are considered to be locked in silicates or associated with fine sulphides that are locked in silicates.

The results from the leaches indicated that most of the residual gold in these samples is associated with pyrite, arsenopyrite or other difficult to leach sulphide minerals for both the CAP and ODM samples. The amount of the residual gold recovered by the aqua regia leach was estimated to be between 62% and 92%. Little to no gold was readily recoverable using intensive cyanide leaching, with four (4) of the six (6) samples having gold pregnant leach solution (PLS) tenors below the detection level and the other two (2) being at the detection level. Higher percentages of the residual gold were recovered using the HCl leach followed by intensive cyanide leach, with approximately 8% to 24% of the residual gold being leached using this method. Three (3) of the six (6) samples had final residual gold below detection limit (0.02 g/t) while the other three (3) samples were measured at 0.02 g/t.

 

13.8.9 Mercury Assays

Mercury assays were performed on two composite samples, measuring mercury levels in the feed, residue, loaded carbon and barren solution streams after undergoing leaching and gold adsorption (CIP). The objective of the testwork was to determine if any mercury leached into solution and adsorbed onto the carbon. All assays were below detection level except for one carbon reading, which had an assay of 0.06 g/t mercury.

 

13.9 Cyanide Destruction Testwork

The SO2/air cyanide destruction process was investigated on three (3) composites: Initial Pit, Remaining-Life-of-Mine and Intrepid Zone. The Intrepid Zone sample was tested after completion of the main pit testwork. The first series of tests on the Intrepid Zone sample yielded high residual cyanide levels, however a repeat of the test showed results in line with those from the main pit samples. One (1) large bulk cyanide destruction and three (3) continuous tests were conducted for each composite.

The cyanide testwork results are presented in Table 13-31.

 

 

13-47


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 13-31: Cyanide Destruction Testwork Results

 

         Pulp
Density
     Retention
Time
     Solution Phase      Reagent Addition  
               pH      CNT      CNWAD      Cu      Fe      g/g CNWAD  

Sample

       %      Min     

 

     mg/L      mg/L1      mg/L2      mg/L      mg/L      SO2      Lime      Cu  

Initial Pit

 

Feed

     —           —           10.7         152         117         —           9.4         1.8         —           —           —     
 

Batch

                                
 

CND 3 

     50         90         8.6         —           —           <0.1         —           —           7.52         3.48         0.13   
 

Continuous

                                
 

CND 3-1 

     50         75         8.6         3.1         0.19         0.40         0.08         0.10         5.33         3.33         0.12   
 

CND 3-2 

     50         81         8.6         4.2         0.49         0.67         0.47         0.43         5.28         2.57         0.00   
 

CND 3-3 

     50         80         8.6         5.2         0.12         0.12         0.73         0.58         4.66         1.89         0.00   

Remaining Life of Mine

 

Feed

     —           —           11.1         128         123         —           11.0         —           —           —           —     
 

Batch

                                
 

CND 4 

     50         180         8.5         —           —           0.4         —           —           12.7         14.9         0.24   
 

Continuous

                                
 

CND 4-1 

     50         88         8.5         3.5         <0.1         0.38         0.07         0.10         4.46         4.47         0.23   
 

CND 4-2 

     50         85         8.5         3.9         <0.1         0.25         <0.05         0.13         4.17         6.71         0.25   
 

CND 4-3 

     50         99         8.5         5.8         0.13         0.29         0.10         0.52         4.24         1.79         0.00   
 

Feed

     —           —           10.7         151         77.4         —           20.0         2.22         —           —           —     

Intrepid Zone

 

Batch

                                
 

CND 2 

     50         150         8.6         —           —           0.26         —           —           11.9         7.68         0.13   
 

Continuous

                                
 

CND 2-1 

     50         58         8.5         0.13         <0.1         4.1         18.0         0.20         4.64         2.36         0.13   
 

CND 2-1 

     50         116         8.6         0.11         <0.1         0.94         7.30         0.20            
 

CND 2-2 

     50         58         8.5         <0.1         <0.1         0.45         5.10         0.30            
 

CND 2-2 

     50         116         8.5         <0.1         <0.1         <0.1         1.10         0.20         5.69         3.64         0.12   

 

1. 

By analytical assay.

2. 

By picric acid.

The results showed that this process is effective at lowering the weak acid dissociable cyanide (CNWAD) levels to well below 5 ppm. The average reagent consumptions were 4.7, 3.5 and 0.1 g/g CNWAD for SO2, lime and copper for the main pit, respectively. The reagent consumptions for the Intrepid Zone sample were comparable to these values. These consumptions are considered to be in agreement with standard industrial practices.

 

13.10 Carbon-in-Pulp Modelling

Carbon-in-Pulp (“CIP”) modelling work was performed to validate the design of the CIP circuit. This technique is usually used for modelling of conventional CIP circuits; however, it has been modified to model the kinetics of a carousel-style pump cell CIP circuit. Only gold is modelled by SGS.

The Initial Pit, Remaining-Life-of-Mine and Intrepid Zone master composites were used for the CIP modeling testwork.

 

 

13-48


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The isotherms from the testwork are presented in Figure 13-19.

 

LOGO

Figure 13-19: CIP Modeling Isotherms

Using the isotherms, it is possible to model the kinetics of gold adsorption onto carbon in CIP. The adsorption kinetics are modelled using a kK value that is the product of the model output kinetic constant (k) and the model output equilibrium constant (K). The kK values from the testwork were 69, 79 and 90 for the Initial Pit, Remaining-Life-of-Mine and Intrepid Zone composites, respectively. These values are slightly lower than the reference value of 100 which is usually used as a cut-off from slow to fast kinetics.

Modeling was performed by SGS to investigate the effect of number of CIP tanks, frequency of carbon movement and size of CIP tanks on adsorption efficiency. The simulations yielded solution losses of between 0.007 to 0.035 mg/L, depending on the configuration. The results indicated that a 7- or 8-tank configuration is required to achieve high gold adsorption efficiency and that the ability to transfer carbon every day is beneficial. Based on these results, the CIP circuit was designed to have seven (7) tanks and the stripping circuit sized to be able to strip and regenerate 100% of the carbon every day.

 

 

13-49


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

It should be noted that the numbers from this model are considered to be a worst case scenario and conservative. It is not recommended to use these numbers for the financial analysis of a project, but rather for sizing the equipment. It was recommended that a constant residual solution gold tenor of 0.007-0.008 mg/L be used for the financial analysis based on the kinetics observed from the three (3) composites.

 

13.11 Thickener Sizing Testwork

 

13.11.1 Flocculant Screening

Flocculant screening was performed by a flocculant supplier, prior to performing sedimentation rate testwork. This was to ensure that all of the sedimentation tests performed by three (3) thickener suppliers were done using the same basis. Pre-leach and pre-detox thickener feed material were tested using two (2) samples: an Initial Pit composite and a Remaining-Life-of-Mine composite. The target grind size for the samples was a P80 of 75 µm.

Four (4) different flocculants were tested and are presented in Table 13-32.

Table 13-32: Flocculant Description

 

          Molecular Weight      Charge Density  

Flocculant

   Charge    (106 Dalton)      (mol %)  

Flocculant 1

   Anionic      ~13-16         5

Flocculant 2

   Anionic      ~13-16         10

Flocculant 3

   Non-ionic      ~9-11         Low   

Flocculant 4

   Anionic      ~14-17         20

The testwork results indicated that the non-ionic flocculant (Flocculant 3) had the most consistent performance in terms of settling rates and overflow clarity. It was also noted that Flocculant 1 showed fairly good performance; however, Flocculants 2 and 4 did not meet requirements. Flocculant 2 had poor overflow clarity for several of the samples, while Flocculant 4 had little effect on either settling rates or overflow clarity. The results clearly indicate that the flocculant selected should have a low charge density and be non-ionic or slightly anionic. It was determined that the sedimentation testwork would be performed with the non-ionic Flocculant 3 (or equivalent).

 

 

13-50


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

It was also noted that dual addition of flocculant was required for certain samples to achieve acceptable overflow clarity. Furthermore, a pH of 10.5 or higher significantly improved the settling rates and overflow clarity.

 

13.11.2 Sedimentation Testwork

Sedimentation testwork was performed at three (3) different supplier laboratories to size the pre-leach and pre-detox thickeners as there is often a significant degree of variation between the different laboratories and methods.

The sedimentation testwork results are presented in Table 13-33.

Table 13-33: Sedimentation Testwork Results

 

    

Description

   Units   Supplier A      Supplier B      Supplier C

Sample

        Pre-
Leach
     Pre-
Detox
     Pre-
Leach
     Pre-
Detox
     Pre-
Leach
   Pre-Detox

Design Feed Rate (Dry)

   t/h     951         951         951         951       951    951

Initial Pit

  

Settling Rate

   t/h/m2     0.65         0.86         0.90         0.90       0.61 – 1.05    0.61 - 1.05
  

Rise Rate

   m/h     <7         <7         —           —         3.4 – 5.9    3.4 - 6.0
  

Flocculant Dosage

   g/t     30-35         40-45         40         30       20 – 40    20 - 41
  

Overflow Clarity

   ppm     <200         <200         <150         <150       10 - 86    9 – 57

Remaining-Life-of-Mine

  

Settling Rate

   t/h/
m
2
    —           —           1.0         1.0       0.65 – 1.14    0.65 – 1.11
  

Rise Rate

   m/h     —           —           —           —         3.6 – 6.3    3.6 – 6.1
  

Flocculant Dosage

   g/t     —           —           25         50       19 – 40    29 – 48
  

Overflow Clarity

   ppm     —           —           <200         <200       50 – 145    29 – 205

Recommended Diameter

   m     45         39         39         39       46    46

The results indicated that the recommended thickener diameter is between 39 and 46 m. The lowest settling rates were observed by Supplier C, while the highest were observed by Supplier B. Based on these results, it is recommended that 45 m diameter pre-leach and pre-detox thickeners be used.

It can also be seen that the flocculant dosage requirements were fairly high. The flocculant dosage ranged from 19 to 40 g/t (with an average for the three (3) suppliers of around 32 g/t) and 20 to 48 g/t (with an average for the three (3) suppliers of around 39 g/t). These results were seen consistently across the three (3) supplier laboratories with little variation.

 

 

13-51


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Intrepid Zone Testwork

Static and dynamic settling tests were also performed at SGS on the Intrepid Zone material. The results indicate that the thickening of the material from the Intrepid Zone is relatively slow. This was noted by the solids loading rates of 0.42 and 0.61 t/h/m2. The flocculant addition rate (25 g/t average in the dynamic tests and 20 g/t in the static tests) is in-line with industrial practices. Good overflow clarity was noted in both the static and dynamic tests. The Intrepid Zone material is not expected to have an impact on design.

 

13.12 Rheology

Rheology testwork was performed on the Initial Pit and RLOM composites using a concentric cylinder rotational viscometer (“CCRV”). The objective of the testwork was to determine the yield stresses at different percent solids for an unsheared and sheared sample. The yield stress is the minimum force that is required to cause the fluid to flow. Using these values, it is possible to determine the Critical Solids Density (“CSD”). The CSD is the density at which an incremental increase in the solids density causes a significant increase in yield stress, or a significant decrease in flowability of the slurry. The CSD is also considered to be a prediction of the maximum underflow solids density that can be achieved by a commercial thickener for the material and is considered to be the optimum thickener underflow percent solids.

The rheology results are presented in Figure 13-20 and Figure 13-21.

 

LOGO

Figure 13-20: Initial Pit Composite Yield Stress vs. Solids Density

 

 

13-52


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 13-21: Remaining-Life-of-Mine Composite Yield Stress vs. Solids Density

It can be seen that the CSD was 62.2% w/w and 63.5% w/w for the Initial Pit and RLOM composites, respectively. These values are in line with the design of the pre-leach and pre-detox thickener underflow densities of 61% and 60%, respectively.

 

13.13 Linear Screen Sizing Testwork

Testwork was performed at a supplier laboratory to determine the sizing of the trash and safety linear screens. This was done by determining the flux rate (m3/m2 /h) at different feed percent solids. The results are presented in Table 13-34.

Table 13-34: Linear Screen Sizing Testwork Results

 

Description

  

Units

   Trash Screen      Safety
Screen
 

Feed Volume

   m3/h      2,777         1,296   

% Solids

   % w/w      28         28         28         28         50   

Screen Aperture

   µm      600         600         700         700         600   

Draining Rate (Flux Rate)

   m3/m 2/h      88         88         98         98         51   

Required Screen Area

   m2      31.6         31.6         28.3         28.3         25.3   

Design Safety Factor

   %      20         20         20         15         20   

Required Screen Area

   m2      37.9         37.9         34.0         32.6         30.4   

Number of Screens

        1         2         1         1         1   

Screen Size

   m2      40         20         40         40         32   

 

 

13-53


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The testwork indicated a flux rate to the trash screen of 88 and 98 m3/m2/h for screen apertures of 600 and 700 µm, respectively. The safety screen indicated a flux rate of 51 m3/m2/h for a 600 µm screen aperture. Based on these results, two (2) 20 m2 trash screens and one (1) 32 m2 safety screen were selected with screen apertures of 600 µm.

 

13.14 Environmental Testwork

AMEC Environment and Infrastructure is conducting environmental geochemical characterization of selected samples representative of the mine rock and overburden in the vicinity of the proposed Rainy River Gold Project open pit and tailings deposition areas.

Table 13-35 summarizes the geochemical testwork. To date, testing has been carried out on three (3) simulated tailings materials, and a total of 659 deposit-wide mine rock samples, of which 366 represent in-pit non-ore mine rock.

Table 13-35: Summary of Geochemical Environmental Testing

 

Analytical Procedure

   Mine Rock      Overburden      Tailings  

Static Testing

        

Acid-base Accounting1

     362         3         6   

Net Acid Generation test

     176         3         6   

Metals Content (aqua-regia ICP)

     362         3         6   

Short-term Leach testing (SFE2)

     74         2         6   

Mineralogy (X-Ray Diffraction)

     39         0         6   

Kinetic Testing

        

Humidity Cell

     20         0         6   

Field Cell

     7         0         0   

 

1. 

Methodology: Sobek with siderite correction, modified Sobek, total inorganic carbon and sulphur speciation.

2. 

SFE = 24 hour shake flask extraction at 3:1 deionized water to solid.

Geochemical studies and bock modeling results indicate that approximately one-half (51%, or 163Mt) of the mine rock waste is potentially acid generating. Results of the tailings analyses indicate a risk for acidic drainage in the future if not appropriately managed. Generally, metal contents in waste materials are typical for their rock types and the risk for metal leaching under neutral conditions appears to be low. However, testing on tailings samples has indicated a potential for release of cadmium and zinc. Laboratory humidity cell tests on mine rock and tailings and in-field barrel tests on mine rock are currently being undertaken to evaluate the long-term acid generation potential and metal leaching characteristics of these materials.

 

 

13-54


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

13.15 Gold and Silver Recovery Curves

Gold and silver recovery curves were developed for the Financial Analysis based on the leaching and gravity recovery results presented in Sections 13.6 and 13.8.7 and the proposed whole rock leach flowsheet, discussed in Chapter 17. The recovery curves were developed using the following format:

 

LOGO

Where:

 

 

RecAu is the overall gold recovery;

 

 

RecAg is the overall silver recovery;

 

 

xAu is the gold head grade;

 

 

xAg is the silver head grade;

 

 

A(Au Res) is the gold residue;

 

 

A(Ag Res) is the silver residue;

 

 

B(Au Gravity Rec) is the gold gravity recovery;

 

 

B(Ag Gravity Rec) is the silver gravity recovery;

 

 

CIPeff-Au is the CIP adsorption efficiency for gold;

 

 

CIPeff-Ag is the CIP adsorption efficiency for silver;

 

 

EWeff is the CIP-stripping solution electrowinning (“EW”) recovery; and

 

 

ILeff is the intensive cyanidation and dedicated electrowinning efficiency.

The residue and gravity recovery curves were developed based on grade-recovery variability testwork and divided into CAP and non-CAP Zones (non-CAP Zones include ODM, Z-433, NZ, HS and Intrepid). These curves are presented in Table 13-36.

 

 

13-55


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 13-36: Residue and Gravity Recovery Curves

 

LOGO

The CIPeff-Au was calculated using a fixed discharge solution gold tenor of 0.007 mg/L based on testwork performed by SGS. Testwork for silver modeling was not performed, and therefore the model was based on discussions with CIP suppliers. The silver adsorption efficiency was estimated to be 96.6%. EWeff and ILeff values were assumed to be 100% since all residual solids and solutions from these circuits are recycled to the process.

Using the inputs presented above, the gold and silver recovery curves were simplified and are presented in Table 13-37.

Table 13-37: Simplified Gold and Silver Recovery Curves

 

LOGO

The expected gold and silver recoveries as a function of head grade (gold or silver, respectively) are presented in Table 13-38.

 

 

13-56


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 13-38: Gold and Silver Recoveries vs. Head Grade

 

      Gold
Recovery
     Silver
Recovery
 

Head Grade (g/t)

   Non-
CAP
     CAP      Non-
CAP
     CAP  

0.2

     72.8         72.1         68.2         72.4   

0.4

     82.3         73.6         67.9         71.7   

0.6

     86.2         74.1         67.6         71.0   

0.8

     88.5         74.2         67.4         70.3   

1

     89.9         74.3         67.1         69.6   

1.2

     91.0         74.4         66.8         68.9   

1.4

     91.8         74.4         66.5         68.2   

1.6

     92.4         74.4         66.2         67.5   

1.8

     92.9         74.4         65.9         66.8   

2

     93.4         74.4         65.6         66.1   

2.5

     94.2         74.4         64.9         64.3   

3.0

     94.8         74.4         64.2         62.6   

3.5

     95.3         74.4         63.5         60.8   

4.0

     95.6         74.3         62.8         59.1   

4.5

     95.9         74.3         62.1         57.3   

5.0

     96.2         74.3         61.4         55.6   

As previously noted, it can be seen that the gold recovery for the CAP Zone is considerably lower than the non-CAP Zones. The annual ratio of Non-CAP and CAP material will have to be an input for the financial analysis to calculate the average gold recovery by year. The silver recovery was identical for both the non-CAP and CAP Zones and is independent of the head grade.

 

13.16 Testwork Interpretation

The results from the SGS testwork are the basis for the mineral reserve estimate and Feasibility Update Study. Based on a trade-off study, it was determined that the whole rock leaching option with gravity separation was the most economical alternative and was therefore used as the basis for the Feasibility Update Study. The main reason for this selection was the significant amount of energy associated with regrinding the flotation concentrate and the high cyanide consumption in the flotation concentrate leaching, in addition to risk associated with ultrafine grinding of this material. All subsequent testwork was based on cyanide leaching of the gravity tailings.

The grinding tests indicate that significant variation exists in the mineral hardness in the ODM Zone, and that the overall deposit is considerably harder than previously indicated in the December 2011 PEA. The design A x b value was modified from 34.0 to 24.2, resulting in an

 

 

13-57


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

increase of close to 50% in terms of power requirements for the SAG mill. The extensive grinding testwork campaign has allowed for definition of the overall hardness of each zone and indicated that there are several portions of the deposit that will have high energy requirements and this will be reflected in the design of the process plant. The strong correlation between the four (4) methods used to size the grind circuit provides a good level of confidence in the sizing of the SAG and ball mill.

Testwork was performed on samples from the Intrepid Zone after completion of the testwork on the main pit. The objective of this testwork program was to confirm that the Intrepid Zone could be treated using the proposed flowsheet and would not have a significant impact on the design of the plant when blended at low tonnages. The Non-CAP Zone recovery curve was determined during the main pit testwork program without the inclusion of the Intrepid Zone material. The test work performed on the Intrepid Zone indicates that the material should not impact design if blended at low tonnage rates. Given the high silver grade of this material, it is not recommended to be blended at high tonnage due to downstream effects on CIP and elution.

A gravity circuit was included in the plant design due to the good GRG results (51.2 and 59.3) along with the moderate gravity recoveries noted for the Non-CAP zones during the variability testwork (average of 25.7%).

The process is expected to yield an overall gold recovery of approximately 90 to 91% and a silver recovery of around 66 to 67% over the life-of-mine without considering solution losses. When considering solution losses, the gold recovery decreases by approximately 0.4% while the silver recovery drops to approximately 64%. The grind size chosen for this study was 75 µm, based on a cost versus revenue study performed by BBA. The gold recovery varies significantly throughout the deposit and the CAP Zone has considerably lower gold recoveries than the other zones. When calculating gold recoveries, the material has been divided into Non-CAP zones (ODM, Z-433, NZ, HS and Intrepid) and CAP Zone.

As per the mine plan schedule, CAP Zone material, when mined, is placed in the low grade ore stockpile and therefore only treated towards the end of the mine life. No CAP Zone material is processed in Years 1 - 8.5, resulting in an elevated recovery for those years.

 

 

13-58


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Average gold and silver recoveries are based on the mine plan and shown in Table 13-39.

Table 13-39: Average Yearly Gold and Silver Recoveries

 

     Gold      Silver  

Years

   Au Head
Grade
(g/t)
     Au
Recovery
(%)
     Ag Head
Grade
(g/t)
     Ag
Recovery
(%)
 

1

     1.44         91.9         2.13         65.5   

2

     1.48         92.1         2.00         65.7   

3

     1.45         92.0         3.80         63.1   

4

     1.43         91.9         3.56         63.5   

5

     1.38         91.7         4.92         61.5   

6

     1.46         92.0         4.27         62.4   

7

     1.50         92.1         2.74         64.6   

8

     1.57         92.3         2.15         65.5   

9

     1.21         91.0         2.04         65.6   

10

     0.68         87.3         1.64         66.2   

11

     0.60         86.2         2.59         64.8   

12

     0.40         82.3         2.81         64.5   

13

     0.33         80.2         2.11         65.5   

14

     0.55         74.2         2.33         64.8   

LOM

     1.12         90.6         2.80         64.1   

 

 

13-59


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

14. MINERAL RESOURCE ESTIMATION

 

14.1 Introduction

The resource estimation work was completed in Toronto by Dorota El-Rassi, P.Eng (PEO #100012348), assisted by Mr. Bob Kusins, P.Geo. (APGO #0196) and under the supervision of Glen Cole, P.Geo. (APGO #1416), all “independent qualified persons”, as this term is defined in National Instrument 43-101.

The Mineral Resource Statement presented herein represents the ninth (9th) mineral resource evaluation prepared for the Rainy River Project since 2003 that includes, for the first time, the Intrepid Zone. The Intrepid Zone is part of the Rainy River Project, located approximately one kilometer east of the main Rainy River deposit.

The Rainy River Project contains volcanic hosted gold-rich polymetallic sulphide mineralization of hydrothermal origin that is crosscut by a small zone of magmatic copper-nickel sulphide mineralization enriched in platinum group metals. The Mineral Resource Statement is reported on the basis of gold and silver content only, although locally significant silver is also present. The consolidated Mineral Resource Statement for the Rainy River Project reports gold and silver grades only. The mineral resources for the copper-nickel sulphide mineralization enriched and silver enriched zones are reported separately because they contain more substantial base metal and silver mineralization, respectively.

This section describes the resource estimation methodology used by SRK and summarizes the key assumptions and parameters used to prepare the ninth (9th) Mineral Resource Statement for the Rainy River Project.

In the opinion of SRK, the resource evaluation reported herein is a reasonable representation of the mineral resources found in the Rainy River Project at the current level of sampling. The mineral resources have been estimated in conformity with generally accepted CIM “Estimation of Mineral Resource and Mineral Reserves Best Practices” guidelines and are reported in accordance with Canadian Securities Administrators NI 43-101. Mineral resources are not mineral reserves and do not have demonstrated economic viability. There is no certainty that all or any part of the mineral resource will be converted into a mineral reserve.

 

 

14-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

14.2 Resource Estimation Procedures

The evaluation of mineral resources for the entire Rainy River Project involved the following procedures:

 

 

Database compilation and verification;

 

 

Construction of wireframe models for major lithological units, using stratigraphy, structural trends and an array of appropriate geochemical indices;

 

 

Definition of geostatistical resource domains;

 

 

Data conditioning (compositing and capping) for geostatistical analysis and variography;

 

 

Selection of estimation strategies and estimation parameters;

 

 

Block modeling and grade interpolation;

 

 

Validation, classification and tabulation;

 

 

Assessment of “reasonable prospects for economic extraction” and selection of reporting cut- off grades; and

 

 

Preparation of Mineral Resource Statement.

 

14.1 Resource Database

Exploration data used to evaluate the mineral resources for the Rainy River Project were provided by Rainy River as a set of Microsoft Excel files containing drilling information (drill collars, surveys, assays and lithological logging) for 1,665 core boreholes (742,424 m) drilled by Rainy River and Nuinsco, the previous Project operator. The database includes 230 boreholes (79,575 m) drilled within the Intrepid Zone during the period from 1996 to August 16th, 2013, 237 boreholes (95,760 m) drilled in 2012, 388 boreholes (188,588 m) drilled by Rainy River in 2011 and early 2012, 165 boreholes (84,134 m) drilled by Rainy River in 2010, 446 boreholes (245,016 m) drilled by Rainy River between 2005 and 2009, and 199 boreholes (49,351 m) drilled by Nuinsco between 1994 and 2004.

All exploration information is located using the local UTM grid (NAD 83 datum, Zone 15). Resource modelling was conducted in this UTM coordinate space.

A topographic surface was also supplied to SRK by Rainy River in DXF format. Upon receipt of the digital drilling data, SRK performed the following validation steps:

 

 

14-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

Checked minimum and maximum values for each quality value field and confirmed/edited those outside of expected ranges;

 

 

Checked for inconsistencies in lithological unit terminology and/or gaps in the lithological table; and

 

 

Checked for gaps, overlaps, and out of sequence intervals for both assays and lithology tables.

SRK has previously reviewed analytical quality control data produced by Rainy River for the periods prior to December 2011 (documented in previous technical reports). For this Study, SRK reviewed the analytical quality control data produced for the main Rainy River deposit between December 2011 and June 2012. For the Intrepid Zone, analytical quality control data was considered for the period from December 2011 to June 2013. The analytical quality control data produced during this period is summarized on bias charts and precision plots presented in Appendix D.

Each interval in the assay table was assigned a new rock code value based on the location of the interval mid-point relative to the modelled gold mineralization. The coded assay data were extracted for statistical analysis.

The database used to estimate the mineral resources was audited by SRK. SRK is of the opinion that the current drilling information is sufficiently reliable to interpret the outlines of the gold mineralization with reasonable confidence, and that the assay data are sufficiently reliable to support mineral resource estimation.

Leapfrog™ software was used to guide geology and mineralization modelling. Gemcom GEMS™ software was used to construct the geological solids, prepare assay data for geostatistical analysis, construct the block model, estimate metal grades and tabulate mineral resources. The Geostatistical Software Library™ (GSLib) family of software and GEMS were used for geostatistical analysis and variography. Conceptual pit optimization work to test the “reasonable prospects” for economic extraction was completed by BBA with MineSight software.

 

 

14-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

14.3 Solid Body Modelling

 

14.3.1 Introduction

SRK and Rainy River constructed a series of 3D wireframes to constrain the extent of the gold mineralization, considering structural features, lithology, alteration, geochemical indices, as well as grade trends. Rainy River generated gold mineralization wireframes for Zone 433, as well as the CAP and HS Zones, whereas SRK generated gold mineralization wireframes for all the other Zones. From these wireframes, resource domains were constructed and used as hard boundaries to constrain grade estimation. The resource domains were updated by SRK to consider the 2012 drilling information (Figure 14-1). The geological interpretation and resource domains have not changed significantly relative to the previous resource model, with the exception of the New Zone, which was amalgamated with the HS Zone. With the discovery of the Intrepid Zone, Rainy River, with SRK’s assistance, constructed a separate 3D domain model expanding the Rainy River Project to the east (Figure 14-2).

The Rainy River Project was subdivided into 13 separate resource domains: six (6) main Zones (ODM/17, 34, 433, HS, CAP, Western), the Intrepid Zone, the Silver Zone; and five (5) isolated pockets outside the main Zones (Table 14-1). The 3D shapes for the six (6) main Zones are illustrated in Figure 14-3. The ODM/17, 433 and Intrepid Zones were subdivided into three (3) grade subdomains (Low, Medium and High grade).

 

 

14-4


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-1: Rock Codes in the Rainy River Project Block Model

 

Zone

  

Domain

   Domain Code  

ODM/17

   Low Grade (below 0.5 g/t gold)      101 to 102   
   Medium Grade (between 0.5 and 0.9 g/t gold)      110 to 114   
   High Grade (above 0.9 g/t gold)      120 to 123   

Zone 34

        200   

Zone 433

   Low Grade (below 0.5 g/t gold)      300   
   Medium Grade (between 0.5 and 0.9 g/t gold)      310   
   High Grade (above 0.9 g/t gold)      320   

HS

        400   

CAP

        500   

Mineralization outside Main Zones

     601 to 605   

Western

        800   

Intrepid

   Low Grade (between 0.3 and 0.8 g/t gold)      100   
   Medium Grade (between 0.8 and 2.0 g/t gold)      200   
   High Grade (above 2.0 g/t gold)      300   

Silver

        901 to 904   

 

LOGO

Figure 14-1: Location of New Boreholes Drilled on the Main Rainy River Deposit

 

 

14-5


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 14-2: Location of Drill Collars and High Grade Subdomain for the Intrepid Zone

 

LOGO

Figure 14-3: Isometric View of the Rainy River Mineralization Wireframes Modelled by SRK with

Borehole Data (View looking towards the West)

 

 

14-6


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The methodology adopted for modelling the main zones of gold mineralization are summarized in the following paragraphs.

 

14.1.1   The ODM/17 Zone

The ODM/17 Zone (Figure 14-1 and Figure 14-3) is interpreted as a generally east-west trending, south-west plunging zone of mineralization. Numerous north-north-east striking faults crosscut the zone. Small offsets along the Beaver Pond Fault were modelled. However, at the scale of the zone, none of these faults were used as hard boundaries. Numerous alteration indices, as well as gold grade shells, suggest a stacked pattern of slightly oblique zones that resemble tight folds. The general outline of the ODM/17 Zone was based on the broad extent of a sericite index (cationic based) larger than 0.7. The outlines initially were guided by a 3D model of the sericite index and a 0.2 g/t gold grade shell.

The hanging wall of the zone coincides with the top of a fragmental volcaniclastic unit that hosts much of the ODM/17 Zone. This rock package is separated from mafic volcanic and intermediate to felsic volcanic rock to the south by a curved but generally east-west trending magnetic lineament. This lineament was modelled and used as the hanging wall boundary of the ODM/17 Zone. This contact becomes cryptic to the east, but was extended parallel to the magnetic lineament. The ODM/17 domain was defined on inclined sections oriented perpendicular to the plunge (azimuth 233 degrees plunge of 47 degrees). The overall ODM/17 Zone was subdivided into three (3) grade subdomains based on the following divisions:

 

• High Grade:

   Greater than 0.9 g/t gold;

• Medium Grade:

   Between 0.5 and 0.9 g/t gold, and

• Low Grade:

   Below 0.5 g/t gold.

The ODM/17 Zone was therefore subdivided into three (3) resource domains that were considered for resource estimation. The geometry of the Medium and High grade subdomains is either parallel to the south-dipping footwall of the overall domain or slightly oblique to it. These are consistent with the geometry of high strain zones bounding the subdomains and the foliation orientation within them.

 

 

14-7


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

14.1.2 The 433, HS and New Zones

The 433 and HS Zones (Figure 14-1 and Figure 14-3) form two (2) of several gold occurrences in the footwall of the ODM/17 Zone, hosted by massive and fragmental felsic to intermediate rock. The boundaries of these zones are not as well defined as for the ODM/17 Zone, but the gold mineralization plunge is similar. Accordingly, the boundaries for the 433 and HS Zones were modelled on the same inclined sections. The sericite index does not clearly define these zones. In the case of the 433 Zone, chalcopyrite is associated with gold mineralization and is a good indicator of the boundaries of that Zone.

The boundaries were modelled using a copper-to-zinc ratio of 0.8. Similarly to the ODM/17 Zone, the overall 433 Zone was also subdivided into three (3) grade subdomains based on the following divisions:

 

• High Grade:

   Greater than 0.9 g/t gold;

• Medium Grade:

   Between 0.5 and 0.9 g/t gold, and

• Low Grade:

   Below 0.5 g/t gold.

The 433 Zone was therefore subdivided into three (3) resource domains that were considered for resource estimation.

No geochemical or lithological criteria successfully outline the HS Zone. The HS Zone was defined with consideration of the lithogical model and by using the interpreted extent of a 0.2 g/t gold threshold (based on 3 m composites) and guided by 0.2 g/t gold Leapfrog™ shells.

The additional infill drilling information suggests that the former New Zone is part of the HS Zone. Accordingly, the two (2) were combined, effectively increasing the size of the HS Zone considerably compared to that in earlier models.

The CAP Zone

The CAP Zone occurs in the hanging wall of the ODM/17 Zone (Figure 14-1 and Figure 14-3 within the upper, predominantly mafic volcanic sequence. On the surface, the zone is associated with a number of quartz-carbonate vein sets and south-dipping shear zones. The latter post-date the foliation and dip both more steeply and more shallowly than the south-dipping foliation. The orientation of the quartz-carbonate veins is highly variable. North-east to north-west striking sulphide veinlets anastomose across several surface outcrops. In core individual high-grade gold intersections are associated with increased sulphide mineralization (particularly chalcopyrite) within and adjacent to shear zone hosted quartz-carbonate veins.

 

 

14-8


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Low-grade gold mineralization in intermediate rocks within the CAP Zone is similar to the ODM/17 Zone, with a noticeably shallower plunge to the south-west. On north-south vertical sections, high-grade gold intersections are aligned along south-dipping planes. In plan view, high-grade gold intersections show continuity along a west-north-west strike. Low-grade mineralization shows good continuity when observed in cross-sections oriented perpendicular to the slightly shallower plunge. The CAP Zone domain was modelled on vertical sections based on a 0.2 g/t gold threshold guided by this preferred geometry.

Western Zone

Gold mineralization appears sporadic in the Western Zone of the Rainy River Project, but can be subdivided into at least two (2) stages of mineralization:

 

 

Early (low- to moderate-grade) gold mineralization associated with sulphide (pyrite- sphalerite-chalcopyrite-galena) stringers and veins and disseminated pyrite in quartz-phyric volcaniclastic rocks and conglomerate; and

 

 

Late (high-grade) gold mineralization associated with quartz-carbonate-pyrite-gold veins and veinlets, and rarely as native gold veins.

This hybrid mineralization consists of an early gold-rich volcanogenic sulphide mineralization overprinted by shear-hosted mesothermal gold mineralization. Gold mineralization is commonly associated with increased sericite and chlorite alteration. Mineralization also appears to have a strong association with strain. Increased strain, characterized by kink folds, boudinage, and strong fabric development, is commonly associated with an increased gold grade. However, at very high strain, mylonitic textures appear and the gold grade is reduced. The Western Zone can be interpreted as a north-west extension of the ODM/17 Zone. The domain was defined on vertical sections guided by 0.2 g/t gold Leapfrog™ shells. At present, gold mineralization in the Western Zone appears erratic and discontinuous; infill drilling would be required to improve grade continuity.

 

 

14-9


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The 34 Zone

The 34 Zone was modelled by Rainy River and modified by SRK using drilling logging data and Leapfrog™. The model was used to constrain mineral resource estimation.

Silver Zone

The Silver Zone occurs in the footwall of the ODM/17 Zone in dacitic tuff and breccias, immediately adjacent to a high strain Zone located at the northern contact of the ODM/17 Zone. The Zone plunges to the south-west in similar orientation to the ODM/17 Zone, and is associated with centimetre-scale sulphide bearing quartz veinlets that typically contain dendritic native silver inclusions. The Silver Zone domain was outlined by Rainy River using a 19 g/t silver cut-off grade (3.0 m composites; less than 4.0 m waste), on inclined cross-sections perpendicular to the plunge of the silver mineralization.

Intrepid Zone

The Intrepid Zone is located one (1) kilometer east of the ODM17 Zone. Similarly to the main Rainy River Project, the Intrepid Zone contains volcanic hosted gold-rich sulphide mineralization of hydrothermal origin. Rainy River, with SRK’s assistance, constructed a series of three-dimensional wireframes to define the limits of the gold mineralization. The Intrepid Zone was modelled on 17 vertical sections spaced at 25 metres. Three (3) nested grade domains were defined based on the gold and silver content:

 

• High Grade:

   Above 2.0 g/t gold equivalent;

• Medium Grade:

   Between 0.8 and 2.0 g/t gold equivalent, and

• Low Grade:

   Between 0.3 and 0.8 g/t gold equivalent.

 

14.4 Compositing

Most of the core assay samples were taken at 1.5 m intervals. A histogram of the raw assay lengths inside the mineralized envelopes in the Main Rainy River deposit is provided in Figure 14-4. For geostatistical analysis, variography and grade estimation, raw assay data were composited to equal 1.5 m lengths. Compositing was completed from entry point of the wireframe, down the hole. Composite residuals that were shorter than 10% of composite length were removed from the data set.

 

 

14-10


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 14-4: Histogram Distribution of Raw Sample Lengths

 

14.5 Evaluation of Outliers

SRK constructed cumulative probability curves for the gold and silver composites within each modelled domain (shown in Figure 14-5). Considering the nature of the statistical distributions of gold assay, SRK is of the opinion that it is necessary to cap high-grade values to limit their influence during grade estimation. The impact of capping was analyzed and capping levels were adjusted for each resource domain (and subdomains therein) and each metal separately. Capping was applied to the composites. Capping levels for gold and silver are summarized in Table 14-2.

 

 

14-11


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-2: Summary of Metal Capping Levels Applied to each Resource Domain

 

      Gold      Silver  

Resource Domain

   Cap (g/t)      Percentile     N capped      Cap (g/t)      Percentile     N capped  

100

     20         99.97     19         100         99.97     20   

MG 110 to 114

     60         99.93     10         120         99.91     13   

HG 120 to 123

     115         99.86     12         80         99.93     6   

200

     3         98.71     6         30         99.35     3   

300

     25         99.97     3         35         99.97     4   

310

     30         99.75     7         40         99.78     6   

320

     70         99.29     7         15         99.19     8   

400

     25         99.94     6         40         99.92     8   

500

     15         99.95     6         70         99.92     9   

Intrepid 100

     5         99.7     6         60         99.7     5   

Intrepid 200

     20         99.6     4         100         99.1     11   

Intrepid 300

     40         99.4     5         225         98.9     9   

601

     30         99.99     8         30         99.87     67   

602

     9         99.98     5         50         99.98     5   

603

     20         99.99     3         150         99.99     4   

604

     10         99.99     9         70         99.98     14   

605

     5         99.98     7         30         99.99     4   

800

     20         99.26     8         55         99.63     4   

901

     0.8         95.42     7         250         97.39     4   

902

     9         96.47     3         80         94.12     5   

903

     4         97.79     3         70         97.79     3   

904

     4         99.52     2         115         99.29     3   

 

 

14-12


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 14-5: Cumulative Frequency Plot for Gold Composites

 

 

14-13


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

14.6 Statistical Analysis and Variography

 

14.6.1 Statistical Analysis

The basic statistics for the composite and capped composite data within all the resource domains for gold and silver are summarized in Table 14-3 to Table 14-6.

The basic statistics for the raw, composited, and capped composited data of the various metals in Domain 200 (34 Zone) are summarized in Table 14-7.

SRK also undertook a domainal statistical analysis of sulphur and calcium extracted from the ICP database. Sulphur and calcium were also interpolated into the block model for use in waste rock characterization and waste management disposal.

The basic statistics for the composite and capped calcium and sulphur composites within the eleven resource domains are summarized in Table 14-8 to Table 14-11.

 

 

14-14


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-3: Basic Statistics for Gold Composites for All Resource Domains

 

Zone

  

Domain

   Subdomain      Count      Minimum      Maximum      Mean      Standard
Deviation
     Sample
Variance
 
   Low      100         74,758         0.00         448.01         0.20         1.77         3.15   
        110         3,337         0.00         61.78         0.72         2.22         4.94   
        111         3,857         0.00         1219.63         1.08         19.82         392.69   
        112         3,490         0.00         110.14         0.87         3.31         10.92   
   Medium      113         2,007         0.00         60.76         0.73         1.93         3.72   
        114         838         0.03         1844.65         3.16         63.83         4073.83   

ODM/17

        115         722         0.00         53.40         1.22         3.00         8.99   
        mg_110_114         14,251         0.00         1844.65         1.02         18.73         350.66   
        120         2,042         0.00         195.28         1.82         6.66         44.33   
        121         3,047         0.00         301.73         2.10         7.65         58.48   
   High      122         3,191         0.00         213.72         2.74         9.57         91.61   
        123         544         0.00         462.03         2.92         21.20         449.48   
        hg_120_123         8,824         0.00         462.03         2.32         9.56         91.39   

Zone 34

   Low      200         465         0.00         26.57         0.35         1.64         2.70   

433

   Low      300         11,553         0.00         60.19         0.27         1.04         1.08   
   Medium      310         2,774         0.00         629.23         1.10         12.30         151.31   
   High      320         986         0.00         2275.98         5.43         75.44         5691.65   

HS

        400         10,276         0.00         249.45         0.48         3.04         9.24   

CAP

        500         11,477         0.00         64.77         0.39         1.13         1.27   

Intrepid

   Low      100         1721         0.01         8.22         0.40         0.60         0.36   
   Medium      200         1159         0.01         84.09         1.39         3.40         11.56   
   High      300         795         0.02         84.20         3.79         6.38         40.70   

600 Series

        601         53,369         0.00         108.06         0.08         0.76         0.58   
        602         30,264         0.00         87.72         0.09         0.67         0.45   
        603         52,241         0.00         104.98         0.08         0.58         0.34   
        604         83,114         0.00         58.55         0.05         0.31         0.10   
        605         38,934         0.00         43.93         0.03         0.33         0.11   

Western

        800         1,078         0.00         324.98         1.15         11.15         124.29   

Silver Zones

        901         153         0.00         4.04         0.23         0.56         0.31   
        902         85         0.11         1039.62         18.75         117.11         13714.41   
        903         136         0.02         19.28         0.95         2.02         4.10   
        904         420         0.00         6.35         0.44         0.70         0.49   

 

 

14-15


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-4: Basic Statistics for Capped Gold Composites for All Resource Domains

 

Zone

  

Domain

   Subdomain      Count      Minimum      Maximum      Mean      Standard
Deviation
     Sample
Variance
 
   Low      100         74,758         0.00         20.00         0.19         0.55         0.31   
        110         3,337         0.00         60.00         0.72         2.20         4.86   
        111         3,857         0.00         60.00         0.76         2.53         6.40   
        112         3,490         0.00         60.00         0.86         2.83         8.04   
   Medium      113         2,007         0.00         60.00         0.73         1.92         3.67   
        114         838         0.03         60.00         0.99         4.00         16.01   

ODM/17

        115         722         0.00         53.40         1.22         3.00         8.99   
        mg_110_114         14,251         0.00         60.00         0.81         2.60         6.76   
        120         2,042         0.00         115.00         1.75         5.08         25.80   
        121         3,047         0.00         115.00         2.02         5.48         30.01   
   High      122         3,191         0.00         115.00         2.64         7.87         61.89   
        123         544         0.00         115.00         2.18         7.72         59.61   
        hg_120_123         8,824         0.00         115.00         2.19         6.52         42.50   

Zone 34

   Low      200         465         0.00         3.00         0.24         0.49         0.24   

433

   Low      300         11,553         0.00         25.00         0.26         0.79         0.63   
   Medium      310         2,774         0.00         30.00         0.83         2.05         4.22   
   High      320         986         0.00         70.00         2.34         7.36         54.14   

HS

        400         10,276         0.00         25.00         0.45         1.11         1.23   

CAP

        500         11,477         0.00         15.00         0.38         0.77         0.59   

Intrepid

   Low      100         1721         0.01         5.00         0.39         0.53         0.28   
   Medium      200         1159         0.01         20.00         1.31         2.07         4.28   
   High      300         795         0.02         40.00         3.65         5.13         26.31   

600 Series

        601         53,369         0.00         30.00         0.08         0.48         0.23   
        602         30,264         0.00         9.00         0.09         0.24         0.06   
        603         52,241         0.00         20.00         0.08         0.32         0.10   
        604         83,114         0.00         10.00         0.04         0.18         0.03   
        605         38,934         0.00         5.00         0.03         0.11         0.01   

Western

        800         1,078         0.00         20.00         0.67         2.01         4.05   

Silver Zones

        901         153         0.00         0.80         0.16         0.20         0.04   
        902         85         0.11         9.00         1.99         2.28         5.20   
        903         136         0.02         5.27         0.78         0.96         0.93   
        904         420         0.00         6.18         0.43         0.66         0.43   

 

 

14-16


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-5: Basic Statistics for Silver Composites for All Resource Domains

 

Zone

  

Domain

   Subdomain      Count      Minimum      Maximum      Mean      Standard
Deviation
     Sample
Variance
 
   Low      100         74,758         0.00         733.61         1.31         5.87         34.50   
        110         3,337         0.00         230.91         3.06         8.85         78.24   
        111         3,857         0.00         99.87         1.29         2.98         8.88   
        112         3,490         0.00         42.00         1.28         2.34         5.45   
   Medium      113         2,007         0.00         99.98         2.54         5.61         31.53   
        114         838         0.00         90.39         4.55         7.73         59.79   

ODM/17

        115         722         0.00         537.98         9.39         31.14         969.39   
        mg_110_114         14,251         0.00         537.98         2.48         9.09         82.54   
        120         2,042         0.00         221.02         4.55         10.53         110.82   
        121         3,047         0.00         114.00         2.11         4.35         18.94   
   High      122         3,191         0.00         66.57         2.21         3.96         15.71   
        123         544         0.00         121.84         2.59         6.21         38.60   
        hg_120_123         8,824         0.00         221.02         2.74         6.42         41.23   

Zone 34

   Low      200         465         0.00         40.19         1.95         4.94         24.38   
   Low      300         11,553         0.00         98.00         0.53         1.69         2.85   

433

   Medium      310         2,774         0.00         99.62         0.79         3.34         11.15   
   High      320         986         0.00         240.25         1.25         8.35         69.71   

HS

        400         10,276         0.00         672.56         0.97         7.04         49.52   

CAP

        500         11,477         0.00         440.33         2.04         6.26         39.25   

Intrepid

   Low      100         1721         0.05         184.77         6.37         8.64         74.64   
   Medium      200         1159         0.05         218.93         15.62         20.08         403.20   
   High      300         795         0.05         463.86         30.54         44.30         1965.51   

600 Series

        601         53,369         0.00         57.63         0.45         1.59         2.54   
        602         30,264         0.00         90.58         0.43         1.64         2.70   
        603         52,241         0.00         476.44         0.59         3.47         12.04   
        604         83,114         0.00         1110.23         0.37         4.41         19.49   
        605         38,934         0.00         151.07         0.36         1.36         1.85   

Western

        800         1,078         0.00         125.35         1.64         7.03         49.36   

Silver Zones

        901         153         0.00         334.11         59.34         67.10         4502.40   
        902         85         0.23         300.52         24.75         39.28         1543.07   
        903         136         0.00         131.98         16.33         19.35         374.29   
        904         420         0.00         204.05         15.86         22.65         512.83   

 

 

14-17


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-6: Basic Statistics for Capped Silver Composites for All Resource Domains

 

Zone

  

Domain

   Subdomain      Count      Minimum      Maximum      Mean      Standard
Deviation
     Sample
Variance
 
   Low      100         74,758         0.00         100.00         1.27         3.36         11.30   
        110         3,337         0.00         120.00         2.98         7.21         51.94   
        111         3,857         0.00         99.87         1.29         2.98         8.88   
        112         3,490         0.00         42.00         1.28         2.34         5.45   
   Medium      113         2,007         0.00         99.98         2.54         5.61         31.53   
        114         838         0.00         90.39         4.55         7.73         59.79   

ODM/17

        115         722         0.00         120.00         7.89         16.72         279.55   
        mg_110_114         14,251         0.00         120.00         2.38         6.36         40.51   
        120         2,042         0.00         80.00         4.34         8.15         66.50   
        121         3,047         0.00         80.00         2.09         3.91         15.27   
   High      122         3,191         0.00         66.57         2.21         3.96         15.71   
        123         544         0.00         80.00         2.51         4.84         23.44   
        hg_120_123         8,824         0.00         80.00         2.68         5.35         28.62   

Zone 34

   Low      200         465         0.00         30.00         1.91         4.70         22.05   
   Low      300         11,553         0.00         35.00         0.52         1.33         1.78   

433

   Medium      310         2,774         0.00         40.00         0.75         2.46         6.04   
   High      320         986         0.00         15.00         0.87         1.91         3.65   

HS

        400         10,276         0.00         40.00         0.90         2.04         4.14   

CAP

        500         11,477         0.00         70.00         1.97         3.75         14.08   

Intrepid

   Low      100         1721         0.05         60.00         6.24         6.93         48.07   
   Medium      200         1159         0.05         100.00         15.16         17.04         290.25   
   High      300         795         0.05         225.00         29.50         37.48         1404.67   

600 Series

        601         53,369         0.00         30.00         0.45         1.49         2.22   
        602         30,264         0.00         50.00         0.42         1.46         2.13   
        603         52,241         0.00         150.00         0.58         2.49         6.22   
        604         83,114         0.00         70.00         0.34         1.36         1.84   
        605         38,934         0.00         30.00         0.36         1.02         1.05   

Western

        800         1,078         0.00         55.00         1.48         4.70         22.10   

Silver Zones

        901         153         0.00         250.00         58.17         63.11         3982.66   
        902         85         0.23         80.00         21.16         22.61         511.19   
        903         136         0.00         70.00         15.77         16.84         283.67   
        904         420         0.00         115.00         15.35         19.30         372.68   

 

 

14-18


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-7: Basic Statistics of Composites for Domain 200 (Zone 34)

 

Data

   Count      Minimum      Maximum      Mean      Standard
Deviation
     Sample
Variance
 

Composite

                 

Ni_ppm

     465         0.00         44,365.77         2,081.04         5,701.44         32,506,462.78   

Cu_ppm

     465         0.00         34,201.35         1,531.24         4,517.75         20,410,052.92   

Pt_ppm

     465         0.00         8,354.73         185.86         701.62         492,277.56   

Pd_ppm

     465         0.00         21,913.27         543.45         1,855.97         3,444,638.38   

Au_g/t

     465         0.00         26.57         0.35         1.64         2.70   

Capped Composite

                 

Ni_ppm

     465         0.00         35,000.00         2,030.65         5,433.71         29,525,257.63   

Cu_ppm

     465         0.00         25,000.00         1,452.73         4,172.56         17,410,263.35   

Pt_ppm

     465         0.00         4,000.00         168.40         563.41         317,430.46   

Pd_ppm

     465         0.00         8,000.00         481.35         1,399.06         1,957,368.18   

Au_g/t

     465         0.00         3.00         0.24         0.49         0.24   

 

 

14-19


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-8: Basic Statistics for Calcium Uncapped Composites for All Resource Domains

 

Zone

  

Domain

   Subdomain      Count      Minimum      Maximum      Mean      Standard
Deviation
     Sample
Variance
 
   Low      100         73,579         0.00         10.37         1.36         1.16         1.34   
        110         3,256         0.01         6.89         0.96         1.01         1.03   
        111         3,842         0.00         8.10         0.76         0.79         0.62   
        112         3,480         0.01         9.79         1.45         1.01         1.02   
   Medium      113         1,832         0.00         8.78         0.83         1.09         1.20   
        114         838         0.01         5.70         1.18         0.84         0.71   

ODM/17

        115         722         0.01         9.07         1.35         1.28         1.65   
        mg_110_114         13,970         0.00         9.79         1.04         1.01         1.03   
        120         1,935         0.00         6.35         0.77         0.90         0.82   
        121         3,044         0.00         8.02         0.62         0.71         0.50   
   High      122         3,184         0.01         5.32         1.21         0.94         0.88   
        123         448         0.01         4.90         0.79         0.88         0.77   
        hg_120_123         8,611         0.00         8.02         0.88         0.89         0.80   

Zone 34

   Low      200         2473         0.00         25.46         0.29         0.90         0.81   

433

   Low      300         11,648         0.01         8.40         1.04         0.85         0.72   
   Medium      310         2,787         0.01         6.77         0.99         0.69         0.48   
   High      320         995         0.00         6.29         0.95         0.64         0.42   

HS

        400         10,308         0.01         8.79         0.99         0.81         0.66   

CAP

        500         11,075         0.01         13.29         2.56         2.12         4.50   

600 Series

        601         53,445         0.01         15.42         1.86         1.54         2.38   
        602         30,451         0.00         9.37         1.44         1.08         1.17   
        603         52,569         0.00         10.00         1.35         1.06         1.13   
        604         83,067         0.00         15.89         1.93         2.00         4.02   
        605         35,989         0.00         13.69         1.74         1.91         3.65   

Western

        800         1,078         0.01         10.03         2.00         1.27         1.62   

Silver Zones

        901         153         0.01         4.16         1.21         0.90         0.81   
        902         115         0.01         3.86         0.77         0.77         0.59   
        903         88         0.08         3.79         1.02         0.98         0.97   
        904         385         0.01         5.86         0.92         0.98         0.96   

 

 

14-20


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-9: Basic Statistics for Calcium Capped Composites for All Resource Domains

 

Zone

  

Domain

   Subdomain      Count      Minimum      Maximum      Mean      Standard
Deviation
     Sample
Variance
 
   Low      100         73,579         0.00         8.50         1.36         1.16         1.34   
        110         3,256         0.01         5.50         0.96         1.01         1.01   
        111         3,842         0.00         5.00         0.75         0.77         0.59   
        112         3,480         0.01         6.00         1.44         0.99         0.99   
   Medium      113         1,832         0.00         7.00         0.82         1.07         1.14   
        114         838         0.01         3.50         1.18         0.83         0.68   

ODM/17

        115         722         0.01         5.00         1.34         1.22         1.49   
        mg_110_114         13,970         0.00         7.00         1.04         0.99         0.99   
        120         1,935         0.00         4.00         0.77         0.89         0.79   
        121         3,044         0.00         5.00         0.62         0.68         0.47   
   High      122         3,184         0.01         5.00         1.21         0.94         0.88   
        123         448         0.01         3.50         0.79         0.85         0.73   
        hg_120_123         8,611         0.00         5.00         0.88         0.88         0.78   

Zone 34

   Low      200         2473         0.01         6.00         0.46         0.95         0.89   

433

   Low      300         11,648         0.01         7.00         1.04         0.84         0.71   
   Medium      310         2,787         0.01         4.00         0.99         0.67         0.44   
   High      320         995         0.00         6.29         0.95         0.64         0.42   

HS

        400         10,308         0.01         8.00         0.99         0.81         0.66   

CAP

        500         11,075         0.01         9.00         2.56         2.12         4.49   

600 Series

        601         53,445         0.01         9.00         1.86         1.54         2.37   
        602         30,451         0.00         7.00         1.44         1.08         1.16   
        603         52,569         0.00         8.00         1.35         1.06         1.13   
        604         83,067         0.00         9.50         1.92         2.00         4.01   
        605         35,989         0.00         9.00         1.74         1.91         3.63   

Western

        800         1,078         0.01         7.00         1.99         1.24         1.53   

Silver Zones

        901         153         0.01         3.00         1.20         0.88         0.77   
        902         115         0.01         3.00         0.77         0.74         0.55   
        903         88         0.08         3.00         1.01         0.96         0.92   
        904         385         0.01         3.00         0.90         0.93         0.86   

 

 

14-21


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-10: Basic Statistics for Sulphur Uncapped Composites for All Resource Domains

 

Zone

  

Domain

   Subdomain      Count      Minimum      Maximum      Mean      Standard
Deviation
     Sample
Variance
 
   Low      100         73,579         0.00         14.52         0.91         1.06         1.12   
        110         3,256         0.00         11.25         1.24         1.46         2.13   
        111         3,842         0.00         10.00         1.22         1.13         1.27   
        112         3,480         0.00         10.10         1.08         1.05         1.10   
   Medium      113         1,832         0.00         4.84         0.63         0.89         0.80   
        114         838         0.01         5.27         1.34         0.91         0.83   

ODM/17

        115         722         0.00         8.70         1.73         1.32         1.73   
        mg_110_114         13,970         0.00         11.25         1.14         1.19         1.42   
        120         1,935         0.00         11.76         1.42         1.68         2.83   
        121         3,044         0.00         11.54         1.48         1.31         1.71   
   High      122         3,184         0.00         10.10         1.43         1.32         1.74   
        123         448         0.01         5.28         0.96         1.13         1.29   
        hg_120_123         8,611         0.00         11.76         1.42         1.40         1.96   

Zone 34

   Low      200         2473         0.01         7.48         0.22         0.57         0.32   

433

   Low      300         11,648         0.00         13.37         1.39         1.75         3.05   
   Medium      310         2,787         0.00         11.42         1.54         1.82         3.32   
   High      320         995         0.00         13.34         1.66         1.78         3.15   

HS

        400         10,308         0.00         11.35         1.53         1.41         2.00   

CAP

        500         11,075         0.01         14.23         1.63         2.13         4.55   

600 Series

        601         53,445         0.01         14.47         1.41         1.82         3.30   
        602         30,451         0.00         13.92         1.00         1.06         1.13   
        603         52,569         0.00         13.79         0.94         1.11         1.22   
        604         83,067         0.00         13.42         0.49         0.95         0.89   
        605         35,989         0.00         11.06         0.47         0.84         0.70   

Western

        800         1,078         0.01         9.99         1.49         1.37         1.86   

Silver Zones

        901         153         0.01         3.66         0.88         0.70         0.49   
        902         115         0.01         3.60         1.29         0.97         0.94   
        903         88         0.01         7.84         2.60         1.92         3.69   
        904         385         0.00         3.32         0.67         0.81         0.66   

 

 

14-22


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-11: Basic Statistics for Sulphur Capped Composites for All Resource Domains

 

Zone

  

Domain

   Subdomain      Count      Minimum      Maximum      Mean      Standard
Deviation
     Sample
Variance
 
   Low      100        73,579         0.00         10.50         0.91         1.05         1.11   
        110         3,256         0.00         9.00         1.23         1.45         2.09   
        111         3,842         0.00         6.00         1.21         1.10         1.21   
        112         3,480         0.00         5.00         1.07         0.98         0.96   
   Medium      113         1,832         0.00         3.50         0.63         0.88         0.78   
        114         838         0.01         3.50         1.34         0.91         0.82   

ODM/17

        115         722         0.00         7.00         1.73         1.31         1.70   
        mg_110_114         13,970         0.00         9.00         1.14         1.17         1.36   
        120         1,935         0.00         9.00         1.42         1.66         2.75   
        121         3,044         0.00         7.00         1.48         1.29         1.65   
   High      122         3,184         0.00         8.00         1.43         1.30         1.69   
        123         448         0.01         4.00         0.95         1.11         1.22   
        hg_120_123         8,611         0.00         9.00         1.42         1.38         1.90   

Zone 34

   Low      200         2473         0.01         4.00         0.22         0.54         0.29   

433

   Low      300         11,648         0.00         10.00         1.39         1.73         3.01   
   Medium      310         2,787         0.00         10.00         1.54         1.82         3.31   
   High      320         995         0.00         9.00         1.64         1.69         2.86   

HS

        400         10,308         0.00         10.00         1.53         1.41         2.00   

CAP

        500         11,075         0.01         10.00         1.63         2.12         4.50   

600 Series

        601         53,445         0.01         12.00         1.41         1.81         3.29   
        602         30,451         0.00         9.50         1.00         1.06         1.12   
        603         52,569         0.00         10.00         0.94         1.10         1.21   
        604         83,067         0.00         10.00         0.49         0.94         0.89   
        605         35,989         0.00         8.50         0.47         0.83         0.69   

Western

        800         1,078         0.01         8.00         1.49         1.34         1.79   

Silver Zones

        901         153         0.01         2.00         0.84         0.61         0.37   
        902         115         0.01         3.00         1.28         0.95         0.89   
        903         88         0.01         4.50         2.43         1.66         2.75   
        904         385         0.00         3.00         0.67         0.81         0.65   

 

 

14-23


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

14.6.2 Variography

Variography was undertaken using GSLib software to characterize the spatial continuity of the metal grade data in each resource domain. Variograms were modelled for gold, silver, calcium, and sulphur for all zones.

The general methodology to calculate and model variograms consists of calculating both directional and isotropic variograms. For each resource domain and for each variable, SRK examined three (3) different spatial metrics: one (1) traditional semivariogram, two (2) traditional correlogram, and three (3) normal score semivariogram.

In general, the correlogram and normal scores transform facilitate the identification of spatial structure, particularly when the traditional variogram shows little continuity. Wherever possible, the traditional variogram was used for modelling; in cases where the traditional variogram was too noisy or unstable, one (1) or a combination of the other three (3) metrics was used to identify the continuity structure.

Generally, the sulphide mineralization at Rainy River strikes at approximately 096° and dips 55° to the south, although local variations do occur. While the majority of the variograms were modelled with two (2) structures, there are a few cases where a third structure was also modelled. In most cases, an exponential model was fitted to the first structure. The remaining structure(s) were often fitted with a spherical model. The down-hole variograms were used to estimate the nugget effect and the ranges in the Z direction (thickness of the domain).

Figure 14-6 presents a sample of the variograms produced by SRK. Variogram parameters are summarized in Table 14-12 to Table 14-15. The variograms for all other resource domains are presented in Appendix E.

 

 

14-24


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 14-6: Examples of Variogram Models for Rainy River Deposit

 

 

14-25


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-12: Modeled Gold Variogram Parameters for All Resource Domains Grade Interpolation

 

Zone

   Domain    Subdomain     No.
Struct.
     Nugget      C1      Mod      RX1      RY1      RZ1      C2      Mod      RX2      RY2      RZ2  

ODM/17 Zone

   Low      100     3         0.2         0.2         2         10         15         10         0.3         2         80         60         70   
   Medium      110        2         0.2         0.7         2         42         50         8         0.1         1         150         90         50   
        111        2         0.2         0.6         2         10         15         5         0.2         1         140         80         25   
        112        2         0.3         0.6         2         15         15         7         0.1         1         100         90         50   
        113     3         0.2         0.5         2         25         0         10         0.1         1         25         90         40   
        114        1         0.25         0.75         1         70         70         8                  
        115        2         0.2         0.65         2         40         40         25         0.15         1         130         130         40   
   High      120        2         0.2         0.6         2         15         15         5         0.2            70         70         25   
        121     3         0.2         0.65         2         15         15         6         0.05         1         15         60         13   
        122     3         0.2         0.5         2         15         15         4         0.15         1         50         70         30   
        123       2         0.2         0.6         2         15         15         5         0.2            70         70         25   

Zone 34

   Low      200        2         0.15         0.25         1         10         10         10         0.6         1         75         55         35   

433 Zone

   Low      300     3         0.1         0.4         2         10         30         8         0.25         1         100         45         25   
   Medium      310        2         0.2         0.6         2         15         35         6         0.2         1         200         60         20   
   High      320        2         0.2         0.45         2         10         10         4         0.35         1         60         30         8   

HS

        400        2         0.2         0.4         2         10         10         5         0.4         1         50         15         20   

CAP

        500        2         0.2         0.55         2         15         15         10         0.2         1         100         100         70   
   Low      100East        2         0.2         0.8         1         110         70         3                  
        100West        2         0.2         0.55         1         50         20         3         0.25         2         60         50         3   

Intrepid

   Medium      200East        2         0.3         0.4         1         30         40         3         0.3         2         40         80         3   
        200West        2         0.3         0.45         1         20         10         3         0.25         2         80         70         3   
   High      300East        2         0.3         0.4         1         60         40         3         0.3         2         80         50         3   
        300West        2         0.3         0.45         1         40         40         6         0.25         2         50         50         6   

Western

        800        1         0.2         0.8         2         200         200         200                  

901-904

        900        1         0.2         0.8         2         60         60         12                  

 

 

1 = Exponential; 2 = Spherical

* For domains of the ODM/17 Zone, a third structure was modelled with a spherical function with:

100: C3 = 0.30, RX3 = 500, RY3 =500, and RZ3 = 70

113: C3 = 0.20, RX3 = 110, RY3 =90, and RZ3 = 40

121: C3 = 0.10, RX3 = 140, RY3 =60, and RZ3 = 18

122: C3 = 0.15, RX3 = 160, RY3 =70, and RZ3 = 30

 

 

Variogram borrowed from 120

 

 

14-26


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-13: Modeled Silver Variogram Parameters for All Resource Domains Grade Interpolation

 

Zone

   Domain    Subdomain     No.
Struct.
     Nugget      C1      Mod      RX1      RY1      RZ1      C2      Mod      RX2      RY2      RZ2  

ODM/17 Zone

   Low      100     3         0.2         0.4         2         35         30         20         0.15         2         35         30         110   
   Medium      110        2         0.2         0.35         2         50         50         20         0.45         1         300         300         40   
        111        2         0.2         0.45         2         25         10         15         0.35         1         70         110         70   
        112        2         0.2         0.55         2         5         5         5         0.25         1         35         35         35   
        113        3         0.2         0.6         2         35         10         20         0.2         1         70         40         40   
        114        1         0.2         0.8         2         50         50         20                  
        115        2         0.2         0.3         2         30         30         30         0.5         1         100         100         40   
   High      120        2         0.2         0.4         2         45         150         30         0.4         1         400         300         30   
        121        2         0.25         0.45         2         35         60         8         0.3         1         80         100         45   
        122        2         0.2         0.5         2         10         10         4         0.3         1         60         60         35   
        123        2         0.2         0.35         2         35         35         7         0.45         1         50         50         10   

Zone 34

   Low      200     3         0.2         0.2         2         10         10         15         0.3         2         80         80         40   

433 Zone

   Low      300     3         0.2         0.3         2         5         5         10         0.25         1         60         60         100   
   Medium      310     3         0.2         0.2         2         45         15         8         0.4         2         45         15         60   
   High      320        2         0.2         0.2         2         10         35         20         0.6         1         110         35         20   

HS

        400     3         0.2         0.3         2         10         10         15         0.25         1         10         10         80   

CAP

        500        2         0.2         0.6         2         25         25         15         0.2         1         300         300         70   

Intrepid

   Low      100East        1         0.2         0.8         2         110         80         3                  
        100West        2         0.2         0.55         1         70         135         6         0.25         2         180         135         6   
   Medium      200East        2         0.3         0.3         1         30         35         3         0.4         2         110         65         3   
        200West        2         0.3         0.45         1         20         10         3         0.25         2         80         70         3   
   High      300East        2         0.3         0.55         1         35         35         3         0.15         2         70         45         3   
        300West        2         0.3         0.45         1         30         15         3         0.25         2         90         45         8   

Western

        800        2         0.2         0.2         1         15         15         15         0.6         1         70         70         70   

901-904

        900        1         0.2         0.8         2         55         55         12                  

 

 

1 = Exponential; 2 = Spherical

* For domains of ODM/17 Zone, a third structure was modelled with a spherical function with:

100: C3 = 0.25, RX3 = 300, RY3 = 300, and RZ3 = 110

200: C3 = 0.30, RX3 = 220, RY3 = 220, and RZ3 = 40

300: C3 = 0.30, RX3 = 120, RY3 = 120, and RZ3 = 100

310: C3 = 0.20, RX3 = 25, RY3 = 90, and RZ3 = 60

400: C3 = 0.25, RX3 = 100, RY3 = 75, and RZ3 = 80

 

 

14-27


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-14: Modeled Calcium Variogram Parameters for All Resource Domains Grade Interpolation

 

Zone

   Domain    Subdomain     No.
Struct.
     Nugget      C1      Mod      RX1      RY1      RZ1      C2      Mod      RX2      RY2      RZ2  

ODM/17 Zone

   Low      100     3         0.2         0.4         2         15         15         120         0.4         2         50         50         140   
   Medium      110     3         0.15         0.35         2         10         15         80         0.2         1         50         15         80   
        111     3         0.15         0.45         2         10         15         60         0.2         1         70         15         60   
        112        2         0.15         0.55         2         15         15         50         0.3         1         200         100         100   
        113        2         0.2         0.6         2         25         25         80         0.3         1         130         130         80   
        114        1         0.25         0.8         1         70         70         70                  
        115        2         0.1         0.3         2         130         130         50         0.15         1         130         130         50   
   High      120     3         0.15         0.4         2         25         25         110         0.25         1         25         120         110   
        121     3         0.15         0.45         2         10         20         55         0.25         1         80         20         55   
        122     3         0.15         0.5         2         10         10         40         0.25         1         10         10         100   
        123        2         0.2         0.35         2         70         15         5         0.3         1         70         20         15   

Zone 34

   Low      200        2         0.2         0.2         2         25         25         10         0.3         1         200         200         35   

433 Zone

   Low      300     3         0.1         0.3         2         40         30         30         0.1         1         250         30         30   
   Medium      310     2         0.2         0.2         2         100         100         80         0.35         1         200         160         80   
   High      320        2         0.2         0.2         2         90         90         30         0.35         1         200         200         80   

HS

        400        2         0.2         0.3         2         40         40         80         0.4         1         60         60         80   

CAP

        500        2         0.2         0.6         2         35         35         45         0.25         1         180         180         70   

Western

        800        1         0.2         0.2         2         30         30         15                  

901-904

        900        1         0.2         0.8         2         60         60         25                  

 

1 = Exponential; 2 = Spherical

* For domains of ODM/17 Zone, a third structure was modelled with a spherical function with:

100: C3 = 0.20, RX3 = 500, RY3 = 500, and RZ3 = 140

110: C3 = 0.20, RX3 = 50, RY3 = 120, and RZ3 = 80

111: C3 = 0.20, RX3 = 70, RY3 = 50, and RZ3 = 60

120: C3 = 0.25, RX3 = 120, RY3 = 120, and RZ3 = 110

121: C3 = 0.25, RX3 = 200, RY3 = 160, and RZ3 = 55

122: C3 = 0.25, RX3 = 180, RY3 = 90, and RZ3 = 100

300: C3 = 0.40, RX3 = 250, RY3 = 200, and RZ3 = 200

 

 

14-28


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-15: Modeled Sulphur Variogram Considered for All Resource Domains Grade Interpolation

 

Zone

   Domain    Subdomain     No.
Struct.
     Nugget      C1      Mod      RX1      RY1      RZ1      C2      Mod      RX2      RY2      RZ2  

ODM/17 Zone

   Low      100        2         0.15         0.75         2         30         30         140         0.1         1         300         300         140   
   Medium      110     3         0.15         0.45         2         10         25         80         0.2         1         45         15         80   
        111        2         0.15         0.45         2         10         10         40         0.4         1         30         30         40   
        112        2         0.15         0.6         2         15         15         70         0.25         1         80         80         100   
        113     3         0.2         0.5         2         70         25         60         0.1         1         130         50         60   
        114        1         0.2         0.8         1         70         70         70                  
        115        1         0.1         0.9         2         100         100         50                  
   High      120     3         0.15         0.35         2         25         25         80         0.25         1         25         90         80   
        121        2         0.15         0.6         2         30         20         55         0.25         1         30         40         55   
        122     3         0.15         0.35         2         10         10         40         0.25         1         10         10         100   
        123        1         0.2         0.8         2         110         40         10                  

Zone 34

   Low      200        2         0.2         0.4         2         30         30         10         0.4         1         30         30         35   

433 Zone

   Low      300        2         0.1         0.4         2         40         25         100         0.5         1         250         170         100   
   Medium      310        2         0.2         0.45         2         90         110         70         0.35         1         250         110         70   
   High      320        2         0.2         0.45         2         140         90         80         0.35         1         250         140         80   

HS

        400        2         0.15         0.65         2         40         40         100         0.2         1         100         100         100   

CAP

        500        2         0.15         0.75         2         10         10         45         0.1         1         80         80         60   

Western

        800        1         0.2         0.8         2         80         80         15                  

901-904

        900        1         0.2         0.8         2         60         60         25                  

 

1 = Spherical; 2 = Exponential

* 

For domains of ODM/17 Zone, a third structure was modelled with a spherical function with:

110: C3 = 0.20, RX3 = 45 RY3 = 120, and RZ3 = 80

113: C3 = 0.20, RX3 = 1,300, RY3 = 50, and RZ3 = 200

120: C3 = 0.25, RX3 = 120, RY3 =110, and RZ3 = 80

122: C3 = 0.25, RX3 = 100, RY3 = 100, and RZ3 = 100

 

 

14-29


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

14.7 Block Model and Grade Estimation

 

14.7.1 Block Model Definition

An unrotated block model was created in Gemcom to cover the entire extent of the Rainy River Project deposit area. Block size was set at 5 m x 5 m x 5 m for the Intrepid Zone and the portion of the main Rainy River deposit amenable to underground mining. The block size for the portion of the Rainy River Project amenable to open pit mining was set at 10 m x 10 m x 10 m (Table 14-16).

Criteria used in the selection of block size includes the borehole spacing, composite assay length, consideration for the potential size of the smallest mining unit and the geometry of the modelled auriferous Zones.

Table 14-16: Rainy River Project Block Model Parameters

 

Model

 

Direction

   Size (m)      Minimum      Maximum      Number of
Cells
 
 

East-West

     10         423,700         427,075         338   

Open Pit

 

North-South

     10         5,408,750         5,411,125         238   
 

Vertical

     10         (-)1,200         450         165   
 

East-West

     5         423,700         427,075         675   

Underground

 

North-South

     5         5,408,750         5,411,125         475   
 

Vertical

     5         (-)1,200         450         330   
 

East-West

     5         427,075         427,675         120   

Intrepid

 

North-South

     5         5,409,500         5,409,950         90   
 

Vertical

     5         (-)180         420         120   

 

14.7.2 Grade and Specific Gravity Estimation

Metal grades were estimated using ordinary Kriging as the principal estimator, separately in each domain, from capped composite data within that domain. Grades in Domains 601 to 605 were estimated using an inverse distance algorithm similarly to that in the previous mineral resource model. In order to test the sensitivity of the grade estimation to the choice of estimation parameters, SRK undertook a series of sensitivity runs varying the interpolation parameters. Results indicate that the models are relatively insensitive to slight variations in the estimation

 

 

14-30


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

parameters. Grade interpolation was completed in two (2) or three (3) successive passes, considering the estimation parameters summarized in Table 14-17 to Table 14-19 for Main Rainy River (amenable to open pit and underground mining) and the Intrepid Zone, respectively. Search neighbourhoods are summarized in Table 14-20 and Table 14-21 for main Rainy River and the Intrepid Zone, respectively.

The search neighbourhoods used for calcium and sulphur interpolation are tabulated in Table 14-22 and Table 14-23, whereas that for Domain 200 (Zone 34) is summarized in Table 14-24. The first estimation pass considered search neighborhoods adjusted to 95% of the variogram sill. The size of the search ellipse was doubled for the second estimation pass.

A third estimation pass was used for Domains 114, 300, and 400, with a search distance set at three (3) times the first pass range in order to populate all the blocks in the entire domain.

Grade interpolation within the 600 domains has been further restricted by limiting the influence of high grades to half the distance of the first pass ellipsoidal search. Considering the higher uncertainty in gold mineralization continuity within the 600 series, a grade restriction of 8 g/t gold was applied.

For the ODM/17, 433, HS and CAP domains, a specific gravity value was estimated in each model block using an inverse distance algorithm in a single pass with the following criteria:

 

 

A minimum of 4 and a maximum of 20 composites;

 

 

A maximum of 3 composites per borehole; and

 

 

A spherical search radius of 500 m.

 

 

14-31


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-17: Resource Estimation Parameters for Part of the Main Rainy River Deposit

Amenable to Open Pit Mining

 

Interpolation Parameters

   1st Pass
(Indicated)
     2nd Pass
(Inferred)
     3rd Pass
(Inferred)
 

Domains 100-500, 800 and 900

        

Interpolation Method

     Ordinary Kriging         Ordinary Kriging         Ordinary Kriging   

Search Type

     Octant         Ellipsoidal         Ellipsoidal   

Minimum Number of Octants

     2         —           —     

Maximum Number of Composites per Octant

     5         —           —     

Minimum Number of Composites

     7         5         2   

Maximum Number of Composites

     12         12         15   

Maximum Number of Composites per Borehole

     5         3         —     

Domains 601 to 605

        

Interpolation Method

    
 
Inverse Distance
Power 2
  
  
    
 
Inverse Distance
Power 2
  
  
    
 
Inverse Distance
Power 2
  
  

Search Type

     Ellipsoidal         Ellipsoidal         Ellipsoidal   

Minimum Number of Composites

     7         5         2   

Maximum Number of Composites

     12         12         15   

Maximum Number of Composites per Hole

     5         3         —     

Domain 200 (Pt, Pd, Ni and Cu)

        

Interpolation Method

     Ordinary Kriging         Ordinary Kriging         Ordinary Kriging   

Search Type

     Octant         Ellipsoidal         Ellipsoidal   

Minimum Number of Octants

     2         —           —     

Maximum Number of Composites per Octant

     5         —           —     

Minimum Number of Composites

     7         5         2   

Maximum Number of Composites

     12         12         15   

Maximum Number of Composites per Hole

     5         3         —     

 

 

14-32


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-18: Resource Estimation Parameters for the Part of the Main Rainy River Deposit

Amenable to Underground Mining

 

Interpolation Parameters

   1st Pass
(Indicated)
     2nd Pass
(Inferred)
     3rd Pass
(Inferred)
 

Domains 100-500, 800 and 900

        

Interpolation Method

     Ordinary Kriging         Ordinary Kriging         Ordinary Kriging   

Search Type

     Octant         Ellipsoidal         Ellipsoidal   

Minimum Number of Octants

     2         —           —     

Maximum Number of Composites per Octant

     5         —           —     

Minimum Number of Composites

     3         2         2   

Maximum Number of Composites

     8         12         12   

Maximum Number of Composites per Borehole

     2         —           —     

Domains 601 to 605

        

Interpolation Method

    
 
Inverse Distance
Power 2
  
  
    
 
Inverse Distance
Power 2
  
  
     —     

Search Type

     Ellipsoidal         Ellipsoidal         —     

Minimum Number of Composites

     3         2         —     

Maximum Number of Composites

     10         15         —     

Maximum Number of Composites per Hole

     2         —           —     

Domain 200 (Pt, Pd, Ni and Cu)

        

Interpolation Method

     Ordinary Kriging         Ordinary Kriging         —     

Search Type

     Octant         Ellipsoidal         —     

Minimum Number of Octants

     2         —           —     

Maximum Number of Composites per Octant

     5         —           —     

Minimum Number of Composites

     3         2         —     

Maximum Number of Composites

     10         12         —     

Maximum Number of Composites per Hole

     2         —           —     

 

 

14-33


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-19: Resource Estimation Parameters for the Intrepid Zone

 

Interpolation Parameters

   1st Pass
(Indicated)
     2nd Pass
(Inferred)
     3rd Pass
(Inferred)
 

Interpolation Method

     Ordinary Kriging         Ordinary Kriging         Ordinary Kriging   

Search Type

     Octant         Ellipsoidal         Ellipsoidal   

Minimum Number of Octants

     2         —           —     

Maximum Number of Composites per Octant

     4         —           —     

Minimum Number of Composites

     5         3         2   

Maximum Number of Composites

     10         15         15   

Maximum Number of Composites per Borehole

     3         2         —     

Table 14-20: Search Neighbourhoods Used for Gold and Silver Estimation in Main Rainy River

 

     Domain      Rotation*      1st Pass      2nd Pass      3rd Pass  
         Search Ranges      Search Ranges      Search Ranges  
      Az      Dip      Plunge      X      Y      Z      X      Y      Z      X      Y      Z  

Au/Ag

     100         -110         -40         132         200         100         50         200         200         100            
     110         -120         -40         122         100         60         35         200         120         70            
     111         -105         -40         145         95         55         20         190         110         40            
     112         -110         -40         132         70         60         35         140         120         70            
     113         -120         -40         122         75         60         30         150         120         60            
     114         -130         -40         112         50         50         10         100         100         20         150         150         30   
     115         -120         -40         122         90         90         30         180         180         60            
     120         -120         -40         122         55         55         25         110         110         50            
     121         -110         -40         132         95         40         15         190         80         30            
     122         -115         -40         127         110         50         25         220         100         50            
     123         -120         -40         55         55         25         110         110         50         55            
     200         45         56         -55         75         55         35         150         110         70            
     300         20         50         -70         70         40         20         140         80         40         175         100         50   
     310         25         50         -65         135         40         15         270         80         30            
     320         20         45         -75         60         30         20         120         60         20            
     400         10         50         -80         50         20         20         100         40         40         150         60         60   
     500         15         55         -75         70         70         50         140         140         100            
     601         78         -47         55         60         60         32         120         120         64            
     602         78         -47         55         120         120         45         240         240         90            
     603         78         -47         55         200         200         20         200         200         20            
     604         78         -47         55         200         200         20         200         200         20            

 

 

14-34


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

     Domain      Rotation*      1st Pass      2nd Pass      3rd Pass
         Search Ranges      Search Ranges      Search Ranges
      Az      Dip      Plunge      X      Y      Z      X      Y      Z      X    Y    Z
     605         78         -47         55         170         110         60         340         220         120            
     800         0         0         0         130         130         130         260         260         260            
     901         40         55         -50         60         60         12         120         120         24            
     902         20         45         -70         60         60         12         120         120         24            
     903         5         55         -85         60         60         12         120         120         24            
     904         20         60         -70         60         60         12         120         120         24            

Table 14-21: Search Neighbourhoods Used for Gold and Silver Estimation in Intrepid Zone

 

     Domain      Rotation*      1st Pass      2nd Pass      3rd Pass  
         Search Ranges      Search Ranges      Search Ranges  
      Az      Dip      Plunge      X      Y      Z      X      Y      Z      X      Y      Z  

Au

     100West         165         -58         75         60         50         3         160         100         6         180         150         9   
     100East         60         58         -60         110         70         3         220         140         6         330         210         9   
     200West         190         -58         75         80         70         3         160         140         6         240         210         9   
     200East         60         58         -60         40         80         3         160         160         3         160         160         9   
     300West         190         -58         75         50         50         3         100         160         6         150         240         9   
     300East         40         58         -60         80         50         3         160         100         6         240         150         9   

Ag

     100West         190         -58         75         120         110         6         240         220         12         240         220         12   
     100East         60         58         -60         110         80         3         220         160         6         220         160         6   
     200West         190         -58         75         80         70         3         160         140         6         160         140         6   
     200East         60         58         -60         85         50         3         170         100         6         170         100         6   
     300West         190         -58         75         90         45         8         180         90         16         180         90         16   
     300East         60         58         -60         70         45         3         140         90         6         140         90         6   

 

 

14-35


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-22: Search Neighbourhoods Used for Calcium

 

     Domain      Rotation*      1st Pass      2nd Pass      3rd Pass  
         Search Ranges      Search Ranges      Search Ranges  
      Az      Dip      Plunge      X      Y      Z      X      Y      Z      X      Y      Z  
Ca      100         -110         -40         132         200         200         50         200         200         100            
     110         -120         -40         122         50         120         80         100         240         180            
     111         -105         -40         145         70         50         60         140         100         120            
     112         -110         -40         132         130         60         75         260         120         150            
     113         -120         -40         122         130         130         80         260         260         160            
     114         -130         -40         112         70         70         70         140         140         140            
     115         -120         -40         122         130         130         50         260         260         100            
     120         -120         -40         122         90         80         90         180         160         180            
     121         -110         -40         132         100         120         45         200         240         90            
     122         -115         -40         127         110         50         70         220         100         140            
     123         -120         -40         122         70         20         15         140         40         30         210         60         45   
     200         45         56         -55         130         130         35         260         260         70            
     300         20         50         -70         180         140         140         360         280         280            
     310         25         50         -65         140         110         65         280         220         130            
     320         20         45         -75         140         140         55         280         280         110            
     400         10         50         -80         60         60         80         120         120         160            
     500         15         55         -75         110         110         70         220         220         140            
     601         78         -47         55         60         60         32         120         120         64            
     602         78         -47         55         120         120         45         240         240         90            
     603         78         -47         55         200         200         20         200         200         20            
     604         78         -47         55         200         200         20         200         200         20            
     605         78         -47         55         170         110         60         340         220         120            
     800         0         0         0         30         30         15         60         60         30         120         120         60   
     901         40         55         -50         60         60         25         120         120         50            
     902         20         45         -70         60         60         25         120         120         50            
     903         5         55         -85         60         60         25         120         120         50            
     904         20         60         -70         60         60         25         120         120         50            

 

 

14-36


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-23: Search Neighbourhoods Used for Sulphur

 

     Domain      Rotation*      1st Pass      2nd Pass      3rd Pass  
         Search Ranges      Search Ranges      Search Ranges  
      Az      Dip      Plunge      X      Y      Z      X      Y      Z      X      Y      Z  
S      100         -110         -40         132         100         100         50         200         200         200            
     110         -120         -40         122         45         120         80         90         240         180            
     111         -105         -40         145         30         30         40         60         60         80         90         90         120   
     112         -110         -40         132         80         80         100         160         160         200            
     113         -120         -40         122         130         50         100         260         100         200            
     114         -130         -40         112         70         70         70         140         140         140            
     115         -120         -40         122         100         100         50         200         200         100            
     120         -120         -40         122         80         80         75         160         160         150            
     121         -110         -40         132         30         40         55         60         40         110            
     122         -115         -40         127         100         100         100         200         200         200            
     123         -120         -40         122         110         40         10         220         80         20            
     200         45         56         -55         30         30         35         60         60         70            
     300         20         50         -70         170         120         75         340         240         150            
     310         25         50         -65         160         110         70         320         220         140            
     320         20         45         -75         170         100         65         320         200         130            
     400         10         50         -80         100         100         100         200         200         200            
     500         15         55         -75         80         80         60         160         160         120            
     601         78         -47         55         60         60         32         120         120         64            
     602         78         -47         55         120         120         45         240         240         90            
     603         78         -47         55         200         200         20         200         200         20            
     604         78         -47         55         200         200         20         200         200         20            
     605         78         -47         55         170         110         60         340         220         120            
     800         0         0         0         80         80         15         160         160         30         160         160         60   
     901         40         55         -50         60         60         25         120         120         50            
     902         20         45         -70         60         60         25         120         120         50            
     903         5         55         -85         60         60         25         120         120         50            
     904         20         60         -70         60         60         25         120         120         50            

 

 

14-37


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-24: Search Neighbourhoods Used for Grade Estimation in Zone 34

 

     Domain      1st Pass
Search Ranges
     2nd Pass
Search Ranges
 
        X      Y      Z      X      Y      Z  

Pt

     200         75         75         18         150         150         35   

Pd

        75         75         18         150         150         35   

Ni

        35         35         23         70         70         45   

Cu

        38         38         18         75         75         35   

 

14.8 Model Validation and Sensitivity

The mineral resource model was validated by visually comparing block estimates to informing borehole data on section by section and elevation by elevation basis (as in Figure 14-7 and Figure 14-8.

 

LOGO

Figure 14-7: Cross-Section 425,775E Comparing Blocks Populated

with Gold Grades and Informing Data

 

 

14-38


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 14-8: Cross-Section 425, 335E Comparing Blocks Populated With Gold Grades and

Informing Data in the Intrepid Zone

SRK has also undertaken a comparative analysis between ordinary Kriging estimates and that estimated using an inverse distance (power of 2) estimator. Both estimation techniques show comparative global results.

 

14.9 Mineral Resource Classification

Mineral resources were classified according to the CIM Definition Standards for Mineral Resources and Mineral Reserves (November 2010) by Dorota El-Rassi, P.Eng. (PEO #100012348) and Glen Cole, P.Geo. (APGO #1416); appropriate independent qualified persons for the purpose of National Instrument 43-101.

The mineral resources are classified primarily based on the basis of a block’s distance from the nearest informing composites and on variography results. Classification is based on gold data alone. Generally, an Indicated classification is assigned to blocks estimated during the first estimation pass using 95% of the variogram sill; whereas an Inferred classification is assigned to all other blocks estimated during the second or third estimation pass. SRK also considered the confidence in the geological interpretation during the classification process.

 

 

14-39


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

As a result of the infill drilling program completed in 2012 and the increased confidence in the geological and grade continuity, SRK considers that a Measured classification can be assigned to certain parts of the OMD/17 Zone (domains 100 and 300) where the drilling information and density is sufficient to confirm the geological and grade continuity within the meaning of the CIM Definition Standards for Mineral Resources and Mineral Reserves. The parameters used to categorize the Measured blocks are summarized in Table 14-25.

The classification strategy also considered the geological setting, as well as what impact additional drill data would have on the shape of the modelled resource domain and the confidence in the grade continuity. All resource blocks within domains 601 to 605 are estimated at a low level of confidence and therefore have been assigned an Inferred classification.

Table 14-25: Search Parameters Used to Code the Measured Blocks

 

Interpolation Parameters

   Measured

Domains 100 and 300

  

Interpolation Method

   Ordinary Kriging

Search Type

   Octant (25x25x25)

Minimum Number of Octants

   3

Maximum Number of Composites per Octant

   4

Minimum Number of Composites

   5

Maximum Number of Composites

   8

Maximum Number of Composites per Borehole

   2

 

14.10 Mineral Resource Statement

CIM Definition Standards for Mineral Resources and Mineral Reserves (November 2010) defines a mineral resource as:

“A concentration or occurrence of diamonds, natural solid inorganic material, or natural solid fossilized organic material including base and precious metals, coal, and industrial minerals in or on the Earth’s crust in such form and quantity and of such a grade or quality that it has reasonable prospects for economic extraction. The location, quantity, grade, geological characteristics and continuity of a Mineral Resource are known, estimated or interpreted from specific geological evidence and knowledge.”

 

 

14-40


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The “reasonable prospects for economic extraction” requirement generally implies that the quantity and grade estimates meet certain economic thresholds and that the mineral resources are reported at an appropriate cut-off grade that takes into account extraction scenarios and processing recoveries. SRK considers that portions of the Rainy River gold deposits are amenable for open pit extraction, while other parts of the deposits could be extracted using an underground mining method.

To assist with determining which portions of the modelled mineralization show “reasonable prospect for economic extraction” from an open pit, and to assist with selecting reasonable reporting assumptions, SRK used a pit optimizer to develop conceptual open pit shells using the assumptions summarized in Table 14-26. The block model quantities and grade estimates were also reviewed to determine the portions of the modelled mineralization having “reasonable prospects for economic extraction” from an underground mine, based on parameters summarized in Table 14-27.

The reader is cautioned that the results from the pit optimization are used solely for the purpose of assessing those portions of the block models that show “reasonable prospects for economic extraction” by an open pit and do not represent an attempt to evaluate mineral reserves. Mineral reserves can only be estimated based on the results of an economic evaluation as part of a preliminary feasibility study or a feasibility study. As such, no mineral reserves have been estimated by SRK. There is no certainty that all or any part of the mineral resource will be converted into mineral reserve.

Table 14-26: Conceptual Assumptions Considered for Open Pit Resource Reporting

 

Parameter

  

Assumption

Pit Wall Angle

   Average 48º

Mining Cost (Ore and Waste)

   CAD $2.00/t rock

Process Cost Including G & A Costs

   USD $7.25/t

Process Recovery

   88% gold, 75% silver

Assumed Process Rate

   32,000 tpd from open pit and underground

Metal Price

   USD $1,400/oz. gold and USD $24.00/oz. silver

Mining Dilution and Losses

   10.0%

 

 

14-41


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-27: Conceptual Assumptions Considered for Underground Resource Reporting

 

Parameter

  

Assumption

Mining Costs    CAD $55.00/t rock
Assumed Process Rate    32,000 tpd from open pit and underground
Assumed Mining Rate    2,500 tpd
Process Cost Including G & A Costs    USD $7.25/t
Process Recovery    90% gold, 75% silver
Metal Price    USD $1,400/oz. gold and USD $24.00/oz. silver
Mining Dilution    20.0%
Mining Recoveries    100%

SRK considers that material above an elevation of -150 metres above sea level (“masl”) offers reasonable prospects for economic extraction from an open pit.

In order to prepare the Mineral Resource Statement for the Rainy River Project, SRK considered a conceptual pit shell defined using a gold price of USD $1,400 and a silver price of USD $24 per ounce. Following review of optimization results, SRK subdivided the block model into two (2) areas for reporting mineral resources (shown in Figure 14-9):

 

1. Open pit, Measured, Indicated, and Inferred mineral resources reported inside the USD $1,400 conceptual pit shell above an elevation of -150 masl;

 

2. Underground, Measured, Indicated and Inferred mineral resources are reported below an elevation of -150 masl and outside the conceptual pit shell above the elevation of -150 masl.

The resources at the Intrepid Zone are reported as underground material with an assigned Indicated and Inferred classification. Generally, an Indicated classification was assigned to those blocks that were coded in the first pass, which used a minimum of three (3) boreholes. Final manual smoothing was applied to the automatic classification to ensure the continuity of similar class blocks. The remaining blocks were classified as Inferred as they lack sufficient continuity to meet the Indicated criteria.

 

 

14-42


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 14-9: Schematic Vertical Section Illustrating Criteria Considered for Preparing the Mineral

Resource Statement for the Rainy River Project (View Looking East)

The mineral resources may be affected by subsequent assessments of mining, environmental, processing, permitting, taxation, socio-economic, and other factors. There is insufficient information at this early stage of the study to assess the extent to which the resources will be affected by these factors.

The Rainy River Project contains gold-rich polymetallic sulphide mineralization of hydrothermal origin, which has been overprinted by magmatic copper-nickel sulphide mineralization enriched in platinum group metals (Zone 34). Copper and nickel grades were estimated in the block model; however, these metals do not contribute significantly to the overall value of the gold-rich sulphide mineralization. Hence, the Mineral Resource Statement for the Rainy River Project is reported on the basis of gold and silver grades only. The mineral resources for Zone 34 and the Silver Zone are reported separately since they contain different metal characteristics.

 

 

14-43


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The Mineral Resource Statement is reported at two (2) gold cut-off grades considering the most likely extraction scenario. Open pit mineral resources are reported at a cut-off grade of 0.30 g/t gold, whereas underground mineral resources are reported at a cut-off grade of 2.50 g/t gold. Cut-off grades are based on a gold price of USD $1,400 per ounce and a gold, metallurgical recovery of 88% and 90% for open pit and underground mineral resources, respectively, without considering revenues from other metals. The consolidated Mineral Resource Statement for the Rainy River Project gold zones is summarized in Table 14-28 and excludes gold mineralization from Zone 34 and the Silver Zone. The effective date of this ninth (9th) Mineral Resource Statement prepared for the Rainy River Project is November 2, 2013.

 

 

14-44


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-28: Consolidated Mineral Resource Statement*, Rainy River Project, Ontario,

SRK Consulting (Canada) Inc., November 2, 20131,2,3,4,5

 

      Quantity
‘000t
     Grade      Metal  

Category

      Au
gpt
     Ag
gpt
     Au
‘000 oz
     Ag
‘000 oz
 

Direct Processing Material

              

Open Pit2

              

Measured

     20,282         1.45         1.93         947         1,261   

Indicated

     80,411         1.35         2.55         3,486         6,584   

O/P Measured & Indicated

     100,693         1.37         2.42         4,433         7,846   

Inferred

     9,388         0.97         2.28         292         687   

Underground2

              

Measured

     89         4.95         2.75         14         8   

Indicated

     5,469         4.53         11.34         796         1,994   

Measured & Indicated

     5,558         4.53         11.20         810         2,002   

Inferred

     2,641         4.46         8.30         379         707   

Stockpile Material3

              

Open Pit

              

Measured

     6,294         0.37         1.29         74         262   

Indicated

     64,816         0.44         2.17         919         4,526   

Measured & Indicated

     71,110         0.43         2.09         993         4,788   

Inferred

     8,626         0.37         1.16         102         323   

Combined Direct Processing and Stockpile Mineral Resources

              

Measured

     26,665         1.21         1.79         1,035         1,531   

Indicated

     150,696         1.07         2.70         5,202         13,104   

Measured and Indicated

     177,361         1.09         2.57         6,236         14,635   

Inferred

     20,655         1.16         2.58         773         1,717   

 

1

Mineral resources are reported in relation to conceptual pit shells which are limited to 150m below sea level and are inclusive of the Intrepid Zone.

2 

Open pit mineral resources are reported at a cut-off grade of 0.30 g/t gold, underground mineral resources are reported at a cut-off grade of 2.50 g/t gold based on a gold price of US$1,400 per ounce, a silver price of US$24.00 per ounce, a foreign exchange rate of C$1.10 to US$1.00, gold recovery of 88% for open pit resources, 90% for underground resources and a silver recovery at 75% for all mineral resources.

3 

Direct processing material is defined as mineralization above a cut-off of 0.45 g/t gold and likely to be mined and processed directly.

4 

Stockpile material includes all material within conceptual open pit shells above a cut-off of 0.30 g/t gold and below a 0.45 g/t gold cut-off as well as material within the CAP Zone (code 500) that is suitable for stockpiling and future processing based on average metallurgical recoveries of 88% gold and 75% silver.

5 

Qualified Persons – The mineral resource statement was prepared by Dorota El-Rassi, P.Eng. (APEO #100012348) and Glen Cole (APGO #1416) from SRK Consulting (Canada) Inc., both Independent “Qualified Persons” as that term is defined in Canadian National Instrument 43-101.

 

 

14-45


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Mineral resources for Zone 34 and the Silver Zone are reported in Table 14-29 and Table 14-30, respectively.

Table 14-29: Mineral Resources1 for Zone 34 (Domain 200), Rainy River Project, Ontario, SRK

Consulting (Canada) Inc., November 2, 2013

 

            Grade      Metal  

Category

   Quantity
‘000 t
     Au
g/t
     Pt
g/t
     Pd
g/t
     Ni
ppm
     Cu
ppm
     Au
‘000 oz.
     Pt
‘000 oz.
     Pd
‘000 oz.
     Ni
t
     Cu
t
 

Open Pit Mineral Resources2

                                

Indicated

     191         0.60         0.23         0.62         1,656         1,424         3.71         1.39         3.80         317         272   

 

1. 

Excluded from the main Mineral Resource Statement. Mineral resources are reported in relation to conceptual pit shells. Mineral resources are not mineral reserves and do not have a demonstrated economic viability. All figures are rounded to reflect the relative accuracy of the estimate. All composites have been capped where appropriate.

2. 

Open pit mineral resources are reported at a cut-off grade of 0.30 g/t gold. Cut-off grades are based on a price of USD $1,400 per ounce of gold, exchange rate of CAD $1.10 to USD $1.00, and gold recovery of 88%.

Table 14-30: Mineral Resources1 for the Silver Zone (Domain 901), Rainy River Project,

SRK Consulting (Canada) Inc., November 2, 2013

 

            Grade      Metal  

Category

   Quantity
‘000 t
     Au
g/t
     Ag g/t      AuEq
g/t
     Au
‘000 oz.
     Ag
‘000 oz.
     AuEq
‘000 oz.
 

Open Pit Mineral Resources2

  

              

Indicated

     2,108         0.54         20.34         0.89         36.51         1,378         60.49   

 

1. 

Excluded from the main Mineral Resource Statement. Mineral resources are reported in relation to conceptual pit shells. Mineral resources are not mineral reserves and do not have a demonstrated economic viability. All figures are rounded to reflect the relative accuracy of the estimate. All composites have been capped where appropriate.

2. 

Open pit mineral resources are reported at a cut-off grade of 0.30 g/t gold equivalent. Gold equivalent grade is based on a gold price of USD $1,400 per ounce, a silver price of USD $24.00 per ounce, a foreign exchange rate of CAD $1.10 to USD $1.00, gold recovery of 88%, and silver recovery of 75%.

Mineral resources reported by zone and classification are summarized in Table 14-31 and Table 14-32 for open pit and underground areas, respectively.

 

 

14-46


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-31: Open Pit Mineral Resources1, Rainy River Project, Ontario, SRK

Consulting (Canada) Inc., November 2, 2013

 

     Measured      Indicated      Inferred  

Domain

   Quantity
‘000 t
     Grade
Au g/t
     Au Metal
‘000 oz.
     Quantity
‘000 t
     Grade
Au g/t
     Au Metal
‘000 oz.
     Quantity
‘000 t
     Grade
Au g/t
     Au Metal
‘000 oz.
 

Within Pit Shells

                          

ODM/17

     22,258         1.20         860         94,639         1.06         3,228         50         0.56         1   

433

     4,318         1.16         161         13,256         1.06         451         257         0.66         5   

HS

              13,774         0.66         292         4,928         0.63         100   

CAP

              23,558         0.57         435         217         0.54         4   

Western

                       1,400         1.26         57   

601

                       1,753         0.74         42   

602

                       2,302         0.72         53   

603

                       1,884         0.71         43   

604

                       4,382         0.52         74   

605

                       841         0.57         15   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Total

     26,576         1.19         1,021         145,227         0.94         4,406         18,014         0.68         394   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

 

1. 

Reported at a cut-off grade of 0.30 g/t gold based on a gold price of USD $1,400 per ounce of gold and assuming a gold metallurgical recovery of 90%. Other metals not considered.

Table 14-32: Underground Mineral Resources1, Rainy River Project, Ontario,

SRK Consulting (Canada) Inc., November 2, 2013

 

     Measured      Indicated      Inferred  

Domain

   Quantity
‘000 t
     Grade
Au g/t
     Au Metal
‘000 oz.
     Quantity
‘000 t
     Grade
Au g/t
     Au Metal
‘000 oz.
     Quantity
‘000 t
     Grade
Au g/t
     Au Metal
‘000 oz.
 

ODM/17

     88         4.97         14         3,915         4.51         568         171         3.96         22   

433

              369         4.43         53         65         4.39         9   

HS

              33         5.50         6         129         3.59         15   

CAP

              13         3.46         1         412         3.33         44   

Western

                       206         5.79         38   

Intrepid

              1,139         4.58         168         136         5.22         23   

601

                       570         6.15         113   

602

                       110         3.64         13   

603

                       438         4.04         57   

604

                       333         3.58         38   

605

                       69         3.08         7   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Total

     88         4.97         14         5,469         4.53         796         2,641         4.46         379   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

 

1. 

Reported at a cut-off grade of 2.50 g/t gold based on a gold price of USD $1,400 per ounce of gold and assuming a gold metallurgical recovery of 90%. Other metals not considered.

 

 

14-47


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

14.11 Grade Sensitivity Analysis

The mineral resources of the Rainy River Project are highly sensitive to the selection of a reporting cut-off grade. To illustrate this sensitivity, grade tonnage curves for the entire mineral resource model are presented in Figure 14-10, block model quantities and grade estimates are also presented in Table 14-33 at various cut-off grades.

Table 14-34 and Table 14-35 show the sensitivity of potential open pit and underground material to the gold cut-off grade. The reader is cautioned that the figures in these tables should not be misconstrued as a Mineral Resource Statement. The figures are only presented to show the sensitivity of the block model estimates to the selection of a reporting cut-off grade.

 

LOGO

Figure 14-10: Rainy River Project Global Grade Tonnage Curves

(Open Pit and Underground Material Combined)

 

 

14-48


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-33: Global Block Model Quantities and Grade Estimates1 at Various Cut-Off Grades

 

Cut-off

   Measured      Indicated      Inferred  

Au

g/t

   Quantity
‘000 t
     Grade
Au g/t
     Au Metal
‘000 oz.
     Quantity
‘000 t
     Grade
Au g/t
     Au Metal
‘000 oz.
     Quantity
‘000 t
     Grade
Au g/t
     Au Metal
‘000 oz.
 

0.1

     43,066         0.83         1144         547,195         0.71         12,451         1,206,710         0.24         9,367   

0.2

     3,884         1.01         1101         384,719         0.94         11,617         393,279         0.46         5,813   

0.3

     7,126         1.20         1047         263,277         1.23         10,441         214,434         0.64         4,406   

0.35

     24,465         1.30         1019         220,328         1.40         9,886         172,427         0.71         3,956   

0.4

     22,440         1.38         995         188,412         1.55         9,413         129,376         0.82         3,421   

0.5

     19,153         1.54         948         153,399         1.78         8,802         70,419         1.13         2,561   

0.6

     16,470         1.70         900         129,794         1.99         8,309         47,711         1.40         2,148   

0.7

     14,197         1.87         853         104,359         2.30         7,714         34,083         1.69         1,848   

0.8

     12,235         2.05         806         85,843         2.60         7,186         23,950         2.06         1,586   

0.9

     10,531         2.24         759         72,175         2.90         6,719         19,280         2.33         1,443   

1.0

     9,255         2.42         720         61,480         3.19         6,307         16,075         2.58         1,331   

1.2

     7,240         2.79         649         51,175         3.52         5,788         12,150         2.99         1,168   

1.4

     5,700         3.19         585         39,949         4.07         5,224         9,843         3.34         1,056   

1.6

     4,736         3.54         539         32,061         4.61         4,751         7,823         3.75         943   

1.8

     3,904         3.93         494         26,195         5.16         4,345         5,776         4.40         817   

2.0

     3,305         4.30         457         21,617         5.72         3,974         4,811         4.83         748   

2.2

     2,785         4.72         422         18,306         6.22         3,659         4,099         5.22         688   

2.4

     2,421         5.08         395         15,655         6.71         3,377         3,396         5.73         626   

2.5

     2,281         5.24         384         13,951         7.13         3,199         3,113         5.98         598   

2.6

     2,172         5.38         375         12,986         7.37         3,077         2,876         6.23         577   

2.8

     1,937         5.70         355         11,788         7.64         2,897         2,493         6.69         537   

3.0

     1,738         6.02         336         10,367         8.07         2,691         2,216         7.08         504   

3.5

     1,320         6.91         293         8,539         8.47         2,325         1,598         8.36         430   

4.0

     1,063         7.68         262         6,666         9.24         1,980         1,216         9.59         375   

5.0

     766         8.90         219         4,956         10.07         1,604         731         11.97         282   

10.0

     195         14.41         90         2,880         10.86         1,006         113         17.31         63   

 

1. The reader is cautioned that the figures in this table should not be misconstrued as a Mineral Resource Statement. The figures are only presented to show the sensitivity of the block model estimates to the selection of a cut-off grade.

 

 

14-49


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-34: Block Model Quantities and Grade Estimates1 at Selective

Cut-off Grades - Potential Open Pit Mining Material

 

Category

   Quantity
‘000 t
     Grade
Au g/t
     Au Metal
‘000 oz.
     Grade
Ag g/t
     Ag Metal
‘000 oz.
 

Cut-off Grade 0.25 g/t Au

              

Measured

     29,712         1.10         1,048         1.72         1,642   

Indicated

     173,409         0.83         4,653         2.27         12,657   

Measured & Indicated

     203,120         0.87         5,702         2.19         14,299   

Inferred

     23,727         0.58         444         1.57         1,198   

Cut-off Grade 0.35 g/t Au

              

Measured

     23,975         1.29         994         1.84         1,415   

Indicated

     122,819         1.06         4,172         2.49         9,830   

Measured & Indicated

     146,794         1.09         5,166         2.38         11,245   

Inferred

     14,109         0.78         354         1.94         879   

 

1. 

The reader is cautioned that the data presented in this table should not be misconstrued as a Mineral Resource Statement. The figures are only shown to illustrate the sensitivities of the block model quantities and grade estimates to the selection of a cut-off grade.

Table 14-35: Block Model Quantities and Grade Estimates1 at Selected

Cut-off Grades – Potential Underground Mining Material

 

Category

   Quantity
‘000 t
     Grade
Au g/t
     Au Metal
‘000 oz.
     Grade
Ag g/t
     Ag Metal
‘000 oz.
 

Cut-off Grade 2.0 g/t Au

              

Measured

     113         4.37         16         2.67         10   

Indicated

     8,550         3.74         1,029         9.62         2,646   

Measured & Indicated

     8,663         3.75         1,044         9.53         2,655   

Inferred

     3,993         3.71         477         7.38         947   

Cut-off grade 3.0 g/t Au

              

Measured

     70         5.57         12         2.96         7   

Indicated

     4,331         5.06         705         13.19         1,838   

Measured & Indicated

     4,401         5.07         717         13.03         1,844   

Inferred

     5,152         5.21         863         7.47         1,237   

 

1. 

The reader is cautioned that the data presented in this table should not be misconstrued as a Mineral Resource Statement. The figures are only shown to illustrate the sensitivities of the block model quantities and grade estimates to the selection of a cut-off grade.

 

 

14-50


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Figure 14-11 presents a plan showing the distribution of the open pit mineral resources relative to the USD $1,400 conceptual pit outline.

 

 

LOGO

Figure 14-11: Distribution of Open Pit Mineral Resources Relative to the Conceptual Pit Outline

 

14.12 Previous Mineral Resource Estimates

A comparison between the October 10, 2012 and the November 2, 2013 Mineral Resource Statements is shown in Table 14-36. The reduction in Measured and Indicated Open Pit Mineral Resources grade is primarily due to the increase in block size in 2013 (from 5 m x 5 m x 5 m to 10 m x 10 m x 10 m) and the reduction in reporting cut-off grade from 0.35 g/t gold to 0.30 g/t gold. The reduction in Inferred resources is due to a difference in mineral resource reporting methodology in relation to a conceptual pit shell. The increase in the Underground Mineral Resources is primarily due to the addition of the Intrepid Zone to the Mineral Resource Statement.

 

 

14-51


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 14-36: Comparison of the October 2012 and November 2013 Mineral Resource Statements

 

      Quantity     Grade (g/t)     Contained Metal (oz.)  

Classification

   (tonnes)     Gold     Silver     Gold     Silver  

Open Pit

          

Measured

     -4     -10     -6     -13     -9

Indicated

     15     -12     -11     0     3

Measured & Indicated

     11     -13     -9     -2     1

Inferred

     -81     -6     -22     -82     -85

Underground

          

Measured

     1     0     0     0     0

Indicated

     32     1     85     33     144

Measured & Indicated

     31     1     85     32     143

Inferred

     194     7     79     216     428

 

 

14-52


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

15. MINERAL RESERVE ESTIMATE

 

15.1 Introduction

As defined by the Canadian Institute of Mining, Metallurgy and Petroleum within the CIM Definition Standards on Mineral Resources and Mineral Reserves (CIM Special Volume 56), the definition of a mineral reserve is as follows:

“A Mineral Reserve is the economically mineable part of a Measured or Indicated Mineral Resource demonstrated by at least a Preliminary Feasibility Study. This Study must include adequate information on mining, processing, metallurgical, economic and other relevant factors that demonstrate, at the time of reporting, that economic extraction can be justified. A Mineral Reserve includes diluting materials and allowances for losses that may occur when the material is mined.”

For studies at the Prefeasibility and Feasibility levels, the CIM guidelines require that only material categorized as Measured or Indicated Resources be classified as a reserve.

 

15.2 Open Pit Mining

BBA was responsible for the design of the open pit mine and the evaluation of the associated capital and operating costs. Surface mining at the Rainy River Project will follow the standard practice of an open pit operation, with a conventional drill and blast, load and haul cycles using a drill/truck/shovel mining fleet. The overburden and waste rock material will be hauled to the overburden and waste disposal areas near the pit. The run-of-mine ore will be drilled, blasted and loaded by hydraulic shovels and delivered by large mining trucks to the primary crusher or stockpiles.

 

15.2.1 Resource Block Model

The mining engineering work required for the Feasibility Study, such as the pit optimization, engineered pit design, mine planning and economic analysis, is based on the resource Block Model prepared by SRK and delivered to BBA on August 6th, 2013. The model was transferred by BBA into the MineSight mining software for the open pit portion of the Feasibility Study. The unit block size in the model is 10 m x 10 m x 10 m. BBA used the same digitized topographical and bedrock mapping data provided by Rainy River for the 2013 Feasibility Study. The UTM NAD83 coordinate system was used.

 

 

15-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The following data was provided by SRK in the model:

 

 

UTM coordinates;

 

 

Rock type (ODM/17, Zone 433, HS Zone, CAP Zone, etc.);

 

 

Density;

 

 

Au (gold in g/t);

 

 

Ag (silver in g/t);

 

 

Percent (% of the block within a modeled wireframe);

 

 

OP/UG (Open pit or underground classification, not used);

 

 

Cat (Categories: 1 = Measured, 2 = Indicated or 3 = Inferred);

 

 

Pt (platinum, not loaded in MineSight);

 

 

Pd (palladium, not loaded in MineSight);

 

 

Ni (nickel, not loaded in MineSight);

 

 

Cu (copper, not loaded in MineSight);

 

 

S (sulphur, not loaded in MineSight);

 

 

Ca (calcium, not loaded in MineSight);

 

 

AP (acid generation classification – acid potential);

 

 

NP (acid generation classification – acid neutralizing capacity); and

 

 

NPR (acid generation classification – net potential ratio).

Additional variables were added to BBA’s MineSight model in order to perform required calculations such as equivalent-gold, and to determine block value.

Following the import of the Block Model into MineSight, a verification of the total mineral resources by category was performed and confirmed in order to insure conformity with the results provided by SRK.

 

15.2.1.1 Model Surfaces

In addition to the block model file, two (2) surface files were provided to BBA. Both files were provided in the same UTM NAD83 coordinate system as the block model:

 

 

Topography surface; and

 

 

Overburden surface (interface bedrock/overburden).

 

 

15-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The two (2) files are used to provide information about the percentage of overburden and rock below the topographic surface and the overburden/bedrock contact.

The overburden surface that was provided is important for understanding the large variability of overburden thickness in the pit area. The overburden thickness can reach up to 50 m in the centre region of the pit as indicated in Figure 15-1.

 

 

LOGO

Figure 15-1: Isopach Mapping of Overburden Thickness

 

15.2.1.2 Density

The density for the mineralized blocks, as coded in the SRK Block Model, range from 2.77 t/m3 to above 3.00 t/m3 and average 2.85 t/m3. The recommended in-situ overburden density (i.e. material that is at least 50% above the bedrock surface and below the topographic surface) is 1.80 t/m3. Blocks in the model that were not coded as ore or overburden were defaulted as waste. These blocks have a density coding of 2.80 t/m3.

 

 

15-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

15.2.1.3 Model Gold and Silver Recoveries

The gold and silver mill recoveries are determined from metallurgical testwork results (presented in Section 13.15 of Chapter 13 of this report) and are coded in the Block Model and used for pit optimization. The gold and silver recovery equations derived from the recovery curves for CAP zone and Non-CAP zones.

It is important to note that the gold and silver recovery in the model was only calculated for the blocks that are either classified as a Measured or Indicated Resource. This is demonstrated by the relevant definitions for the CIM Standards/NI 43-101, that state that a Mineral Reserve is the economically mineable section of a Measured or Indicated Mineral Resource demonstrated by at least a Preliminary Feasibility Study. Using this definition, no recovery, and no economic value is given to the blocks within the model that are categorized as an Inferred Resource.

 

15.2.2 Open Pit Optimization

In order to develop an optimal engineered pit design for the Rainy River deposit, an optimized pit shell was first prepared using the Lerchs-Grossman (LG) 3D open pit optimization routine in MineSight (LG 3D). The LG 3D pit optimizer algorithm will find a set of blocks with the maximum value per tonne, creating an optimized pit shell from the 3D block model.

With defined pit optimization parameters including gold and silver prices, mining, processing and other indirect costs, Au and Ag recoveries for each ore type (as determined from metallurgical testwork), pit slopes (as recommended by AMEC based on a geotechnical pit slope study) and other project related constraints, the pit optimizer searches for the pit shell with the highest undiscounted cash flow. In accordance with the guidelines of the NI 43-101 and the Canadian Institute of Mine Metallurgy and Petroleum Definition Standards for Mineral Resources and Mineral Reserves, only blocks classified as either Measured or Indicated are allowed to drive the pit optimizer for a feasibility study.

 

 

15-4


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

15.2.2.1 Pit Optimization Parameters

The main pit optimization parameters used in the LG 3D routine are listed in Table 15-1.

The costs for the pit optimization process were based on best information available at the time of the study, including costs from the initial 2013 Feasibility Study, gold and silver mill recoveries developed during the initial phase of the Feasibility Study, costs from similar mining operations and BBA experience.

Table 15-1: Pit Optimization Parameters

 

Type of Activity

   Unit    Values

Mining Cost of Rock1

   $/t mined    1.95

Mining Cost of Overburden1

   $/t mined    1.50

Processing Cost1

   $/t milled    8.65

General and Administration Cost1

   $/t milled    1.21

Gold Recovery (average)

   %    89.9

Gold Recovery for CAP zone (average)

   %    74.3

Silver Recovery (average)

   %    67.1

Silver Recovery for CAP zone (average)

   %    69.5

Gold Selling Price

   USD/oz.    Varied by $100 increments

Silver Selling Price

   USD/oz.    25

Exchange Rate

   CAD/USD    1.05

Overall Pit Slope Angle

   degree    Varies from 37 to 53
depending on zone

Overall Overburden Slope Angle

   degree    16

Pit Limitation

      RRP Property

Depth/elevation constraint

   masl    -50

 

1. 

Pit optimization parameters differ from the final operating cost figures. The pit optimization parameters were taken as an initial iteration to determine the optimized pit shell.

The LG 3D pit optimization was run using complex slopes approach due to various pit slope angles by sectors. It is important to note that all the slopes have been reduced by 3 degrees on average from the final design specification provided by AMEC and presented in Chapter 16 in order to account for operational design factors such as ramps, geotechnical berms and benching arrangements that will be incorporated subsequently in the final engineering design process.

 

 

15-5


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

In addition to the aforementioned processing and pit slope parameters, there were also various limits and constraints that were imposed as agreed upon by BBA and New Gold. These are as follows:

 

 

A constraint was provided from Bayfield’s Burns property to the east of the pit (New Gold owns surface rights to the Burns property while mineral rights are owned by Bayfield Ventures Corp.); and

 

 

A -50 masl elevation constraint was applied to the pit optimization. In accordance with the PEA Update results, New Gold decided that the option for an open pit be limited to a depth of -50 m with the underground operation for the Feasibility Study. The average topographic elevation of the pit is 350 m and is limited to a depth of 400 m.

The aforementioned constraints and buffer zones are indicated in Figure 15-2, along with the selected theoretical pit shell.

 

15.2.2.2 Pit Optimization Results

Using the technical and economic parameters described previously, the MineSight LG 3D pit optimizer tool was used to produce an optimum pit shell at various gold prices for the Rainy River deposit. Once the series of pit shells are generated, the total material moved, total in-pit resource and stripping ratios were used to select the optimum pit shell. The selection methodology was based on the stripping ratio and a mine life of approximately 15 years to maximize the NPV. Based on this analysis, the chosen optimized pit for this Feasibility Study was the pit having a gold price of US$800/oz.

A plan view of the LG 3D pit shell is shown in Figure 15-3. The pit edge commences at an elevation of approximately 350 masl with the pit bottom is located at approximately -50 masl.

The theoretical pit shell resulting from the LG 3D optimization is only preliminary and does not represent a practical design for mining. This optimized pit shell was used as a guide for the detailed mine design based on the required operational haulage ramp, proper pit slopes and benching arrangements as presented in Section 15.2.2.1.

 

 

15-6


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 15-2: Rainy River Theoretical Pit Shell and Bayfield constraint (Plan View)

 

15.2.2.3 Mill Cut-Off Grade

The break-even cut-off grade or the milling cut-off grade (“COG”) is used to classify the material inside the pit limits as rock or waste. For material located inside the pit, the break-even cut-off is the grade required to cover the costs for processing, General and Administrative (“G&A”) costs and other costs related to gold refining and transport. The mill COG was calculated at 0.30 g/t Au, including an average dilution rate of 5%.

Table 15-2 presents the results of a sensitivity analysis of the gold mill COG versus various gold prices and dilution. This analysis confirms the selected COG of 0.30 g/t Au, and benchmarks well with similar gold operations.

 

 

15-7


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 15-2: Mill COG Calculated at Various % Dilution and Gold Prices1

 

Gold Price    % Dilution using 0.2g/t Au grade  

(USD/oz.)

   0%      5%      10%      15%  

800

     0.42         0.44         0.46         0.48   

900

     0.37         0.39         0.41         0.42   

1000

     0.33         0.35         0.37         0.38   

1100

     0.30         0.32         0.33         0.35   

1200

     0.28         0.29         0.31         0.32   

1300

     0.26         0.27         0.28         0.29   

1400

     0.24         0.25         0.26         0.27   

 

15.2.2.4 Equivalent Gold Grade

An equivalent gold grade (Au eq Grade) is used in order to take into account the silver revenues when using the gold COG to classify a block as ore or waste. The silver grade is transferred to its corresponding gold grade using the following calculation:

 

  Eq Au (g/t) = Au (g/t) +   Ag (g/t) * Ag price ($/oz.) * Ag mill recovery (%)
   

Au price ($/oz.) * Au mill recovery (%)

 

15.2.3 Detailed Mine Design

The detailed mine design was carried out using the selected LG 3D pit shell as a guide. The proposed pit design includes the practical geometry required in a mine, including pit access and haulage ramp to all pit benches, pit slope design, benching configurations, smoothed pit walls and catch berms. The major design parameters used are described in Table 15-3.

Table 15-3: Detailed Open Pit Mine Design Parameters

 

Parameter

  

Value

Benching Arrangement

   3 x 10 m

Berm Width

   10.5 m – 12 m (AMEC 2013F)

Inter-Ramp Angle (IRA)

   40° - 56.3° (AMEC 2013F)

Bench Face Angle (BFA)

   50°- 75° (AMEC 2013F)

Ramp Width (1-lane)

   20 m

Ramp Width (2-lane)

   33 m

Ramp Grade

   10%

 

 

15-8


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The in-pit haulage roads are 33 m wide to accommodate the proposed 220-tonne haul trucks. This ramp will provide sufficient room for 2-way traffic and minimize the truck cycle times. A single-lane ramp of 20 m wide will be placed near the bottom of the pit design in order to minimize the overall stripping ratio of the pit. All in-pit ramps have been restricted to a 10% gradient. All slope configurations and angles are based on recommendations indicated in the AMEC Geotechnical studies.

There are two (2) in-pit haulage ramps in the final pit design as follows:

 

 

The main ramp exits on the east side of the pit in order to provide easy access to the site infrastructure such as the primary crusher, the east rock pile and to the low grade ore stockpile;

 

 

The second ramp exits on the west side of the pit for a shortened access to the west rock pile and overburden pile. The designed pit is approximately 1,700 m in length by 1,400 m wide and 400 m deep. The lowest bench is at an elevation of 50 m below sea level.

Figure 15-3 presents a detailed plan view of the proposed open pit mine (final pit) and Figure 15-4 presents an isometric view of the final pit and the selected optimized pit shell. Figures 15-5 to 15-12 present typical bench plans and cross-sections of the detailed pit versus the optimized pit. A COG of 0.30 g/t Au eq is shown in the coloured blocks.

 

 

15-9


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

 

Figure 15-3: Detailed Open Pit Mine Design (Plan View)

 

 

15-10


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 15-4: Final Pit Design and LG Optimization – Isometric View

 

 

15-11


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 15-5: Final Pit Design and LG Optimization – Elevation 290 masl

 

 

15-12


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 15-6: Final Pit Design and LG Optimization – Elevation 160 masl

 

 

15-13


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 15-7: Final Pit Design and LG Optimization – Elevation 10 masl

 

 

15-14


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 15-8: Final Pit Design and LG Optimization – Cross Section (East 425 400, looking West)

 

 

15-15


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 15-9: Final Pit Design and LG Optimization – Cross Section (East 425 500, looking West)

 

 

15-16


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 15-10: Final Pit Design and LG Optimization – Cross Section (East 425 600, looking West)

 

 

15-17


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 15-11: Final Pit Design and LG Optimization – Cross Section (East 425 700, looking West)

 

 

15-18


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 15-12: Final Pit Design and LG Optimization – Cross Section (East 425 800, looking West)

 

 

15-19


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

15.2.4 In-Pit Dilution and Mine Recovery

The mining dilution encountered during mining operation is defined as the addition of the material below the COG delivered to the mill due to over-mining at the ore/waste contacts and ore blocks below the COG inside mineralized zones that cannot be physically separated from mining methods. “Orphan” ore blocks that cannot be separated from waste are not mined. The mine recovery is the percentage of recovered ore blocks above the COG.

Using the resource block model, the dilution rate and the mine recovery were estimated for the mine. In the estimation, it was assumed that the selected mining method will be optimum, i.e., good blasting practice as well as a good practice of dilution control. Under this best case scenario, it was assumed that the main source of dilution and mine mineralized material loss will be at the contact between the mineralized material and waste.

The method used to estimate the mining dilution and mine recovery is based on a manual procedure that involves drawing mining polygons on a series of equally-spaced bench plans inside the mine design area. This method is based on the following guidelines to ensure that the estimate is consistent and systematic throughout the selected benches:

 

 

The minimum mining width is 7 m (1 block);

 

 

Contact dilution of 1 m at the mineralized material/waste contact;

 

 

Contact mineralized material loss of 0.5 m when the mining width exceeds the minimum mining width (7 m);

 

 

The “orphan” blocks are not mined; and

 

 

The estimation of the in-pit dilution was carried out on five (5) selected equally spaced benches.

Using the assumptions outlined above, BBA has estimated a total mining dilution of 7.79% at a grade of 0.21 g/t Au in the 10m x 10m x 10m block model for the Feasibility Study.

In the 5m x 5m x 5m block model for the original 2013 Feasibility Study, the average grade was 0.998 g/t Au, based on a COG of 0.30 g/t Au. Using the same COG, the average grade became 0.955 g/t Au in the 10m x 10m x10m block model for the Feasibility Study, indicating that a “built-in” dilution was inherently added when using larger unit block sizes. BBA has estimated the “built-in” dilution in the block model and the net mining dilution as follows:

 

 

15-20


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

• Total dilution estimate in the 10m x10m x 10m model:

   7.79%

• Gold average grade in the 5m x 5m x 5m model:

   0.998 g/t

• Gold average grade in the 10m x 10m x 10m model:

   0.955 g/t

• “Built-in” dilution in 10m x 10m x 10m block model:

   4.31%,e.g.(0.998-0.955)/0.988

• Net dilution estimate in the 10m x 10m x 10m model:

   3.48%, e.g. 7.79% - 4.31%

Table 15-4 presents the final values of dilution, dilution grade and mine recovery (or ore loss) used.

Table 15-4: Estimation of In-pit Dilution and Mine Recovery

 

Parameter

   Units    Value

In-Pit Dilution

   %    4.0

Dilution Au Grade

   g/t Au    0.21

Dilution Ag Grade

   g/t Ag    1.19

Mine Recovery (ore loss)

   %    95 (5)

15.2.5 Open Pit Mineral Reserves

     

 

15.2.5 Open Pit Mineral Reverves

Using the engineered pit design, the open pit mine contains 100.1 Mt of diluted reserves in the Proven and Probable categories at an average grade of 0.96 g/t Au and 2.49 g/t Ag. Total waste material amounts to 318.2 Mt of waste rock and 73.6 Mt of overburden resulting in an overall open pit strip ratio of 3.91 (tonnes of waste rock and overburden per tonne of ore). Table 15-5 presents the final open pit Mineral Reserves for the Rainy River pit.

Table 15-5: Open Pit Mineral Reserves Statement1,2

 

Open Pit Mineral

Reserves

   Tonnage
(Mt)
     Gold Grade
(g/t)
     Silver Grade
(g/t)
     Contained Gold
(oz)
     Contained Silver
(oz)
 

Proven

     22.7         1.14         1.88         830 279         137 0407   

Probable

     77.4         0.91         2.67         2 274 646         6 651 985   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

TOTAL

     100.1         0.96         2.49         3 104 924         8,022,391   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

 

1. 

Open pit mineral reserves have been estimated using a cut-off grade of 0.30 g/t gold-equivalent, based on metal prices of USD $800 per ounce gold and USD $25 per ounce silver, a foreign exchange rate of CAD$1.05 to USD$1.00, gold recovery of 89.9% (non-CAP zone) and 74.3% (CAP zone) and a silver recovery of 67.1% (non-CAP zone) and 69.5% (CAP zone).

2. 

Open pit reserves have been estimated using a dilution of 4% at 0.21 g/t Au and 1.19 g/t Ag. Open Pit reserves have been estimated using a mine recovery of 95%.

 

 

15-21


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

15.3 Underground Mining

The underground mine design and the underground Mineral Reserve estimate were completed by AMC to a level of detail normally associated with feasibility studies. The Mineral Reserve estimate stated herein is consistent with the Canadian Institute of Mining, Metallurgy and Petroleum (CIM) Standards on Mineral Resources and Mineral Reserves and is suitable for public reporting.

All underground Mineral Reserves have been classified within the Probable category, and have been estimated from Measured and Indicated Mineral Resources through an appropriate consideration of practical mining constraints, ore recovery estimates and dilution estimates.

Inferred resources within in the underground mine plan account for 0.07% of the Mineral Reserves tonnage and were assigned zero grade values. AMC considers this inclusion immaterial.

The Mineral Reserves were developed from two (2) independent resource models that cover resources beneath the open pit (“ALL_FP1.dm” block model) and those in the Intrepid zone (“ALL_FINAL2.dm” block model). The two (2) resource models were provided by SRK to AMC on behalf of New Gold in August 2013 and September 2013 respectively.

 

15.3.1 Underground Mineral Reserves

15.3.1.1 Orebody Description

Ore-grade mineralization occurs in seven independent areas of differing geometry and grade; ODM West, ODM Main (Upper and Lower zones), ODM East, 433, 17 East Lower, 17 East Upper and the Intrepid zone. The bulk of the underground Mineral Reserves are contained within the ODM Main and Intrepid Zones (refer to Figure 15-13).

Ore occurs in subvertical horizons in varying widths from about 3 m to 20 m. Widths over 15 m are rare, and the weighted average across all zones is approximately 8 m. The ore footwall (FW) and hangingwall (HW) generally dip at 60 degrees or more, but can flatten locally to as low as 45 degrees in some areas. Figure 15-14 and Figure 15-15 illustrate typical sections through the ODM Main and Intrepid zones respectively.

 

 

15-22


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 15-13 : Isometric View of the Rainy River Underground Mine

 

LOGO

Figure 15-14 : Typical ODM Main Zone Cross-Sections

 

 

15-23


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 15-15 : Typical Intrepid Zone Cross-Sections

15.3.1.2 Cut-off Grade (“COG”)

A preliminary estimate of breakeven operating costs was made early in the Feasibility Study to define mining shapes from which the Mineral Reserves would be formed.

It was recognized at the time that it might be appropriate to lower the COG applied in the initial 2013 Feasibility Study (3.5 g/t Au eq) to 2.5 g/t Au eq based on the preliminary estimate of site operating costs (Table 15-6).

 

 

15-24


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 15-6: Preliminary Estimation of Operating Costs and Breakeven Cut-off Grade

 

Parameter

   Units    Values  

Mining Cost

   $/t      75.52   

Processing Cost

   $/t      8.65   

General and Administration Cost

   $/t      1.21   

Refining & Transport

   $/t      0.14   

Sustaining Capital

   $/t      2.00   

Royalties

   $/t      0.54   

Total

   $/t      88.06   

Gold Recovery

   %      88

Silver Recovery

   %      75

Gold Selling Price

   $USD/oz      1,250   

Silver Selling Price

   $USD/oz      20   

Exchange Rate

   CAD:USD      1.0   

Breakeven Au equivalent (Au eq)

   g/t      2.49   

The costs shown above were largely drawn from the initial 2013 Feasibility Study, resulting in a potential breakeven COG of 2.49 g/t Au eq. However, AMC recognized the possibility of an increase in the site operating cost projection during the Feasibility Study. An increase in mining costs to $100/t was considered to be a reasonable expectation given that the previous mining plan incorporated a significant amount of Cut-and-Fill (“C&F”) mining. The potential impact would be to increase site operating costs to $112/t and result in a breakeven COG of 3.2 g/t Au eq. Any potential increase in surface costs would further increase the breakeven COG.

Considering the above, the 3.5 g/t Au eq COG was retained for the purpose of the Feasibility Study. This COG underpins the current statement of underground Mineral Reserves.

All inputs into the calculation of the breakeven COG evolved over the course of the Feasibility Study, including the metal price scenario, metallurgical recoveries, exchange rate, underground mining costs and surface costs. Estimation of the breakeven COG based on the final inputs to the Feasibility Study yields a value of 2.75 g/t Au eq (Table 15-7).

 

 

15-25


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 15-7: Updated Estimation of Breakeven Cost and COG

 

Parameter

   Units    Values  

Mining Cost

   $/t      90.10   

Processing Cost

   $/t      9.00   

General and Administration Cost

   $/t      1.50   

Refining & Transport

   $/t      0.14   

Sustaining Capital

   $/t      6.71   

Royalties

   $/t      2.37   

Total

   $/t      109.82   

Gold Recovery

   %      95

Silver Recovery

   %      75

Gold Selling Price

   $USD/oz      1,300   

Silver Selling Price

   $USD/oz      22   

Exchange Rate

   CAD:USD      1.05   

Breakeven Au equivalent (Au eq)1

   g/t      2.75   

 

1. Also includes recognition of backfill dilution

The results indicate that COG optimization work should be undertaken at a later stage. Lowering the COG may not necessarily increase project value, and may negatively impact the head-grade in the early years of mine life. However, a detailed evaluation is required to understand all impacts associated with a change in COG.

The underground Mineral Reserves include material from both longhole stopes and the development within mineralized horizons required to access those stopes. Development through low-grade areas is inevitable in the current mine plan. As such, a lower (1.5 g/t Au eq) cut-off grade was applied to development within mineralized horizons on the basis that the mining cost is effectively sunk, and the remaining costs to process this material as mill-feed are marginal. Material below the 1.5 g/t Au eq COG will be retained underground as backfill.

15.3.1.3 Gold Equivalent (Au eq) Calculation

The application of a metal equivalent COG considered both payable metals, gold and silver. The gold to silver ratio varies throughout the deposit, most notably in the Intrepid Zone, that contains significantly more silver than the other zones. Metal prices and process recoveries were provided by New Gold.

 

 

15-26


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The Mineral Reserves have been defined on a 3.5 g/t Au eq COG. The Au eq value of each block in the resource block models was assigned through the expression below, using the parameters shown in Table 15-8:

 

  Eq Au (g/t) = Au (g/t) +   Ag (g/t) * Ag price ($/oz.) * Ag mill recovery (%)
   

Au price ($/oz.) * Au mill recovery (%)

Table 15-8: Au eq Calculation Parameters

 

Parameter

   Units    Value

Gold Selling Price

   $USD/oz    1,250

Gold Recovery

   %    88

Silver Selling Price

   $USD/oz    20

Silver Recovery

   %    75

 

15.3.2 Mining Shapes

AMC used the Mineable Shape Optimizer (“MSO”) module from the Datamine Studio 3 mine planning software package to produce design excavations (shapes) that meet both the COG and operational design criteria.

The design criteria constrain the geometry of all planned excavations to what is achievable through the planned mining methods. The preliminary shapes were refined to minimize the amount of sub-economic material within the shape volumes. Chapter 16 provides further detail on mining shapes and design parameters.

In numerous cases, the MSO process identified mineable shapes around small tonnages of mineralization meeting COG but at a considerable distance from the nearest centre of mining activity. These shapes (orphans) were invariably removed as being uneconomic to mine after consideration of the development cost required to access them.

 

15.3.3 Dilution and Recovery Estimates

The Mineral Reserves account for planned and unplanned dilution.

Planned dilution represents the portion of the design excavation (shape) that is sub-economic on a standalone basis, but must be mined to render the economic portion recoverable for practical reasons.

 

 

15-27


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Unplanned dilution includes those sources of sub-economic material that are external to the design excavation but inevitably dilute the ore in varying degrees. Unplanned dilution is manageable through proper design and mining practice, but is inherent to all operations and must be added to the base tonnage within the design mining shapes in the estimation of Mineral Reserves. These sources include waste rock dilution from stope wall sloughing and/or blasting over-break, backfill dilution from sloughing of the cemented aggregate fill (“CAF”) exposure of the previous stope in the sequence, and over-mucking of backfill that will often form the stope floor.

Stope sloughing may occur at the stope walls, and particularly at the hangingwall. The equivalent linear over-break/slough (“ELOS”) method was used by AMEC in the estimation of slough volume for the 2013 Feasibility Study. The results indicated that, on average, 0.25 m of HW overbreak/slough can be expected. Likewise, 0.25 m footwall dilution on average was estimated due to blasting over-break. AMC considers the AMEC overbreak/slough dilution assessment to be reasonable. The results are illustrated in Figure 15-16.

 

 

LOGO

Figure 15-16 : Unplanned Dilution from Hangingwall and Footwall Rock

The total unplanned dilution from rock sources (hangingwall and footwall) is estimated to be 7.4% of the design stope tonnage, as shown in Table 15-9. The design stope shapes were expanded by 0.25 m on both the hangingwall and footwall sides such that the metal value in the incremental volume would be captured when the shapes were evaluated against the block models.

 

 

15-28


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 15-9: Dilution Estimate for Hangingwall Slough and Blasting Over-break

 

Dilution source

   Depth (m)      Percent (%)  

Hanging wall slough dilution

     0.25         3.7   

Blasting overbreak dilution

     0.25         3.7   
     Total         7.4   

Backfill dilution will originate from two sources: over-mucking the floors in the longitudinal longhole open stoping (“LHOS”), and sloughing of cemented rock fill (“CRF”) from the end of the longitudinal LHOS. Backfill dilution is assumed to carry no metal grades in the compilation of Mineral Reserves.

In the longitudinal LHOS, the mucking will be a combination of manual and remote mucking. Manual mucking provides a high degree of operator control and can minimize the introduction of dilution into the production stream. Conversely, remote mucking results in less operator control and it is estimated that, on average, over-digging into the floor will introduce 0.25 m of backfill dilution.

Sloughing of the cemented aggregate fill from the previous stope in the sequence has been estimated at 0.75 m width on average. Figure 15-7 illustrates the two sources of backfill dilution.

 

 

LOGO

Figure 15-17 : Backfill Dilution

The total estimated stope dilution from end-wall sloughing and over-mucking the floor has been summarized in Table 15-10. End-wall sloughing introduces 3.3 % dilution and over-mucking of the stope floor introduces 1.0 % dilution.

 

 

15-29


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 15-10: Dilution Estimate from Backfill Sources

 

Dilution Source

   Depth (m)      Percent (%)  

End-wall sloughing from CAF

     0.75         3.3   

Over-mucking from rockfill and CAF

     0.25         1.0   
     Total         4.3   

 

15.3.4 Recovery Factors

Mining recovery factors are applied to account for the percentage of ore in the design stope that is not recovered. With longitudinal LHOS, potential ore losses can occur due to the difficulty in mucking in stope corners and edges, inefficient drilling and/or blasting in stope corners and walls, or abandoning of stopes due to excessive dilution from waste rock or backfill. AMC has applied 95% recovery to the stope inventory based on its experience.

 

15.3.5 Mineral Reserves

The total unplanned dilution is estimated to be 11.7% of the stoping inventory based on 7.4% rock dilution and 4.3% backfill dilution. Recovery of the stoping inventory is estimated to be 95%. Ore development is considered to be 100% recoverable with no dilution. When dilution is expressed on a global basis, inclusive of ore development tonnage, the average dilution of the Mineral Reserves is 8.3% and the average recovery is 96.5%. Table 15-11 presents the final underground Mineral Reserves across all zones.

Table 15-11: Underground Mineral Reserves Statement1

 

Underground
Mineral
Reserves

   Tonnage
(‘000 t)
   Gold Grade
(g/t)
   Silver Grade
(g/t)
   Contained Gold
(‘000 oz)
   Contained
Silver
(‘000 oz)

Probable

   4,187    4.96    10.31    668    1,388

 

1. Underground Mineral Reserves include 3.29 Mt of ore above a 3.5 g/t Au eq COG, grading 5.58 g/t Au and 10.72 g/t Ag, and a further 0.89 Mt of ore grading 2.70 g/t Au and 8.81 g/t Ag between 1.5 g/t Au eq COG and 3.5 g/t Au eq COG. Au price and metallurgical recovery assumed to be $USD 1,250/troy ounce and 88% respectively. Ag price and metallurgical recovery assumed to be $USD 20/troy ounce and 75% respectively. Exchange rate of $CAD = $USD. Average dilution and mining recovery estimated at 8.3% and 96.5% respectively.

 

15.4 Open Pit and Underground Mineral Reserves

In accordance with the NI 43-101 standards of mineral classification, the measured and indicated resources inside the final pit limits have been transferred into Proven and Probable reserves. All underground reserves have been transferred into Probable reserves. Table 15-12 shows a detailed summary of the in-pit and underground reserves.

 

 

15-30


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 15-12: Open Pit and Underground Proven and Probable Mineral Reserves1,2,3,4,5,6

 

Mineral Reserves
Category

  Tonnage
(‘000 t)
    Au Grade
(g/t)
    Ag Grade
(g/t)
    Contained
Metal Au (koz)
    Contained
Metal Ag (koz)
 

Direct Processing Material

         

Open Pit

         

Proven

    15,839        1.47        2.04        746        1,038   

Probable

    46,866        1.26        3.05        1,896        4,594   

Underground

         

Proven

    —          —          —          —          —     

Probable

    4,187        4.96        10.31        668        1,388   
 

 

 

   

 

 

   

 

 

   

 

 

   

 

 

 

Total Direct Processing Material

    66,892        1.54        3.26        3,311        7,021   
 

 

 

   

 

 

   

 

 

   

 

 

   

 

 

 

Stockpile Material

         

Open Pit

         

Proven

    6,843        0.38        1.51        84        332   

Probable

    30,541        0.39        2.10        378        2,058   
 

 

 

   

 

 

   

 

 

   

 

 

   

 

 

 

Total Stockpile Material

    37,384        0.38        1.99        462        2,390   
 

 

 

   

 

 

   

 

 

   

 

 

   

 

 

 

Combined Direct Processing and Stockpile Material

         

Open Pit

         

Proven

    22,681        1.14        1.88        830        1,370   

Probable

    77,407        0.91        2.67        2,275        6,652   
 

 

 

   

 

 

   

 

 

   

 

 

   

 

 

 

Total

    100,088        0.96        2.49        3,105        8,022   
 

 

 

   

 

 

   

 

 

   

 

 

   

 

 

 

Underground

         

Proven

    —          —          —          —          —     

Probable

    4,187        4.96        10.31        668        1,388   
 

 

 

   

 

 

   

 

 

   

 

 

   

 

 

 

Total

    4,187        4.96        10.31        668        1,388   
 

 

 

   

 

 

   

 

 

   

 

 

   

 

 

 

Total Combined

         

Proven

    22,681        1.14        1.88        830        1,370   

Probable

    81,594        1.12        3.06        2,943        8,040   
 

 

 

   

 

 

   

 

 

   

 

 

   

 

 

 

TOTAL

    104,275        1.13        2.81        3,773        9,410   
 

 

 

   

 

 

   

 

 

   

 

 

   

 

 

 

 

1. 

Open pit mineral reserves have been estimated using an optimized pit shell based on metal prices of USD $800 per ounce gold and USD $25 per ounce silver, a foreign exchange rate of CAD $1.05 to USD $1.00, gold recovery of 89.9% (non-CAP zone) and 74.3% (CAP zone) and a silver recovery of 67.1% (non-CAP zone) and 69.5% (CAP zone). The cut-off grade is based on a gold price of USD $1,200. Underground reserves have been estimated from mining shapes generated using a cut-off grade of 3.5 g/t gold-equivalent. Development material from stope access drives above a cut-off grade of 1.5 g/t gold-equivalent is also assumed to be sent to the mill for processing. Underground breakeven cut-off grade calculated at 2.75 g/t gold-equivalent based on metal prices of USD $1,300 per ounce gold and USD $22 per ounce silver, a foreign exchange rate of CAD $1.05 to USD $1.00, gold recovery of 95% and a silver recovery of 75%.

2. 

Open pit reserves have been estimated using a dilution of 4% at 0.21 g/t Au and 1.19 g/t Ag. An average dilution of 11.7% for the underground stoping (8.3% total underground, inclusive of development ore that includes dilution from both overbreak and backfill. Open pit and underground reserves have been estimated using a mine recovery of 95% and 96.5%, respectively.

3. 

Open pit direct processing material is defined as mineralization likely to be mined and processed directly and above a variable cut-off grade ranging from 0.3-0.7 g/t.

4. 

Stockpile material includes all material within designed open pit between variable cut-offs described above in Note 3, as well as material within the CAP zone (code 500) that is suitable for stockpiling and future processing.

5. 

Mineral Reserves for the open pit are derived from the resource model effective November 2, 2013. Models for the underground reserves were derived from the August 2013 and September 2013 models for the main ODM zone and Intrepid Zone, respectively. Models were prepared by Dorota El-Rassi, P.Eng. (APEO #100012348) and Glen Cole, P.Geo. (APGO #1416), of SRK, both independent “Qualified Persons” as that term is defined in Canadian National Instrument 43-101. The combined mineral resource statement, including the Intrepid Zone was provided to BBA on November 2, 2013. Rainy River’s exploration program in Richardson Township is being supervised by Mark A. Petersen, (AIPG Certified Professional Geologist #10563), Vice President, Exploration for New Gold and a “Qualified Person” as defined in Canadian National Instrument 43-101. New Gold continues to implement a rigorous QA/QC program to ensure best practices in drill core sampling, analysis and data management.

6. 

Qualified persons - The open pit portion of the mineral reserve statement was prepared under the supervision of Patrice Live (OIQ #38991) of BBA, and the underground portion of the mineral reserve statement was prepared by Colm Keogh, P.Eng. (APEGBC #37433) of AMC Mining Consultants (Canada) Ltd., both independent “Qualified Persons” as that term is defined in Canadian National Instrument 43-101.

 

 

15-31


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

16. MINING METHODS

 

16.1 Introduction

The Feasibility Study assumes both open pit and underground mining methods will be used for reserve extraction. The milling throughput rate was established at 21,000 tpd (19,500 tpd from the open pit and 1,500 tpd from underground when full production is achieved). The location of the open pit, underground access ramp (main portal), haul roads, stockpiles and waste rock piles are shown on the Project general layout in Appendix F. The open pit operations will deliver material to a gyratory crusher for primary size reduction and delivery to the processing plant. Ore from the underground operation will be fed to a portable crushing system for size reduction and tramp metal removal prior to being delivered to the gyratory crusher. Utilization of New Gold’s mining equipment and personnel is envisaged for the development of the open pit, as well as for the removal of overburden. In addition, a combination of New Gold personnel and various contractors will be used for underground development and ongoing production activities.

Figure 16-1 shows a representation of the underground and open pit mine at the end of Year 2030, looking north.

 

 

LOGO

Figure 16-1: Isometric View of the Rainy River Open Pit and Underground Mine, Looking North

 

 

16-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

16.2 Open Pit Mining Methods

 

16.2.1 Open Pit and Stockpiles Geotechnical Designs

 

16.2.1.1 Open Pit Geotechnical Design

The feasibility level site investigation work and open pit slope design criteria were developed by AMEC (2012F; 2012G, 2013D, 2013E, 2013F) and provided to BBA for open pit development. The approximate dimensions of the pit will be 1,700 m [length] x 1,400 m [width] x 400 [depth] (in the main south pit, ODM Zone). The northern section of the pit (433 Zone) will be approximately 325 m deep.

The bedrock geology is composed of metavolcanic rock that hosts the multi-lens gold deposit. These lenses dip between 50° to 65°. For the most part, the bedrock is overlain by 10 to 40 m of overburden consisting of primarily silty clays separated by clay till, with gravelly sand till and boulders directly overlaying the bedrock. The assessment of various rock structural domains was based on the analysis of 10 NQ sized boreholes, with geomechanical logging of oriented core and packer testing. These boreholes were oriented in various azimuths, dipping at around 65° and totalling 4.4 km of drilling. Additionally, 10 exploration boreholes were surveyed by DGI Geoscience Inc. using acoustic and optical televiewer tools.

The primary jointing identified at the site is the foliation set that follows the dip of the ore lenses, strikes approximately east-west and dips to the south, at approximately 55° (in the south ODM pit) or 49° (in the north 433 pit). The two (2) other sets are sub-vertical, striking essentially north-south, and in the south pit dip towards the west at approximately 75°, while in the north pit dip towards the west at 85°. A persistent east dipping fault striking north-south transects the pit (Figure 16-2); however, due to the fault orientation and only a localized increase in the fracture frequency, the fault is not expected to impact the overall wall stability. The rock mass typically observed has two (2) to two plus (2+) random major joint sets with a “good” rock mass rating and geological strength index (“GSI”) ranging from 64 to 72. A total of 176 core samples were collected for strength testing with 268 test specimen prepared. A total of 117 specimens were tested for uniaxial compressive strength (“UCS”); 42 for triaxial strength; 100 for Brazilian tensile strength, and nine (9) for direct shear tests of open joints (AMEC, 2013D). Based on laboratory strength testing, felsic volcanics (the predominant wall rock) were found to be strong, to very strong rocks ranging from 71 to 116 MPa in UCS.

 

 

16-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Design sectors for the open pit were based on probabilistic kinematic analysis to identify plane, wedge and toppling failure cumulative probabilities; plane and wedge failure probabilistic stability analyses; as well as probabilistic overall slope stability analyses using limit equilibrium (Figure 16-2). Most bench face angles (“BFA”) will be cut at 70° to 75°, with inter-ramp angles (“IRA”) comprised between 54.5° and 56.3° and overall slope angles (“OSA”) in bedrock of 40.6° to 54.5°, with an average bench width of 10.5 m and final bench height of 30 m. To ensure stability, bench widths will be increased to 12 m to prevent toppling failure in the south walls of both pits, as well as in the west wall of the south pit. Additionally, BFAs will be reduced to 50° or 55° to limit planar or wedge failures in the north walls of both pits. A summary of the design guidelines and bench configurations can be seen in Figure 16-2 and Table 16-1. A 20 m set-back at the overburden-bedrock interface will be placed to allow access and monitoring of overburden slopes and the pit. A 20 m geotechnical berm is recommended for the south wall of ODM, in which the inter ramp spacing is greater than 200 m. Under partially saturated conditions, with a disturbance factor of 0.7 and a seismic (pseudo static) load of 0.1, the worst case scenario for the south wall of ODM will have a deterministic factor of safety (“FOS”) of 1.29, and a probability of failure (“POF”) of 7.7%, which meets the accepted minimum FOS used for designing operating open pits. The other bedrock walls typically have an FOS ranging from 1.37 to 2.5 for similar conditions (AMEC 2013F).

Table 16-1: Recommended Overall Slope Geometry by Sector (AMEC, 2013F)

 

Rock

  

Segment

  

Bench Face
Angle

(°)

  

Bench
Height
(m)

  

Bench
Width
(m)

  

IRA
(°)

FLS

   5, 10    50    3x10    10.5    40.0

FLS

   3    55    3x10    10.5    43.6

FLS

   4, 6, 7, 9    70    3x10    10.5    54.5

FLS

   1    73    3x10    12    54.8

FLS

   2, 8    75    3x10    12    56.3

In order to maintain short and long-term stability of the overburden material, the slopes in the overburden will range from 20° (2.75W:1H) to 17° (3.25W:1H) for overburden less than 25 m thick, and between 17° (3.25W:1H) to 14° (4W:1H) for overburden greater than 25 m, respectively (AMEC, 2012F).

 

 

16-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 16-2: Open Pit Design Zones & Recommendations (AMEC, 2013F)

 

16.2.1.2 Waste Rock and Overburden Stockpile Design

Geotechnical slope stability recommendations were provided for the mine waste rock and overburden stockpiles (AMEC 2013c). The rate of stockpile development will control stability due to excess pore pressures generated in the foundation soils (AMEC 2013a). From a stability perspective, the slopes at the south perimeter of the West Mine Rock Stockpile and west side of the East Mine Rock Stockpile are critical, as the height is greatest and the upper varved clay strata is the thickest.

Mine rock stockpile slopes of 6H:1V have been adopted in the critical areas. The high in-situ moisture contents of the end-dumped overburden, which will have low strength and tend to develop high induced pore water pressure during construction, dictate shallower external slopes of 8H:1V to meet the required safety factors.

 

 

16-4


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Stockpile construction will follow the observational approach. If higher than expected pore pressures or significant deformations in the foundation are noted, then mitigative measures such as flattening the overall slope or raising the toe berm along the south side of the West Mine Rock Stockpile will be implemented to ensure stability, in particular adjacent to the Pinewood River.

 

16.2.2 Open Pit Mine Planning

 

16.2.2.1 Whittle Consulting Enterprise Optimization (Whittle, 2012)

In July 2012, Ausenco (in partnership with Whittle Consulting) provided recommendations on the open pit mine planning strategy based on the Whittle Consulting Enterprise Optimization (“EO”) methodology; an in-house strategic tool for mining operations. The EO methodology is an integrated approach to maximizing the NPV of a mining operation by simultaneously optimizing up to ten (10) different mechanisms across the mining value chain. The main objective is to isolate the critical cost drivers and maximize value throughout the mining system. Contained in the business model are a series of calculations that are performed on every block in the resource model to generate revenue and cost fields that are then used for pit optimization and scheduling by Prober software. Prober is a Whittle Consulting in-house software used for strategic mine planning.

The EO Study was conducted to support the PEA Update and subsequent studies for the Rainy River Project. The EO process is iterative and the business model tends to evolve with the costs and resource model. Two (2) generations of resource models have been used thus far in the Study, with several fixed gold recoveries. Costs also evolved slightly during the PEA Update process.

Analyses conducted for the PEA Update and FS, using the June 2011 block model include:

 

 

Base case assessment;

 

 

Variable cut-off grade and stockpile value contributions;

 

 

Mining capacity trade-off;

 

 

Processing capacity trade-off;

 

 

16-5


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

Underground cut-over trade-off;

 

 

Pit and phase design based on Enterprise Optimization economics using the theory of constraints and activity-based costing; and

 

 

NPV-optimized schedules calculated by Whittle Consulting’s proprietary software, Prober.

Whittle Consulting generated a series of mining scenarios by varying different parameters such as mining capacity, processing capacity and depth limit. BBA was provided with a pit phasing and stockpile movement strategy by period that was used as a guideline for detailed mine planning. The results of the mining rate assessment provided in the EO study suggested that a constant mining rate of 100 Mtpa of total material moved would yield the highest NPV. Since the initial EO study was based on the PEA results for a milling rate of 32 ktpd, the mining rate was adjusted to approximately 60 Mtpa to match the selected milling rate of 21 ktpd in the current Feasibility Update Study. The use of an elevated cut-off grade strategy over the life of mine has resulted in a significant amount of low grade ore stockpiled material.

 

16.2.2.2 Open Pit Mining Phases

Based on the EO report, BBA prepared an open pit mine production schedule based on the August 2013 block model provided by SRK. In order to optimize the operational stripping ratio in the early years of the Project, and to increase the Project’s NPV, two (2) optimized shells for an initial pit (Phase 1) and an intermediate pit (Phase 2), representing four (4) to five (5) years of mining each, were generated using the Lerchs-Grossman 3D MineSight optimization algorithm. The open pit mining phases were designed using the same design parameters as the final pit design (Phase 3) and were used as a guide to prepare the first few years of the LOM mine plan. Between each mining phase, there will be a transitional period during which stripping of the next phase will be started before the end of the previous phase in order to maintain a constant supply of ore to the mill.

The mining phases presented in Figure 16-3 show the mining phases in 3D view where the years represent the rock excavation period. Figures 16-4 and 16-5 show the mining phases in longitudinal cross-section.

 

 

16-6


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 16-3 - Phase 1, Phase 2 and Final Pit - 3D View

 

LOGO

Figure 16-4: Phase 1, Phase 2 and Final Pit – Cross-section (East 425 500,

Looking West)

 

 

16-7


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 16-5: Phase 1, Phase 2 and Final Pit – Cross-section (East 425 700,

Looking West)

 

16.2.2.3 Elevated Cut-Off Grade (“COG”) Strategy

Based on the strategic mine plan study prepared by Whittle Consulting, an elevated COG was strategically employed from years 2016 to 2024 with the objective to maximize the Project’s IRR and NPV. Material between the LOM COG (0.30 g/t Au eq) and the yearly COG was stockpiled for processing at the end of the mine life. The total low grade ore material stockpiled during the open pit operations amounts to 37.5 Mt at an average grade of 0.39 g/t Au and 1.99 g/t Ag.

 

16.2.2.4 Mill Ramp-up

The Project production schedule was developed using the mill ramp-up as follows:

 

 

November 2016: from 0% to 30% (average 3.15 ktpd during the month);

 

 

December 2016: from 30% to 60% (average 9.45 ktpd during the month);

 

 

January 2017: from 60% to 100% (average 16.8 ktpd during the month); and

 

 

February 2017: 100% (21 ktpd).

 

 

16-8


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The milling rate remains at 21 ktpd until the mineral reserves are depleted.

 

16.2.2.4.1 Pre-Production Period

The mining production schedule is based on a pre-stripping period of 24 months, starting in Q1 2015 and ending in Q4 2016. Mill start-up is slated to begin at the end of Q4 2016. The pre-production plan was developed on a quarterly basis using the MineSight-Interactive Planner tool.

The pre-production first quarter starts in the bedrock outcrop above the CAP zone (south part of Phase 1), to provide aggregate for the construction of the plant area and access roads. The remainder of the pre-production period focus is to prepare for mine operation by opening faces on ore in Phase 1 pit. The overburden stripping of Phase 2 starts during the last quarter of the pre-production period (Q4 2016). Approximately 22.4 Mt of material is moved in 2015 (Year -2) and 25.7 Mt in 2016 (Year -1), see Figure 16-6 and Figure 16-7.

 

LOGO

Figure 16-6: Open Pit Mine Planning – End of 2015 (Year -2)

 

 

16-9


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 16-7: Open Pit Mine Planning—End of 2016 (Year -1)

 

16.2.2.4.2 Production Period

The production period plan has been designed on a quarterly basis for 2017 (Year 1) and the first two (2) quarters of 2018 (Year 2), on a semi-annual basis for the second half of 2018 (Y2) and 2019 (Year 3), and on an annual basis for the following years.

Ore production starts in November 2016 in Phase 1 and an elevated COG of 0.6 g/t Au to 0.7 g/t Au is applied for the first two (2) years of production. Phase 1 continues until the beginning of 2020 (Y4). Ore is mined from Phase 2 in 2018 (Year 3) to 2022 (Year 6) and from Phase 3 in 2021 (Y5) to 2025 (Y9).

After the mill ramp-up period (Q4 2016 – Q1 2017), the mill will be fed with ore from the open pit at a rate of 21,000 tpd until 2018. During the period between 2019 and 2028, the open pit mine and underground mine will feed approximately 19,500 tpd and 1,500 tpd of ore, respectively, to the mill.

The total material moved is 53.2 Mt in 2017 (Year 1) and ramps up to a maximum annual mining rate of approximately 68 Mt in 2019 (Year 3) and 2020 (Year 4). Open Pit mine production slowly decreases until the pit is depleted mid-way through 2025 (Year 10).

 

 

16-10


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Figure 16-8 to Figure 16-12 show a series of key end-of-period maps.

 

LOGO

Figure 16-8: Open Pit Mine Planning – End of 2017 (Year 1)

 

LOGO

Figure 16-9: Open Pit Mine Planning – End of 2018 (Year 2)

 

 

16-11


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 16-10: Open Pit Mine Planning – End of 2020 (Year 4)

 

LOGO

Figure 16-11: Open Pit Mine Planning – End of 2022 (Year 6)

 

 

16-12


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 16-12: Final Pit Contour—End of 2025 (Year 9)

 

16.2.2.4.3 Low-grade Ore Stockpile Rehandling Period

During the open pit operation, 37.5 Mt of low-grade ore at an average grade of 0.39 g/t Au and 1.99 g/t Ag are stockpiled in an effort to increase the initial feed grade to the mill. From the total, 4.2 Mt of ore from the CAP zone, regardless of the gold grade, will be separated and kept on a designated area on the low-grade ore stockpile for processing at the end of the mine life due to its resistance to cyanide leaching and hence, lower gold recoveries.

The low-grade ore stockpile is located between the East Mine Rock Stockpile and the primary crusher, in the East Mine Rock Stockpile area. The East Mine Rock Stockpile is approximately 1 km (road distance) from the primary crusher. After the pit is depleted, the mill is fed at a rate of 19,500 to 21,000 tpd from the low-grade ore stockpile mid-way through 2025 (Year 9) to 2030 (Year 14), depending on the underground production in Years 2025 (Year 9) to 2028 (Year 12).

The open pit material movement trends over the life of the mine can be seen graphically in Figure 16-13. The effect of the stockpiling strategy is significant as the mill head grade (green line) is higher in the early years due to a higher mill COG when compared to the average mill head grade of 0.96 g/t Au over the mine life.

 

 

16-13


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 16-13: Open Pit Material Movement over the Life-of-Mine

 

 

16-14


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

16.2.3 Material Management

During the pre-production and production stages of the Project, a significant amount of waste rock and overburden material is removed and stored in nearby disposal areas. A portion of this material will be used for tailings dam and road construction, as well as for site reclamation. The waste rock and overburden piles presented in this section were designed without removing any waste material that might be used for site construction. All design parameters for the various stockpiles are based on the AMEC recommendations (AMEC 2013D, E, F, G).

The waste rock material will be placed onto two (2) waste stockpiles: the West Mine Rock Stockpile (the non-potentially acid generating pile (“NPAG”)) and the East Mine Rock Stockpile (the potentially acid generating pile (“PAG”)). The neutralization potential ratio (“NPR”) is used to classify the waste rock: the waste rock with a NPR > 2 is considered as NPAG and the waste with a NPR £ 2 is considered as PAG. According to the NPR, approximately 50% of the waste rock in the open pit is considered to be PAG material.

The West Mine Rock Stockpile area is located west of the pit and contains the NPAG and the overburden (“OB”) material. The East Mine Rock Stockpile area is located east of the pit contains the PAG and low-grade ore material. The general arrangement of the piles around the pit can be seen in Figure 16-14.

Plan views of the stockpiling areas with slope and height details are presented in Figure 16-15 and Figure 16-16.

 

 

16-15


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 16-14: Site Plan Showing West and East Mine Rock Stockpiles

 

LOGO

Figure 16-15: East Mine Rock Stockpile Area

 

 

16-16


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 16-16: West Mine Rock Stockpile Area

 

16.2.3.1 Waste Mine Rock Stockpile Design

The waste mine rock stockpiles have been designed according to the waste requirements of the pit and are located around the periphery of the mine to minimize the haulage distance. An in-situ waste rock density of 2.8 t/m3 and a swell factor of 30% have been assumed for the design of the waste mine rock stockpiles. The West and East Mine Rock Stockpiles are located and sized to fit entirely within New Gold’s land holdings and are kept at an adequate distance from all major water basins.

The waste mine rock stockpiles were designed according to the parameters presented in Table 16-2. These parameters were selected according to an inter-ramp slope of 6H:1V, as recommended by AMEC. This inter-ramp slope has been used for the external stockpile slopes only. A steeper angle of 3H:1V has been used for internal slopes on the East Mine Rock Stockpile area, as shown in Figure 16-15. Due to the bearing capacity of the ground in the south area of the East Mine Rock Stockpile, AMEC also recommends that a shallower inter-ramp angle of 8H:1V be used for the south slope of the East Mine Rock Stockpile.

 

 

16-17


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 16-2: Waste Mine Rock and Low-Grade Ore Stockpile Design Parameters

 

Waste Mine Rock and Low-Grade Ore Piles

   Unit    Value

Bench Face Angle

   degrees    33

Inter-ramp Slope Angle

   degrees    Varied from 3H:1V to 8H:1V

Catch Bench Width

   m    Varied from 20 to 66

Bench Height

   m    15

Ramp Width

   m    33

Ramp Grade

   %    10

Swell Factor

   %    30

The West (NPAG) and East (PAG) Mine Rock Stockpiles have a capacity of approximately 75 Mm3 each and are built in 5 m lifts, with 15 m bench heights. Stockpiling has been sequenced in phases to allow for shorter hauls during earlier years of operation. The design summary of the West and East Mine Rock Stockpiles can be found in Table 16-3.

Table 16-3: Waste Mine Rock Stockpile Characteristics

 

Parameters

   Unit   Value  

West Mine Rock Stockpile (NPAG)

    

Height

   m     60   

Top Elevation

   masl     410   

Footprint Area

   M m2     2.2   

East Mine Rock Stockpile (PAG)

    

Height

   m     45   

Top Elevation

   masl     422   

Footprint Area

   M m2     3.0   

 

16.2.3.2 Low Grade Ore Stockpile Design

The low-grade ore material between the LOM COG and the yearly COG is stockpiled in a reserved area of the East Mine Rock Stockpile next to the PAG material. It is located close to the crusher to reduce the haulage distance during the reclaiming process. The material property assumptions used for the design of the low-grade ore stockpile are an in-situ ore density of 2.85 t/m3 and a swell factor of 30%. The low grade ore stockpile is also located entirely within

 

 

16-18


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Rainy River’s mining claims. The low-grade ore stockpile has a capacity of 17 Mm3 and is designed according to the same design parameters as the waste rock piles in Table 16-2. The design summary of the low-grade ore stockpile can be found in Table 16-4.

Table 16-4: Low-Grade Ore Stockpile Characteristics

 

Low-Grade Ore Stockpile

   Unit   Value  

Height

   m     45   

Top Elevation

   masl     422   

Footprint Area

   M m2     0.57   

 

16.2.3.3 Overburden Stockpile Design

Overburden material will be removed during the period from 2015 (Year -2) to 2021 (Year 5). The Overburden Stockpile located west of the pit will have a capacity of 50 Mm3. The material property assumptions used for the design of the Overburden Stockpile is an in situ density of 1.8 t/m3 and a swell factor of 20%. The stockpile is entirely located within Rainy River’s mining claims or leasing claims.

The Overburden Stockpile is designed according to the design parameters presented in Table 16-5. These parameters were selected according to an inter-ramp slope of 8H:1V, as recommended by AMEC (AMEC 2013).

Table 16-5: Overburden Stockpile Design Parameters

 

Overburden Stockpile

   Unit    Value

Bench Face Angle

   degrees    20

Inter-ramp Slope Angle

      8H:1V

Berm Width

   m    81

Bench Height

   m    15

Ramp Width

   m    33

Ramp Grade

   %    10

Swell Factor

   %    20

The Overburden Stockpile will be built in 5 m lifts, with 15 m bench heights. The design summary can be found in Table 16-6.

 

 

16-19


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 16-6: Overburden Stockpile Design Summary

 

Overburden Stockpile

   Unit   Value  

Height

   m     60   

Top Elevation

   masl     410   

Footprint Area

   M m2     1.95   

 

16.2.3.4 In-Pit Dumping

In order to reduce the cycle time, quantity of haul trucks and to limit the environmental impact of the stockpile, an in-pit dumping area will be used for NPAG material. The dump is located on the north extension of the pit and has a capacity of 15 Mt of NPAG waste rock. The area will be used from the end of Year 7 to the end of Year 8 to store a portion of the NPAG material.

Figure 16-17 shows an isometric view of the in-pit dump and the dumping sequence proposed.

 

LOGO

Figure 16-17: In-Pit Dumping Area and Dumping Sequence

 

 

16-20


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

16.2.4 Open Pit Mine Equipment and Operations

The Rainy River deposit will be mined using conventional open pit mining methods based on a truck/shovel operation. All equipment will be diesel-powered, except for one (1) electric hydraulic shovel. The mining fleet requirement was calculated using the production schedule presented in Table 16-27. All equipment is assumed to be owned, operated and maintained by New Gold.

Open pit mine operations are based on 720 shifts per year and correspond to operations running 2 x 12 hour shifts per day, 7 days per week and 360 days per year, with the assumption that five (5) operating days will be lost on average due to weather conditions. The open pit mining operations division will consist of the pit operations, maintenance, engineering and geology departments.

The mining methods are based on conventional drilling and blasting, followed by loading and hauling. The selection of the primary fleet is based on operating time assumptions, mechanical availability, mechanical utilization, haulage distance assumptions, cycle time assumptions, truck speed and fuel consumption profiles. The primary mining fleet consists of the following:

 

 

The primary loading equipment for overburden, waste rock and ore are: two (2) diesel hydraulic shovels with a rated bucket capacity of 26 m3 and one (1) electric hydraulic shovel with a rated bucket capacity of 29 m3. One (1) wheel loader (18 m3 class) will be used on an as needed basis to complete the loading equipment fleet. However, the loader will be used to its full capacity from 2018 (Year 2) to 2021 (Year 5) and an extra unit (rented) will be required as well for 2019 (Year 3) and 2020 (Year 4). The flexibility of the loader, with its fast response time, justifies its use in replacing a shovel in loading support activities;

 

 

The haul truck fleet is based on trucks with a 220-tonne class payload, which matches well with the selected hydraulic shovels. The haul truck fleet starts with six (6) trucks in the pre-production phase and will gradually increase to a maximum of 22 trucks in Year 2020 (Year 4 of production); and

 

 

Production drilling will be accomplished using a fleet of diesel powered Down-the-Hole (“DTH”) blast hole rigs drilling 8 1/2” diameter holes.

 

 

16-21


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

16.2.4.1 Operating Time Assumptions

The productive operating time available for each shift has been calculated for two (2) categories: 1) primary equipment; and 2) drills. They are separated in order to take into account extra scheduled delays typically associated with the drills, such as additional time required for moving between drill patterns and spotting time between blast holes.

Scheduled delays for the primary equipment and drills take into account operator lunch breaks, inspection and fueling, shift changes, and coffee breaks. Table 16-7 provides information on the scheduled delays taken into consideration.

Table 16-8 shows how net operating hours (“NOH”) are derived from scheduled and unscheduled delays. Unscheduled delays are defined as delays that are outside of human control and cannot be predicted. These types of delays can take into account traffic delays, matching factors and the efficiency of equipment movement. These factors were estimated based on similar operations.

Table 16-7: Operating Shift Parameters

 

Shift Parameters

   Value     Unit

Shifts per Day

     2     
Worker and Equipment Shift Operating Time

Shift Change

     15      min

Inspection

     15      min

Coffee Break

     20      min

Lunch Break

     30      min

Job Efficiency Factor (JEF)

     83  
Drills Operating Time

Shift Change

     15      min

Inspection

     15      min

Coffee Break

     20      min

Lunch Break

     30      min

Job Efficiency Factor (JEF)

     75  

 

 

16-22


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 16-8: Equipment and Worker Operating Time

 

Operating Time Calculations

   Value      Unit
Worker and Equipment Operating Time

Scheduled Time

     720       min

Scheduled Delays

     80       min

Scheduled Operating Time

     640       min

Unscheduled Delays

     107       min

Total Delays

     187       min

Net Operating Time

     533       min

Net Operating Hours

     8.89       hr
Drills Operating Time

Scheduled Time

     720       min

Scheduled Delays

     80       min

Scheduled Operating Time

     640       min

Unscheduled Delays

     160       min

Total Delays

     240       min

Net Operating Time

     480       min

Net Operating Hours

     8.00       hr

 

16.2.4.2 Equipment Mechanical Availability, Utilization and Operator Skill Factors

For each piece of major equipment, mechanical availability, utilization and operator skill factors were designated. The mechanical availability is a percentage that represents the hours when the equipment cannot be operated due to breakdowns or planned maintenance. These factors were derived from supplier recommendations and/or experience. Equipment utilization, also referred to as the “use of availability”, refers to the time that a piece of equipment is available and operated productively. It takes into account the low efficiency of the equipment operator during the first months of utilization (learning curve). The mechanical availability and utilization factors used over the LOM are illustrated in Table 16-9.

 

 

16-23


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 16-9: Major Equipment Availability and Utilization

 

     Time Interval

Equipment

   0 - 6,000
hrs
    6,000 -
12,000
hrs
    12,000 -
18,000
hrs
    18,000 -
24,000
hrs
    24,000 -
30,000
hrs
    30,000 hrs -
expected life of
equipment

Haul Trucks

            

Haul Truck Availability

     88     88     87     87     86   83% – 85%

Haul Truck Utilization

     95     95     95     95     95   95%

Shovels

            

Diesel Shovel Availability

     88     87     85     85     84   81% – 83%

Diesel Shovel Utilization

     95     95     95     95     95   95%

Electric Shovel Availability

     89     88     86     86     85   81% – 83%

Electric Shovel Utilization

     95     95     95     95     95   95%

Drills

            

Drill Availability

     88     87     86     84     83   83%

Drill Utilization

     95     95     95     95     95   95%

The operator skill factor has been applied to haul trucks, hydraulic shovels, drills and loaders, as presented in Figure 16-10.

Table 16-10: Major Equipment Operator Skill

 

Year

   Operator Skill Factor  

2015 (Year - 2)

     90

2016 (Year - 1)

     90

2017 (Year 1) and +

     100

A mechanical availability of 88%, a variable utilization and an operating skill of 100% have been used for other support equipment.

 

16.2.4.3 Drilling and Blasting

The drill and blast design for the Study was developed by BBA, in collaboration with explosive suppliers familiar with this type of operation.

 

 

16-24


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The ore zones will be drilled using 8- 1/2 inch diameter holes on a drilling pattern of 5.5 m spacing x 6.5 m burden. Waste rock areas will use the same hole diameter, but a larger drilling pattern of 7.0 m x 7.5 m. The spacing and burden for the ore zone is tighter to produce better fragmentation and selectivity. It was assumed that 20% of the waste zone will be drilled using the ore zone pattern.

Holes will be drilled to a total depth of 11.2 m, including 1.2 m of sub-drilling for a 10 m bench height. A stemming height of approximately 4.0 m will be used to maximize the effectiveness of the explosive column. Based on the production schedule, up to three (3) drills will be required.

Blasting will be executed under contract with an explosive company that will supply the blasting materials and technology, as well as the equipment to store and deliver the explosive products. The explosives will be manufactured on-site by the explosives supplier in a purpose built bulk emulsion plant. The explosive supplier will also be responsible for providing a down-the-hole service.

Blasting will be conducted using a 100% emulsion-type explosive with an average density of 1.25 kg/m3. Bulk emulsion was selected as it is easily transportable and has a lower environmental impact than other types of explosives resulting in lower ammonium nitrate levels emitted into the watershed.

Based on the drilling pattern described above, the powder factor has been estimated at 0.323 kg/tonne in ore and 0.224 kg/tonne in waste.

It is also assumed that pre-split will be required for the final walls. Pre-split is executed on a 30 m bench using a spacing of 1.7 m and a hole diameter of 5.5 inches. The holes are loaded with continuous water gel or emulsion cartridges which are more precise and practical to use for this application.

A summary of the drill and blast specifications can be found in Table 16-11.

 

 

16-25


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 16-11: Drill and Blast Specifications

 

Drill Specifications

 

Parameter

   Unit   Ore      Waste  

Hole diameter

   mm     215.9         215.9   

Hole area

   m2     0.0366         0.0366   

Bench height

   m     10         10   

Sub-drill

   m     1.2         1.2   

Stemming

   m     4.0         4.0   

Loaded length

   m     7.2         7.2   

Hole spacing

   m     5.5         7.0   

Burden

   m     6.5         7.5   

Penetration rate

   m/hr     42.0         42.0   

Re-drill

   %     10         10   

Rock mass/hole

   t     1,019         1,470   

Bulk Emulsion

 

Density

   kg/m3     1,250         1,250   

kg/hole

   kg/hole     329         329   

Powder factor

   kg/tonne     0.323         0.224   

 

16.2.4.4 Loading and Hauling

Production will be carried out using a fleet of 220-tonne class capacity haul trucks and hydraulic shovels with a bucket capacity of 26 m3 in ore and 26 m3 to 29 m3 in waste rock. The number of trucks operating at any given time is dependent on the annual production rate and varies over the mine life. This fleet combination should allow for four (4) pass-loadings of trucks hauling ore and waste and five (5) to six (6) pass-loadings of trucks hauling overburden. A maximum of 22 haul trucks will be required in the peak years.

The maximum shovel productivity per shift has been estimated at 30,300 tonnes of ore, 35,900 tonnes of waste per shift and 22,500 tonnes of overburden. Loading operations will also be assisted by one (1) large wheel loader to maximize the flexibility of the operation. The loader will be used as production equipment but also as a replacement for the shovel in down-time situations, as well as for other tasks involving material handling.

 

 

16-26


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Average annual haul profiles were created for ore, waste rock and overburden. The haulage distances were further divided for in-pit flat hauls, in-pit ramp hauls, flat on topography hauls and for crusher and waste piles. In the MineSight® software, haul routes were traced according to mining centroids for every bench (and material) for each year. Subsequently, with these centroid distances and the respective tonnage per bench (per material) mined, the weighted and averaged distances were calculated on a yearly basis. The in-pit ramp distances were also averaged in the same manner.

In order to optimize the waste cycle times for operation, dumping has been sequenced in phases to allocate shorter hauls during earlier years of the LOM. Centroid and up-ramp distances were traced for the waste pile locations and crusher location.

Haulage travel speeds and fuel consumptions for the trucks were based on supplier experience and were fine-tuned using factors from BBA’s equipment database. The travel speeds and fuel consumptions are shown segmented by type of haul in Table 16-12.

Table 16-12: Truck Speed and Fuel Consumption (Loaded and Empty)

 

     Haul Truck Loaded  

Parameter

   Acceleration
100 m
     Flat (0%)
Topo
     Flat (0%)
In-Pit/
Crusher/
Dump
     Slope Up
(10%)
     Deceleration
100 m
 

Speed (km/h)

     20         40         40         13         20   

Fuel consumption (litres/hr)

     393         150         200         375         27   
     Haul Truck Empty  

Parameter

   Acceleration
100 m
     Flat (0%)
Topo
     Flat (0%)
In-Pit/
Crusher/
Dump
     Slope
Down
(-10%)
     Deceleration
100 m
 

Speed (km/h)

     25         50         50         25         25   

Fuel consumption (litres/hr)

     118         118         118         27         27   

 

 

16-27


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The calculated cycle times were based on round-trip haulage profiles, haul truck speeds, and load/stop dump times determined for each material. A trend of cycle time for each material type over the LOM is shown in Figure 16-18.

 

LOGO

Figure 16-18: Cycle Time Trend over LOM

 

16.2.4.5 Equipment Annual Fleet Requirements

The primary mining fleet was selected based on the scale of this mining operation, optimization fleet size utilization and matching of equipment, efficiency and reliability. At the peak point in the mine life (2020 - 2022), primary equipment requirements will be as follows:

 

 

22 x 220-tonne class diesel haul trucks;

 

 

2 x 26m3 diesel-hydraulic shovels;

 

 

1 x 29m3 electric-hydraulic shovel;

 

 

1 x 18m3 front end loader; and

 

 

3 x 8  1/2” DTH blast hole drills.

 

 

16-28


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The haul truck fleet is shown in Figure 16-19 and follows the mined material trend over the LOM. The truck fleet takes also into consideration the units used during the construction of the tailings dam and during the PAG pile reclamation work.

 

LOGO

Figure 16-19: LOM Haul Truck Fleet

To complement the primary mining equipment fleet, a list of auxiliary and support equipment was developed by BBA and validated with New Gold based on experience in similar open pit mining operations. The requirements for support equipment were determined primarily based on the scale of the operation, the size and number of active waste rock piles and length of haul roads to be maintained.

Over the life of the operation, no primary equipment replacement is required. After 2025 (Year 9), the final pit is depleted and most pieces of equipment are no longer needed. Hence, during the stockpile re-handling period, less equipment is required and utilization is reduced significantly. The only equipment replacement will be the used auxiliary loader in 2020 (Year 4) that will be used mainly in the aggregate plant area.

 

 

16-29


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 16-13 shows the annual mine equipment fleet requirements over the open pit production stage to support the mining operation for each year.

During the open pit post-production stage (stockpile reclaim from 2025 to 2030), fewer equipment will be required to support activities related to stockpile re-handling, site rehabilitation and site maintenance. The necessary post-open pit equipment is: three (3) trucks (two (2) operating and one (1) back-up), one (1) diesel-hydraulic shovel, one (1) large wheel loader as a replacement for the shovel in down time, three (3) track-dozers, one (1) wheel-dozer and one (1) motor-grader. The mine will also keep some key equipment that will be operated only on an as needed basis, such as one (1) water truck and one (1) fuel truck.

 

 

16-30


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 16-13: Annual Open Pit Mine Equipment Requirements

 

     Pre-Production
Period
     Production Period      Stockpile Rehandling Period  
     2015      2016      2017      2018      2019      2020      2021      2022      2023      2024      2025-
Q1 Q2
     2025-
Q3 Q4
     2026      2027      2028      2029      2030  

Haul Truck Fleet

                                                  

Haul Truck

     6         7         13         19         21         22         22         22         20         12         8         2         2         2         2         2         2   

Shovel Fleet

                                                  

Hydraulic Shovel (Diesel)

     2         2         2         2         2         2         2         2         2         2         2         1         1         1         1         1         1   

Hydraulic Shovel (Electric)

           1         1         1         1         1         1         1         1                        

Drill Fleet

                                                  

Blastholes Drill

     1         2         3         3         3         3         3         3         2         2         1                     

DTH Drill (Reverse Circulation Sample, Pre- Split)

     2         2         2         2         2         2         2         2         2         1         1                     

Support Fleet

                                                  

Wheel Loader

     1         1         1         1         1         1         1         1         1         1         1         1         1         1         1         1         1   

Rental Loader

                 1         1                                    

Motor Grader

     1         2         3         3         3         3         3         3         3         3         2         1         1         1         1         1         1   

Track-Dozer 580 HP

     3         4         5         5         5         5         5         5         5         5         2         2         2         2         2         2         2   

Track-Dozer 580 HP / for dyke construction and site rehabilitation

     1         1         1         1         1         1         1         1         1         1         1         1         1         1         1         

Wheel-Dozer 680 HP

           1         1         1         1         1         1         1         1         1         1         1         1         1         1         1   

Auxiliary Fleet

                                                  

Compactor

           1         1         1         1         1         1         1         1         1         1         1               

Water Truck (30 KL)

     1         1         1         1         1         1         1         1         1         1         1         1         1         1         1         1         1   

Water Truck (75 KL)

     1         1         1         1         1         1         1         1         1         1         1                     

Fuel/Lube Truck

     2         2         2         2         2         2         2         2         2         2         1         1         1         1         1         1         1   

Boom Truck

     1         1         2         2         2         2         2         2         2         1         1                     

 

 

16-31


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

     Pre-Production
Period
     Production Period      Stockpile Rehandling Period  
     2015      2016      2017      2018      2019      2020      2021      2022      2023      2024      2025-
Q1 Q2
     2025-
Q3 Q4
     2026      2027      2028      2029      2030  

Wheel Loader (Used)

     1         1         1         1         1         1         1         1         1         1         1                     

Tow Haul Truck (Used)

     1         1         1         1         1         1         1         1         1         1         1                     

Hydraulic Crane, truck-mounted

     1         1         1         1         1         1         1         1         1         1         1         1         1         1         1         1         1   

Dewatering Pump (100 HP electric)

     1         2         2         2         2         2         2         2         2         2         2                     

Mobile Pump (150 HP)

     2         2         4         4         4         4         4         4         4         4         4                     

Service Truck

     1         1         1         1         1         1         1         1         1         1         1         1         1         1         1         1         1   

Tire Changer, truck-mounted

     1         1         1         1         1         1         1         1         1         1         1         1         1         1         1         1         1   

Mini Bus

     1         1         2         2         2         2         2         2         2         1         1                     

Pick-up Truck Crew Cab

     6         12         12         12         12         12         12         12         12         6         6         3         3         3         3         3         3   

Stemming Loader

     1         1         1         1         1         2         2         2         2         1         1                     

Cable Reeler (Used)

           1         1         1         1         1         1         1         1         1                     

Aggregate Plant

     1         1         1         1         1         1         1         1         1         1         1                     

Lighting Tower, 4-post of 1000 W / Diesel Generator

     4         4         6         6         6         6         6         6         6         6         6         2         2         2         2         2         2   

Total

                                                  
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Total Primary Fleet

     9         11         19         25         27         28         28         28         25         17         11         3         3         3         3         3         3   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Auxiliary Equipment

     34         43         54         54         55         56         55         55         55         45         40         17         17         16         16         15         15   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Total Mining Equipment

     43         54         73         79         82         84         83         83         80         62         51         20         20         19         19         18         18   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

 

 

16-32


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

16.2.5 Open Pit Mine Personnel Requirements

The personnel requirement for the open pit mine includes all of the hourly staff working in open pit operations that are required for the operation and maintenance of the equipment involved with or supporting mining activities, as well as the salaried engineering, geology and supervisory staff.

The number of hourly personnel reaches a peak of 267 in 2021 (Year 5). A complete list of the hourly personnel requirements is listed in Table 16-14.

The maximum number of salaried employees is 51. The mine salaried staff requirements over the life of the mine are presented in Table 16-15.

The number of operators required for the major mining equipment (haul trucks, shovels, and drills) was determined according to the number of operating units and number of rotations during which the equipment is in operation. Most of the operators for the major mine equipment are based on a four (4) crew rotation. Hourly maintenance employee requirements were determined based on the amount of equipment to maintain. The ratio of maintenance/operation for the hourly employees is approximately 0.6 during the normal years of operation. This ratio assumes that maintenance activities such as rebuilding components and machining will be performed off-site. The hourly personnel calculation also includes a 5-weeks allocation for VSA (vacation, sickness and absenteeism).

Post-operation activities (from Years 2026 to 2030), consisting of stockpile re-handling, environmental and site maintenance work, and personnel for operations and maintenance work, will allow personnel requirements to be reduced accordingly. Consequently, after the open pit is depleted, the number of hourly and salaried staff will be reduced to a total of 27.

 

 

16-33


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 16-14: Annual Hourly Personnel Requirements

 

     Pre-Production Period      Production Period      Stockpile Rehandling Period  
     2015      2016      2017      2018      2019      2020      2021      2022      2023      2024      2025-
Q1 Q2
     2025-
Q3 Q4
     2026      2027      2028      2029      2030  

Operations

                                                  

Shovel Operators

     6         6         12         12         12         12         12         10         8         4         4         4         4         4         4         4         4   

Loader Operators

     2         2         2         2         8         8         6         2         2         2         0         0         0         0         0         0         0   

Haul Truck Operators

     17         21         46         61         69         70         75         74         54         30         22         6         6         6         6         6         6   

Drill Operators

     9         10         15         16         17         17         17         17         14         8         7         0         0         0         0         0         0   

Dozer Operators

     15         15         23         23         23         23         23         23         23         23         12         4         4         4         4         4         4   

Grader Operators

     4         4         12         12         12         12         12         12         12         10         4         2         2         2         2         2         2   

Water Truck Operator/ Snow Plow/ Sanding

     4         4         4         4         4         4         4         4         4         4         4         0         0         0         0         0         0   

Auxiliary Equipment Operators

     6         8         10         10         10         10         10         10         10         10         6         2         2         2         2         2         2   

General Labour

     4         4         6         6         6         6         6         6         6         6         4         0         0         0         0         0         0   

Janitor

     2         2         2         2         2         2         2         2         2         2         1         1         1         1         1         1         1   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Hourly Open Pit Operations Total

     69         76         132         148         163         164         167         160         135         99         64         19         19         19         19         19         19   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Field Maintenance

                                                  

Field General Mechanics

     4         6         8         12         14         16         16         16         14         10         4         0         0         0         0         0         0   

Field Welder

     2         2         6         6         8         8         8         8         8         6         4         0         0         0         0         0         0   

Field Electrician

     4         4         6         6         8         8         8         8         8         6         4         0         0         0         0         0         0   

Shovel Mechanics

     4         4         8         12         12         12         12         12         12         6         4         2         2         2         2         2         2   

Shop Maintenance

                                                  

Shop Electrician

     4         4         5         5         5         5         5         5         4         4         2         0         0         0         0         0         0   

Shop Mechanic

     6         6         12         18         20         22         22         22         16         8         6         2         2         2         2         2         2   

Mechanic Helper

     2         2         10         10         10         10         10         10         6         3         1         1         1         1         1         1         1   

Welder-machinist

     2         2         4         6         6         6         6         6         4         4         1         0         0         0         0         0         0   

Lube/Service Truck

     4         4         5         5         5         5         5         5         4         4         2         0         0         0         0         0         0   

Electronics Technician

     2         2         2         2         2         2         2         2         2         2         1         0         0         0         0         0         0   

Tool Crib Attendant

     2         4         4         4         4         4         4         4         4         2         2         0         0         0         0         0         0   

Janitor

     2         2         2         2         2         2         2         2         2         2         2         0         0         0         0         0         0   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Hourly Mine Maintenance Total

     38         42         72         88         96         100         100         100         84         57         33         5         5         5         5         5         5   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Hourly Personnel Total

     107         118         204         236         259         264         267         260         219         156         97         24         24         24         24         24         24   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

 

 

16-34


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 16-15: Salaried Open Pit Personnel Requirements

 

     Pre-Production
Period
     Production Period      Stockpile Rehandling Period  
     2015      2016      2017      2018      2019      2020      2021      2022      2023      2024      2025
Q1 Q2
     2025-
Q3 Q4
     2026      2027      2028      2029      2030  

Operations

                                                  

Open Pit Superintendent

           1         1         1         1         1         1         1         1         1                     

General Mine Foreman

     1         1         2         2         2         2         2         2         2         2         1                     

Mine Shift Foreman

     4         4         8         8         8         8         8         8         8         4         4                     

Drill & Blast Foreman

        1         1         1         1         1         1         1         1         1         1                     

Blaster

     1         2         2         2         2         2         2         2         2         1         1                     

Blaster Helper

     1         2         2         2         2         2         2         2         2         1         1                     

Dispatcher

     2         4         4         4         4         4         4         4         4         2         2                     

Training Foreman

     1         1         1         1         1         1         1         1         1         1                        

Production / Mine Clerk

        1         1         1         1         1         1         1         1         1         1                     

Secretary

        1         1         1         1         1         1         1         1         1         1                     
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Salaried Open Pit Operations Total

     10         17         23         23         23         23         23         23         23         15         13         0         0         0         0         0         0   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Maintenance

                                                  

Maintenance Superintendent

           1         1         1         1         1         1         1         1         1                     

Maintenance General Foreman

     1         1         1         1         1         1         1         1         1         1         1                     

Maintenance Planner

        2         2         2         2         2         2         2         2         2         1                     

Mechanical Engineer

        1         1         1         1         1         1         1         1         1         1                     

Maintenance Foreman

     1         2         4         4         4         4         4         4         4         4         2         1         1         1         1         1         1   

Maintenance Trainer

     1         1         1         1         1         1         1         1         1         1                        

Maintenance Clerk

        1         1         1         1         1         1         1         1         1         1                     
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Salaried Mine Maintenance Total

     3         8         11         11         11         11         11         11         11         11         7         1         1         1         1         1         1   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Engineering

                                                  

Chief Engineer

           1         1         1         1         1         1         1         1         1                     

Senior Mine Planning Engineer

     1         1         1         1         1         1         1         1         1         1         1                     

Open Pit Engineer

     1         1         1         1         1         1         1         1         1         1         1                     

Geotechnical Engineer

     1         1         1         1         1         1         1         1         1         1                        

Blasting Engineer

        1         1         1         1         1         1         1         1         1                        

Mining Engineering Technician

     1         1         2         2         2         2         2         2         2         2         1                     

Mine Surveyor

     1         2         2         2         2         2         2         2         2         2         1         1         1         1         1         1         1   

Assistant Surveyor

     1         2         2         2         2         2         2         2         2         2         1                     

 

 

16-35


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

     Pre-Production
Period
     Production Period      Stockpile Rehandling Period  
     2015      2016      2017      2018      2019      2020      2021      2022      2023      2024      2025
Q1 Q2
     2025-
Q3 Q4
     2026      2027      2028      2029      2030  

Salaried Mine Engineering Total

     6         9         11         11         11         11         11         11         11         11         6         1         1         1         1         1         1   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Geology

                                                  

Chief Geologist

           1         1         1         1         1         1         1         1                        

Geologist

        1         1         1         1         1         1         1         1         1         1         1         1         1         1         1         1   

Grade Control Geologist

     1         1         2         2         2         2         2         2         2         2         1                     

Geology Technician

     1         1         2         2         2         2         2         2         2         2         1                     
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Salaried Geology Total

     2         3         6         6         6         6         6         6         6         6         3         1         1         1         1         1         1   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Total Salaried Staff

     21         37         51         51         51         51         51         51         51         43         29         3         3         3         3         3         3   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

 

 

16-36


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

16.3 Underground Mining Methods

The proposed underground mine design supports the extraction of 1,500 t/d of ore by longitudinal longhole open stoping (“LHOS”), a mining technique suitable for the geometry and ground conditions of the Rainy River underground resources. Backfilling with cemented aggregate fill (“CAF”) is a significant aspect of the project with respect to maximization of both resource recovery and mining productivity. Modern trackless equipment will be employed in the majority of mining activities.

A main decline from a surface portal located to the east of the open pit will be used to access the mine. A fleet of 7 m3 Load Haul Dump trucks (“LHDs”) and 45-tonne trucks will be used for material loading and transport from the various underground working areas through an internal ramp system that connects all levels to the main decline. Loading will occur in close proximity to the stoping areas and ore will be hauled directly to a surface coarse ore stockpile adjacent to the portal.

An extensive underground development program that attains a peak of 560 m/month of jumbo advance is required to develop and maintain access to adequate resources to sustain 1,500 tpd of ore production. The ramp-up period to full production will require five (5) years from the onset of mine development. Waste generated through infrastructure development will be disposed of in underground stopes whenever operationally practical, however, an estimated excess of 1.80 Mt must be hauled to the surface waste stockpile over the life of mine.

Key mine infrastructure includes a backfill delivery raise that terminates at an underground truck loading station, a cement storage and grout mixing facility, two (2) main dewatering stations, an equipment maintenance facility, electrical substations, and other smaller, ancillary installations. Permanent fans located on surface will provide fresh air to the mine. A propane air heating system will be used during the winter months.

Ore occurs in subvertical horizons in varying widths from about 3 m to 20 m. Widths over 15 m are rare, and the weighted average across all zones is approximately 8 m. The ore footwall (“fw”) and hangingwall (“hw”) generally dip at 60 degrees or more, but can flatten locally to as low as 45 degrees in some areas.

Ore-grade mineralization occurs in seven independent areas of differing geometry and grade. The spatial separation defines multiple working areas that support the projected 1,500 tpd production rate, and has afforded the flexibility in the production schedule to recover higher grade material earlier in the life of mine.

 

 

16-37


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Rock mass conditions are projected to be generally very good and little water ingress is anticipated.

 

16.3.1 Mine Design

 

16.3.1.1 Access and Mine Infrastructure

A 4 km main decline driven at a -15% gradient from the surface portal will provide access for personnel and equipment. The main decline will connect to independent internal production ramps that will service all levels in each mining area. In the interest of good visibility, minimizing haulage time and minimizing equipment wear, the length of straight segments was maximized in the design of the decline.

Internal production ramps are of spiral configuration, and will be generally driven at a -10% gradient to provide level access on each revolution. A 25 m minimum turning radius was employed. Passing bays, remucks and safety bays were incorporated into the decline and all internal production ramps.

The mine design includes a significant amount of raise development to establish and extend the primary air circuit. Three (3) raises to surface (two (2) exhaust raises and one (1) fresh air raise) will be required. As the mining levels are developed from the internal ramps, raising from level to level will be necessary to permit the exhaust of contaminated air by advancing the primary circuit in increments. A backfill raise from surface has also been included for the delivery of aggregate to an underground CAF plant.

Mine infrastructure will also include:

 

 

A workshop for the maintenance and repair of underground equipment

 

 

An explosives magazine and a cap magazine

 

 

A permanent refuge/lunchroom

 

 

Two (2) refueling locations for mobile equipment

 

 

A main substation near the workshop area

 

 

Two (2) main dewatering stations and a suite of local settling sumps

 

 

Definition drilling drives and cubbies where required

 

 

16-38


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

16.3.1.2 Level Development

Sublevels will be accessed from the ramps on a 20 m vertical interval that is defined by the planned stoping heights. Ramp development will be set back a minimum of 30 m from the ore contact. This arrangement promotes long-term geotechnical stability and provides adequate space for the placement of a return air raise and other services such as sumps, remucks and portable refuge locations.

Remucks on all levels will be used for the placement of blasted ore during the mining cycle. During the backfilling cycle, CAF and waste rock will be tipped here for rehandling into the stopes by LHD.

Ore drives will be developed along strike in two (2) directions from a common access point to the strike extent of the zone. In several areas, where multiple ore horizons are present, these ore drives will cross a waste divide to access stopes in the other horizons. The arrangement minimizes waste development as traditional fw drives along the strike of the orebody are not required. However, in the absence of fw drives, definition drilling must be accomplished from waste drives dedicated to this activity. The savings in waste development compared to an fw drive arrangement is significant.

Ore drives are designed to follow mineralized horizons even when they are not within ore-grade areas where stoping has been planned. This approach will generate approximately 900 kt of low-grade material (below the 3.5 g/t Au eq mining cut-off grade, but above 1.5 g/t Au eq); this material will be processed given that the mining costs are sunk and a profit can still be made from a marginal cost perspective. Material generated from the ore drives below 1.5 g/t Au eq will be retained u/g as backfill.

Figure 16-20 shows a sublevel arrangement in cross-section and Figure 16-21 shows typical level development requirements.

 

 

16-39


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 16-20: Sublevel Arrangement in Cross-section

 

LOGO

Figure 16-21: Typical Level Plan

Development design standards considered equipment size, services, and required activity. Ontario mining regulations require that main haulageways regularly used by pedestrians be at least 1.5 m wider than the maximum width of a motor vehicle. Furthermore, if the haulageway is

 

 

16-40


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

less than 2 m wider than the maximum width of the vehicle, safety bays must be included. The widest mobile equipment at New Gold, the 45-tonne truck, is 3.18 m in width. Therefore, haulageways (designed at 5 m width) with truck and pedestrian traffic such as the main and production ramps, include safety bays.

To provide adequate overhead clearance between equipment and services such as ventilation ducting, a 5 m high drive is required. The main ramp, internal production ramps, level accesses and most ventilation drives are 5 m high by 5 m wide.

Ore drives were also designed at 5 m high by 5 m wide. This width will permit adequate spacing for a remote stand for remote stope loading. AMC recommends that cut-outs for remote stands should also be considered relative to what may be seen as common and best practice in Ontario mines. The height and width also provide sufficient operating clearance for the production drill rig.

Development design parameters are summarized in Table 16-16 and Table 16-17. Figure 16-22 and Figure 16-23 illustrate standard designs for ore drives and the main decline, internal production ramps and level accesses, respectively.

 

 

16-41


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 16-16: Lateral Development Design Parameters

 

    Lateral  

Parameter

  Remuck     Ore
Drive
    Level
Access
    Main
Decline
    Expanded
Main
Decline
    Exhaust
Drift
    Production
Ramp
    Passing
Bay
    Definition
Drilling
Drift
    Safety
Bay
    Substation     Sump  

Width (m)

    5        5        5        5        6        5        5        4        5        1.5        5        5   

Height (m)

    7        5        5        5        6        5        5        5        5        2        5        4   

Length (m)

    15        —          —          —          —          —          —          20        —          1.8        8        8   

Max Gradient (%)

    2        2        2        15        15        15        15        15        2        2        2        15   

Table 16-17: Vertical Development Design Parameters

 

    Vertical  

Parameter

  Fresh Air Raise     Return Air Raise     Ventilation Drop
Raise
    Alimak Raise     Backfill Aggregate
Raise
 

Width (m)

    3     3     3        3        2

Height (m)

    —          —          3        3        —     

Length (m)

    —          —          —          —          389   

 

* Diameter

 

 

16-42


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 16-22: Standard Design – Ore Drive

 

LOGO

Figure 16-23: Standard Design – Main Decline, Internal Ramps and Level Accesses

 

 

16-43


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

16.3.2 Stope Design

AMC used the Mineable Shape Optimizer (“MSO”) module from the Datamine Studio 3 mine planning software package to produce conceptual stope shapes. Key design parameters used in MSO are summarized in Table 16-18. The conceptual stope shapes were refined as necessary to minimize the amount of planned dilution and to meet practical mining constraints.

Table 16-18: Stope Design Parameters

 

     

Parameter

  

Units

  

All Zones

 

MSO Parameters

   Au eq Cut-off*    gpt      3.5   
   Level Spacing    m      20   
   Stope length increments    m      2   
   Minimum Mining Width    m      3   
   Minimum Waste Pillar Width    m      10   
   Minimum Footwall Dip    degrees      55   
   Minimum Hanging Wall Dip    degrees      55   
   Footwall Overbreak    m      0.25   
   Hangingwall Overbreak    m      0.25   

Au eq Parameters

   Au (Gold) price    $/oz      1,250   
   Au (Gold) recovery    %      88   
   Ag (Silver) price    $/oz      20   
   Ag (Silver) recovery    %      75   

Isolated areas meeting cut-off grade were evaluated against access development costs to determine economic viability, before including them in the Mineral Reserves.

The Intrepid lower, 17 East lower, ODM West, and the upper portion of the 433 Zone contained economically marginal material that required individual analysis to determine profitability. Considering the capital development required to access and mine this material, the analysis indicated that this marginal material carried sufficient profit margin and was therefore kept within the current mine plan.

The LOM plan includes approximately 520 stopes across all mining areas. Figure 16-24 and Figure 16-25 are long-section views showing stope shapes generated by the MSO process.

 

 

16-44


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 16-24: Mineable Stope Shape – Intrepid Zone

 

LOGO

Figure 16-25: Mineable Stope Shape – ODM and 17 East Zones

 

 

16-45


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

16.3.3 Mining Method and Sequence

 

16.3.3.1 Zone Definition

The orebody zones were defined by spatial location and elevation, which facilitate 1,500 t/d of production through the creation of multiple working areas. The ore footwall (“fw”) and hanging wall (“hw”) generally dip at 60 degrees or more, but can flatten locally to as low as 45 degrees in some areas. The maximum lateral extent of the ore bodies varies significantly from 570 meters, in the ODM Main Zone to 75 m in the 17 East Upper Zone. Figure 16-26 shows the zone locations.

The Intrepid Zone contains an area of waste material effectively creating a natural sill that further divides the area into an upper and lower zone. To allow production in the ODM Main Zone without having to develop to the bottom of the zone first, a sill pillar, located in lower grade ore, is included, creating an upper and lower ODM Zone.

 

LOGO

Figure 16-26: Mining Zones

 

 

16-46


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

16.3.3.2 Stope Cycle and Sequence

The mining method will be longitudinal LHOS, retreating from the strike extent of ore on each level. Stopes are typically 20 m in length along strike and 20 m high. Stope widths (thickness of mineralization) range from about 3 m to 20 m but average approximately 8 m.

From each level access, drives will be developed within the mineralized horizon along strike on the top sill and bottom sill levels. Force ventilation will provide fresh air to the working faces. Stope production begins with a drop raise followed by a slot blast and production ring drilling. Production blasting and mucking will proceed cyclically until the stope is depleted and all ore has been mucked out.

Longitudinal LHOS is a non-entry method, with remote mucking of blasted ore required once the drawpoint brow is open to the extent where the operator may be exposed to uncontrolled sloughing from the stope cavity. To protect the operator from the remotely operated loader, a remote mucking stand is the minimum requirement; an excavated cubby may also be desirable.

The remote mucking stand is a portable prefabricated platform designed to withstand the impact of a loader in the event that control has been lost by the operator. Past practice has generally involved securing the stand to the drift sidewall for stability. Increasingly, cubbies are excavated into the drift sidewall to position the operator off any potential line of travel of the loader.

AMC recognizes that both approaches are currently used in Ontario and does not prescribe which approach should be adopted by New Gold. AMC has used the prefabricated remote mucking stand in this study for costing purposes only. Ultimately, remote mucking procedures must be established by New Gold through risk assessment and consideration of (best) safe work practices.

Once mucking of blasted ore is complete, backfilling commences with the placement of a sufficient volume of CRF to provide stability of the backfill that is re-exposed during the extraction of the next stope in sequence. Once this volume of CRF has been placed, uncemented waste from underground development or from surface is used to fill the remaining void – see Figure 16-27 and Figure 16-28.

 

 

16-47


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 16-27: Typical Stope Long Section

 

LOGO

Figure 16-28: Typical Stope Cross-sections

 

 

16-48


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Mining proceeds upwards from the lowest level of the zone or from an adopted sill elevation, with backfill providing the working platform for each successive lift. To achieve and maintain 1,500 t/d of production, multiple zones will be concurrently active.

 

16.3.3.3 Backfilling Options

An assessment of backfilling options was completed as part of the Feasibility Update Study. The proposed mining method, filling cycle time, availability of fill materials, capital cost and operating costs were the main criteria in the selection of the backfill option. The backfill types investigated include aggregate fill (“AF”) and cemented aggregate fill (“CAF”), rock fill and cemented rock fill (“RF & CRF”), paste fill (“PF”), hydraulic fill and cemented hydraulic fill (“HF/CHF”). AMC has estimated cement-dosing rates based on experience with similar operations. The outcome of the options study indicated the following conclusions and recommendations.

Conclusions:

 

 

There are a limited number of mining areas available at any time such that a short mining cycle time is essential to achieve production targets. The CAF system has the shortest filling cycle time;

 

 

The CAF system has relatively low up-front capital and acceptable operating costs. The crusher dedicated to surface road aggregate and stemming production will also produce aggregate for underground backfill; and

 

 

Implementation time for the CAF fill system is minimal, requiring only a few months to complete the surface batch plant, the underground grout delivery reticulation and the underground loading and spraying system.

Recommendations:

 

 

A CAF system should be implemented for backfilling the underground mine;

 

 

CAF trials should be conducted to enable an initial assessment of the quality of the aggregate that can be produced from crushed waste rock;

 

 

The trials should target the preparation of CAF samples containing 3% w/w to 6% w/w cement using a cement slurry of approximately 55% w/w cement, or a water to cement ratio of 0.8;

 

 

16-49


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

These trial samples should be sealed and cured in a humid environment and strength-tested after 3, 5, 7, 14, 28 and 56 days; and

 

 

Confirm bulk density of the aggregate over a number of samples.

 

16.3.3.4 Proposed CAF System Description

Backfilling with cemented aggregate is an integral part of the mining cycle. The void to backfill was based on the average 1,500 tpd planned ore production. This corresponds to an average daily void to backfill of approximately 550 m3. A stockpile of crushed and graded aggregate on surface will feed an aggregate fill pass down to 400 metres below surface. The fill pass, 2.0 m in diameter, will be constantly fed and maintained full at all times.

The surface infrastructure consists of a 100 tonne cement silo, a calibrated transfer system and a small 4 m3 agitated slurry tank to prepare batches of cement slurry. On demand from underground, the slurry will be discharged to the underground holding tank via a 2” slick line in a borehole. After each batch, the line will be flushed automatically, with the flush water being diverted to the sump in the underground backfill station.

The underground infrastructure consists of an aggregate loading station and cement slurry system. A loading chute fitted to the base of the aggregate raise will be used to fill the backfill truck. As the driver operates the chute, a batch of cement slurry will be sprayed onto the aggregate as it falls into the truck, pumped from a 6 m3 agitated slurry tank. The volume of cement slurry will vary with the required cement dosage for that batch.

The driver will then transport the CAF to a mixing bay adjacent to the entry cross cut on the level where fill is required and tip the load into the mixing bay.

An LHD will remix the CAF in the mixing bay and then pick up a bucket load of CAF and transport it to the tipping point at the stope. The LHD will approach the stop-block slowly, then tip a bucket load of CAF into the stope. This process will be repeated until the CAF rill reaches the floor elevation of the drift or the required volume of CAF has been placed.

If additional CAF is required and it is impractical to tip it over the stop-block, then the fill operation will change to remote loading operations to ensure the safety of the operator. The stop-block will be removed and, using remote loading procedures, the next two (2) CAF buckets will be tipped on the floor in front of the rill. The LHD will then push the two (2) piles forward over the rill, taking care not to overextend. This operation will continue until the required volume of CAF has been placed.

 

 

16-50


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The remaining stope volume can then be filled using the same remote loading procedure with uncemented development waste rock until the fill has reached the level of the fill horizon. In some high grade stopes, a thin layer (~0.5 m) of CAF may be placed on top of the RF to achieve a distinct mucking surface and reduce loss of ore into the RF. Figure 16-29 shows a schematic of the CAF system.

 

LOGO

Figure 16-29: CAF System Schematic

 

16.3.4 Waste Management and Stope Filling

Considerable waste rock will need to be disposed of on an ongoing basis throughout the mine life. Stopes will be filled with uncemented development waste rock wherever possible and as required, but some waste will inevitably be hauled to surface for disposal in waste stockpiles. As a priority, waste rock from development faces will be placed as required in available stopes voids. If voids are unavailable, waste can be stockpiled underground, as capacity permits.

 

 

16-51


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

As development activity will slow down in the last two (2) years of production, sufficient development waste will not be generated to provide material for backfilling. The balance will be made up with uncemented crushed aggregate. Table 16-19 tabulates the mass of waste to be generated from development headings and the destination of these volumes over time. Over the LOM, 39% of development waste ore is estimated to be placed back underground. The balance will be disposed of in surface waste stockpiles.

 

 

16-52


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 16-19: Life of Mine Backfilling Waste Rock

 

Year

   Ore Tonnes
(‘000 t)
     Waste Tonnes
Developed
(‘000 t)
     Waste Tonnes
as RF

(‘000 t)
     Waste Tonnes
to Surface
(‘000 t)
     Crushed Aggregate
Required for RF
(‘000 t)
     CAF Tonnes
Required
(‘000 t)
     Cement Tonnes
Required
(‘000t)
 

2013

     0         0         0         0         0         0         0   

2014

     0         0         0         0         0         0         0   

2015

     0         106         0         106         0         0         0   

2016

     16         382         0         382         0         0         0   

2017

     198         369         40         329         0         48         2   

2018

     237         429         77         353         0         92         4   

2019

     425         319         117         202         0         140         6   

2020

     551         231         147         85         0         176         7   

2021

     552         244         159         85         0         191         8   

2022

     554         290         193         97         0         232         9   

2023

     550         301         199         101         0         239         10   

2024

     543         231         173         59         0         207         8   

2025

     443         16         16         0         177         231         9   

2026

     119         0         0         0         47         56         2   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Total

     4,187         2,920         1,121         1,799         224         1,613         65   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

 

 

16-53


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

16.3.5 Development and Production Schedule

 

16.3.5.1 Production Rate

AMC completed a stope cycle time analysis on parameters representative of the average stope size to define the maximum schedulable rate that any given stope may be extracted in the LOM plan. The results of this exercise yielded the following:

 

 

Stopes are mined at 350 tpd once development is complete.

 

 

Stopes are backfilled at 500 m3/day once mining is complete.

In each zone, the order of stope extraction was then linked in a sequence that respects the constraints of the mining method and the development that must be accomplished before any given level may be put into production. A preliminary schedule was created based on the maximum schedulable rates.

The preliminary schedule was then refined through an iterative process to:

 

 

Maintain a constant 1,500 tpd production rate following the ramp up period;

 

 

Optimize the grade profile over the LOM, favouring higher grade areas earlier; and

 

 

Accomplish the above with levelled and reasonable development rates and resources.

AMC concludes that 1,500 tpd is sustainable, and that the target rate is a reasonable estimation of the capacity of the underground mine in consideration of development requirements.

 

16.3.5.2 Pre-Production Development

Pre-production development will span a 24-month time frame before the first ore is mined in the Intrepid Zone. The ramp-up period to full production will require five (5) years from the onset of mine development.

Given its proximity to surface, the development strategy targets the Intrepid upper block as the first priority, followed by the more distant zones to achieve full production. Hence, the first stope will be extracted from the Intrepid upper block.

Critical path pre-production activities include:

 

 

Portal construction and development of the main decline to the Intrepid Zone.

 

 

18-54


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

 

Establishment of the Intrepid ventilation raise to support the advancement of the main decline towards the ODM zone and provide secondary egress from the Intrepid area.

 

 

Partial development of the Intrepid production ramp and levels.

 

 

Definition drilling of the Intrepid Zone

The Intrepid Zone will be the unique source of ore production in 2019, and will still represent the largest (75%) source of production in 2020. It is not until 2021, the fifth year of underground development, that significant tonnage can be extracted from the ODM Zone.

Figure 16-30 illustrates the extent of development at the onset of stope production in the Intrepid Zone in April 2019. A total development requirement of approximately 7,200 lateral metres and 485 vertical metres is planned in the first 24 months. Up to 560 m/month of development advance will be required at the peak activity level. Relative to company strategy and goals beyond the feasibility study, AMC believes that opportunities may exist for further optimization of the development and production scheduling.

 

LOGO

Figure 16-30: Extent of Mine Development at the Onset of Production (April 2019)

 

16.3.5.3 Sustaining Development

The Upper Intrepid Zone will be mined to bring as much production into the earlier years as possible. However, the production rate achievable in the Intrepid Zone is constrained by a limited number of working areas such that achieving and sustaining full 1,500 tpd production is dependent on the development of the ODM zone. The ODM Main zone has been prioritized in the schedule given its size (Reserve tonnage) and the above-average grade.

 

 

16-55


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Key infrastructure that is required to develop the ODM Main Zone includes the westerly extension of the main decline by approximately 2 km, the main air intake raise, the main exhaust raise and the exhaust ramp to complete the primary circuit. The workshop area and CAF plant will also be completed during this phase.

The ODM Main Zone is divided into a lower mining block and an upper mining block, separated by a sill, to reduce development requirements before the zone can be put into production. The upper block has been prioritized as it requires the least development and contains the highest grade Reserves.

Two (2) other zones are accessed in parallel to the OMD Main zone, the 433 Zone and the ODM West zone. The upper area of the 433 Zone is under the final pit and will be mined as a priority before the pit has developed down to this level. The lower portion of the 433 zone will be mined as resources become available. The ODM West Zone is a smaller, yet high grade zone located in the western extent of the mine.

Significant development is required to access and ventilate the 17 East Lower Zone. Its low grade dictates a lower priority and is developed as resources become available.

The Lower Intrepid Zone is low grade and narrow and will be delayed until toward the end of the mine life. The last zone to be mined is the 17 East Upper. This will be accessed with an adit into the pit wall and will be delayed to avoid concurrent development with the open pit.

 

16.3.5.4 LOM Production Schedule

Full 1,500 t/d production will be effectively achieved in 2022.

Figure 16-31 illustrates the ramp-up to full production tonnage as the various zones are brought into production.

 

 

16-56


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 16-31: Underground Production Profile

Figure 16-32 shows the LOM split of production by development and stoping.

 

LOGO

Figure 16-32: Production by Activity

 

 

16-57


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

16.3.6 Geotechnical

The feasibility level site investigation work (AMEC 2013E) and underground mine design criteria for stope stability, ground support and backfill were performed by AMEC (2013A; 2013B; 2013C; 2013D; 2013G, 2014A) and recommended to Australian Mining Consultants (AMC) to support underground mining engineering. Figure 16-33 provides a North West view of the underground mine geometry developed for stress modelling.

During the 2012 drilling campaign (AMEC, 2013E), three (3) main zones of the ODM 17 were intercepted: the West (BH12-UG-01), Central (BH12-UG-02) and East (BH12-UG-03) zones, while the 433 UG North was delineated with the deeper borehole sections of BH12-OP-05 &-06. As part of this Feasibility Study, New Gold additionally performed orientation of cores for four (4) boreholes in the Intrepid Zone. These holes, including other selected exploration cores, were subsequently geomechanically logged by AMEC to provide additional supporting data for geomechanical design (AMEC, 2014A).

 

LOGO

Figure 16-33: View North West of the Underground Mine Geometry

Developed for the Map3D Numerical Stress Modelling, Indicating Zones and

Main Underground Boreholes (AMEC, 2013G).

 

 

16-58


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

In terms of rock mass quality, RQD’s were found to be excellent, ranging from 90% to 100% throughout all stoping domains and with respect to the Modified NGI Q-system, Q’ (after Barton et. al., 1974), average values of 23, 17, and 19, were obtained characterizing the hangwall (“hw”), ore zone (“oz”) and footwall (“fw”) domains of the largest west zone respectively. Typical rock mass qualities in the Intrepid Zone had average Q’ values of 21, 22 and 17, were obtained for the hw, oz and fw domains. The rock mass in all domains can be characterised as good (Barton et. al, 1974), however, there is a slight decrease in the quality in the central zone of the ODM based on the present data. Additional, above and to the east of the Intrepid Zone, there is a zone of brecciated rock that is found to be developed in sub horizontal structures that terminate rapidly. These also have a lower RQD in the range of 10 to 70 (average of 40), and an average Q’ of ~ 4, however, mining does not intersect these zones and the crown pillar thickness is upward of greater than 50 m and considered to be stable.

Intact failure curves were developed based on laboratory testing of 30 UCS, 27 triaxial tests and 24 Brazilian tensile tests. The overall average UCS results, used for linear elastic numerical stress analysis using the Hoek and Brown brittle failure criteria (Martin et. al., 1999; Diederichs et. al., 2002; and Coulson, 2009) for the hw, oz, fw and oz+fw, and found to be 87, 125, 104 and 114 MPa respectively, indicating strong to very strong rocks.

Linear elastic stress analysis using the Hoek-Brown brittle failure criteria was used to review the sequencing and stress evolution around the development, and to estimate the levels of ground support required. Based on this and stope design using the Canadian Open Stope Stability Graph Method (Potvin, 1988; Hadjigeorgiou et. al., 1995), Longitudinal LHOS retreat stope panels will be 20 m along strike in all zones and the LHOS shallower than 500 m will not require cable bolt support to maintain back or hangingwall stability at shallow depths (Figure 16-34). For LHOS deeper than 500 m and with transverse widths (ore thicknesses) greater than 15 m, cable bolt support is recommended in the back of stopes, however, this accounts for only 3 % of these deep stopes (AMEC, 2013G; AMEC, 2014A).

 

 

16-59


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 16-34: Modified Stability Graph for ODM West Zone above 500 m depth Indicating Stability

of Stope Surfaces Based on Potential Design Limits and Actual Final Stope Dimensions

[Longitudinal LHOS Retreat 20 mH x 20 mL x 12 mW average dip 59 degrees] (AMEC, 2013G)

Ground support for the underground mine development at the RRU will consist of three (3) packages of increasing complexity (Table 16-20) depending on the location of the opening. Standard ground support will consist of resin rebar on a 1.2 m by 1.2 m pattern using #9 gauge wire mesh. The second and third packages account for development located in regions with increased damage due to mining induced stress. Most of the mine infrastructure will be supported with a standard ground support package, except for some longhole stopes where increased levels of ground support have been assumed based on linear elastic modelling of the mine sequence. Overall, it is anticipated that approximately 5% of ore development above 500 m in depth will require shotcrete, while 15% of lateral ore development below 500 m depth will require shotcrete. Additionally, based on the numerical stress modelling, approximately 5% of the lateral ore development below 500 m, will require a high stress support system, which is recommended to consist of mechanized cone bolts (“MCB”), installed in a similar pattern to that

 

 

16-60


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

in the Sudbury basin and Brunswick Mine (Simser et. al., 2002). Additionally, shotcrete is estimated to be required for 5% of all access development and 10% for the main ramp. Cable bolts are recommended in intersections with spans greater than 10 m.

Table 16-20: Ground Support Recommendations

 

Development

Type

  

Maximum

Profile

  

Code

  

Ground Support Levels

        

1

  

2

  

3

Standard

Footwall

Development

Drives

   4.5 mW x 4.5 mH    A   

Back 2.4 m long-resin rebar on 1.2 x 1.2 m pattern with #9 gauge weldwire mesh

 

Wall 1.5 m long-resin rebar on 1.2 x 1.2 m pattern

  

As per A1 except upgrade screen to #6 gauge for DL11

 

For DL22 add 60 mm of plain shotcrete

  

As per A2 plus based on DL 33

 

2.3 m  3/4“ MCB on
1 x 1 m pattern installed in the back and side walls connected with 0 gauge screen strapping

Intersections    > 10 m Span    B    As per A1 plus 6 m single Garford (GF) cables on a 2 x 2 m pattern    As per A2 plus 6 m single GF cables on a 2 x 2 m pattern    N/A

Ramp Passing

Lane

   10.5 x 20 m    C    As per A1 plus 3 central 8 m GF cables and 2 outside 6 m GF cables spaced 2 m on 2 m rings    N/A    N/A
LHOS Sill Drives   

Deep Stopes

Spans 20

mL x

> 15 mW

   D    As per A1 plus 6 m double GF cables on a nominal 2 x 2 m pattern fanned in back   

As per D1 except upgrade screen to #6 gauge, replace wall bolts with 1.8 m long split sets (SS-39) for DL11

 

For DL22 add 60 mm of plain shotcrete

  

As per D2 plus based on DL33

 

2.3 m  3/4“ MCB on
1 x 1 m pattern installed in the back and side walls connected with 0 gauge screen strapping

LHOS Draw

Points

  

4.5 mW x

4.5 mH

   E   

As per A1 plus min 4 x rings, spaced 1 m apart of 3 m resin rebar

OR

3 x rings of 3 x single GF cables spaced 2 m

   N/A    N/A

 

1.

DL1 = Linear elastic model induced stress = 0.33 sc < s1 - s3 < 0.4 sc (equiv. H-B brittle failure at m=0, s=0.11).

2.

DL2 = Linear elastic model induced stress = 0.4 sc < s1 - s3 < 0.5 sc (equiv. H-B brittle failure at m=0, s=0.16).

3.

DL3 = Linear elastic model induced stress = 0.5 sc < s1 - s3 (equiv. H-B brittle failure at m=0, s=0.25).

 

 

16-61


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

All stopes will be partially backfilled with cemented aggregate fill (“CAF”) at an average binder dosage of 5%, the cemented backfill being placed at an angle of repose until level with the top cut, the rest of the stope being filled with uncemented rock fill. Testing indicates that a 3% binder consisting of 10% cement (NPC) and 90% Slag has acceptable strength development at 28 days of 1 MPa and no degeneration in strength was noticed for testing at 180 days (AMEC, 2013B, 2013v).

Stope dilution has been based on the empirical estimation of wall slough after Pakalnis (2002) (Figure 16-35). Depending on the ore zones, stope hw dip and depth, 0.25 m to 0.5 m of Equivalent Linear Overbreak/Sloughs (“ELOS”) are estimated, for a sublevel spacing of 20 m, and 20 m strike length for the majority of stopes. CAF backfill dilution from stope walls have been estimated at 0.3 m based on bench marking to similar operations (AMEC, 2013G).

 

LOGO

Figure 16-35: Empirical Estimation of Wall Slough (ELOS) for Varying HW Dip Cases for the 4 Main

Underground Design Zones Above 500 m Depth in which LHOS Was Applied (AMEC, 2013G).

 

 

16-62


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Based on the present mine plan, no crown pillars will be required below the open pit, since the stopes directly below the pit will be mined in advance, they are relatively narrow and will be backfilled with cemented rockfill. The stopes will contain relatively stiff cemented rock fill, and as such are not anticipated to cause any instability to the open pit due to their limited extent. As previously noted, a crown pillar will exist for the new Intrepid Zone, that based on the present mine geometry the crown pillar thickness of competent rock to the bedrock surface, above mining is expected to be between 45 to 100 m thick. Based on a mining width of 20 m by 6 m, this crown is considered stable. A sill pillar will be developed in the ODM/17 zone between -150 and -170 m elevation. This sill will be moderately stressed, but will be mined towards the end of mine life, however, only account for a limited number of stopes (5 stopes), in which a reduced extraction ratio has been assumed.

As some stress induced damage may be anticipated a 32 channel microseismic system is recommended for the deeper region of stopes and the region below the pit. Additionally, standard displacement monitoring and cable bolt monitoring instrumentation will be used.

 

16.3.7 Drill and Blast

 

16.3.7.1 Bulk Explosive Product

Ammonium nitrate and fuel oil (“ANFO”) is the most basic bulk explosive product. It is widely available and can be poured or blown into long holes. The equipment required to use ANFO is basic and easily maintained. ANFO is the primary explosive product that will be used for both the lateral development and stoping at the Rainy River mine.

 

16.3.7.2 Initiation System – Boosters and Detonators

Boosters are basic solid cartridge explosive products that are readily available from explosive products suppliers, and are planned for lateral development and stoping. Boosters can be initiated with high strength electric, electronic and non-electric detonators.

Electronic detonators are planned for blast initiation (i.e. starter cap) of lateral development and stopes. They have multiple security features that make them virtually immune to interference, unauthorized use, or unplanned detonation.

 

 

16-63


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

16.3.7.3 Longitudinal Down-Hole Stope Design

Figure 16-36 and Figure 16-37 show a typical long section and cross section of the longitudinal down-hole stope of a height of 20 m (floor to floor), average width of 8 m (Widths range from 3.5 m to 15 m, but 8 m is examined), and length of 20 m. Longitudinal down-hole stopes account for the majority of the planned stope tonnage (approximately 97%). A minor amount of transverse stoping and uppers will be required but, given their very minor contribution to the LOM plan, the detail is not examined here.

 

LOGO

Figure 16-36: Longitudinal Downhole Stope Long Section

 

LOGO

Figure 16-37: Drop Raise Drillhole Pattern for the Longitudinal Downhole Stope (Section View)

 

 

16-64


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

16.3.7.4 Explosive Consumption

The Rainy River underground mine will consume approximately 42 tonnes/month of ANFO, 4700 detonators/month, and 4700 boosters/month, which is based on the peak production rate of 1,500 tpd and a development advance rate of 8 m/d. A small reserve of cartridge explosive products will also be required for special situations (i.e. wet holes in long hole stopes and development rounds).

 

16.3.8 Mobile Equipment Requirements

 

16.3.8.1 Underground Contract Mining Phase

A contractor will be engaged to provide experienced personnel and expertise during the first three years of underground activity and will be responsible for all development and mining activities during this period. The underground mining equipment will be supplied by New Gold. Table 16-21 shows the equipment build-up during this period.

The transition to New Gold personnel underground will likely commence during 2019, the third year of development. However, for the purpose of cost estimation, AMC has assumed contract labour rates for all manpower in 2019.

Contractor assistance will extend beyond 2019 but will be limited to mechanized raise development (Alimak), the installation of ladderways and any residual construction to complete the workshop area.

Temporary maintenance capacity for mobile equipment will be required before commissioning of the permanent arrangement. During the contract mining phase, the temporary facilities will be provided for, and managed, by the contractor in the portal area. It may be advantageous to equip a second temporary workshop for minor and routine maintenance closer to the working areas until the permanent workshop is completed in 2020.

 

 

16-65


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 16-21: Mobile Equipment Requirements – Contract Mining Phase

 

Mobile Equipment

   2017      2018      2019  

Drill Jumbo, 2-Boom

     1         2         0   

Drill Longhole

     1         0         1   

Haulage Truck, 45 Tonne

     2         0         1   

LHD, 7.2m3 with Remote

     2         0         1   

Bolter

     1         1         0   

Lubrication Service Truck

     1         0         1   

Boom Truck

     1         0         0   

Scissor Lift

     1         0         0   

Face Charger, Explosives

     1         1         0   

Pneumatic Cartridge Loader

     0         1         0   

Pneumatic ANFO Loader

     0         1         0   

Blasting Utility

     1         0         0   

Shotcrete Sprayer

     1         0         0   

Personnel Carrier

     1         1         0   

Transmixer

     1         0         0   

Motor Grader

     0         1         0   

Face Mapper

     0         1         0   

Fork Lift

     0         1         0   
  

 

 

    

 

 

    

 

 

 

Total

     15         10         4   
  

 

 

    

 

 

    

 

 

 

 

16.3.8.2 Production Phase – 2019 Onwards

During steady state operations, New Gold will supply the labour force and continue to supply all equipment with the exception of mechanized raise climbers “(“MRC”). MRCs will be used for internal ventilation raises in the ODM East and ODM Upper zones and are included in the raising contract. In addition to production and development equipment, support equipment is also required. Table 16-22 and Table 16-23 show the required equipment for development, stoping and support activities, respectively.

Utilizations were determined by calculating the number of hours per year required for each piece of equipment to achieve the targeted mine production and development rates. The hours were calculated using first principles. The utilization hours were then set against the total hours per

 

 

16-66


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

year that the equipment was available. The available hours were determined by multiplying the estimated availability by effective working hours per year. To reduce the potential for production delays, additional unit(s) of key equipment that perform tasks directly related to production were, in some cases, scheduled to be purchased for redundancy.

Table 16-22: Underground Development and Production Equipment List

 

Description

   Availability     Utilization     Qty  
     Peak     Average    

Two boom mining jumbo

     85     50     50     3   

LHD, 17 tonne (diesel - development/production/backfill)

     85     80     80     4   

Haulage Truck, 45 Tonne

     85     80     80     6   

Bolter

     85     80     80     2   

Top hammer longhole drill

     85     50     50     2   

Face Charger, Explosives Loader

     85     80     80     2   

Production Explosives Loader

     85     50     50     1   

Pneumatic Cartridge Loader, Explosives

     85     50     10     1   

Shotcrete Sprayer

     85     10     10     1   

Transmixer

     85     30     30     1   

Table 16-23: Support Equipment

 

Description

   Availability     Utilization     Qty  

Personnel Carrier, Diesel, Underground

     85     30     3   

Scissor Lift Truck, Diesel

     85     30     1   

Lubrication Service Truck, Diesel

     85     30     2   

Boom Truck, Diesel

     85     35     1   

Explosives Utility, (Transport)

     85     30     1   

Forklift

     85     30     1   

Utility Platform Lift

     85     35     1   

Jumbos

During steady state operations, an average of 475 m/month of lateral development must be achieved. A two boom jumbo capable of drilling holes up to 4.3 m deep was selected based on the average drift size.

 

 

16-67


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Based on first principles estimation of Jumbo productivities, three units are required.

Haulage Trucks and Loaders

A study was completed to determine which truck and loader combination would provide the highest productivity for the lowest total cost. Considering both capital and operating costs, the study concluded that 45 tonne trucks and 17 tonne loaders provide the lowest capital cost and operating cost (on a per tonne basis).

For the scheduled stope, development and CRF and RF volumes, four (4) 17-tonne loaders and six (6) 45-tonne trucks are required.

Bolters

Typical bolting patterns involve 2.4 m long resin grouted rebar on a 1.2 m square pattern on the back,1.5 m long resin grouted rebar on a 1.2 m square pattern in the walls and welded wire mesh. To maintain the targeted development rates, first principle productivities indicate two bolters are required. The bolter will be fitted with a mesh handling arm.

Longhole Drills

The primary function of the longhole drill is for production drilling. The longhole drill is also specified for cable bolt and drop raise drilling. First principle productivity estimates indicate that two longhole drills are sufficient to meet the projected demand.

Explosive Loaders

For development loading, two face charging units will be required to load as many as six (6) rounds per day. For production loading of up-holes and down-holes, a pneumatic ANFO loader is required. A pneumatic cartridge loader is also specified for the loading of wet upholes.

Shotcrete Sprayers

It is anticipated that approximately 5 - 15% of ore and waste development advance will require wet fibre-reinforced shotcrete. A minor amount will also be required for the construction of ventilation bulkheads and other infrequent applications. Although the anticipated volume is less than one cubic metre per day, the campaign nature of shotcrete spraying, the ability to meet development targets and consideration of operator safety supports the purchase of this unit, in contrast to the employment of hand sprayers. One (1) unit will meet the forecast volume.

 

 

16-68


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Transmixers

Shotcrete will be delivered from the surface batch plant to the underground headings in a transmixer. As shotcrete and concrete volumes are estimated to be low, only one (1) transmixer will be required.

Personnel Carriers

Personnel carriers will be needed for employee transport. The transporter selected is capable of carrying nine people. With three transporters, 27 people can be brought to their work places each shift. Personnel required underground on an as-needed basis, such as technical staff, are also transported underground in the personnel carriers.

Scissor Lift Truck

The scissor lift truck will be required to install and remove services (pipe reticulation, power cables and ventilation ducting) hanging fans, and assisting with construction. One scissor lift truck is specified. For redundancy, the fork lift fitted with a man basket and the utility platform lift are also capable performing similar tasks.

Lubrication Truck

A lubrication truck will be required to deliver grease, hydraulic oil and engine oil to equipment that is not likely to return to the shop area at frequent intervals. Utilization can be increased by keeping equipment near the working headings. This will reduce traffic on ramps and the main decline and reduce non-productive travel time for key equipment. This equipment would include trucks, LHDs, jumbos, longhole drills and, bolters. The service truck will travel between these equipment pieces to perform the required servicing.

Boom Truck

Bulk explosives (bagged ANFO) products will be transported from the surface to the underground powder magazine with a boom truck. This unit will also serve to transport materials from surface to underground. Material stockpiles will be set up throughout the mine for supplies such as rock bolts, screen, resin, pipes, vent duct, etc.

 

 

16-69


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Explosives Utility Vehicle

A Personnel Carrier will be dedicated to the transfer of explosives products from the surface magazines to the underground magazines. This includes packaged explosives products, detonating cord, non-electric caps, and electronic detonators.

Forklift

A fork lift with an integrated tool carrier will be required for general service activities. The integrated tool carrier can operate with a wide variety of accessories such as a man basket, forks and small loader bucket. Primary uses include, but are not limited to, handling of explosive pallets, providing personnel access to the backs and distributing road base material. One unit is specified.

Utility Platform Lift

The development cycle will include chip sampling and geological mapping of each round, to be accomplished safely in the absence of face bolting. The identification of bootlegs and face mark-up for drilling is also performed at this stage in the cycle. A utility platform lift has been dedicated to these activities, and it will be required to service approximately two rounds per shift on average, although variations in workload will vary.

 

16.3.9 Ventilation

The function of the ventilation system is to dilute/remove airborne dust, diesel emissions and explosive gases, and to maintain temperatures at levels necessary to ensure safe production throughout the life of the mine. The ventilation system has been designed to meet the requirement of the Occupational Health and Safety Act, R.R.O. 1990, Regulation 854 – Mines and Mining Plants (The Regulations).

The design is based on an exhausting system configuration with the main surface fans located at the Intrepid Exhaust and Primary Exhaust raises. Direct-fired mine air heating systems are located at the portal and Primary Intake raise. Fans are also located at these intakes to ensure balance of airflow across the propane burners.

Fresh air enters the mine through both the portal and primary fresh air raise with fresh air generally being distributed through the mine’s various ramp systems. Return air is exhausted from the mine through internal raises adjacent to each ore block. For the main production areas the return air progresses to a transfer drift and subsequently the Primary Exhaust Raise. Due to its distance from the other ore zones, the Intrepid Zone is exhausted independently to the surface.

 

 

16-70


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Level distribution is designed such that fresh air will be sourced from ramp accesses via auxiliary fan and duct into each operating level. Contaminated air from development and production level activities returns to an internal return air raise. A total of 335 m³/s is planned for ventilation of the Rainy River underground operation.

Two means of egress are provided for each production area of the mine. The primary means of egress is via the ramp system. Secondary emergency egress is provided in all internal raises and the Intrepid exhaust raise by means of installed ladderways. In the event of compromised egress to the surface through the main ramp, the Primary Intake Raise is fitted with an Alimak-Hek elevator. Figure 16-38 shows an isometric view of the Rainy River ventilation system.

 

 

16-71


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 16-38: Rainy River Ventilation System

 

 

16-72


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

16.3.9.1 Total Airflow Requirements

Air volume requirements are calculated to ensure safe production. The amount of air required is largely determined by the number and size of diesel equipment operating underground. The air volume supplied must be able to dilute and remove dust and noxious gases as well as diesel particulate matter generated by the use of such equipment.

The Regulations state that the ventilation quantity shall be at least 0.06 cubic metres per second for each kilowatt of power of the diesel-powered equipment operating in the workplace.

Primary infrastructure underground requiring continual ventilation is accounted for in the total airflow calculation. An airflow allowance is also determined for underground infrastructure and leakage and balancing inefficiencies.

Based on the scheduled production and development activities, airflow allocations are summarized in Table 16-24.

 

 

16-73


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 16-24: Total Airflow Requirements

 

Equipment

   Number      kW      hp      Utilization1     Total Airflow
(m³/s)
     Total Airflow
(cfm)
 

Haul Truck

     6         438         587         85     134         283,989   

Scoop

     4         321         430         85     65         138,753   

Jumbo

     3         110         147         15     3         6,293   

Bolter

     2         110         147         15     2         4,195   

Longhole

     3         110         147         10     2         4,195   

Personnel Carrier

     3         95         128         40     7         14,568   

Scissor Lift

     2         110         147         30     4         8,391   

Lube Truck

     1         120         161         40     3         6,102   

Boom Truck

     1         120         161         40     3         6,102   

Blasters Truck

     1         95         128         40     2         4,856   

Shotcrete Sprayer

     2         120         161         15     2         4,577   

Face Charger

     2         110         147         15     2         4,195   

Transmixer

     1         155         208         40     4         7,882   

Grader

     1         129         173         50     4         8,200   

Face Mapper

     1         96         129         15     1         1,831   

Fork Lift

     1         54         72         40     1         2,746   

Sub-Total – Diesel Equipment

                239         506,876   

 

Infrastructure

   Number      Unit Airflow (m³/s)      Total
Airflow
(m³/s)
     Total
Airflow
(cfm)
 

Shop Complex

     1         26         26         55,091   

Fuel Bays

     1         26         26         55,091   

Magazines

     0         0         0         0   

Sub-Total – Infrastructure

           52         110,182   

 

Final Volume

   Total Airflow (m³/s)      Total Airflow (cfm)  

Sub-Total – Diesel & Infrastructure

     291         617,058   

Contingency/Leakage – 15%

     44         92,559   

Final Volume

     335         709,616   

 

1 

The utilization factor presented in this table reflects the expected peak ventilation requirements during a typical shift underground.

 

 

16-74


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

16.3.9.2 Ventilation Modelling

AMC developed a ventilation model (using Ventsim) for the Rainy River Project for three (3) primary purposes:

 

 

To validate the operability of the ventilation circuit to ensure airflow can be provided to all the required areas.

 

 

To ensure compliance with design criteria.

 

 

To determine fan duties and energy requirements.

 

16.3.9.3 Permanent Primary Fans – Exhaust

Over the life of mine, the ventilation circuit will change depending on the type of activities and their location throughout the mine. AMC has modelled the circuit to reflect the peak primary fan duties that could be reasonably expected.

Applying the Ventsim model to this mine design, the model was run with a total volume of 335 m³/s of which 220 m³/s is exhausted from the primary exhaust fans and 115 m³/s from the Intrepid exhaust fans. The design duty point for each exhaust fan is as follows:

 

16.3.9.3.1 Primary Exhaust Raise Fans

 

 

Twin horizontal mount axial fans in a parallel arrangement

 

 

Design duty point for each fan: 110 m³/s at 3,090 Pa

 

 

Power consumed during operation: 474 kW per fan

 

 

Approximate motor size (typical North American supplied motor): 800 hp

 

16.3.9.3.2 Intrepid Exhaust Fans

 

 

Twin horizontal mount axial fans in a parallel arrangement

 

 

Design duty point for each fan: 57.5 m³/s at 2,765 Pa

 

 

Power consumed during operation: 215 kW per fan

 

 

Approximate motor size (typical North American supplied motor): 400 hp

An allowance for variable frequency drive (“VFD”) starters for the main fans is included. A VFD allows the electric motors to run at the speed necessary to supply the demand air volume to realize fan energy savings. As a further benefit, any reduction in the air flow volume during winter means that mine air heater energy savings can also be realized.

 

 

16-75


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

16.3.9.4 Mine Air Heating

This study assumes that all intake air entering the mine is at a temperature above freezing point for the following reasons:

 

 

Protect the health and safety of personnel working or travelling in intake airways.

 

 

Prevent the freezing of service water and discharge lines.

 

 

Maintain roadways ice-free and safely trafficable.

 

 

Prevent rock surface expansion / contraction damage from freezing and thawing of rock joints in the upper parts of the intake airways.

 

 

Prevent ice build-up in airways that would potentially lead to unsafe conditions, particularly in the primary intake raise hosting the escape-way.

In the colder months the targeted delivery air temperature for the intake air is 2°C. This value was selected on the basis that the air be heated above freezing point while avoiding unnecessary heating costs.

The estimated total heating requirements (combination of both primary intake raise and portal) by month and year are shown in Table 16-25. This table also shows the expected profile of ventilation requirements during the whole of mine life.

 

 

16-76


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 16-25: Estimated Heating Consumption

 

Airflow

   Jan      Feb      Mar      Apr      May      Jun      Jul      Aug      Sep      Oct      Nov      Dec      Total  

2017 45 m³/s

     114,387         77,830         41,729         7,056         0         0         0         0         0         2,942         36,525         93,451         373,920   

2018 135 m³/s

     343,160         233,490         125,186         21,169         0         0         0         0         0         8,827         109,576         280,352         1,121,759   

2019 225 m³/s

     571,933         389,149         208,643         35,281         0         0         0         0         0         14,711         182,627         467,254         1,869,599   

2020 260 m³/s

     660,900         449,684         241,099         40,769         0         0         0         0         0         17,000         211,036         539,938         2,160,426   

2021 305 m³/s

     775,287         527,513         282,828         47,825         0         0         0         0         0         19,942         247,561         633,389         2,534,345   

Years 2022 to 2026 335 m³/s

     851,545         579,400         310,647         52,529         0         0         0         0         0         21,904         271,911         695,689         2,783,625   

2027 240 m³/s

     610,062         415,093         222,553         37,633         0         0         0         0         0         15,692         194,802         498,404         1,994,239   

2028 140 m³/s

     355,869         242,137         129,823         21,953         0         0         0         0         0         9,154         113,635         290,736         1,163,306   

 

 

16-77


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

16.3.9.5 Auxiliary Ventilation

All work areas in the mine not supplied with a split of fresh air must be ventilated using auxiliary systems. The most effective means for providing airflow to areas without primary airflow is typically with small diameter axial fans combined with low leakage, flexible ducting.

 

16.3.9.6 Main Decline Development Ventilation

The design criteria for airflow for development of the main decline considered the operation of 1 x 45 Tonne truck (438 kW) and 1 x 7m3 Loader (321 kW). At 0.06 m³/s per diesel kW, 46 m³/s is required for ramp development.

It is planned that this will be accomplished via two auxiliary fan and duct installations in the ramp; one delivering air to the face and the second duct discharging at the remuck. To ensure each fan/duct installation delivers 23 m³/sec to the face, and to account for a small amount of leakage at each duct join (assumed 1.5%), it is estimated that a 110 kW fan is required. This arrangement will deliver the required air for a maximum 600 metres.

Noting that the maximum length of a single heading in the main ramp is expected to be around 1200 m, once a single heading exceeds 600m in length, a second 110 kW fan will need to be placed in series with the original fan for each duct.

 

16.3.9.7 Level Development and Production Ventilation

During level development and production activities, distances up to 500 m are required to be ventilated using auxiliary systems on each level. The peak individual airflow requirement during development activities will be that for a scoop and a small piece of equipment equal to a total 25 m³/s. At 500 m duct length, a single 110 kW fan will be sufficient, provided good installation and maintenance practices are employed.

 

16.3.10 Emergency Preparedness

In development of the ventilation strategy for Rainy River, and with due regard to other operational issues, consideration has been given to the potential for mine emergencies. As such, the following criteria have been established:

 

 

In general, ramps will be in fresh air once developed.

 

 

16-78


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

On almost all levels, escape can be either to a ramp or to the escape ladderway in the internal raises.

 

 

In each ramp, escape may either be up the ramp or down the ramp to a safe area.

 

 

One permanent 20-person refuge station will be established adjacent to the main decline and access to the 433 ore zone.

 

 

Three other portable refuge chambers are required for flexibility of location at the most appropriate points in the mine.

 

 

Whilst the primary means of communication will be by radio, a stench system will be in place for introduction of ethyl mercaptan into both portal and primary fresh air raise concurrently in the event of fire.

 

 

Fire doors will be located in accordance with legislated requirements and to isolate areas of high fire potential to ensure noxious gases are not distributed through the mine workings.

There are a variety of incidents that will trigger the emergency response plan and/or evacuation plan. Such events may be fire, rock fall, injured personnel or major ventilation equipment breakdown.

In the event that the primary egress (main ramp and portal) is unavailable, a secondary means of egress from the mine must be available to allow evacuation of all underground persons when it is safe to do so.

The primary fresh air raise is designated as the secondary means of egress. An Alimak-Hek elevator system will be installed in the raise with landings at the surface and bottom of the raise adjacent to the main decline, and with an intermediate landing at the exhaust air transfer level. The cage is sized to allow room for a full mine rescue team with apparatus.

For the production stoping blocks, a ladderway is installed in each of the raises located next to main ramps. The raises are sized to afford easy passageway. The route of travel for personnel is to use the ladderway to reach the exhaust air transfer drift and walk to the intermediate Alimak landing.

The primary exhaust raise to surface is for ventilation only and not used as a second means of egress. However, as the Intrepid ore zone is remote from the other ore production areas, the exhaust raise for the zone must be the secondary egress. A ladderway is to be installed in this raise to allow escape to surface.

 

 

16-79


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

A static refuge station will be established adjacent to the main decline and access to the 433 ore zone. It is required to provide refuge during an emergency for 20 persons. Section 10.1 of this report details this station.

The remaining personnel working underground, namely the production development and service crews, are provided refuge by means of three, 12-person mobile self-sufficient rescue chambers. These will be independent of a compressed air supply, with appropriate provisions for safe refuge. They will be located in areas where secondary egress is not, or has not yet been, established, and will be sited relative to the active working areas to be within the average walking pace duration of a personal self-rescuer device.

The primary purposes of fire doors are to prevent noxious gases from reaching workers should they be trapped underground and to prevent fire from spreading as much as possible. Fire doors will be required to isolate the workshop.

 

16.4 Underground infrastructure

 

16.4.1 Refuge Stations

There will be three (3) portable and one (1) permanent refuge stations located throughout the mine. The permanent station as shown in Figure 16-39 (main refuge station) will be located at the intersection of the main decline and the ramp to the 433 zone. This station will accommodate 20 persons and will be equipped with an airlock entrance, a battery backup electrical system, an air conditioning unit, a CO2/CO scrubbing unit and emergency supply of first aid, food, water, and oxygen candles. This refuge station will be located in a bay and will be separated from the drift by a concrete wall. Access to the station is through an air-lock system. Emergency air will be supplied by a dedicated air compressor located on surface at the top of the nearby Fresh Air Raise and supplied via piping down the Raise to the refuge station. This refuge station will also service as the main lunchroom. In addition to the main refuge station there will be three smaller, portable refuge stations. They will be located at the Intrepid, ODM and 17 East zones.

 

 

16-80


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 16-39: General Arrangement Refuge Station Plan

 

16.4.2 Mine Dewatering

Previous hydraulic conductivity work indicated that hydraulic conductivity of deep bedrock increases by a factor of 5 at 1,630 m3/day of inflow. This translates into approximately 18.7 L/s. For this study, AMC and its subconsultant Nordmin, factored this estimate to 28.6 L/s throughout the mine for sizing of sumps and pumps at each station. Mine dewatering for the New Gold Rainy River underground will be handled by a combination of submersible and horizontal centrifugal pumps located throughout the Intrepid Zone, 17 East Zone, 433 Zone and ODM Zone working levels. The pumps will handle ground in-flow and spent drill water via multiple lifts throughout the mine to minimize pump size and power. Maximum drill water volumes reporting to any single sump are estimated at 7.9 L/s. The level sumps are designed to handle 36.6 L/s. A total of nine lift stations are in the current design. The breakdown is as follows:

 

 

ODM zone: 4 pump stations

 

 

17 East zone: 3 pump stations

 

 

Intrepid Zone: 2 pump stations

 

 

16-81


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

These stations will be designed with consistent vertical intervals to maintain similar pump head characteristics, reducing the variety of different pump sizes required. A typical sump will allow for solids settling with an overflow weir to a clear water side before pumping to a holding tank. The holding tank is sized to take several charges from the sump before pumping the tank contents to the next level sump. The sumps in all areas with the exception of Intrepid will report to a pumping station near the workshops. The Intrepid mining zone sumps and the workshop area water will ultimately report to a main sump located in the Intrepid Zone, from where the water is finally pumped out via the portal to surface. Figure 16-40, Figure 16-41 and Figure 16-42 show the typical sump flow diagram and long section and plan view sump general arrangement, respectively.

 

LOGO

Figure 16-40: Typical Sump Flow Diagram

 

LOGO

Figure 16-41: Dewatering Level Sump and Pumping

 

 

16-82


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 16-42: General Arrangement Underground Main Sump Layout

 

16.4.3 Compressed Air

Compressed air for equipment will be supplied by portable and onboard compressors. No central compressed air facility will be constructed and no compressed air reticulation will be required other than for the permanent refuge station. The underground Maintenance and Service Bay area will have a dedicated compressor permanently installed with air lines from the air receiver routed to convenient locations in the shop area. In addition to the permanent compressors, several smaller, portable compressors will be available. An emergency air compressor will be located at the top of the Fresh Air Raise to supply air down to the permanent refuge station in case of an emergency.

 

16.4.4 Mine Water Supply

Water supply for underground mining processes and dust control will be supplied via a 4” steel line at the portal. The line will continue through the decline following the development to the underground workings. As pressures rise due to increasing static head with depth, Pressure Reducing Valve (“PRV”) stations will be installed to reduce the water supply pressure below 100 psi.

 

 

16-83


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

A typical PRV station as shown in Figure 16-43 will follow the development down until the supply pressure rises above 400 psi, when the station will then be permanently located and another PRV station inserted to continue following the development down. It is expected to have eight (8) permanent PRV stations servicing the Intrepid, 17 East, and ODM levels when the main development for the underground is complete.

 

LOGO

Figure 16-43: Typical Pressure Reducing Valve (“PRV”) Station

 

16.4.5 Fuelling and Lubrication

The underground fuel consumption profile for the LOM is shown in Figure 16-44.

Trucks that make regular trips to surface will fuel up mainly above ground in the service area near the portal away from other pit traffic. There will be one main refuelling area by the underground workshops as shown in Figure 16-45, and satellite fuelling stations (Satstats) in the Intrepid, ODM and 17 East zones. Fuel storage and pumping will be accomplished with self-contained satellite portable fuel cubes. The Satstats are equipped with fire suppression system and fuel spillage containment. They can be re-used and re-located to active areas. The lubricants such as grease, hydraulic and break fluids are kept in the main workshop. The main workshops have been designed with fire doors at each end that are normally open. They will shut during a fire emergency in the shops.

 

 

16-84


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 16-44: Underground Fuel Consumption Profile

 

LOGO

Figure 16-45: General Arrangement – Underground Fuel Station

 

16.4.6 Workshop Facility

The underground maintenance workshop area, as shown in Figure 16-46, consists of two large bays, each 10 metres wide to accommodate several trucks. The two service bays are joined by a crosscut allowing for forklift and foot traffic to move from one bay to the other without exiting the shop area. One sidewall along the length of each bay will accommodate tool cribs with the crosscut having common short-term storage of oil and greases. One service bay will be

 

 

16-85


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

equipped with a monorail running the length of the bay. The service area will be equipped with a stationary compressor and air lines to power air tools and provide compressed air as needed. Several welding plugs will be distributed throughout this area along with regular electrical plugs to power shop tools. An office, a storage bay and a wash bay will be also located in the maintenance area. The wash bay will have a collection sump with an oil separator installed.

 

LOGO

Figure 16-46: Underground Maintenance Workshops Layout

 

16.4.7 Explosives Magazine

Two bays will be provided for the storage of ANFO, explosive accessories such as boosters and detonators and cartridge explosives. The entrance to the storage bays will be controlled with a lockable chain link fence and doors. The bays will contain wooden shelves for storage of the explosives material.

 

 

16-86


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The arrangements are shown in Figure 16-47 and Figure 16-48.

 

LOGO

Figure 16-47: ANFO Storage Plan and Sections

 

LOGO

Figure 16-48: Cap & Powder Magazine Plan and Sections

 

16.4.8 Underground (CAF Loading Station)

CAF will be required for all stopes with exposed fill and will represent around 60% of all fill placed underground. The remaining 40% will consist of development waste rock directly tipped into stopes. The CAF system will require a surface slurry plant, aggregate production and stockpiles and a loading station underground.

 

 

16-87


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The underground loading station will have concrete floors, a sump for spilled slurry and a signalling system to control the delivery of slurry from surface. This will be a simple level sensing indicator in the underground tank which will request the delivery of the next batch of slurry from surface.

The loading station will be provided with fixed lighting and frequent cleaning will be required to remove any spillage from the floors and sump areas. Haulage trucks underground will load aggregate from the chute and cement will be sprayed in batches to manage the cement dosing requirement. Figure 16-49 depicts the underground CRF loading station.

 

LOGO

Figure 16-49: Underground Cemented Rock Fill Loading Station

 

16.4.9 Communications and Automation

Radio communications are to be established underground by virtue of VHF leaky feeder. VHF-based hand-held radios, fixed vehicle and base station radios will have access to six separate channels. A head end unit will serve as the master repeater relaying voice channels down the leaky feeder media into the drifts. The head end unit will be readily available to connect surface antennas and equipment as necessary.

 

 

16-88


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

One 48 core fibre optic cable will serve IT communications, VOIP and PLC systems. Fibre optic patch panels and fibre to Ethernet switches will be placed in key locations throughout the mine to convert the fibre network to copper for integration with necessary equipment.

Personnel tracking (should it be required) will be accomplished by virtue of a WiFi RFID tag system. Vehicles will also contain RFID tags. The system will be integrated into Impact Software, a browser based tracking and reporting application, allowing operators and mine controllers to monitor, track and allocate personnel and resources. The RFID system can also be integrated into a ventilation-on-demand (“VOD”) system.

Fixed underground monitoring and control will be by virtue of a PLC system. The monitoring and control of underground systems including but not limited to: ventilation, pumping and power monitoring will be by virtue of remote PLC racks placed near the equipment as necessary. The remote racks will come complete with their own processors and, should the communication link fail, the systems they are controlling will continue to operate.

The remote PLC racks will communicate by virtue of a fibre optic backbone stemming from the portal substation. Fibre cables will branch out through the portal into the underground ramp and out into drifts as required. At substations and at remote PLC locations, fibre to copper switches will be installed bridging the network together.

Blasting will be performed by virtue of a VHF radio controlled Smart Blast system. Smart Blast has the capability to initiate non-electric shock tube as well as standard electric blasting caps. The controller receives confirmation back on all of the remote firing devices. The controller and firing devices may be used anywhere there is leaky feeder coverage. Typically the controller is used in a central blasting location.

The voice over IP (“VOIP”) underground telephone system and IP network communications will also be over the fibre optic backbone stemming from the portal substation. A centralized processor will be installed in a key control location to be determined. Fibre cables will branch out through the portal into the underground ramp and out into the drifts as required. At substations, control rooms, lunch rooms, shops and other key locations fibre to copper power over Ethernet (“POE”) switches will be installed bridging the network together.

 

 

16-89


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

16.4.10 Electrical Distribution

The underground LOM power requirement profile is shown in Figure 16-50.

Electrical power will be supplied to the underground mine from a 27.6 kV overhead line from the main surface substation to the underground mine portal. A 5 MVA 27.6 kV / 13.8 kV unit substation will be installed at the portal, complete with five (5) 13.8 kV secondary breakers. The secondary breakers will feed:

 

 

13.8 kV to a 500 kVA 13.8 kV / 600 V mine power centre for 600 V loads at the portal and for initial ramp development.

 

 

13.8 kV underground via parallel redundant feeders. Each feeder will have the capacity to source the required power underground, currently estimated at slightly less than 2.5 MVA.

 

 

13.8 kV to a 2.5 MVA 13.8 kV / 600 V unit substation at the primary exhaust / fresh air raise area via a short 15 kV overhead line from the portal.

 

 

13.8 kV to a 500 kVA 13.8 kV / 600 V mine power centre at the intrepid exhaust raise area via a short 15 kV overhead line from the portal. 600 V loads including a 400 HP VFD will be fed from this mine power centre.

A building at the primary exhaust and supply raise will contain an electrical room that will house the 2.5 MVA 13.8 kV / 600 V unit substation complete with secondary breakers; as well as:

 

 

Two 800 HP VFDs for the primary exhaust fans.

 

 

Two 150 HP VFDs for the primary supply fans.

 

 

A 600V MCC c/w automatic transfer switch to supply power to the Alimak, as well as emergency air compressors.

A 250 kW 600V self-contained back-up emergency diesel generator will be installed adjacent to the building complete with integral fuel tank and skin-tight enclosure. The generator will tie in to the automatic transfer switch in the MCC and provide emergency power to the emergency air compressor, the emergency egress elevator and the emergency 600 V MCC in the event of an electrical outage.

The parallel redundant underground feeders will route the length of the main ramp and supply mine power centres for main ramp development and will be alternately connected between feeders allowing for the “leap frogging” of power centres without loss of development power. The

 

 

16-90


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

redundant feeder approach also ensures minimal down time if a cable is damaged, allows for the utilization of additional power if required in the future, prevents blackouts on equipment addition and ensures added safety from the portal substation to the underground. Two (2) 1000 kVA mine power centres have been allotted for main ramp development.

The first permanent underground substation will be established near the Intrepid ramp. A 1000 kVA mine power centre will be installed in the substation along with switchgear with parallel line side connections and sufficient load side breakers to allow for ramp feeder redundancy to continue down the ramp and to the Intrepid development area.

The primary underground substation will be located at the shop / clear sump area. A 2000 kVA 13.8 kV / 600 V unit substation complete with secondary breakers will provide power for the clear sump pumps, shop, and underground development as needed.

Each development area will be fed from the redundant main ramp feeders as mining progresses and each area will be fitted with 13.8 kV and 600V distribution to suit mine development / mining. Portable substations will follow the development to provide 600V power from the 13.8 kV line to the mining equipment, fans, and pumps up to a distance of 300 metres away from the substation.

Figure 16-50 illustrates the projected power requirement profile over the LOM.

 

LOGO

Figure 16-50: Underground Power Requirement Profile

 

 

16-91


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

16.5 Underground Manpower Requirements

 

16.5.1 Manpower

During the first three (3) years of underground activity, a contract labour force has been assumed. During months 30 through 36, the labour force will transition from contractor to New Gold personnel resources.

 

16.5.2 Schedule

Hourly labour will generally work a one-week-on, one-week-off, rotation schedule, whereas technical staff and supervision will largely work a normal five-days-on, two-days-off working week. The working time per day is based on two, 10-hour shifts per day. This will allow up to two hours for blasting fumes to clear between shifts, although in practice, less fume clearance time will be required such that mine access may be regained in less than an hour.

AMC estimates the effective working time per shift during production operations to be 7.25 hours in consideration of travel time, daily safety briefs, and pre-start safety checks.

 

16.5.3 Organization

The underground mining team will be organized into operational groups consisting of supervision, technical support, maintenance and operations. Table 16-26 shows the projected manpower loading to sustain 1,500 tpd of production once the ramp-up period has been completed.

Table 16-26: Underground Manpower Loading At Full Production

 

Engineering and Geology

   # of People  

Chief Mine Engineer

     1   

Senior Mine Engineer

     1   

Mine Engineers

     1   

Surveyors

     4   

Mine Technicians

     1   

Mine Geologists

     2   

Geological Technicians

     4   

Ground Control Technician

     1   

Ground Control Engineer

     1   

 

 

16-92


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Mine Supervision

  

Mine Superintendent

     1   

Mine Captain

     2   

Mine Clerk

     1   

Mine Operations

  

Mine Shift Supervisors

     8   

Jumbo Operators

     8   

LH Drill Operators

     8   

LHD Operators

     16   

Truck Drivers

     24   

Trainer (equip & safety)

     2   

Diamond Drillers

     2   

Blasters

     16   

Bolters & Ground Support

     8   

Grader Operator

     2   

General Labourers

     8   

Services

     12   

Backfill Plant Operators

     4   

Mine Maintenance

  

Maintenance & Electrical Superintendent

     1   

Maintenance Planner

     1   

UG Warehouse Person

     2   

Mechanical Foreman

     1   

Welders

     2   

Mechanics

     16   

Electrical Foreman

     1   

Electrician

     8   

Apprentices

     2   

Labourers

     4   

Total

     176   

 

 

16-93


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Figure 16-51 shows the manpower loading through the mine life. Years -2 and -1 are periods of construction of surface infrastructure and early development of the open pit. Underground activity commences in Year 1. Initial loading will primarily be provided by the contractor, with technical support provided by New Gold. During Year 3, mine forces will transition from contractor to New Gold personnel.

 

LOGO

Figure 16-51: Manpower Loading By Year

 

16.6 Combined Production Schedule

Figure 16-52 and Figure 16-53 show the annual concentrator feed summary and gold production. A combined production schedule for both open pit and underground operations is summarized in Table 16-27.

 

 

16-94


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 16-52: Annual Concentrator Feed

 

 

16-95


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 16-53: Annual Concentrator Feed

 

 

16-96


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 16-27: Open Pit and Underground Mine Production Schedule

 

    Ore Milled (OP & UG
Combined)
    Gold     Silver     OP Direct
Proce-
ssing
(Mine to Mill)
    UG Direct
Proce-

ssing
    OP
Stockpiled
Total
    OP Stockpile
Reclaim Total
    OP
Waste

Rock
    Over-
burden
    OP S/
R

(exc.
Stock-
pile)
    OP S/
R

(inc.
Stock-
pile)
 

Period

  Ton-
nes
(Mt)
    Au
(g/t)
    Ag
(g/t)
    Au
Recov-

ery (%)
    Ag
Recov-

ery (%)
    ‘000
oz
    ‘000
oz
    Ton-
nes
(Mt)
    Au
(g/t)
    Ag
(g/t)
    Ton-
nes
(Mt)
    Au
(g/t)
    Ag
(g/t)
    Ton-
nes
(Mt)
    Au
(g/t)
    Ag
(g/t)
    Ton-
nes
(Mt)
    Au
(g/t)
    Ag
(g/t)
    Ton-
nes
(Mt)
    Ton-
nes
(Mt)
     

2015(Y-2)

                              0.16        0.71        1.84              8.8        13.4       

2016(Y-1) 1

    0.38        1.50        3.00            17        24        0.38        1.50        3.00              0.75        0.45        1.76              12.7        11.9       

2017(Y1)

    7.54        1.44        2.13        91.9     65.5     322        337        7.54        1.44        2.13              6.83        0.42        1.56              26.7        12.1        5.15        6.06   

2018(Y2)

    7.67        1.48        2.00        92.1     65.7     337        323        7.65        1.48        1.95        0.02        4.65        24.79        4.30        0.41        1.46              42.7        10.4        6.95        7.51   

2019(Y3)

    7.67        1.45        3.80        92.0     63.1     328        591        7.47        1.37        3.03        0.20        4.48        32.69        6.31        0.37        1.91              45.4        9.0        7.29        8.13   

2020(Y4)

    7.66        1.43        3.56        91.9     63.5     324        556        7.43        1.31        2.65        0.24        5.13        31.94        4.61        0.41        1.93              44.9        11.8        7.63        8.25   

2021(Y5)

    7.67        1.38        4.92        91.7     61.5     312        746        7.24        1.14        4.59        0.42        5.46        10.65        5.03        0.38        2.94              47.6        4.9        7.25        7.95   

2022(Y6)

    7.67        1.46        4.27        92.0     62.4     332        657        7.11        1.17        4.18        0.55        5.31        5.41        5.91        0.35        2.43              44.3        0.0        6.23        7.06   

2023(Y7)

    7.66        1.50        2.74        92.1     64.6     340        436        7.11        1.21        2.59        0.55        5.23        4.63        3.09        0.34        1.78              29.8        0.0        4.20        4.63   

2024(Y8)

    7.66        1.57        2.15        92.3     65.5     358        347        7.11        1.30        1.88        0.55        5.12        5.58        0.48        0.30        1.20              12.6        0.0        1.77        1.84   

2025(Y9)

    7.67        1.21        2.04        91.0     65.6     271        331        3.58        1.41        1.59        0.55        4.93        8.51              3.54        0.42        1.50        2.5        0.0        0.36        0.71   

2026(Y10)

    7.66        0.68        1.64        87.3     66.2     147        268              0.54        4.57        4.21              7.12        0.39        1.45           

2027(Y11)

    7.66        0.60        2.59        86.2     64.8     127        413              0.44        4.37        14.12              7.21        0.37        1.88           

2028(Y12)

    7.64        0.40        2.81        82.3     64.5     81        445              0.12        4.29        19.94              7.52        0.34        2.54           

2029(Y13)

    7.66        0.33        2.11        80.2     65.5     66        341                          7.66        0.33        2.11           

2030(Y14)

    4.41        0.55        2.33        74.2     64.8     58        214                          4.41        0.55        2.33           

2031(Y15)

                                             
 

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

 

Grand Total

    104.28        1.13        2.81        90.6     64.1     3,402        6,004        62.62        1.31        2.79        4.19        4.96        10.31        37.46        0.39        1.99        37.46        0.39        1.99        318.18        73.57        3.91        6.85   
 

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

   

 

 

 

 

1. 

Gold recovered during the ramp up period is considered as a credit within the Owner’s Costs. The gold sold is used as a credit based on New Gold’s estimated ramp up processing capabilities, recoveries and expenditures during this period.

 

 

16-97


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

17. RECOVERY METHODS

 

17.1 Proposed Process Flowsheet

A flowsheet including crushing, grinding, gravity recovery, cyanide leach, carbon-in-pulp circuit, electrowinning and refining was developed based on metallurgical testwork conducted at SGS Lakefield, equipment suppliers and on BBA’s experience on similar projects. This flowsheet utilizes the results of the testwork completed to-date and is the basis for the plant design and mill operating cost developed in this Study.

The proposed general process flowsheet for the Rainy River Project is shown in Figure 17-1.

 

 

17-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

LOGO

Figure 17-1: Whole Rock Leach Process Schematic Diagram

 

 

17-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Process Design Criteria

The design and sizing of equipment was based on a total process plant throughput of 21,000 tpd, or 7.7 Mtpa. This includes 1,500 tpd from the underground mine starting in Year 3.

All equipment in the grinding circuit was designed based on the 80th percentile of results from the comminution testwork program.

The general Process Design Criteria for the plant is shown in Table 17-1.

Table 17-1: General Process Design Criteria

 

Criterion

   Unit      Value  

Plant Availability

     %         92   

Throughput

     Mtpa         7.7   
     tpd         21,000   
     t/h         951   

Duration of Operation

     years         13.6   

Average Feed Grade (Open Pit and Underground, Blended, First 8.5 Years Operation)

    

 

g/t Au

g/t Ag

  

  

    

 

1.48

3.13

  

  

Average Feed Grade (Open pit, excluding stockpile)

    

 

 

g/t Au

g/t Ag

g/t Au

  

  

  

    

 

 

1.31

2.79

4.96

  

  

  

Average Feed Grade (Underground)

    

 

g/t Ag

g/t Au

  

  

    

 

10.31

0.39

  

  

Average Feed Grade (Stockpile)

     g/t Ag         1.99   

Average Feed Grade (Open pit and Underground, blended, life of mine)

    

 

 

g/t Au

g/t Ag

g/t Au

  

  

  

    

 

 

1.12

2.80

2.50

  

  

  

Design Feed Grade

     g/t Ag         6.00   

Primary Crushing

     

Number of Crushers

        1   

Crusher Type

        Gyratory   

Utilization

     %         65   

P80

     mm         163   

Hourly Throughput

     t/h         1,346   

Grinding

     

Number of SAG Mills

        1   

SAG Mill T80

     µm         2,800   

SAG Power Requirements

     kWh/t         13.3   

 

 

17-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Criterion

   Unit      Value  

Pebble Crusher P80

     mm         13   

Number of Ball Mills

        1   

Ball Mill P80

     µm         75   

Bond Ball Mill Index

     kWh/t         15.0   

Cyanide Leaching

     

Total Retention Time

     hours         30   

pH

        10.5   

Number of Tanks

        8   

Carbon-in-Pulp

     

Number of CIP Circuits

        1   

Carbon Tonnage per tank

     t         20   

Carbon Transfers per Day

        0.5   

Average Carbon Loading (Silver + Gold)

     g/t         7,500   

Number of Tanks

        7   

 

17.2 Process and Plant Facilities Description and Design Characteristics

The current design accounts for two (2) main mineral processing buildings:

 

 

Primary Crushing Building; and

 

 

Main Process Plant.

A general building site layout representing the electrical substation, process plant, stockpile and the primary crusher is presented in Figure 17-2.

 

 

17-4


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 17-2: General Processing Area and Buildings Site Layout

 

 

17-5


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

17.2.1 Primary Crushing

The primary crusher will be located on bedrock near the pit exit ramp outside the ultimate mine pit and outside the blasting perimeter. The pad will be approximately 140 by 120 m to allow for mine truck circulation and an emergency run of mine rock stockpile area on the south end of the pad .

Open pit mine trucks (220-tonne class) will dump rock into two (2) dump points, feeding a 1,372 x 1,905 mm (54” x 75”) gyratory crusher. The crusher will process 21,000 tpd, or 1,346 t/h at 65% utilization. The crusher will be powered by a 596 kW, 600 RPM squirrel cage induction motor.

A rock breaker will be used to break any large boulders and to manipulate rocks to avoid bridging the mouth of the crusher. Inside the crusher building, three (3) manual hoists will be used for general maintenance purposes. The auxiliary equipment located below the primary crusher is accessed through a hatch. A 25-tonne gyratory crusher service hatch crane will be used for moving heavy equipment and pieces. A mobile crane will be used for moving the crusher spider and main shaft and for crusher liner replacement.

The primary crusher building is approximately 800 m from the process plant and houses the gyratory crusher and the tail end of the stockpile feed conveyor. The layout of the building foundation is based on using mechanically stabilized earth (“MSE”) to minimize capital costs. A mechanically stabilized earth wall will be built so that the conveyor to the coarse ore storage remains aboveground. The total depth of the building will be approximately 30.5 m below grade.

Crushed rock with an estimated maximum size of 350 mm (approx.14”) will be discharged to a surge pocket with a 440-tonne capacity. The surge pocket will serve as a buffer for the apron feeder during operation and will also be the access point under the gyratory crusher for maintenance.

One (1) 2,134 mm wide variable speed apron feeder will reclaim crushed rock from the surge pocket and discharge onto the 1,372 mm wide crushed rock conveyor at a controlled rate. The apron feeder is sized to handle the full capacity of the gyratory crusher at 65% utilization. A dribble chute located under the apron feeder will be used to collect and discharge fines onto the crushed rock belt conveyor.

 

 

17-6


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

A maintenance building will be built beside the crusher building for maintenance of major crusher components.

Sump pumps at the reclaim level will be sized to handle all the incoming flows including ground water, service water from operation and the runoff water that will come from the conveyor’s trench.

 

17.2.2 Crushed Rock Handling and Storage

The gyratory crusher discharge conveyor will discharge onto the stockpile feed conveyor (stacking conveyor) via a transfer tower.

The crushed rock stockpile pad is 75 m in diameter with a 14,240-tonne live capacity and an overall capacity of 71,830 tonnes. Under the stockpile, a reclaim tunnel is installed to recover the stored material. A prefabricated electrical and mechanical room is located adjacent and above the reclaim tunnel.

The crushed rock will be reclaimed by three (3) 2,134 mm wide apron feeders all in operation with the capability to operate two (2) at full production capacity while conducting maintenance. The apron feeders will feed a single 1,372 mm wide SAG mill feed conveyor. A belt scale will be installed on a horizontal section of the conveyor belt to monitor the feed rate to the processing plant.

 

17.2.3 Processing Plant and Tailings Handling

The main processing building houses the grinding circuit (SAG mill, ball mill, and hydrocyclone), pebble crushing, gravity recovery, CIP, carbon stripping, electrowinning, refining and reagent preparation areas, as well as the tailings pumps, compressors and metallurgical laboratory. Three (3) electrical rooms supply power to the plant. The pre-leach thickener, leach tanks, pre-detox thickener, lime slaking, offices and dry, and cyanide destruction areas are located outside of the processing building.

The general plant layout is shown in Figure 17-3.

 

 

17-7


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 17-3: Process Plant General Arrangement Drawing (Including Primary Electrical Substation)

 

 

17-8


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

17.2.4 Primary and Secondary Grinding

The 11.0 m x 6.1 m, dual-pinion 15,000 kW SAG mill will process an average 951 t/h of fresh feed with an F80 of 163 mm. The SAG mill will be equipped with two (2) 7,500 kW motors (dual pinion) and a variable speed drive system. Process water will be added to the mill to achieve a density of approximately 70% solids. Steel grinding media (5” or 125 mm diameter) will be used in the mill with a volumetric grinding media charge of approximately 13%. The discharge from the mill will be fed onto a single deck 3.6 m x 7.3 m scalping screen to size the ball mill circuit feed. The oversize from the sizing screen will be fed to the pebble recycle conveyor located at the discharge of the screen, which then feeds another recycle conveyor to a 448 kW pebble crusher. The sizing screen oversize tonnage will be approximately 25% of the fresh feed. The fresh feed from the stockpile will be combined with the crushed pebbles recycled from the pebble crusher to feed the SAG mill.

The scalping screen undersize, with a T80 of 2,800 µm, discharges into the cyclone feed pump box.

The slurry from the cyclone feed pump box will be pumped to a cyclone cluster in closed-circuit with a 7.9 m x 12.3 m, 15,000 kW ball mill. The overflow from the cyclone cluster will feed the pre-leach thickener via two (2) 20 m2 linear trash screens placed in parallel to remove any unwanted material and will have a P80 of 75 µm. The cyclone underflow will be fed to the ball mill and the overall circulating load of the ball mill closed circuit is estimated to be 300%. A fraction of the ball mill discharge will be diverted to the gravity recovery circuit.

The ball mill will be equipped with two (2) 7,500 kW motors (dual-pinion) and a variable speed drive system. The variable speed on the ball mill will permit closer control on the product size and will also permit a soft start for frozen charge control. The drive size was chosen to match the SAG drives, as this was the most economical sizing option.

Sufficient space will be provided behind and around the ball and SAG mill to use a mill liner handler for effective mill maintenance. The mill liner handlers will be the hydraulic driven type. There will be a hydraulic inching drive provided for both the SAG and ball mills to rotate the mills to the desired position during liner maintenance.

 

 

17-9


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The grinding building is a one-bay building covering all the grinding facilities, containing the SAG and ball mill, along with the sizing screen, pebble crusher, cyclone cluster and gravity recovery equipment. This area is serviced by one (1) overhead crane with a 60/20-tonne capacity to lift the heaviest pieces of the mills. The SAG mill electrical room is located on the ground floor under the SAG mill feed area.

Grinding media is stored in three (3) ball pits located along the exterior wall beside the SAG mill. Balls are retrieved from the ball pit by means of the 60/20-tonne capacity crane through a ball flow gate system and ball bucket. The grinding media is fed into the SAG and ball mill through ball addition chutes.

 

17.2.5 Gravity Circuit

The feed to the gravity recovery circuit is anticipated to handle approximately 600 t/h. The gravity feed will be a portion of the ball mill discharge that is diverted from the ball mill discharge chute to a dedicated gravity circuit feed pump box and pumps. Two (2) 1,800 x 4,900 mm screens will scalp off any coarse material prior to the gravity concentrators. The undersized material from the screens will feed two (2) 56 kW gravity concentrators, placed in parallel. The gold concentrate from the gravity concentrators will feed an intensive cyanidation vessel. The pregnant leach solution from the cyanidation vessel will be pumped to a dedicated electrowinning cell via a pregnant solution tank located in the gold room. The gravity tailings will be returned to the ball mill pump box.

 

17.2.6 Cyanide Leaching Circuit

A 45 m diameter pre-leach, above-ground thickener positioned outside of the concentrator building will increase the density of the ball mill cyclone overflow to approximately 61% solids. Lime (CaO) will be added to the thickener feed box to raise the pH of the slurry to around 10.5 to improve the solids settling rate. The underflow from the thickener will be fed to the leach tanks by slurry pumps and diluted to 50% solids with cyanide bearing process water in the leach circuit feed tank. The thickener overflow will flow into the 17 m diameter process water tank (non cyanide bearing) located between the thickener and the process plant. The process water pumps will be located inside the plant. The thickener drive mechanism will be enclosed in a shelter to prevent snow, ice and other weather hazards from damaging the equipment and to facilitate operation and maintenance during winter.

 

 

17-10


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Gold leaching will be performed using sodium cyanide (“NaCN”). Lime slurry will be added as required to maintain the pH of the solution around 10.5-11. Eight (8) 18 m diameter agitated leach tanks will be used in a series arrangement, allowing for a 30-hour retention time. The heights of the tanks will range from 22.7 m to 19.2 m, with the slurry flowing from the tallest tank to the shortest. Oxygen will be used in the leach tanks to improve reaction efficiency and pacify sulphides. While no improvements in kinetic were noted using oxygen over air in testwork (refer to Section 13.8.4), a trade-off study indicated that using oxygen was more economically favourable than compressed air. The leach tanks will be installed on concrete rings resting on rock. A concrete slab and concrete wall poured on a granular backfill will serve as secondary containment around the tanks. Any seepage through the steel bottom of the tanks and concrete slab will be contained by a high-density polyethylene (“HDPE”) membrane installed in the backfill. Tanks and agitator drives will be serviced by a mobile crane.

 

17.2.7 Carbon-in-Pulp Circuit, Carbon Stripping and Reactivation

A carousel style CIP circuit was selected. Seven (7) tanks with a volume of 360 m3 will be required, with each tank containing 20 tonnes of carbon. The retention time for each tank will be approximately 17 minutes, with approximately 117 minutes total retention for the circuit.

With the carousel system, it is estimated that the maximum carbon loading will be approximately 10,000 grams of gold and silver per tonne of carbon (g/t), with average loadings of approximately 7,500 g/t. In normal operation, one (1) tank from the CIP circuit will be emptied and transferred to the stripping circuit every two (2) days however the design of the circuit allows for a transfer every day. The contents of the tank will be pumped to the loaded carbon recovery screen located on top of the carbon stripping circuit. The carbon retained on this screen will feed the stripping circuit while the slurry and wash water undersize will be recycled to the CIP circuit.

The strip solution will exit the barren solution tank and will be heated via heat exchangers and immersion heaters. This solution, containing sodium cyanide and caustic soda, will elute gold from the carbon located in the stripping vessel and will be cooled down via the same heat exchanger arrangement prior to electrowinning. The electrowinning circuit will produce a gold and silver sludge, which will be dried and smelted into doré bars as a final product. The now barren solution discharged from the electrowinning cells will then be returned to the barren solution tank.

 

 

17-11


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The stripped carbon discharged from the stripping circuit will be screened: the oversize will be reactivated in a kiln and recycled to the CIP circuit, while the fines will be recovered and sold to a refinery for gold credits.

Fresh carbon will be added into a carbon attrition tank via a hopper. Carbon transport water will be added to the tank and the tank’s agitator will condition the carbon. The carbon slurry will be pumped to a fresh carbon sizing screen. The oversize from the screen will be discharged into the quench tank while the undersize will be discharged into the fine carbon collection tank.

 

17.2.8 Tailings Management and Cyanide Destruction

The CIP tailings will be pumped to a 45 m diameter pre-detox thickener via a 32 m2 safety screen, allowing recovery of carbon that may have passed through a broken carbon retention screen. The objective of the pre-detox thickener is to recycle residual cyanide from the CIP tailings. The overflow from the thickener will be stored in the cyanide bearing process water tank and used as cyanide bearing process water, predominately for the dilution of the pre-leach thickener underflow. The pre-detox thickener underflow, discharged at 60% solids will be diluted to 50% solids using non-cyanide bearing process water. The diluted underflow will be pumped to the cyanide destruction circuit.

The cyanide destruction circuit will use a conventional liquid SO2/air process to lower the weak-acid dissociable cyanide (“CNWAD”) and total cyanide (“CNT”) levels to acceptable levels for discharge into the tailings pond. Sulphur dioxide (“SO”) will be added along with oxygen (in the 2 form of compressed air) to dissociate the cyanide, along with dissolved copper acting as a catalyst. Hydrated copper sulphate (“CuSO4•5H2O”) will be added to raise copper levels in the solution and act as a catalyst. Lime will be used to neutralize any sulphuric acid (“H2SO4”) produced in the cyanide destruction reaction. The cyanide destruction circuit will require one (1) 14 m x 16 m tank in order to provide 90 minutes of retention time. The cyanide destruction tank will be located outside the process building, installed on a concrete ring resting on rock. A concrete slab and concrete wall poured on a granular backfill will serve as secondary containment around the tanks. Any seepage through the steel bottom of the tanks and concrete slab will be contained by a HDPE membrane installed in the backfill. The product from the cyanide destruction circuit will be pumped to the tailings pond. Water from the tailings pond will be reclaimed and pumped into the process as non-cyanide bearing water.

 

 

17-12


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

A single pipeline will be used for tailings pumping. The pipeline will be approximately 6.8 km in length at the beginning of operations, will be expanded to a total length of 10.4 km and will be made of HDPE. There will be a set of standby tailings pumps that can be used when the other pumps are in maintenance or shut down. Reclaim water will be returned via a HDPE pipeline with the use of a floating reclamation barge.

In case of an extended power outage, the contents of the tailing pipelines will be flushed with reclaim water and then drained by gravity into two (2) outside emergency retention ponds to prevent settling of the slurry and pipeline blockage.

 

17.2.9 Refining Area and Gold Room

The refining area and gold room will be a secure area with two (2) separate entrances. The first entrance is a personnel entrance to the gold room office. The personnel entrance consists of a reinforced security door that leads into a staging room. The staging room leads into the gold room through another reinforced security door, which can only be opened when the first security door is locked. The second entrance is for the armoured truck to enter the gold room. An external safety fence is erected around the reinforced garage door and is setup in the same way as the personnel entrance, where the security fence gate must be locked before the reinforced garage door is opened.

This area will contain the electrowinning circuit, the induction furnace to produce the doré bars, a vault, and the gold room office. It is anticipated that during full production, an average of 12 doré bars will be poured per week.

 

17.2.10 Reagent Areas

All process reagents will be located in a separately contained area within the process plant building to prevent contamination of the plant in case of a spill. The reagent area will also include the exterior lime storage bin.

 

17.2.11 Control Room and Maintenance Shop

The control room will be located in the grinding area on an elevated floor, overlooking the SAG and ball mill circuits. The plant maintenance shops will be located on the ground floor in the grinding area. This area will be serviced by a 10-tonne capacity overhead crane.

 

 

17-13


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

17.2.12 Offices and Change House

The process plant staff offices will be located outside and adjacent to the process plant in a prefabricated building. This building will house the conference room, documentation room, computer server room, lunch room and washrooms. Change rooms for men and women will be located in the prefabricated building.

 

17.2.13 Metallurgical Laboratory

A metallurgical laboratory will be included in the process plant. The laboratory will be located on the eastern side of the plant, adjacent to the reagent storage area.

 

17.3 Energy, Water and Consumable Requirements

 

17.3.1 Energy

The power demand of the process plant will be approximately 44.2 MW, or a total energy consumption of 46.5 kWh/t milled for 21,000 tpd. The grinding circuits represent approximately 60-65% of the total operating power of the plant. The processing plant power demand is shown in Table 17-2.

Table 17-2: Process Plant Power Demand by Area

 

Area

   Power Demand  (MW)1  

Primary Crushing (Gyratory)

     1.2   

Grinding (SAG and Ball Mill)

     25.7   

Processing (Peripherals and Back end)

     12.5   

Network Loss (2%)

     0.7   

Power Demand Subtotal

     40.2   

Security Factor (10%)

     4.0   

Process Plant Power Demand2

     44.2   

 

1. 

The power demand was calculated using various efficiency, load and diversity factors.

2. 

Tailings barge is not included in total process plant power demand. Refer to Chapter 18 for the whole site power demand.

 

17.3.2 Water

A water balance has been developed and is shown in Figure 17-4. The addition of cyanide into the circuit will initially be done after the pre-leach thickener; however, the design allows for cyanide to be added into the grinding circuit in the future, if required. The overflow from the pre-leach thickener will be combined with reclaim water from the Tailings Management Area (“TMA”) and Mine Rock Pond (“MRP”) to make up the non-cyanide bearing process water. The MRP serves as a catchment basin for the mine waste rock pile.

 

 

17-14


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 17-4: Process Plant and Tailings Pond Water Balance

 

 

17-15


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

It can be seen that process water will be obtained from both the TMA (reclaim water) and from the MRP. Approximately 40% of the make-up process water will come from the TMA. The reclaim water will be used as gland seal water, heat exchanger water for cooling of major pumps and make-up to the process water tank. The remaining process make-up water will be taken from the MRP. Overflow from the Stockpile Pond (“SP”) will also be pumped and collected in the MRP. The total process water make-up has been estimated at approximately 870 m3/h.

Fresh water will be obtained from the Water Management Pond (“WMP”) and will be used for reagent preparation, surface utilities and fresh water plant requirements. The total fresh water requirement is estimated to be approximately 75 m3/h.

 

17.3.3 Consumables

Reagents will be required for various areas of the plant such as: cyanide leaching, CIP, stripping and refining, thickening and cyanide destruction.

Lime

Quick lime will be delivered in trucks with 30-tonne capacity into a 183-tonne storage silo, sufficient for 10-day capacity. Volumetric screw feeders at the bottom of the silo will convey the quick lime to two (2) lime slaking trains (one (1) operating, one (1) stand-by), where water is added to the quicklime to form a hydrated lime slurry. The 150 m3 holding tank will have a capacity of 1.5 days. The hydrated lime slurry will have a solution strength of 25% w/w (mass fraction weight/weight).

The lime slurry will be fed by two (2) distribution loops to the grinding circuit, pre-leach thickener, leach tanks and cyanide destruction circuit. A by-pass line to the leach tanks will be provided in the event of a pH variation.

The total autonomy of the system will be approximately 12 days.

Cyanide

Sodium cyanide will be delivered as solid briquettes in 20-tonne capacity ISO containers. The briquettes will be mixed with water and caustic soda to form a 23% w/w solution in a 100 m3 mixing tank. Two (2) recirculation pumps will be provided to recirculate the solution with the ISO container to ensure proper dissolution of the sodium cyanide. A 150 m3 holding tank will also be provided. Two (2) variable speed pumps will deliver the cyanide solution into the leach circuit, stripping circuit and intensive cyanidation unit using flowmeters as control elements.

 

 

17-16


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The total autonomy of the system will be approximately seven (7) days. One (1) extra ISO container is left on-site, allowing an extra three (3) days autonomy.

Oxygen

A turnkey oxygen plant will be installed and operated on site by a third party beginning in Year 3 (2019). During the first two (2) years of operation, oxygen will be supplied as bulk liquid and vaporized on site. This will be done due to the lower tonnages expected in Year one (1) prior reaching steady state and to gather a better understanding of the oxygen requirements prior to installing an on-site oxygen generator (“VPSA”).

The vacuum pressure swing adsorption VPSA plant will be capable of supplying approximately 750 m3/h of oxygen. A liquid oxygen backup system, as used in Years 1-2, will also be integrated into the package. This arrangement will ensure a constant gaseous oxygen supply to the leach tanks. All oxygen piping will be stainless steel.

Caustic Soda

Caustic soda will be delivered in liquid form (50% w/w) in tanker trucks of 30 tonnes. A 50 m3 mixing tank will be provided to dilute the caustic soda solution to 30% w/w. The holding tank will have a volume of 70 m3. The caustic soda will be pumped to the cyanide mixing tank, the stripping circuit and the intensive cyanidation unit.

The total autonomy of the system will be approximately 30 days.

Anti-Scalant

Anti-scalant will be used in various areas to minimize the scale build-up. Each area will have its own anti-scalant metering pump. Anti-scalant will be delivered in 30-tonne tankers and stored inside in a 44 m3 reservoir.

The total autonomy of the system will be approximately 140 days.

 

 

17-17


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Nitric Acid

Nitric acid will be delivered at a concentration of 67% w/w by a 30-tonne tanker truck and transferred to the 37 m3 nitric acid holding tank. The nitric acid will be diluted and used in the stripping circuit for acid washing.

The total autonomy of the system will be 30 days.

Carbon

Natural coconut shell-type activated carbon (typical dimensions 6 mesh x 12 mesh) will be used in the adsorption circuit. The total estimated consumption will be approximately 30 g of carbon per tonne milled, based on operation standards and the utilization of the carbon-in-pulp pump cell circuit minimizing carbon losses as fines. Monthly consumption will be approximately 20 tonnes of carbon. Carbon will be delivered in super bags and stored outdoors.

Sulphur Dioxide

Sulphur dioxide (“SO2”) will be delivered in liquid form by a tanker truck of approximately 20 t and stored in a 64 m3 pressurized horizontal holding vessel. The package will be complete with a padding system assembly including air compressors, dryers and compressed air receiver. The padding system will ensure storage of sulphur dioxide in its liquid form by pressurizing the horizontal vessel. In addition, it will also allow delivery of the liquid sulphur dioxide to the cyanide destruction tank. Package will be complete with all required instrumentation for metered reagent delivery. The selected arrangement ensures that no compressed air lines connected to the SO2 system enter the process plant.

The total autonomy of the system will be 10 days.

Copper Sulphate

Copper sulphate (“CuSO4·5H2 O”) will be delivered in 1,000 kg super bags. The bags will be mixed with fresh water and dissolved to 10% w/w. The 36 m3 mixing tank will be sized for 1.5 days of production. The solution will be transferred from the mixing tank to a 54 m3 holding tank by a transfer pump, from where it will be pumped to the cyanide destruction tanks via metering pumps.

 

 

17-18


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The total autonomy of the system will be approximately seven (7) days. The on-site storage of solid copper sulphate in super bags will ensure an autonomy of approximately 30 days.

Flocculant

Flocculant will be delivered to the plant in 750 kg super bags. The two (2) thickeners will require approximately two (2) bags per day. The flocculant bags will be stored in an outdoor container. A small supply will be kept in the mixing area. The bags are lifted over a hopper that feeds a wetting device to form 0.75% w/w slurry. The slurry will then report to an agitated mixing tank prior to being transferred to a flocculant holding tank by progressive cavity pumps. The mixing tank was sized to have a 4-hour capacity.

From the holding tank, the flocculant will be metered independently to both thickener feed wells by progressive cavity pumps. As the polymer is pumped by the metering pumps, it will pass through a flocculant dilution board (static mixers), where it will be diluted further to 0.05% w/w. The holding tank will have a 24-hour capacity.

The total autonomy of the system will be 28 hours. The on-site storage of flocculant in super bags will ensure an autonomy of approximately 30 days.

Reagent Consumption

A breakdown of the estimated reagent consumptions per tonne milled and total annual consumption is presented in Table 17-3.

 

 

17-19


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 17-3: Process Plant Reagent Consumption

 

               Estimated Consumption  

Reagent

   Formula   

Physical State

   g/t milled      tpa  

Lime

   CaO    Solid      820         6,260   

Sodium Cyanide

   NaCN    Solid      280         2,150   

Oxygen

   O2    Liquid1      650         5,000   

Caustic Soda

   NaOH    50% w/w Solution      120         910   

Sulphur Dioxide

   SO2    100% w/w Liquid      390         3,000   

Copper Sulphate

   CuSO4Ÿ5H2O    Hydrated Crystals      70         520   

Nitric Acid

   HNO3    67% w/w Solution      60         430   

Carbon

   —      Solid      30         260   

Anti-Scalant

   —      Solution      15         100   

Refining Fluxes

   —      Solid      1         8   

Flocculant

   —      Solid      70         550   

 

1. 

Oxygen to be received as liquid during first two years of operation with on-site oxygen generation installed in Year 3 of operation.

The reagent consumptions were based on project specific testwork, supplier recommendations and operating practice in existing plants.

Grinding Media Consumption

Other consumables include the grinding media for the SAG mill and ball mill. The media consumptions were estimated using two (2) methods (Bond and Molycop Tools) and validated through discussions with Vendors. Consumptions were estimated on a g/kWh basis and tonnage consumptions were estimated based on the annual power consumptions for the SAG and ball mill.

The type, size and estimated consumption of grinding media by piece of equipment are shown in Table 17-4.

Table 17-4: Grinding Media Consumptions by Mill Type

 

     Type      Size
(mm)
     Estimated Consumption  

Equipment

         g/kWh      g/t      tpa  

SAG Mill

     Forged Steel         125         49         650         5,000   

Ball Mill

     Forged Steel         50-75         58         750         5,750   

 

 

17-20


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

18. PROJECT INFRASTRUCTURE

A general layout drawing of the infrastructure, including the process plant, offices, administration building, main electrical substation, truck shop, truck wash facilities, coarse ore storage and crusher building is provided in Appendix F.

 

18.1 General Site Works

General site preparation will consist of clearing, grubbing, topsoil removal and surface leveling throughout the construction areas. Clearing, grubbing and topsoil removal needs were estimated from aerial photographs showing tree and ground cover. Topsoil removal and grubbing are considered to be carried out at the same time for material take-off purposes. Clearing is done in and around all construction areas to provide easy access. Topsoil is removed to provide a stable sub-base for platforms and to provide slope stability below the perimeter of the overburden and waste rock stockpiles.

Site drainage to support construction works will be achieved with the excavation of drainage ditches bordering building platforms and roads, feeding to culverts and sedimentation ponds.

Underground sanitary sewers, underground fire protection and potable water pipes, as well as sewage and potable water treatment plants will be constructed according to local requirements. Potable water will be distributed to the process plant area and the mine garage. These areas will also have sanitary sewers and fire protection. All areas will have a granular access platform surrounding the facilities.

Engineered fills on clay foundations must have at least 3H:1 V side slopes to avoid overstressing the clay. Excavations deeper than 2 m must have slopes no steeper than 3H:1 V for stability and safe working conditions. A frost depth of 2.7 m is also to be considered for building foundations and underground piping that are not sitting on rock.

 

18.1.1 Primary Site and Access Roads

The plant site is very well situated and makes use of existing roads. As such, these onsite roads will provide access to the Tailings Management Area (“TMA”) and the explosives plant. The road widths will be enlarged to allow space for tailings and reclaim water pipes, as well as light traffic (emulsion tankers and pickup trucks). Existing roads will be resurfaced with crushed stone.

 

 

18-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Plant site roads will connect the process plant area to the coarse ore storage and the crusher area. The roads represent a total length of approximately 1,050 m.

TBT was commissioned by Rainy River Resources Ltd. to undertake a study for construction of an East Access Road that will serve as the main access from Kings Highway 71 to the proposed mine development area and provide maintenance access alongside the tailings pipes.

The TBT study also determined the optimal route for the proposed realignment of a segment of Provincial Highway 600, currently passing through the development area.

Based on the findings of the TBT study, the preferred alignment for rerouting Highway 600 around the proposed development area optimizes the use of existing road easements and is the preference of both the Township of Chapple and Rainy River.

Access to Marr Road will be provided from the new proposed East Access Road.

 

18.1.2 Mine Haul Roads

Mine haul roads will be built to connect the open pit to the overburden and waste rock stockpiles. These haul roads will also connect the pit to the crusher pad, mine facilities (truck shop and truck wash) and tailings dike. The total length for the mine haul roads outside the pit limit is approximately 6,000 m. These roads will be built at the start of the Project and will remain in use for the duration of the mine life. Mine haul roads will also be built between the open pit and the tailings dam to haul mine material to the dam.

 

18.1.3 Geotechnical

AMEC carried out a series of geotechnical drilling campaigns at the open pit, tailings and water management dam sites, mineral waste stockpiles and critical areas between the open pit and Pinewood River to characterize the site conditions and the subsurface stratigraphy, and to determine the soil and rock characteristics relevant to the design of the facilities.

The geotechnical site investigations for the purposes of slope and dam design included 16 boreholes for the tailings dams, five (5) boreholes for the overburden stockpile and five (5) boreholes at the mine rock stockpile. An additional 26 boreholes were put down to allow for the design of the open pit overburden slopes, to obtain samples for characterization of the mine waste overburden for use as dam construction material, and to determine the hydrogeological conditions between the pit and the Pinewood River. A further five (5) boreholes and six (6) test pits were put down in 2013 to obtain information on a clay borrow material area from within the footprint of the Water Management Pond.

 

 

18-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The geotechnical investigations for the process plant, carried out under BBA’s specifications and requirements, included a comprehensive drilling and bedrock depth probing program consisting of two drilling campaigns comprising 34 geotechnical boreholes, 38 test pits and 73 dynamic cone penetration tests. An iterative process between AMEC and BBA was followed in order to place the process plant facilities on bedrock.

AMEC (2013a) and AMEC (2013k) provides further details on the geotechnical and hydrogeological investigations. The scale of drilling and bedrock depth probing campaign is considered adequate for the feasibility level design of the facilities.

The foundation design recommendations for the plant facilities provided in AMEC (2012b) were incorporated into the design of the facilities by BBA.

 

18.2 Mine Services Facilities

The mine services facilities for both the open pit and underground operations include the mine garage and the truck wash facility. The facility dimensions are based on a typical 220 tonne class haul truck. The overall vehicle dimensions and recommended repair bay specifications are summarized in the Table 18-1 and Table 18-2.

Table 18-1: Mining Vehicle Dimensions

 

Dimension

   Haul Truck  

Overall Length

     13,702 mm   

Overall Canopy Width

     8,295 mm   

Overall Canopy Height

     6,603 mm   

Overall Tire Width

     7,605 mm   

Overall Height Body Raised

     13,878 mm   

 

 

18-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 18-2: Mining Vehicle Repair Bay Specifications

 

Specification

   Haul Truck  

Bay Doors

     10.0 m x 7.5 m   

Bay Size

     21.0 m x 18.0 m   

Overhead Crane

     50 t / 15 t   

Crane Hook Height

     14.0 m   

The mine garage will have a total of six (6) maintenance bays, including two (2) bays for auxiliary vehicles and one (1) bay dedicated for welding. The bays will be aligned in a row with one (1) 50-tonne overhead crane servicing all bays. The building will include a 1,400 m2 warehouse and a mechanical workshop that will also serve as a maintenance area for small vehicles. The workshop will be equipped with a 10-tonne overhead crane. The facility will also be equipped with a centralized lube distribution system for oils, grease and other fluids which will feed the lube stations at every bay. Every lube station will also have compressed air and service water outlets.

The truck wash facility will be located approximately 80 m south of the mine garage. The truck wash system will have mud-settling basins, a skimmer for oil and grease removal, and a water filtration system for continuous recycling of wash water. As a result, the filtration system will only require minimal make-up water (5-10%) to prevent mineral build-up. Both the mine garage and truck wash buildings have been designed in a rectangular shape with an inclined roof to make them suitable for a pre-engineered structure. The structures are supported by shallow foundations founded on native soils.

 

18.3 General Offices and Assay Laboratory

All office facilities will be prefabricated type buildings made up of 12’ x 60’ modules. The buildings will be erected on concrete blocks with adjustable trestles founded on engineered fill. There will be three (3) main buildings: the main administration, the mine office and dry, and the plant office. The office requirements for each building are based on the staffing plans presented in Chapter 16. Table 18-3 shows a summary of the office staff requirements and office allocation in the peak year (Year 5, 2021).

 

 

18-4


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 18-3: Staff Requirements

 

Total Requirements

   Peak
Personnel
# Total
     Office
Personnel
Requirements
 

Open Pit Mining

     318         33   

Underground Mining

     168         10   

Process Plant

     91         11   

General and Administrative

     29         26   
  

 

 

    

 

 

 

Total:

     606         80   
  

 

 

    

 

 

 

 

18.3.1 Main Administration Building

The main administration building will be located at the entrance of the mine site and will house administration and safety/security staff only. The office design has ten (10) closed offices and space available for open workstations. There will also be a small kitchen area and three (3) meeting rooms.

 

18.3.2 Mine Office and Dry

The mine office will be located next to the truck shop and will house the mine, maintenance and engineering office staff. The building will also have dry facilities with lockers. There will be one (1) dry changing room for men and one (1) for women. The dry rooms will consist of lockers and sanitary installations designed to accommodate a varying men/women ratio of 90/10% to 75/25%, to allow for possible variations in staff. The locker requirements are doubled to include a dirty side locker and a clean side locker for each employee. The facility will also have meeting rooms, open areas for drawing reviews, a 136-seat lunch area which can also serve as a large conference/training room and a muster room on the ground floor for daily shift meetings.

 

18.3.3 Plant Office

The process plant office will be located on the west side of the process building between the leach tanks and the pre-leach thickener and will be connected to the main building via a short corridor. The building will house the process operations/maintenance office staff, and a dry facility. The building will also have a small lunch room and a 45-seat conference room.

 

 

18-5


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

18.4 Parking Area

Parking for employee vehicles and other service vehicles will be located in proximity to the process plant building and will have capacity for 150 vehicles. The parking area will also have space to accommodate two (2) passenger buses.

 

18.5 Assay Lab

The assay lab is located next to the parking area and is expected to handle approximately 200 samples per day and will have 17 employees. The assay lab includes a sample preparation area, wet laboratory area, fire assay, balance room, instrumentation room, an environmental lab, two (2) offices, a lunch room and two (2) washrooms.

 

18.6 Fuel Storage and Dispensing

The fuel island will be located close to the crusher on the main haul road to the plant and facilities. The tank farm will be located outside the blast radius of the pit, on the plant site road between the crusher and stock pile. The fuel storage will be in seven (7) 80,000 L double-walled tanks. The total capacity is 560,000 L, which represents an autonomy of approximately six (6) days (95,000 L/day fleet consumption). Tanks will be prefabricated and delivered to site on skids with piping and pre-installed valve racks.

Diesel and gasoline will be made available for the light vehicle fleet which is expected to be mostly diesel pickup trucks. This light vehicle fueling station will be at a separate location from the fuel island that is required for the mining vehicles. The light vehicle fueling station will consist of horizontal double-walled tanks, equipped with all the required pumps and distribution equipment.

Explosive Plant and Storage

A pad for an explosive plant and storage depot will be built at a safe distance, north of the process plant area. These buildings will be supplied and constructed by the explosive supplier.

 

 

18-6


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

18.7 Electrical and Communication

Tie-Point Switching Station, Power Line, Main Substation, and Site Electrical Distribution. The total power demand of the Project was determined to be approximately 58.4 MW, based on the estimated connected load, running load and running power.

Table 18-4 shows the power demand breakdown by sector. The power demand was calculated using an average efficiency factor, load factor and diversity factor. Specific numbers were used for the largest loads (primary crusher, SAG mill, ball mill and pebble crusher motors).

Table 18-4: Estimated Total Project Power Demand

 

Area

   Power Demand
(MW)
 

Processing Plant

     39.4   

Site Infrastructure (including reclaim water barge)

     6.0   

Open Pit Mine

     2.1   

Underground Mine

     4.6   

Network Loss (2%)

     1.0   

Power Demand Subtotal

     53.1   

Security Factor (10%)

     5.3   
  

 

 

 

Total Power Demand

     58.4   
  

 

 

 

Electricity will be supplied to the site by a new 16.7 km long 230 kV power line, to be built and subsequently connected to the region’s existing 230 kV Hydro One line currently connecting Fort Frances and Kenora. For interconnection purposes, a 230 kV tie-point switching station is required. An optional feed at 115 kV was studied during the Feasibility Study but was not chosen because of lower reliability, less flexibility and higher losses.

The main 230–27.6 kV substation will be located near the concentrator building where the large electric loads are installed. Both dual-pinion SAG and ball mills are equipped with one (1) active front-end Variable Frequency Drive (“VFD”) with an installed power of 15,000 kW (7,500 kW per motor). The mills will be fed directly from the 27.6 kV switchgear. Two (2) main 230-27.6 kV, 60/80/100 MVA transformers will be used for a combined firm power of 100 MVA.

This option provides ample room for a future expansion, while at the same time mitigating the risk of long downtimes due to transformer failure. A 36 kV Gas Insulated Switchgear (“GIS”), complete with electrical protection devices is included.

In addition to the mills, there will be several induction motors (“SCIM”), with powers ranging from 0.5 to 2,000 HP, which will be driven at 4.16 kV or 600 V feed.

 

 

18-7


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The open pit mine will require an electrification system at 7.2 kV to feed the hydraulic shovel. A dedicated 27.6 kV overhead line will feed a step-down mine substation located near the open pit blast limit. This mine substation will provide 7.5 MVA of power at 7.2 kV for the electrification of the open pit. The 7.2 kV will first be routed on an overhead line to bring it closer to the mining equipment where it will then change over to an insulated cabling system. The switch from overhead line to insulated cables will be optimally placed to minimize the 7.2 kV mine network and shorten the total length of the 7.2 kV trailing cables, which are exposed to potential damage by mobile equipment and flying rocks during the blasts.

The electrical distribution to the site infrastructure will consist of a dedicated 27.6 kV OHL (overhead line) distribution network, equipped with 4/0 ACSR conductors.

The underground mine electrical distribution network will be developed and operated using the decline ramps. Electricity will be provided through an extension of the 27.6 kV mine OHL. A pole-mounted vacuum recloser (“VCR”) will be installed on the last pole and will allow a transition to insulated cables at 27.6 kV to feed the underground mine electrical system. After a few years, the 27.6 kV OHL can be extended to reach the ODM west vent shaft and provide power at that point.

 

18.7.1 Emergency Power

Two (2) emergency power systems (4.16 kV and 600 V) are installed for the purpose of supplying the critical installations when the main power is lost. During a power outage, a Programmable Logic Control (“PLC”) will manage the critical loads. To achieve this task, the loads are regrouped under three (3) different categories; fixed loads (i.e., lighting, heating, leach tank agitator lube pumps), sequential loads (i.e., leach tank agitators, cyanide destruction tank agitators) and manually operated loads (i.e., sump pumps, rake mechanism, reactive heating).

At 4.16 kV, the critical loads are the tailings pumps, heat exchanger feed pumps, leach tank agitators and cyanide destruction tank agitators.

 

 

18-8


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

At 600 V, the main critical loads are as follows: process water pumps, service air compressor, tailing pumps, pre-leach thickener underflow pumps, CIP tank pump screens, pre-detox thickener underflow pumps, sump pumps and gland seal pumps.

The proposed emergency generator fleet for the process buildings and the reclaim water (barge) are presented in Table 18-5.

Table 18-5: Proposed Emergency Generators

 

Location

   MW      Voltage  

Crusher Building

     0.25         600   

Concentrator Building

    

 

1.50

2.50

  

  

    

 

600

4,160

  

  

Reclaim Water TMA

     1.50         600   

The 4.16 kV emergency power supply of the process plant is a centralized system connected to the main 4.16 kV switchgear. However, generator starting is realized by a free-standing control panel. The system controls include a generator demand priority control function to automatically match the on-line generator capacity to the loads. The process plant 600 V emergency power supply is similar to the 4.16 kV systems, except that it is connected to dedicated switchgear that incorporates all the controls (starting and synchronizing).

 

18.7.2 Communication

A combined fibre optic self-healing loop backbone will interconnect all areas. This loop will use the same poles as the 27.6 kV overhead distribution lines and can transmit voice, video and data on the following systems:

 

 

Telemetry, data acquisition, and control between the process plant and exterior process equipment;

 

 

Computer network between all departments;

 

 

Local telephone services;

 

 

Computer network for maintenance on all electrical equipment data;

 

 

Fire Detection;

 

 

Video Surveillance and Access Control Systems; and

 

 

Electrical Teleprotection Equipment.

 

 

18-9


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

18.8 Tailings Management Area

The means of tailings deposition and storage is a key element for the operability and long-term closure strategy for the RRP. The TMA site was selected as it is in close proximity to the process plant and mine for tailings pumping. For dam construction considerations, it has relatively good topographic containment and is suitable for the enclosure of potentially acid generating (PAG) tailings.

The TMA covers an area of approximately 765 ha (excluding associated external ponds and infrastructure) and provides adequate storage capacity for the approximately 74 Mm3 of tailings anticipated to be produced over the projected mine life, based on an average deposited tailings dry density of 1.4 t/m3. The facility is bounded by natural topography (high ground) in the north-east and by impoundment dams along the remaining perimeter, and has the potential for expansion if additional mineral resources are identified through ongoing exploration.

An overview of the TMA design is provided in the following sections. The design basis and analyses are provided in AMEC (2013c).

 

18.8.1 Tailings Deposition Plan

Tailings will be deposited from spigots located along the inside perimeter of the TMA dams in order to develop a tailings beach in front of the dam. Perimeter discharge is a standard practice that enhances dam stability by keeping the pond away from the surrounding dams. The pond will be maintained within the central northern part of the basin to allow easy reclaim of water by barge and pump.

After approximately Year 9 (2024), the spigots will require extension inwards late in the mine life to fill the basin efficiently and minimize the volume of water required for the closure water cover over the tailings.

The starter dam has a crest elevation of 366.5 masl (~10.5 m in height) and can contain approximately two (2) years of tailings with 2 m of freeboard to the crest. The dams will be raised sequentially over the life of the mine to the maximum dam height of 23.5 m to contain the design tonnage.

 

 

18-10


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 18-6 summarizes the design parameters for sizing the starter and ultimate dams.

Table 18-6: Tailings Dam Sizing

 

Parameter

   Stage 1
(Starter Dam)
  Stage 2   Stage 3   Stage 4   Stage 5 (Ultimate)

Construction Period

   Pre-production   By end of Year 2   By end of Year 5   By end of Year 8   By end of Year 11

Dam crest elevation (masl)

   366.5   371.5   374.5   377.5   379.5

Maximum height

   10.5 m   15.5 m   18.5 m   21.5 m   23.5 m

Struck-level storage capacity with 2 m freeboard to the crest

   10.4 M m3   33.2 m3   50.5 m3   69.5 m3   94.6 M m3

 

18.8.2 Dam Design

The TMA dams have a very high hazard classification due to the potential environmental and economic consequences of a potential failure, and have therefore been designed for the most severe flood and earthquake criteria. The site has low-to-moderate seismic risk with a 0.096 g horizontal peak ground acceleration for a 10,000-year return period earthquake;

The design criteria adopted are:

 

 

Required minimum FOS values for the design slopes are:

 

   

Short term, end of construction with induced pore pressures: 1.3

 

   

Long term, when excess pore pressures have fully dissipated: 1.5

 

   

Rapid draw down (of the Water Management Pond slope): 1.2

 

   

Worst case, with potentially slicken-sided upper varved clay: 1.0

 

   

Pseudo-static loading with a seismic coefficient of 50% of the peak ground acceleration (“PGA”): 1.0

 

 

18-11


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The design dam slopes are 4H:1V for heights up to 15 m, which includes approximately 70% of the dam length. The higher south dam section requires a 4.6H:1V slope and an appropriately sized mine rock toe berm to reduce the overall slope to 5.5H:1V for stability. The slopes are designed to transition between the two sections.

Stability analyses of the TMA dam slopes were carried out for critical sections using the limit equilibrium method for subsurface soil stratigraphy determined from the geotechnical investigations. The design and construction follow the observational design approach, considering the presence of thick, highly plastic clay and varved glacio-lacustrine units. Engineering judgement was used to select appropriate assumptions regarding excess pore pressures generated in the foundation soils and dam fill during construction that could govern stability. Dam instrumentation and monitoring will be required to be in place during the construction and operation phases. Details on the slope stability analyses are provided in AMEC (2013c).

The primary dam construction materials are mine waste rock and select clay (overburden) and from open pit development, which are available primarily during the pre-production and early years of operations.

The typical cross sections of the tailings dam are comprised of four (4) primary zones, as shown in Figure 18-1 and Figure 18-2. The legend is presented in Table 18-7:

 

 

Zone 1 is select overburden from open pit development that is placed in lifts with controlled compaction to act as the water retaining element (core) of the dam;

 

 

Zone 2 is random rockfill (NPAG or PAG) or overburden placed and compacted by the mine fleet to form the upstream shell of the dam;

 

 

Zone 3 is a NPAG mine rock that forms the downstream shell of the dam and toe berm for stability (South Dam only); and

 

 

Zone 4 is select or processed sand filter/drain downstream of the core to protect against cracks or construction defects and as a downstream shell foundation filter;

 

 

Zone 5 is a select sand and gravel or processed rock transition between the Zone 4 filters and Zone 3 rockfill.

 

 

18-12


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

18.8.3 Construction and Operational Considerations

The geometry of the dams allows for a significant portion of the construction material to be placed using haul trucks from the mine fleet. The dam core, filter, drain and erosion protection zones will be constructed by a qualified earthworks contractor.

TMA construction will follow the observational approach that approaches the design on the basis of the expected conditions (i.e., excess pore pressures generated in the foundation), while accommodating a realistic worst case in the form of contingency plans that can be realistically implemented, if the observed conditions (i.e., measured pore pressures of displacements) indicate the need. Remedial work, such as flattening the overall slope or increasing the size of the toe stabilization berm, could be implemented within an appropriate timeframe.

Overburden zones within the pit pre-strip area that are suitable for dam core construction were delineated in the block model using trafficability criteria inferred from in situ water content (AMEC, 2012a). The mine plan and dam construction schedule are coordinated such that enough suitable overburden is available for dam construction in any given period. Further detail on the overburden sampling and characterization are provided in AMEC (2013a). A clay test embankment has been planned to guide the development of the overburden fill compaction specifications (AMEC, 2013d).

 

 

18-13


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 18-1: Typical Cross Section – TMA South Dam Section

(Refer to Table 18-8 for the construction fill material descriptions)

 

 

18-14


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 18-2: Typical Cross Section – TMA West and North Sections

(Refer to Table 18-7 for the construction fill material descriptions)

 

 

18-15


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 18-7: Construction Fill Materials (Figures 18-1 and 18-2)

 

     

Construction Fill Materials

1

   Core – select clay

2

   Shell – random fill

3

   Downstream Shell – clean mine rock

4

   Filter – Sand

4a

   Fine filter – Sand

5

   Transition – processed rock

6

   Road Surface – sand & gravel

7

   U/S Erosion Protection – cobbles & boulders

8

   D/S Erosion Protection – cobbles

9

   Bedding – sand & gravel

10

   Armour Stone

11

   Rip Rap

 

18.8.4 Site Water Management

The primary objectives of the water management system are to:

 

 

Generate a reliable water source for mill operations and ancillary uses;

 

 

Dewater the open pit and underground mine workings to ensure worker safety and operability;

 

 

Provide for general site drainage; and

 

 

Optimize the quantity and quality of site effluents released into the environment.

The system relies primarily on recycling water from various constructed ponds for mill process water in order to minimize the volume of fresh water to be taken from local watercourses. The system has been designed to ensure a reliable water supply at all times of the year and to allow for contingencies, such as dry years. The system includes five (5) constructed ponds for water management, in addition to one (1) temporary and two (2) permanent sediment control ponds, and one (1) direct freshwater source for potable water (West Creek Pond). A constructed wetland with four (4) constructed ponds is to be built downstream of the TMA as part of the site effluent treatment system. The locations of the water management infrastructure are shown in the general site drawing (Appendix F).

 

 

18-16


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Details of the water balance modelling and the overall site water management can be found in AMEC (2013e).

 

18.8.5 Water Management Structures

A brief description of each of the primary water management ponds required for the site water balance is provided below. The preliminary design characteristics of each pond are summarized in Table 18-8.

The Mine Rock Pond (“MRP”) has been sized to operate based on the largest monthly pond volume for the 20-year wet annual precipitation conditions on an ultimate footprint of the east mine rock stockpile and open pit prior to the environmental design flood (“EDF”; a 24 hour/100-year return period storm event). Approximately 50% of the mill make-up water is provided from the mine rock pond. This rate was selected to ensure that the pond can be kept in balance year over year in mean annual precipitation conditions. Regulation of water recycled to the process plant will ensure there is adequate storage available to contain the EDF with no discharge to the environment.

The West Creek Pond (“WCP”) is established to divert the West Creek flows from a watershed of 808 ha around the open pit. The WCP also provides water to be treated for potable water supply.

A pond is expected to be developed at the head of the Clark Creek diversion (Clark Creek Pond) to facilitate the diversion into the lower reach of Clark Creek.

The TMA Pond (“TMAP”) is internal to the TMA and provides a relatively large volume of water for water supply to the process plant. The TMAP has significant available storage capacity and can store excess water during wet events, or in the event that the effluent cannot be discharged in the desired quantity due to low receiver flows. For preliminary purposes, the TMA/WMP was sized to contain a target volume of 7.0 Mm3 of water prior to winter. The TMA has ample capacity to contain the EDF event.

The Water Management Pond (“WMP”) receives the decant flows from the TMA for additional aging and has a catchment area of 109 ha. It was sized for the wettest month of the 20-year annual wet conditions and will contain the EDF. The dam crest of the water management pond is 373.0 masl. The water supply required for start-up will be developed by constructing the water management pond in a single stage early in the project development. The WMP will also provide a significant portion of the processing plant water demand. Further details on the WMP are provided in AMEC (2013e).

 

 

18-17


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The Water Discharge Pond (“WDP”) receives decanted water from the water management pond and runoff from the local catchment area (100 ha) and decants managed flows, at a nominal rate of up to 10,000 m3/d from the WMP, to the constructed wetland. The emergency spillway invert is at 354.3 masl and the dam crest elevation is 355.2 masl. Flows in excess of the wetland capacity will be directed to the Pinewood River to maintain effluent treatment efficiencies and to prevent damage to the constructed wetland due to high flows.

The constructed wetland is proposed to be established downstream of the water discharge pond within the Loslo Creek valley, upstream of the Pinewood River. The constructed wetland has been designed to take advantage of the natural topography present and support the additional passive treatment of a limited volume of discharge from the WDP for nutrient and metal removal. The managed volume discharge will help mitigate flow reduction concerns associated with the Pinewood River and site surface water capture.

A flood protection berm/access road is also proposed south of the open pit to ensure that even under extreme flood conditions such as the EDF, the Pinewood River will not overflow into the open pit. Should the Pinewood River spill into the pit, it would cause excessive erosion of the overburden slope and potentially flood the pit. The preliminary flood protection design includes a 2.24 m high berm (including 0.3 m freeboard) having 3H:1V slopes and length of approximately 3,600 m, situated approximately 120 m from the Pinewood River. An access road will be situated on top of the berm.

 

18.8.6 Runoff and Seepage Collection

Runoff and seepage collection are required from mine site facilities as per Federal requirements. Runoff and seepage collected from the plant site area will be pumped to the MRP, either directly from the mill area external sumps, or indirectly in the case of any runoff and seepage that bypasses these facilities and enters the open pit directly. The majority of the PAG mine rock stockpile area will drain by gravity to the MRP. PAG mine rock will be placed within that portion of the PAG mine rock stockpile that will drain by gravity to the MRP, such that any acid rock drainage associated with this rock would be captured by the MRP both during operations and following mine closure. All runoff and seepage captured by the MRP will be contained within the overall water management system and will not be discharged directly into the environment.

 

 

18-18


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Runoff and seepage collected in ditches along much of the south perimeter of the TMA will be routed through ditches to the WDP. Ditching bordering the northwest and west margins of the TMA will report to a collection pond, with this water being: released directly into the environment if it is of suitable quality; pumped back to the WMP if water quality is not suitable for direct discharge to the environment; or maintained in the water management system to enhance the existing water inventory.

Runoff and seepage from the overburden/NPAG stockpile will be collected by east and west perimeter ditches that report to terminal collection ponds (Sediment Ponds #1 and #2) located along the boundary of the stockpile. Runoff collected from the overburden stockpile could contain relatively high levels of suspended solids and, as a result, will require sufficient retention time for the solids to settle out of solution naturally, and for the water to meet applicable water quality standards for direct release into the environment. If necessary, coagulants and flocculants could be used to aid the settling of suspended solids.

 

 

18-19


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 18-8: Summary of Water Management Ponds

 

                Maximum      Environmental Design
Flood
     Dam  

Pond

  

Discharge Pumped (P) /
Decant or Spillway (D)

to

  

Water

Requirement

   Operating
Pond
(20-year wet
year) (Mm3)
     EDF
Runoff
(Mm3)
     Pond
Volume
including the
EDF (Mm3)
     Crest
Elevation

(masl)
     Average
Height

(m)
     Length
(m)
 

MRP

  

To process plant (P)

  

Process water

     2.93         0.31         3.24         362.0         5.4         1,650   

WCP

  

To process plant (P)

  

Potable and other fresh water needs

     0.20         N/A         N/A         364.9         4.0         450   

TMAP

  

To WMP (D)

  

Decanting for discharge

     5.57         0.97         6.45         379.5         —           —     

WMP

  

To the environment (Pinewood River below McCallum Creek; (P)

 

To WDP (D)

  

Process water, freshwater with excess discharged to the environment

     6.64         0.13         6.77         373.0         6.7         3,750   

WDP

  

To Constructed Wetland (D)

  

Excess discharged to the environment

     0.08         0.03         0.112         355.2         1.2         360   

 

Notes:   The maximum operating pond volume represents the largest monthly pond volume 20-year wet year.
  EDF - Environmental Design Flood, taken as the 1:100 year 24 hour storm event for ponds collecting mine affected water.
  All elevations are based on preliminary pond capacity information and required confirmation.

 

 

18-20


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

18.8.7 Process Plant Water Supply – Preparations for Start-up

The primary water reservoir to support process plant start-up will be the WMP that is located immediately adjacent to and southwest of the TMA. Construction of the WMP is planned to start once regulatory approvals are obtained. It is currently assumed that the WMP will be constructed and be able to begin receiving water inflow in 2016 at the latest.

For the initial start-up, water will be pumped from the local site watersheds and from the Pinewood River and stored in the WMP for future use, in addition to natural inflows. A water intake structure will be constructed on the Pinewood River downstream of McCallum Creek. This location was chosen because the Pinewood River catchment and flow increase substantively downstream of the two (2) major tributaries, Tait Creek and McCallum Creek.

It is assumed that up to 20% of the spring flow (April to June; or March in the event of an early spring thaw), and up to 15% of the river flow during the period of July through November, will be withdrawn from the Pinewood River to develop the Project’s water inventory in the WMP. This approach is consistent with other Ontario mining projects. Water would be taken from the Pinewood River in 2015 and 2016, and possibly 2017 under extreme drought conditions. Thereafter, it is envisioned that there would be no direct water taking from the Pinewood River, except possibly for contingency purposes.

The available water from the Pinewood River under the percentage flow restrictions described above is shown in Table 18-9 for average and low runoff conditions. If flows approaching or above mean annual flow conditions are encountered, the percentage taken from the river would be reduced, as there would be excess water available under these conditions.

Table 18-9: Water Availability from the Pinewood River below the McCallum Creek Inflow

 

      Month (‘000 m3)      Total  

Condition

   Apr      May      Jun      Jul      Aug      Sep      Oct      Nov     

Mean

     2,233         1,716         1,260         571         277         312         424         334         7,127   

5th P

     756         581         426         193         94         106         144         113         2,412   

10th P

     928         713         523         237         115         130         176         139         2,961   

25th P

     1,306         1,003         736         334         162         182         248         195         4,167   

 

Note:   Tabled values represent a 20% taking of the spring flow (Apr-Jun) and a 15% taking for other months; no winter (Dec-Mar) water taking is proposed. Percentile (P) values are calculated as annualized and not monthly percentiles.

 

 

18-21


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

18.8.8 Process Plant Water Supply – Operations

At full production capacity the process plant will require an approximate water input of 21,400 m3/d. Process plant outputs will include approximately 21,000 m3/d of water discharged to the TMA with the tailings slurry, and 400 m3/d of water lost to evaporation in the mill. Process water for process plant operations will result from recycling contact water from the MRP, as well as from the TMAP and the WMP. Under typical, average annual operating conditions, an estimated 10,145 m3/d would be derived from the MRP; 1,690 m3/d would be derived from the WMP; 9,065 m3/d would be derived from the TMAP; and 500 m3/d would enter the process plant with the ore. Ample water storage is available in the WMP and the TMAP to provide process plant water during the winter months, or during prolonged summer/fall drought conditions.

With regard to water availability in the TMAP, a portion of the water contained in the process plant slurry discharged to the TMA would be retained in the pore space within the deposited tailings. This expected water loss into permanent storage has been calculated as an average 7,447 m3/d. This value is based on a specific gravity of 2.82 for the ore and a settled tailings solids density of 1.41 t/m3. The difference between the volume of water in the tailings slurry discharged to the TMA, and the volume of water permanently stored within the tailings solids void space, would become available water for recycle back to the process plant for on-going processing. Excess TMA water not needed for processing would be discharged to the WMP for aging and recycling back to the process as ‘freshwater’, with the excess discharged to the Pinewood River, either indirectly through the constructed wetland and the lower reach of Loslo Creek, or directly by pipeline to the Pinewood River just downstream of McCallum Creek.

Other sources of water for recycling to the process plant include precipitation and runoff collected within the TMA, and runoff and mine water that would be routed through the MRP. Modeling indicates that once steady state conditions are achieved, mine water will need to be removed at a net rate of approximately 6,600 to 9,800 m3/d (including direct precipitation and runoff), in order to maintain a reasonably dry and safe working environment. These values allow for the return of a small portion of mine water to support the mining operations, such as cooling water needed to support mine drilling activities. This excess mine water will be pumped to the MRP and will become part of the water inventory. The MRP will also collect natural runoff and seepage from the PAG Mine Rock Stockpile area, as well as water pumped from the plant site area. Upstream areas of the Clark Creek watershed will be diverted away from the PAG Mine Rock Stockpile area by means of the Clark Creek Diversion.

 

 

18-22


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The MRP will provide a direct process water feed to the process plant, and will be designed with a storage capacity of approximately 2.93 Mm3. As the PAG Mine Rock Stockpile will store potentially acid generating and non-potentially acid generating rock, the MRP will contain water with increased suspended solids, possibly low levels of dissolved metals dependent upon geochemical reaction rates and residual ammonia from the use of blasting agents. If required, the water from the MRP will be drawn down in preparation for winter, to reduce water inventory losses to ice cover formation, by decreasing the amount of water going to the process plant from the TMAP and increasing the draw from the MRP.

A dedicated pond, the WCP, will be established in line with West Creek for the purpose of providing compensatory fish habitat, and to supply potable water. The WCP will only contain natural, non-contact water, and therefore does not require further management or treatment prior to release. The West Creek diversion channel will be kept separate from the Constructed Wetland downstream of the TMA, so as not to mix the natural creek water with TMA effluent.

 

18.9 Water Treatment Design Basis and Operation

As part of the feasibility and assessment process, metallurgical aging tests were conducted. These tests revealed that zinc (Zn) and cadmium (Cd) could potentially be leached from the Rainy River Project tailings at a level that could raise concern for meeting regulatory requirements for subsequent effluent quality. Treatability tests conducted at AMEC’s Pointe-Claire laboratory proved that hydroxide precipitation using lime treatment could effectively reduce Cd and Zn concentrations in Rainy River tailings water to desired levels (AMEC 2013h). AMEC was requested to use the results obtained during this testing along with the site water management plan (AMEC 2013i) to design and cost a water treatment plant (“WTP”) for the site at a feasibility level (AMEC 2013j).

Table 18-10 provides a summary of the major WTP design criteria. The design flow was derived from the requirement to treat 7.4 Mm3 in six (6) months, in order to ensure release of properly aged water from the WMP at key times during the year. The minimum flow was set to 50% of this value and the maximum flow, representing the hydraulic capacity of the system, was set to 120% of the design value. The raw water quality assumed was that used for the laboratory

 

 

18-23


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

testing with Zn and Cd concentrations of 50 and 4.2 µg/L, respectively (AMEC 2013h). The design effluent quality targets were established from Provincial and Federal guidelines: less than 20 µg/L for Zn and less than 0.1 µg/L for Cd. Any other heavy metals that may be present would also be removed to low levels by treating these two elements.

Three (3) treatment scenarios were evaluated:

 

1. Treating the water in a WTP located between the tailings pond in the tailings management area (TMA) and the water management pond (WMP);

 

2. Treating the water in a WTP located between the WMP and the discharge to the environment; and

 

3. Treating the water in the WMP.

A comparison of options determined that a modification to Option 3 (Option 3A) was considered most suitable, which involved converting a small portion of the WMP into a settling pond by building an internal dam and then treating the water in the resulting pond.

 

18.9.1 Water Treatment Design and Operation

Under the preferred treatment scenario (Option 3A), tailings water from the TMA will be raised to a pH > 11.0 with lime and, metal hydroxides will be allowed to settle out of suspension in the settling pond. The continuous settling pond outflow will be acidified to a pH of 8.0 to ensure that biological activity is maintained within the WMP. Sulphuric acid will be used for neutralization purposes, since the use of CO2 would instead add unnecessary suspended solids into the system. This approach will confine the solids produced due to lime treatment to the settling pond, therefore limiting the area that will require periodic dredging.

 

 

18-24


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 18-10: Summary of WTP Design Criteria

 

     Units   Minimum      Design      Maximum  

Feed Rate

          
   m3/h     833         1,667         2,000   
   m3/d     20,000         40,000         48,000   
   L/min     13,889         27,778         33,333   
   US gpm     3,669         7,339         8,807   

Retention Times (at specified flow)

          

Reactor #1 (lime)

   min     10.0         5.0         4.2   

Settling Pond

   days     6.0         3.0         2.5   

Reactor #2 (acid)

   min     10.0         5.0         4.2   

Reagent Consumption

          

Hydrated Lime – Ca(OH)2

   g/L     0.070         0.090         0.160   

Quicklime (CaO)

   g/L     0.059         0.076         0.136   

Sulphuric Acid (93%)

   mL/m3     30.0         40.0         50   

Sludge Production

          

Solids Production

   g/L     0.060         0.075         0.100   

A process flow diagram, process and instrumentation diagrams (3 drawings), and the general arrangements (2 drawings) were prepared (AMEC 2013j).

In order to ensure that there would be no hydraulic short-circuiting of the pond, the WTP location was set in the northwest corner, opposite and distant from the WMP outlet. Selection of this location also helped minimize dam construction costs. In order to have both the reagent addition points and all major equipment in the same general location the settling pond was designed with a u-shaped configuration. This reduces distances for power supply and facilitates operation and maintenance of process equipment.

Due to the existence of significant depths of clay, it was decided to build the plant on structural rock fill. This allows for the plant to be built entirely within the catchment basin of the settling pond itself. The structural fill will begin at the edge of the WMP dam crest and will be graded towards the settling pond.

 

 

18-25


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The key sludge production parameters are summarized in Table 18-11. The calculation suggests that each year at design flow approximately 27,000 m3 of sludge would need to be dredged. Dredged sludge will be disposed of in the TMA.

Table 18-11: Expected Production of Sludge at Design Flow

 

Description

  

Units

   Value  

Sludge generation rate

   g/L      0.075   

Sludge production dry weight basis

   Mt/d      3   
   Mtpa
(180 days of operation per year )
     540   

Sludge percent solids (typical)

   w/w      2

Sludge production wet wt basis @ 2% solids

   m3/d      150   

Sludge disposal rate

   m3/yr
(180 days of operation per year )
     27,000   

 

18.9.2 Water Treatment Plant Opportunities

Listed below are a number of opportunities that could lower capital and/or operating costs and may wish to be considered during detailed design:

 

 

The use of hydrated lime instead of quicklime will reduce the initial capital cost of the lime preparation system at the expense of higher reagent costs. Quicklime was selected at this stage as it is planned for use at the processing plant.

 

 

Slurried lime could be pumped into a tanker truck and regularly transported to the WTP as needed due to the relatively low lime consumption and since a lime slaker is already planned for the processing plant.

 

 

The length of the settling pond internal berm could be reduced by a third without affecting settling the overall performance of the pond and constructed in parallel with the WMP dams.

Doing so will save on the extra fill material provisioned in the current design to allow for the flexibility of raising the settling ponds dams, as needed.

 

 

The building size was established before defining all the process and electrical needs for the plant. It has been determined now that the building size could be reduced without impacting operational ease.

 

 

The size of the compacted fill could also be reduced. It is necessary to ensure sufficient space for the reagent truck access and building stability but the size has not been optimized.

 

 

18-26


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

Reactor #1 could be moved closer to the WTP building. This could save on the lengths of piping and wiring and would also facilitate operation.

 

18.10 Fish Compensation Works

 

18.10.1 Background

The RRP is somewhat unique from an environmental perspective in that there are no lakes located within, or adjacent to, the main site. While limited bait fishing does occur with certain project area streams, the area does not support a significant commercial or recreational fishery. Development of the Rainy River Project site will result in unavoidable harm to fish, fish habitat and infilling of waters frequented by fish, which requires the development and implementation of offsets (compensation) pursuant to the Fisheries Act and Metal Mining Effluent Regulations.

The potential impacts to the aquatic environment and fish habitat are as follows (Figure 18-3):

 

 

Direct loss or alteration of habitat resulting from the infilling and destruction of portions of creeks in the immediate footprint of the mine due to development of the tailings management area, open pit, overburden and mine rock stockpiles, and other infrastructure elements associated with mine development (road crossings, pipeline crossings and outlets);

 

 

Alteration of habitats due to the realignment or interception of some site watercourses to accommodate project infrastructure or to collect water for processing plant and other usage; and

 

 

Potential indirect effects to habitat due to flow reductions in the Pinewood River resulting from creek runoff collection at site, groundwater interception by the mine workings (open pit and underground) and/or direct water taking from the Pinewood River (construction and potentially closure / post-closure phases).

Through a collaborative process initiated in mid-2012 with First Nations, Township of Chapple, as well as the Department of Fisheries and Oceans Canada and the Ministry of Natural Resources a fish habitat offset framework has been developed that is being reviewed by the regulatory authorities in parallel with the Federal / Provincial environmental process. Approvals are anticipated to be obtained by either the Fisheries Act Section 35 Authorization requirements, or the Metal Mining Effluent Regulations Schedule 2 amendment process.

 

 

18-27


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 18-3: Altered/Displaced Waters Frequented by Fish

 

 

18-28


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

18.10.2 Proposed Offset Measures

The predicted impact not associated with mine waste and as such authorized under Section 35(2) of the Fisheries Act represents approximately or 45,543 m2 or 10,148 weighted usable area habitat loss as shown in Table 18-13. Weighted usable area is a combined measure of the quality and quantity of habitat such that fish habitat of different locations and types (pond vs. creek) can be compared. The value is unit-less. The proposed habitat compensation balance provides for a net increase in fisheries habitats in a blended approach, including both like for like habitat replacement and watershed-based habitat improvements.

West Creek (including the minor drainage / tributary east of the plant site known as the stockpile pond) will be diverted to the West Creek Pond, which in turn will outlet at its western margin at the West Creek Diversion. The diversion will be constructed to flow in a north-westerly direction before changing direction and flowing in a south-westerly direction where it will converge with the existing Loslo Creek (Cowser Drain) downstream of the proposed constructed wetland. The West Creek pond will be used as a potable water source for the mine during operation, but will maintain a functional wetted habitat throughout mine life and beyond. The West Creek diversion channel downstream of the West Creek pond will be constructed with frequent pooled habitats to provide fish refuge during periods of reduced or intermittent flow which occurs naturally within the system. The pond outlet channel through the emergency spillway will be constructed with a similar low flow channel and slope as the main diversion channel to maintain fish passage between the constructed diversion channel, the pond and upstream sections of the watercourse.

The tributary associated with the stockpile pond east of the plant site will also be diverted through a similarly constructed channel into the West Creek pond.

The Clark Creek system will be intercepted to avoid the east mine rock stockpile and will be diverted through the Clark Creek Diversion Channel to a tributary of the Pinewood River. The developed impoundment structure and the Clark Creek Pond will create sufficient water elevation to redirect flows into the Clark Creek diversion channel. At the terminus of the Clark Creek diversion channel an additional pond (Teeple Road Pond) will be constructed to provide fisheries offsets, and to moderate peak flows from the Clark Creek system into the Pinewood River Tributary. The diversion and impoundment will be created in the same ecotype as the habitat overlaid from Clark Creek.

 

 

18-29


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The created ponds (West Creek pond, Clark Creek pond, Teeple Road Pond and stockpile pond) will vary in depth. Deeper sections, 1 m or greater, will ensure abundant overwintering conditions in the entire pond habitat, while providing large shallow littoral areas for greater productivity and wetland attributes. Maximum depth will range from 3 to 3.5 m in the West Creek pond, 1.5 to 2.25 m in the Clark Creek pond and Teeple Road Pond and 3.5 to 4 m in the stockpile pond.

Stakeholders have expressed an interest in seeing watershed based and water quality focused offset measures implemented in the local area to mitigate past non-mining impacts in the area rather than just habitat replacement. Restoration measures could include cattle fencing, offline cattle watering sources, and channel and riparian zone restoration. The proposed strategy would make every effort to compliment and work with existing local programs and initiatives, such as the Rainy River First Nations Watershed Program, and Ministry of Natural Resources District Partnership Programs (stewardship council). This means that the compensation program would be set up to support local groups and efforts with a mechanism to track these contributions.

The like for like habitat replacement is fully considered and costed in the Feasibility Update Study. An allowance has also been made for support for watershed-based habitat improvements currently under discussion.

 

 

18-30


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 18-12: Summary of Proposed Habitat Offset Balance for Schedule 2 Amendment Waterbodies

 

     Total Area Overprinted (m2)      Weighted Usable Area
Overprinted
          Total Area
of Offset
(m2)
     Weighted
Usability
Value
     Weighted
Useable
Area Offset
 

Mine Feature

   Loslo
Creek
(Cowser
Drain)
     Marr
Creek
     Total      Loslo
Creek
(Cowser
Drain)
     Marr
Creek
     Total     

Offset Feature

        

Tailing Management Area

     143,344         14,949         158,293         32,895         3,434         36,329       West Creek Diversion Channel and Stockpile Pond Diversion Channel      47,241         0.21         9,921   

Constructed Wetland / Water Discharge Pond

     47,437         0         47,437         10,941         0         10,941       West Creek Pond      150,089         0.23         34,520   

West Mine Rock Stockpile

     0         5,514         5,514         0         1,230         1,230       Clark Creek Diversion Channel      8,470         0.22         1,863   

Overburden Stockpile

     0         1,945         1,945         0         428         428       Clark Creek Pond      30,000         0.23         6,900   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

       

 

 

       

 

 

 

Total

     186,898         22,408         213,189         42,947         5,092         48,928       Total      235,800            53,204   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

       

 

 

       

 

 

 
                     Net Gain = 22,611 m2         Net Gain = 4,276 WUA   

Table 18-13: Summary of Proposed Habitat Offset Balance for Section 35(2) Authorization Waterbodies

 

     Total Area Overprinted (m2 )      Weighted Usable Area (WUA)
Overprinted
    

Offset Feature

   Total Area
of Offset
(m2)
  Weighted
Usability
Value
   Weighted
Useable
Area Offset

Mine Feature

   Marr
Creek
     West
Creek
     Clark
Creek
(Teeple
Drain)
     Total      Marr
Creek
     West
Creek
     Clark
Creek
(Teeple
Drain)
     Total             

Clark Creek Diversion, East Mine Rock Stockpile

     —           —           21,355         21,355         —           —           4,828         4,828       Cattle fencing, offline watering, riparian and channel restoration    To be
determined
  To be
determined
   To be
determined

Open Pit

     —           17,412         —           17,412         —           3,768         —           3,768              

Dam Structures

     196         —           227         423         41         —           47         88              

Plant Site / Ancillary Facilities

     —           2,139         —           2,139         —           447         —           447       Clark Creek Pond at Teeple road Like for Like Habitat    Minimum
of 45,543 m2
  0.23    Minimum of
10,148

Remnant Channels

     4,214         —           —           4,214         1,017         —           —           1,017              
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

            

Total

     4,410         19,551         21,582         45,543         1,058         4,215         4,875         10,148              
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

            
                         
 
Net
Result
  
  
   Blended Approach    Minimum
45,543
  Varies    Minimum
10,148 plus
Offsite

 

 

18-31


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

19. MARKET STUDIES AND CONTRACTS

 

19.1 Market Studies

Neither BBA, nor New Gold has conducted a market study in relation to the gold and silver doré that will be produced by the Rainy River Project. Gold and silver are freely traded commodities on the world market for which there is a steady demand from numerous buyers.

 

19.2 Commodity Price Projections

Commodity pricing is based on base case metal prices and exchange rates consistent with current consensus estimates.

 

19.3 Contracts

There are no refining agreements or sales contracts currently in place for the Rainy River Project that are relevant to this Technical Report. New Gold expects that terms contained within any sales contract that could be entered into would be typical of and consistent with standard industry practices and be similar to contracts for the supply of gold elsewhere in the world. In the opinion of the QPs, New Gold will be able to market gold produced from the Project.

 

 

19-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

20. ENVIRONMENTAL STUDIES, PERMITTING AND SOCIAL OR COMMUNITY IMPACT

 

20.1 General Approach

As demonstrated through its Health, Safety, Environment and Sustainability Policy, Rainy River is committed to excellence in the management of health, safety, the environment and sustainability in the conduct of its operations. The Company’s objectives are to:

 

 

Ensure the health and safety of employees, contractors and visitors in the workplace;

 

 

Responsibly manage the impact that its mineral exploration and development operations may cause to the environment; and

 

 

Demonstrate its commitment to fostering sustainable development in the communities in which it operates.

Environmental aspects have figured prominently in the development of the preliminary layouts and designs for the Rainy River Project described in this report. These include consideration of the implications of design alternatives from an environmental management and approvals perspective, related to mineral waste management, and the siting and location of facilities and infrastructure.

 

20.2 Consultation Activities

 

20.2.1 Community and Government Communications

Rainy River is an active member of the local community with offices in both Emo and Thunder Bay that offer residents easily accessible locations to learn about the Rainy River Project. Rainy River has engaged the local communities, as well as local First Nations and Métis community members, in its Project planning activities. Through meetings, site tours, and regular communications, Rainy River strives to ensure engagement with all members of the local communities. Project open houses have been held in various communities to discuss the Project and to help people understand the Project as it moves forward.

 

 

20-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The involvement of stakeholders will continue over time throughout the various project stages. Key stakeholders who have demonstrated an interest in the Rainy River Project include the following categories:

 

 

Municipal Governments: Townships of Alberton, Chapple, Dawson, Morley and Sioux Narrows – Nestor Falls; Towns of Emo, Fort Frances and Rainy River;

 

 

Various business, organizations and non-governmental organizations;

 

 

General public;

 

 

Federal Government: Aboriginal Affairs and Northern Development Canada, Canadian Environmental Assessment Agency, Environment Canada, Fisheries and Oceans Canada, Health Canada, International Joint Commission (Canada–United States), Major Projects Management Office, Natural Resources Canada and Transport Canada; and

 

 

Provincial (Ontario) Government: Ministry of Aboriginal Affairs, Ministry of Agriculture and Food, Ministry of Economic Development, Trade and Employment, Ministry of Energy, Ministry of Health and Long-Term Care, Ministry of Infrastructure, Ministry of Labour, Ministry of Municipal Affairs and Housing, Ministry of Natural Resources, Ministry of Northern Development and Mines, Ministry of the Environment, Ministry of Tourism, Culture and Sport and Ministry of Transportation.

 

20.2.2 Aboriginal Communications

The Aboriginal groups initially consulted with and engaged in relation to the Rainy River Project were identified using the following criteria:

 

 

Direction from the Provincial Crown and Federal Crown;

 

 

Proximity to the Rainy River Project;

 

 

Past or current interest in similar projects or developments in the region;

 

 

Demonstrated previous interest in potential biophysical and socio-economic environmental effects of the Rainy River Project; or

 

 

Aboriginal groups with traditional lands encompassing the Rainy River Project site and its related proposed infrastructure.

Rainy River Resources requested advice from the Ministry of Northern Development and Mines in 2010 and again in 2011 as to which Aboriginal groups should be engaged regarding the Rainy River Project due to the potential impact of exploration and mine development on Aboriginal or Treaty rights. Following advice provided at the time by the Ministry of Northern Development and Mines, Rainy River Resources engaged nine (9) First Nations, along with the Métis Nation of Ontario, that could be affected by the Rainy River Project (Table 20-1).

 

 

20-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 20-1: Local Aboriginal Groups Engaged as Instructed by MNDM, December 2011

 

First Nation or

Métis Group

  

First Nation
Number

  

Reserves Near

Project Site

  

Distance to Rainy
River Project Pit
Centroid (km)

Anishinaabeg of

Naongashiing (Big Island)

First Nation

     

Big Island Mainland 93

Saug-A-Gaw-Sing 1

   35

39

   125      
        
     

Agency 1

Couchiching 16A

   53

40

Couchiching First Nation

   126      
        

Lac La Croix First Nation

   127    Neguaguon Lake 25D    142

Mishkosiminiziibiing (Big

Grassy River) First Nation

   124    Big Grassy River 35 G    28
     

Agency 1

Rainy Lake 18C

   53

47

Mitaanjigamiing First Nation

   133      
        
      Agency 1    53

Naicatchewenin First Nation

   128    Rainy Lake 17A    29
      Rainy Lake 17B    19
     

 

Agency 1

Rainy Lake 26A

Rainy Lake 26B

Rainy Lake 26C

   53

79

78

91

Nigigoonsiminikaaning First

Nation

        
   129      
        
        
     

 

Manitou Rapids 11

Long Sault 12

   18

21

Rainy River First Nations

   130      
        

Seine River First Nation

     

 

Seine River 23A

Seine River 23B

Sturgeon Falls 23

   113
   132       90
         119

Sunset Country Métis

        

In May 2012, the Provincial government identified changes and considerably expanded the list of Aboriginal groups Rainy River Resources would have to consult or notify about mine development (Table 20-2). The majority of these additional groups are located in the Lake of the Woods area. Rainy River Resources elected to have the Provincial Crown coordinate notification in August of 2012.

 

 

20-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 20-2: Aboriginal Groups Identified by the Provincial Government

to be Consulted or Notified, May 2012

 

First Nation or

Métis Group

  

First Nation
Number (as
applicable)

  

Reserve Locations

(as applicable)

  

Distance to Rainy
River Project Pit
Centroid (km)

Aboriginal Groups to Consult:

        

Anishinaabeg of Naongashiing (Big

Island) First Nation

  

125

  

Agency 30

Big Island 31D

Big Island 31E

Big Island 31F

Big Island Mainland 93

Lake of the Woods 31B

Lake of the Woods 31C

Lake of the Woods 31G

Lake of the Woods 31H

Naongashing 31A

Saug-A-Gaw-Sing 1

Shoal Lake 31J

   73

55

54

59

35

96

78

92

58

57

39

104

        
        
        
        
        
        
        
        
        
        
        
        

Mishkosiminiziibiing (Big Grassy

River) First Nation

   124   

 

Agency 30

Assabaska

Big Grassy River 35G

Lake of the Woods 35J

Naongashing 35A

Obabikong 35B

  

 

73

35

28

49

57

48

 

Métis – Rainy River Lake of the Woods Regional Consultation Committee Region #1

Naicatchewenin First Nation

  

128

  

 

Agency 1

Rainy Lake 17A

Rainy Lake 17B

  

 

53

         29
         19

Naotkamegwanning (Whitefish Bay)

First Nation

  

158

  

 

Agency 30

Sabaskong Bay 32C

Whitefish Bay 32A

  

 

73

41

64

        
        
        
      Yellow Girl Bay 32B    76
     

 

Agency 30

  

 

73

      Assabaska    35

Ojibways of Onigaming First Nation

   131    Sabaskong Bay 35C    40
      Sabaskong Bay 35D    39
      Sabaskong Bay 35F    34
      Sabaskong Bay 35H    42

 

 

20-4


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

First Nation or

Métis Group

  

First Nation
Number (as
applicable)

  

Reserve Locations

(as applicable)

  

Distance to Rainy
River Project Pit
Centroid (km)

     

Manitou Rapids 11

Long Sault 12

   18

21

Rainy River First Nations

   130      
        

Buffalo Point First Nation

   265   

Agency 30

Buffalo Point 36

Buffalo Point First Nation 1

Buffalo Point First Nation 2

Buffalo Point First Nation 3

Reed River 36A

   73

94

103

98

101
100

Aboriginal Groups to Notify:

        

Anishinabe of Wauzhushk Onigum

First Nation (Rat Portage)

   153   

Agency 30

Kenora 38B

   73

101

Couchiching First Nation

   126   

Agency 1

Couchiching 16A

   53

40

Lac La Croix First Nation

   127    Neguaguon Lake 25D    142

Mitaanjigamiing (Stanjikoming) First

Nation

   133   

Agency 1

Rainy Lake 18C

   53

47

Nigigoonsiminikaaning

(Nicickousemenecaning) First Nation

  

129

  

Agency 1

Rainy Lake 26A

Rainy Lake 26B

Rainy Lake 26C

   53

79

78

91

      Agency 30    73

Northwest Angle #33 First Nation

   151    Northwest Angle 33B    95
      Whitefish Bay 33A    58
      Agency 30    73
      Big Island 37    67
      Lake of the Woods 34    69
      Lake of the Woods 37    85

Northwest Angle #37 First Nation

   152    Lake of the Woods 37B    79
      Northwest Angle 34C    104
      Northwest Angle 34C and 37B    102
      Northwest Angle 37C    102
      Shoal Lake 34B1    104
      Shoal Lake 37A    110
      Whitefish Bay 34A    61

 

 

20-5


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

First Nation or

Métis Group

  

First Nation
Number (as
applicable)

  

Reserve Locations
(as applicable)

  

Distance to Rainy
River Project Pit
Centroid (km)

      Seine River 23A    113

Seine River First Nation

   132    Seine River 23B    90
      Sturgeon Falls 23    119

 

Notes:   

Rainy River Resources will also continue to consult and involve the Fort Frances Chiefs Secretariat and Pwi-Di-Goo-Zing-Ne-Yaa-Zhing Advisory Services Tribal organizations.

 

Rainy River Resources elected to have the Provincial Crown coordinate notification in August of 2012.

Rainy River Resources received guidance from the CEA Agency in September 2012 with regard to Aboriginal engagement (Table 20-3). The preliminary depth of consultation provided to Rainy River Resources by the CEA Agency is intended to take into account the strength of the community’s claim to Aboriginal or Treaty Rights and the seriousness of potential adverse impacts.

Table 20-3: Aboriginal Groups Identified by the Federal Government through the

Results of Preliminary Depth of Consultation, September 2012

 

Preliminary

Consultation Depth

  

First Nation or Métis Group

High:

  

Naicatchewenin First Nation

Rainy River First Nations

Anishinaabeg of Naongashiing First Nation (Big Island)

Mishkosiminiziibiing (Big Grassy River) First Nation

Ojibways of Onigaming First Nation

Naotkamegwanning (Whitefish Bay) First Nation

  
  
  
  
  
  

Moderate:

   Métis – Rainy River Lake of the Wood Regional Consultation Committee Region #1

Low:

  

Mitaanjigamiing (Stanjikoming) First Nation

Couchiching First Nation

Buffalo Point First Nation

Northwest Angle #33 First Nation

Northwest Angle #37 First Nation

Anishinabe of Wauzhushk Onigum First Nation (Rat Portage)

Lac La Croix First Nation

Seine River First Nation

Nigigoonsiminikaaning (Nicickousemenecaning) First Nation

  
  
  
  
  
  
  
  

 

 

20-6


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

An important part of the mine permitting and planning process is proactive engagement with area Aboriginal communities. For the Rainy River Project, this engagement included ensuring potentially affected Aboriginal communities are informed and engaged in the development of the project, responding to their interests and concerns, and continuing to build and maintain positive relationships. This has been and is currently being achieved by creating a forum for dialogue and information exchange (verbal and written) and fostering an ongoing relationship between the potentially affected Aboriginal communities and Rainy River Resources.

 

20.2.3 Comments on the Project

Through the Federal and Provincial environmental process to date, including meeting all regulatory requirements, as well as the voluntary issuance of a draft Terms of Reference and two (2) draft Environmental Assessment (“EA”) Reports (Version 1 for Aboriginal review and Version 2 for all stakeholders and Aboriginal groups) and other measures; Rainy River Resources has made extra efforts to obtain feedback from stakeholders and Aboriginal groups regarding the Rainy River Project. Rainy River Resources has also committed financial resources to the Aboriginal groups for an independent technical review of the draft EA Report (Version 1). The draft Environmental Assessment Report (Version 1) was specifically issued in order to afford Aboriginal groups additional time for review. This has resulted in a very extensive consultation record.

While Rainy River Resources has received positive feedback, including letters of support regarding the Rainy River Project and its potential to bring opportunity to an economically depressed area, some concerns have been expressed by stakeholders and Aboriginal groups regarding the project. Rainy River Resources has responded and attempted to resolve these issues and concerns by a variety of means, including:

 

 

Alteration to the Rainy River Project where appropriate;

 

 

Provision for further information or greater clarity on information already provided;

 

 

Revision to regulatory documentation; and/or

 

 

Discussions and meetings with the individuals or groups involved.

 

 

20-7


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Nonetheless, as with all major industrial developments, a number of concerns will require follow-up. The primary concerns expressed are summarized in Table 20-4, along with the proposed approach to reduce and eventually remove the concern.

Table 20-4: Summary of Concerns and Proposed Approach to Resolve

 

Outstanding Concern or Issue

  

Proposed Approach to Reduce and Remove Concern

Stakeholders

  
Additional engineering detail was requested by Government agencies regarding certain project elements, including closure planning.    To be resolved through ongoing meetings and provision of additional information within environmental approval applications, once additional engineering detail is available.
  
  
  

Potential impacts to surface water and

groundwater, quality and quantity through

the development of the Rainy River Project.

   Effluents released from the Rainy River Project are expected to be consistent with Federal and Provincial regulations and policies for environmental protection. Measures have also been taken to limit project flow effects on the receiver, and groundwater drawdown effects on both the receiver and other potential users. Mitigation of the potential effects will continue to be optimized through the construction and operations phase of the Rainy River Project, including ongoing monitoring to confirm impact predictions summarized in the final EA Report. If appropriate, further design changes will be made to ensure compliance with environmental approvals.
  
  
  
  
  
  
  
  
  
Development and operation of the Rainy River Project is expected to impact local aquatic resources and wildlife, largely through displacement of habitat. While compensation will be made in accordance with regulatory requirements, there is a concern that the effects could be greater than anticipated.    Follow up monitoring is proposed to confirm the predicted impact of the Rainy River Project on the local environment. If monitoring should reveal unexpected effects, or effects significantly greater than predicted, then additional mitigation measures would be identified and implemented as appropriate to address the effect. Reclamation once operations cease will return the site to a naturalized setting that will encourage the return of wildlife to the site.

Outstanding Concern or Issue

  

Proposed Approach to Reduce and Remove Concern

Aboriginal Groups

  

Traditional Knowledge/Traditional Land Use (TK / TLU):

 

Concern was expressed regarding the role of TK / TLU in the EA and future project planning, the availability of studies lead by each First Nations community and information sharing.

   TK/TLU data has been widely collected for the Rainy River Project, including from the closest communities of Big Grassy River First Nation, Rainy River First Nations and Naicatchewenin First Nation. All TK/TLU sessions were community driven, meaning that the method of data collection was community specific. No TK/TLU data has been identified for the Project area specifically. The majority of the data has been broad and overreaching, which Rainy River Resources (Rainy River Resources) will continue to respect as it serves as the basis for First Nations’ unique relationship to the land. TK/TLU collection will continue; information collected will be appropriately considered for construction, operation and closure phases. For example, Rainy River Resources will further investigate the historical travel corridor and appropriately incorporate any new information that may become available.
   Rainy River Resources will share results of the TK/TLU data sessions in a non-public First Nations forum(s).

 

 

20-8


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Outstanding Concern or Issue

  

Proposed Approach to Reduce and Remove Concern

Aquatic Resources:

 

Comments were provided regarding the potential for impact to local water quality and fisheries.

   Rainy River Resources will commit to a joint water quality monitoring and reporting program with the area’s First Nations as part of the existing monthly water quality monitoring program that is currently carried out by Rainy River Resources. The program will be funded by Rainy River Resources and form an integral part of the overall environmental management program, as it relates to First Nations traditional knowledge and assurances of maintaining water quality and by extension, aquatic biota protection. The program will be developed jointly with the First Nations in lead-up to the initiation of mine construction.

Communication of Information:

 

The First Nations wish to be kept up to date on the Project, including any potential changes.

   Rainy River Resources will continue to communicate closely with First Nations regarding the Project.

Environmental Monitoring:

 

Ensure that First Nations have an active role in monitoring plans and programs.

   Rainy River Resources has an open invitation for First Nations to participate in all baseline and environmental monitoring programs, including Whip-poor-will, where appropriate, and to share monitoring results. Rainy River Resources will continue to advise on the opportunity of public forums in order to encourage anyone who’s interested in participating.

Cultural Awareness Training:

 

Provide cultural awareness training for those working at the mine.

   All Rainy River Resources staff will undergo cultural awareness training. Temporary contractors will undergo an awareness program as part of the regular induction program when working at the mine.

Lake Sturgeon:

 

Consider obtaining new information on Sturgeon.

   Additional information related to Lake Sturgeon and the Rainy River First Nations management program will be added to the Final EA Report. Rainy River Resources has committed to a program of close coordination with Rainy River First Nations in support of the pre-existing First Nations Watershed Program and water quality protection. Company funding will be provided as part of the fisheries compensation program to further water quality enhancement programs for the Pinewood and similar agriculturally-impacted waterways.

Baseline Health Information:

 

The Proponent may wish to contact the Seven Generations School and/or Ministry of Natural Resources to obtain additional information.

   Rainy River Resources will reach out to the Seven Generations Education Institute and/or the Ministry of Natural Resources to obtain any additional information on baseline health of animals and fish.

Closure Planning:

 

Describe what mechanisms are in place to deliver a successful closure plan over time, including incorporation of TK and community engagement activities.

   First Nations will play an active role in the development of the mine Closure Plan, including development of the monitoring and mitigation programs. While the Closure Plan will be completed prior to construction, Rainy River Resources will consult on significant revisions periodically during operations to ensure incorporation of TK and best management practices.

Wildlife Studies:

 

Investigate whether there will be changes to ungulates (moose, deer).

   Monitoring programs targeted at ungulates will be coordinated with First Nations.

First Nation Water Supply:

 

Concern expressed regarding the potential for effects to water supply from the Rainy River Project.

   Rainy River Resources would be pleased to assemble a map showing the locations of the closest First Nations community water supply intakes upon receipt of the locations/coordinates.

 

 

20-9


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Outstanding Concern or Issue

  

Proposed Approach to Reduce and Remove Concern

First Nation Member Health:

 

The First Nations wish to be kept up to date on the Project, including any potential changes. It is suggested that the Proponent and the First Nations work together through a committee to mitigate any potential social problems with workers staying in nearby villages and camps. The largest issue is the potential for more drugs and alcohol to be brought in and consumed in the area.

  

While the Draft EA has shown no impact to First Nations or non-Aboriginal people’s health, any new information that has a potential to impact health will be provided to First Nations.

 

Rainy River Resources will work with First Nations to ensure employee overall well-being. Programs to highlight the dangers of drug use combined with drug testing will be implemented.

The Métis Nation of Ontario is in the process of completing a TK / TLU and technical review of the Rainy River Project EA Report.    Rainy River Resources anticipates that, as part of the consultation process, an addendum outlining any additional follow-up programs or agreements may need to be submitted in parallel with the final EA Report review.

 

20.3 Environmental Studies

 

20.3.1 Overview

Five (5) years of environmental baseline investigations have been completed in support of the Rainy River Project. The description of the existing environment provided herein is a focused summary based on extensive baseline studies conducted to date for the Rainy River Project. The intent of this section is to familiarize the reader with the local setting. Further details, including copies of the majority of the baseline reports, are provided in the EA Report.

The objectives of the baseline studies are to characterize the natural (or biophysical) and human environment aspects of potentially impacted areas, as well as reference locations (such as upstream locations), where appropriate for comparison. Environmental baseline data (description of the existing environment):

 

 

Helps inform Project designs (for example, knowledge of rock characteristics assists in determining how to best handle and store the material);

 

 

Will allow an assessment to be made of likely Project environmental effects, including comparisons with established environmental guidelines, thresholds and limits, where applicable; and

 

 

Provide a reference for future environmental monitoring (that is, it allows for a comparison to be made of pre-development and post development conditions).

 

 

20-10


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Studies to-date have been completed using standard field protocols and scientific methodologies to accurately document a real and temporal variability, and have considered the information needs of regulatory agencies for approval of previous Ontario mining projects. Traditional Knowledge (“TK”) and Traditional Land Use (“TLU”) data are also being collected as part of the ongoing Aboriginal consultation program.

The list below contains the environmental baseline study reports prepared for the Rainy River Project:

 

 

AMEC. 2011. Rainy River Project, 2011 Wildlife Baseline Study.

 

 

AMEC. 2012H. Rainy River Project, Aquatic Resources 2011 Baseline Investigation.

 

 

AMEC. 2012I. Rainy River Project, 2011 Wildlife Baseline Study.

 

 

AMEC. 2012J. Rainy River Project, 2011 Species at Risk Report.

 

 

AMEC. 2012K. Rainy River Project, 2012 Terrestrial Baseline Study.

 

 

AMEC. 2012L. Rainy River Project, 2012 Species at Risk Report.

 

 

AMEC. 2013m. Rainy River Project, Climate, Air Quality and Sound Baseline Study.

 

 

AMEC. 2013n. Rainy River Project, Socio-economic Baseline Report.

 

 

AMEC. 2013o. Rainy River Project, 2012 Aquatic Resources Baseline Report.

 

 

AMEC. 2013p. Rainy River Project, Hydrogeology Baseline Report.

 

 

AMEC. 2013q. Rainy River Project, Report on Metal Leaching and Acid Rock Drainage Characterization of Mine Rock and Tailings.

 

 

AMEC 2013r. Rainy River Project. 2013 Aquatic Resources Baseline Report.

 

 

AMEC. 2013s. Rainy River Project. 2013 Species at Risk Report.

 

 

AMEC. 2013t. Rainy River Project. 2013 Terrestrial Baseline Study: Bats.

 

 

AMEC. 2013u. Rainy River Project. 2013 Fish and Fish Habitat Existing Conditions for Highway 600 Realignment.

 

 

Klohn Crippen Berger. 2011b. Rainy River Project, Baseline Report 2008-2010.

 

 

Klohn Crippen Berger. 2011c. Geochemical Baseline Report 2008 to 2010.

 

 

Klohn Crippen Berger. 2011d. Rainy River Project Species at Risk Baseline Report 2008-2010.

 

 

Ross Archaeological Research Associates. 2011. Stage 1 Archaeological Assessment, Rainy River Advanced Exploration Project, Richardson Township, District of Rainy River. Prepared.

 

 

20-11


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

Woodland Heritage Services. 2012. Stage 1 Archaeological and Cultural Heritage Resource Assessment of the Rainy River Resources Advanced Exploration Project Northwest of Fort Frances, Rainy River District, Ontario.

 

 

Woodland Heritage Services Limited. 2013. Stage 2 Archaeological and Cultural Heritage Resource Assessment of Rainy River Resources’ Proposed Mining Site, Richardson Township, in the Chapple Township Municipality, Rainy River District, Ontario. MTCS PIF #P208-037-2012 (in progress).

 

 

Unterman McPhail Associates. 2013. Cultural Heritage Assessment Report: Cultural Landscapes & Built Heritage Resources, Rainy River Project.

Information from other field investigations / work not formally documented as of the issuance of this document may also have been used in the preparation of the EA and Feasibility Update Report.

 

20.3.2 Climate, Air Quality and Sound

 

20.3.2.1 Climate

The nearest Environment Canada climate station to the Rainy River Project site, for which long-term, current records are available, is located at Barwick, Ontario. This station is located 23 km southwest from the site, at coordinates 428807E and 5387043N, and has climate records dating back to 1978. Mean monthly temperatures range from a low of -15.9°C in January to a high of 18.8°C in July. The mean annual precipitation for Barwick is 695.7 mm, with 79.5% of this average value occurring as rain. June is typically the wettest month.

A dedicated climate station has been operating at the Project site since June of 2009. Temperature and precipitation results show strong agreement between the Project site and Barwick station precipitation records. Wind speeds for the Rainy River Project climate station show average daily speeds ranging from 2 to 15 km/h, with maximum daily wind speeds ranging from 10 to 80 km/h. There was no overall dominant wind direction noted, but the strongest sustained prevailing winds tend to come from the northwest and the southeast.

 

 

20-12


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

20.3.2.2 Air Quality

There are no large urban centres and industrial sources near the Rainy River Project. Background air quality and sound levels are therefore typical of rural, low-density agricultural regions. Air quality in the Rainy River Project area will, however, be influenced by long-range transport of air emissions from the south and also by natural sources, such as volatile organic emissions from vegetation and natural fires. The greatest potential local influence to air quality is increased particulate matter from traffic, logging/cattle ranching operations and drilling.

Background air quality data were developed for the Rainy River Project site from regional monitoring stations that are able to provide multi-year data for a variety of parameters. All parameters assessed were within the maximum desirable level for the National Ambient Air Quality Objectives. Background particulate matter data were supplemented by KCB onsite monitoring.

 

20.3.2.3 Sound

Ambient noise surveys have been conducted periodically at the Project site since 2009. Measured daytime sound levels have been relatively consistent with background Energy Equivalent Continuous Sound Levels (“Leq levels”) generally ranging from about 40 to 50 A-weighted decibels for most sites, but showing more typical values in the 35 to 40 A-weighted decibel range with the more distant sites (sites >200 m from roads). Night time sound levels were generally lower, as would be expected.

 

20.3.3 Physiography, Soils and Geology

 

20.3.3.1 Physiography

Terrain in the Project site area transitions from the upland bedrock controlled lake areas to the northeast, to the lower-lying to gently undulating terrain to the southwest. The Pinewood River system that drains most of the Project site area occupies a broad lacustrine plain. Lands in the immediate Project site vicinity are typically gently rolling to flat, with wetlands occurring in low-lying areas, and rounded bedrock outcrops and subcrops occurring in upland areas. Elevations increase to as much as 430 m above sea level in highlands northeast of the Project site, and decline to approximately 340 m above sea level in lower reaches of the Pinewood River valley southwest of the Rainy River Project site. Maximum slopes in localized areas are typically in the order of 5 to 10%. Low-lying areas were inundated by glacial Lake Agassiz that left a variably thick veneer of lacustrine clay over much of the landscape.

 

 

20-13


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The overburden sequence at the Project site consists of discontinuous Labradorean Till, overlain by Keewatin Till, with the Keewatin Till typically being overlain and underlain by Lake Agassiz lacustrine deposits. Extensive surface peat deposits occur in many low-lying areas. Alluvial deposits occur in the creek and river valleys. The Labradorean Till consists mainly of silty sands and gravels, and forms localized aquifers, frequently kept under pressure by the overlying lower permeability Keewatin Till. The Keewatin Till is clay-rich and clast poor and is prevalent throughout the area except where it is disrupted by bedrock and subcrop zones. Average Keewatin Till thickness at the Rainy River Project site is in the order of 20 to 25 m, whereas the underlying Labradorean Till is typically less than 5 m in thickness, and is discontinuous. Lake Agassiz lacustrine sediments, comprising clays, with minor silts and sands, typically occur above and below the Keewatin Till, but can also occur locally in more complex sequences. Overall overburden thicknesses can range up to 100 m in some places, but are typically in the order of 20 to 30 m in areas closer to the Project site that are not disrupted by bedrock exposures. Peat deposits are typically <1.5 m in thickness but can be thicker and are widespread in low-lying areas.

 

20.3.3.2 Soils

Soils in the Project area are generally comprised of gray luvisols, gleysols, humisols, and rockland soils, with lesser expressions of podzolic and brunisolic soils. Gray luvisols are typically clay or clay/silt rich and imperfectly drained. Gleysols are poorly drained/frequently saturated, and in the Project site area generally consist of silt loams to more coarse textured soils. Humisols (organic soils) are associated with wetland systems. From a textural perspective, the majority of Project site area soils consist of clay and clay loam soils, with lesser quantities of sandy clay loam, sandy loam, loam, silt loam and silty clay. Site specific investigations included 95 soil samples collected from 50 test pits.

The Project soils are overwhelmingly calcareous, except for the organic soils, due to the nature of the parent material. Organic soils are acidic. Cation exchange capacity tends to be relatively high because of the elevated organic and clay content of most soils present. Soil metal contents were typical of expected background soil conditions for the soil types present.

 

 

20-14


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

20.3.3.3 Geochemistry

Section 7 provides a description of local geology from a resource-based perspective.

Gold mineralization is associated with earlier sulphide formations consisting of pyrite, sphalerite, chalcopyrite and galena stringers and veins, and disseminated pyrite, together with later formed quartz-pyrite-chalcopyrite veins and veinlets.

AMEC is conducting environmental geochemical characterizations of selected samples, representative of the mine rock and overburden in the vicinity of the proposed Rainy River Project open pit, and tailings produced in metallurgical testwork. To date, testing has been carried out on three (3) simulated tailings materials, and a total of 659 deposit-wide mine rock samples, of which 366 represent in-pit non-ore mine rock.

Geochemical studies to date on the mine rock indicate that approximately half the samples may have the potential to produce acid rock drainage. A block model was developed to refine the estimated tonnage of potentially acid generating rock. Generally, metal contents in mine rock materials are typical for their rock types and the risk for metal leaching under neutral conditions appears to be low. Humidity cell analysis is ongoing on the mine rock to evaluate the long term metal leaching characteristics of these materials. Preliminary results have identified a potential risk of short term neutral metal leaching (cadmium and zinc) from the tailings. These results suggest that a simple lime treatment system may be required for the tailings management area discharge to the water management pond during operations, but not post-closure.

The results of the mine rock and tailings analyzes indicate a future risk for acid rock drainage from a portion of the Rainy River Project mineral waste, if not appropriately managed. The Rainy River Project design has taken this into account in the operation and closure of the east mine rock stockpile and tailings management area.

 

20.3.4 Hydrology and Hydrogeology

 

20.3.4.1 Hydrology

Much of the Project area has been cleared over the years for both timber harvesting and through cattle ranching. Most of the natural drainage systems have been altered near the Rainy River Project site through the development of agricultural drains and ongoing beaver activities.

 

 

20-15


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Regional hydrological data are available from four (4) Water Survey of Canada stations: two (2) on the Pinewood River and two (2) on the much larger Rainy River. More limited flow data are available for Rainy River Project local creek systems. Data from the Pinewood River at Highway 617 are particularly relevant to the local study area because they are on the same river system (the Pinewood River), data are collected year-round, the station is currently active and the watershed is comparatively small, allowing for direct prorated data derivations for other site area watersheds. In addition to the Water Survey of Canada data, water level / flow data have been collected periodically from local creek systems.

As with all of northern Ontario, peak stream flows occur in the spring, with a secondary smaller peak flow in the fall. Low flows occur in the winter under ice cover, and also more variably depending on the year in the late summer or early autumn.

The Pinewood River is a low gradient system with a watershed of 575 km2. Local creek catchments draining to the Pinewood River range in size from less than 10 km2 to approximately 25 km2. The creeks generally originate in rocky uplands, but also frequently originate from or pass through headwater wetland systems. Peak stream flows occur in the spring, with a secondary smaller peak flow in the late fall. Low flows occur in the late winter, and more variably during the late summer and early fall. The average annual runoff for the Rainy River Project site area is approximately 195 mm.

Hydrological systems to the northeast (upstream) of the Project site show an abrupt transition to larger lake systems in bedrock-dominated terrain. This lake terrain is remote from proposed project development areas, with the exception of the transmission line corridor that passes through this northeast area, but will not impact directly on any lakes.

Groundwater base flow to area creeks is limited due to the prevailing clay substrates, such that, in certain years, zero or near zero flows are experienced in both local creeks and the Pinewood River during late winter and late summer periods.

 

20.3.4.2 Hydrogeology

The groundwater regime is governed by the overall structure and hydraulic properties of the overburden and bedrock sequences, and by the local topography and associated surface watercourses. A network of over 100 installations has been used to assess site area

 

 

20-16


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

groundwater conditions, consisting of monitoring wells, test wells, drill holes, auger holes, mini-piezometers, and cone penetration test holes. AMEC has developed a hydrogeological model using the Modular Finite-Difference Groundwater Flow Model to estimate:

 

 

Seepage rate into the proposed open pit and the underground workings;

 

 

Drawdown in Pleistocene lower granular deposit / shallow bedrock, caused by the mine dewatering;

 

 

Potential reduction in groundwater discharge to the surface water features; and

 

 

Inflow from tailings management area and east mine rock stockpile, as well as their potential groundwater pathways.

Based on model applications and sensitivity analyses, the predicted groundwater seepage rates into the open pit and underground workings are expected to be in the order of 2,900 m3/d to 3,900 m3/d at full open pit development. The predicted drawdown cone from dewatering of the open pit is predicted to extend approximately 3 to 4 kilometres in all directions from the pit by the end of mining. No private wells will be located within the current estimated drawdown cone. Parts of the Pinewood River and several of its tributaries also lie within the projected drawdown cone. The impact of a reduction in groundwater discharge to the Pinewood River is expected to be minor and difficult to measure, given that flow in these sections of the river and its tributaries is dominated by surface water runoff contributions and these features can often be dry. A monitoring network of wells and surface water level stations is proposed to confirm the predicted impact.

Based on the high clay content of the Keewatin Till and the associated glacial Lake Agassiz sediments, the local creek and wetland systems are expected to be perched, and not overly sensitive to open pit dewatering effects.

 

20.3.5 Surface Water, Sediment and Groundwater Quality

 

20.3.5.1 Surface Water

Twenty (20) surface water sampling stations were established for the Rainy River Project during the period of 2007 through 2010, with 14 of these stations still being active and sampled on an approximate monthly basis. Attempts have been made to position stations upstream and downstream of potential future developments within the limitations of the local drainage systems.

 

 

20-17


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Since June 2010, water quality samples have been collected at approximate monthly intervals to provide a full seasonal spectrum of data, with samples being analyzed for a broad range of general parameters and metals.

Surface water quality in the area is generally quite good, with all parameters typically meeting applicable objectives/guidelines for the protection of aquatic life, except for:

 

 

iron, aluminum and phosphorus, which were commonly above their respective objectives;

 

 

cadmium, copper and cobalt, which occasionally to commonly exceeded either Federal or Provincial objectives; and

 

 

occasional to rare exceedances for arsenic, lead, nickel and zinc.

Increased coliform levels were also noted at some stations that may be related to area cattle operations and cattle foraging activities. It is not unusual for baseline water quality to exceed objectives/guidelines for various metals as a result of high suspended solids loadings in some samples, naturally elevated metal content in the local soil and rock, and because of seasonal ion concentration processes involving ice formation in winter and evaporative process in summer. Erodible clay/silt soils, cattle activity, and low creek base flow conditions (making them prone to ion concentration effects), are all contributing factors to observed water quality conditions.

 

20.3.5.2 Sediment

Sediment quality samples were collected from 2008 to 2013 from various upstream and downstream stations and analyzed for a suite of parameters. Sediment quality is generally good with parameters generally found below Federal guideline values, and below Provincial sediment quality guideline lowest effect levels.

 

20.3.5.3 Groundwater

Groundwater quality samples were collected periodically from 2007 to present from monitoring well and drill holes near to the Project site. Samples were analyzed for a complete suite of parameters and compared with Federal and Provincial objectives and guidelines for the protection of aquatic life, as well as the drinking water standards; recognizing that neither of these criteria are not directly applicable. Groundwater baseline water quality reflects the naturally elevated metal content in the local soil and rock. Results from Municipal and private wells showed generally good water quality, with occasional exceedances of drinking water objectives for some parameters.

 

 

20-18


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

20.3.6 Biological Environment - Existing Conditions

 

20.3.6.1 Aquatic Resources

The Rainy River Project is somewhat unique from an environmental perspective, in that there are no lakes located within, or adjacent to the main Rainy River Project site. While limited bait fishing does occur within certain project area creeks, the area does not support a significant commercial or recreational fishery. In addition, the creeks present within the Rainy River Project site often encounter zero flow during dry periods.

Multi-season studies of fisheries and aquatic resources have been carried out for the Rainy River Project from 2008 through 2013. In the general vicinity of the Rainy River Project area, the Pinewood River shows typical widths of 10 to 15 m, with wider sections associated with beaver impoundments and drowned oxbows. Summer water depths are typically 0.9 to 1.7 m, with maximum summer water depths in the order of 2 m. Substrates consist of clays and silts, with some detritus. Gravel, rock or cobble substrates are sparse and contribute little to in-stream habitat / cover for fish. Turbidity is high because of erosion of the clay and silt substrates, and agricultural drainage inputs. Beaver dams are frequent and present periodic obstacles to fish passageways in the local study area.

The smaller creeks / Municipal drains that flow into the Pinewood River (Loslo Creek / Cowser Drain, Marr Creek, West Creek, Clark Creek / Teeple Drain, Tait Creek and Blackhawk Creek) typically exhibit summer widths of 0.5 to 3 m, except where they are impounded by beaver dams, with upper creek reaches being smaller, generally from <0.5 to 1.5 m and frequently exhibiting intermittent flow. Headwater areas of many of these tributary creek systems are associated with wetland systems. Beaver impoundments are frequent.

Large-bodied fish species (Northern Pike, Brown Bullhead and White Sucker) were found only in the Pinewood River and not in the smaller tributaries, with the exception of White Sucker (also found in Loslo Creek and Clark Creek). Walleye and Yellow Perch occur further downstream in the Pinewood River, but not in the general area of the Rainy River Project site. Lake Sturgeon, classified Provincially as Threatened (Endangered Species Act) in the area, were not present

 

 

20-19


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

within the Rainy River Project site area and environs during the spring 2013 survey. Three (3) Lake Sturgeon were however caught during the spring of 2013 approximately 27 km downstream of the proposed Rainy River Project open pit. As this was the result of a focussed effort at regulatory request, it potentially indicates a lack of suitable habitat and/or a small spawning population specific to the lower Pinewood River.

Small-bodied fish of several species are abundant within the Pinewood River mainstem, as well as in its tributaries. These tributaries likely provide seasonal refuge from predators and contribute to the overall productivity of the Pinewood River system. All fish species present in the system are spring / early summer spawners.

Area benthic communities exhibit a low-to-moderate abundance, with a relatively poor representation of taxa used as indices for characterization and comparison of benthic invertebrate communities, due to the lack of larger substrate particles and dominant clay-silt conditions.

 

20.3.6.2 Vegetation Communities

The Rainy River Project and environs occur within the Agassiz Clay Plain Ecoregion that extends from Lake of the Woods in the west to Fort Frances in the east, and from the United States border northward. The Pinewood River watershed is dominated by mixed Poplar and Black Spruce forests, and by non-forested areas (mainly agricultural lands), together with wetlands. The local area shows an even greater preponderance of mixed poplar forests that occupy more than 50% of the landscape, together with wetlands and agricultural lands. Wetlands are comprised mainly of treed and open fens, together with wetland thickets and marsh areas. Agricultural lands are mainly pasture and hay fields. Poplar forests, comprised principally of Trembling Aspen, are indicative of disturbed lands as Trembling Aspen are a successional species in Ontario.

Only two (2) Provincially rare species have been identified in the local area: New England Violet and Field Sedge. Muskroot, another rare species, has been identified as being present historically. There are no specific approvals related to these species.

 

 

20-20


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

20.3.6.3 Wildlife

Wildlife surveys were carried out for the Rainy River Project and its immediate environs. These surveys were focused principally on birds due to regulatory requirements, and to a lesser extent on mammals, amphibians and dragonflies/damselflies. A proactive focus was placed on Species at Risk assessment and permitting planning by Rainy River Resources and the Ministry of Natural Resources.

Focused surveys have been conducted on forest birds, breeding birds, owls, marsh birds and waterfowl species, Sharp-tailed Grouse, nocturnal avian species (Whip-poor-will, Common Nighthawk and owls), raptors and amphibians, using established survey protocols. The relatively high avian species diversity present in the area reflects the mosaic of principal habitats in the areas (forest, wetlands, fields and shrublands), and the transitional (or near transitional) position of the study area relative to the Great Lakes, Boreal and Prairie regions. The Mississippi Flyway passes over the regional study area, but results from KCB 2010 migration surveys indicate that the Rainy River Project site area is not considered an important migratory stopover location, as very low numbers of migrating waterfowl, raptors, shorebirds and songbirds were recorded.

Twenty-two mammal species have been identified in the Rainy River Project environs through direct observation, trapping records or sign. Species of cultural significance protected under the Fish and Wildlife Conservation Act, including game animals (Black Bear, Snowshoe Hare, Moose, Elk and White-tailed Deer), furbearers (Red Squirrel, Beaver, Muskrat, weasels, American Mink, American Marten, Fisher, River Otter, Bobcat, Lynx, wolf and Red Fox) and specially protected mammalian guilds (bats, shrews and chipmunks), have been recorded in the local study area. Three (3) commercial trap lines overlap with the local area. Fur returns for these trap lines for the period of 1993 through 2008 indicated that Beaver, American Marten, Red Fox, Otter, Fisher and Mink are the most frequently and valued furbearers taken.

Amphibian and reptile surveys identified eight (8) frog species and three (3) reptile species. No salamander species were observed. Twelve species of dragonflies/damselflies were observed, or are known to occur, in or adjacent to the Rainy River Project, three (3) of which are provincially rare (Horned Clubtail, Arrowhead Spiketail and Green-faced Clubtail) but do not require special permit or authorization considerations.

 

 

20-21


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

20.3.6.4 Species at Risk and Critical Habitat

The Species at Risk known to occur in the Rainy River Project environs are listed in Table 20-5. Rainy River Resources has been working closely with the Ministry of Natural Resources, since June of 2010, in support of meeting permitting requirements of the Ontario Endangered Species Act. The Species at Risk permitting process is currently in progress.

Table 20-5: Species at Risk Known to Occur in the Rainy River Project Environs

 

Species Common Name

  

Endangered
Species Act

  

Species at Risk Act

Birds

     
Barn Swallow    Threatened   
Bobolink    Threatened   
Whip-poor-will    Threatened    Threatened
American White Pelican    Threatened    Not at Risk
Bald Eagle    Special Concern    Not at Risk
Canada Warbler    Special Concern    Threatened
Common Nighthawk    Special Concern    Threatened
Golden-winged Warbler    Special Concern    Threatened
Olive-sided Flycatcher    Special Concern    Threatened
Peregrine Falcon (migrant)    Special Concern    Special Concern
Red-headed Woodpecker    Special Concern    Threatened
Short-eared Owl    Special Concern    Special Concern

Mammals

     
Little Brown Myotis (bat)    Endangered   
Northern Myotis (bat)    Endangered   

Reptiles

     
Snapping Turtle    Special Concern    Special Concern

 

20.3.7 Human Environment

 

20.3.7.1 Population and Demographics

The population of the Rainy River District was 17,912 in the 2011 Census, a decline of 1.8% from the 2006 Census, itself a 2.5% decline from the 2001 Census. Approximately 55% of the Rainy River District’s population resides in the largest urban centre, Fort Frances, which has a population of 7,952. Excluding the smaller hamlets, Emo is the closest community to the Rainy River Project site with a population of 1,252. The trend of population decline is expected to continue in the region over the long term (Ministry of Finance 2009), due in part to loss of employment in the forestry sector.

 

 

20-22


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The region has approximately equal representation of males and females, with the youngest and oldest age cohorts being higher than the Provincial averages. Overall, the median age is higher than the province’s, at 43.2 and even older in the rural areas (unorganized) of the District.

 

20.3.7.2 Regional Economy

The regional economy in the Rainy River District is primarily supported by the forestry sector with three (3) of the ten (10) major employers involved in forestry manufacturing. The remainder of the major employers are in public (health, education, municipal government) and retail services. In 2006, the participation in the labour force for the Rainy River district was 64.2%. This rate is slightly lower than the province’s (67.1%), with a significantly higher unemployment rate (7.9%) compared with the province’s (6.4%). The Rainy River district had a larger workforce share employed in occupations unique to primary industry and trades, transport and equipment operation and related occupations in 2006, compared to Ontario as a whole. This suggests that the workforce is well positioned to service the Rainy River Project.

 

20.3.7.3 Community Infrastructure and Services

Given that the region has experienced population declines, service capacity may be able to handle additional demands that could be experienced by these communities in the event of population increases either temporarily during the construction phase or permanently in operations phase of the Rainy River Project. The available information suggests that there could be some near-term capacity challenges for housing and accommodation, as well as for cellular communications services that Rainy River Resources is currently investigating.

The region is very well serviced and accessible from Highways 71, 11 and 600. The Canadian National Railway runs east-west through the region and within 40 km of the Project site with links to Winnipeg (Manitoba), Thunder Bay (Ontario) and Duluth (Minnesota). Fort Frances has regular commercial air service.

 

 

20-23


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

20.4 Traditional Knowledge (“TK”) and Traditional Land Use (“TLU”)

Opportunities for TK / TLU consultations were offered to the following First Nations between July 2012 and February 2013:

 

 

Anishinaabeg of Naongashiing First Nation (Big Island);

 

 

Buffalo Point First Nation;

 

 

Mishkosiminiziibiing (Big Grassy River) First Nation;

 

 

Naicatchewenin First Nation;

 

 

Naotkamegwanning (Whitefish Bay) First Nation;

 

 

Ojibways of Onigaming First Nation; and

 

 

Rainy River First Nations.

The following First Nations worked closely with Rainy River Resources to collect TK / TLU information:

 

 

Mishkosiminiziibiing (Big Grassy River) First Nation;

 

 

Naicatchewenin First Nation; and

 

 

Rainy River First Nations.

TK / TLU sessions were held with several of the notification Aboriginal groups, including: Couchiching First Nation, Mitaanjigamiing (Stanjikoming) First Nation, and Seine River First Nation.

The TK / TLU studies were led by Ms. Stacey Jack, Rainy River Resources Community Coordinator. Ms. Jack is a licensed Archaeologist, who, as a resident of the District and member of the Couchiching First Nation, has extensive knowledge of regional history. She has worked extensively with area First Nations over the past 20 years, including a leadership role in the development of the Manitou Mounds National Historic Site that is located approximately 35 km south of the Rainy River Project site. In support of the TK / TLU studies, data sharing agreements were signed with these First Nations to ensure that sensitive information is protected and held strictly between the First Nations and Rainy River Resources.

The Métis Nation of Ontario is in the process of completing a TK / TLU study and technical review of the EA report. Rainy River Resources anticipates that as part of the consultation process with the Métis Nation of Ontario an addenda outlining any follow-up programs or agreements may need to be submitted in parallel with the final EA report review.

 

 

20-24


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Through these consultations, no traditional activities were identified within the Rainy River Project area. Rainy River Resources has committed to undertaking a joint water quality monitoring and reporting program with the area First Nations as part of the existing monthly water quality monitoring program carried out by Rainy River Resources. The program will be funded by Rainy River Resources and form an integral part of the overall environmental management program as it relates to First Nations TK, and assurances of maintaining water quality and by extension aquatic life protection.

Big Grassy River First Nation undertook a second independent review that was provided to the company on October 18, 2013. The review concluded that additional work with the community was required and Rainy River Resources has committed to continuing the close engagement with the community in support of project development.

 

20.5 Cultural Heritage Resources

The cultural pre-European contact history of the Rainy River District is similar to that in eastern Manitoba and northern Minnesota, and can be divided into the following generalized temporal and cultural sequences: Late Paleo (circa 9000 to 6000 BC), Shield Archaic (circa 6000 to 500 BC) and Middle / Late Woodland (circa 500 BC to AD 1600), and Historic (circa AD 1600 to present).

Prior to the Stage 2 work associated with the Rainy River Project, there were only two (2) previously recorded archaeological registered sites within 15 km of the Rainy River Project. Little information is known about these sites but they appear to be surface collections of unknown age. During 2012 and 2013, Stage 2 archaeological assessment within the Rainy River Project study area, identified eight (8) pre-contact archaeological sites and six (6) historic sites. As required by regulations, these sites have been registered with the Province and are afforded protection under the Ontario Heritage Act until clearance is obtained from the Ministry of Tourism Culture and Sport.

In regard to the already identified sites, preliminary application of the Ministry of Tourism Culture and Sport Stage 3 criteria indicate that four (4) pre-contact archaeological sites and two (2) historic archaeological sites will require Stage 3 excavations. Further Stage 4 work may also be required depending on the Stage 3 results. Consultation with Aboriginal people will continue throughout the archaeological research.

 

 

20-25


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Unterman McPhail Associates and Jean Simonton, Heritage Consultant, undertook a survey to identify cultural heritage landscapes and built heritage resources within the study area. Twenty-one (21) sites were identified that could be generally described as: rural landscapes (agriculture), township survey, transportation (roadscape), settlement (hamlet), agricultural farm complexes, residences and recreation (trail). The Minister of Ministry of Tourism, Culture and Sport has not designated any of the cultural heritage resources (such as those listed in Table 1 under Part IV of the Ontario Heritage Act) within or adjacent to the study area. In addition, there are no road bridges listed in the Ontario Heritage Bridge Guideline and no Ontario Heritage Trust easement properties or Federally recognized properties within or adjacent to the study area (Unterman McPhail 2013).

 

20.6 Environmental Sensitivities

There are a number of Species at Risk known or expected to occur within the Rainy River Project footprint or environs. Avoidance of critical Species at Risk habitat is one of the mitigation measures that has already been incorporated into the Project design to a practical level. Based on information currently available, Provincial Species at Risk Permits, pursuant to requirements of the Endangered Species Act, are required for Whip-poor-will and Bobolink. Rainy River Resources with AMEC’s support have been pursuing these approvals in parallel with the EA process.

There are no Federal lands within the Project footprint and Federal Species at Risk Permits will not be required.

There are no Areas of Natural Scientific and Interest, Environmentally Sensitive Areas, Provincially Significant Wetlands, or Federal or Provincial parks within the Project area.

 

 

20-26


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

20.7 Regulatory Context

 

20.7.1 Current Regulatory Status

Exploration has been conducted at the Project site since 2007. Based on AMEC’s site inspections to-date, the exploration has been completed in an appropriate manner from an environmental perspective. AMEC understands that the site is fully compliant with existing environmental approvals and has conducted the exploration with due regard to environmental considerations.

 

20.7.2 Environmental Approvals Required for Proposed Operations

 

20.7.2.1 Environmental Assessments

Most mining projects in Canada are reviewed under one or more Environmental Assessment (EA) processes. The EA process is a means of project review whereby project design choices, environmental impact and proposed mitigation measures are compared and reviewed to determine how best to proceed through the environmental approvals and permitting stages. Entities involved in the review process normally include government agencies, municipalities, Aboriginal groups, various interested parties and the general public.

The Rainy River Project requires completion of a Federal EA, pursuant to the Canadian Environmental Assessment Act, 2012. The Federal Regulation Designating Physical Activities identifies the physical activities that constitute the designated projects that could require an EA. As the Project had elements that met these requirements, Rainy River submitted a Project Description to the Canadian Environmental Assessment Agency in August 2012 that was subsequently accepted. Based on the Project Description, the Canadian Environmental Assessment Agency confirmed that a Federal Standard EA is required. The Environmental Impact Statement Guidelines that identify the scope of the EA required for the Project were issued on December 18, 2012.

In addition to needing to meet Federal EA requirements, Rainy River entered into a Voluntary Agreement with the Ontario Ministry of the Environment on May 4, 2012, to conduct a Provincial EA for the Rainy River Project that will meet the requirements of the Ontario Environmental Assessment Act. Rainy River entered into the Voluntary Agreement in order to facilitate meeting the Provincial EA requirements to allow issuance of Provincial approvals to construct the mine.

 

 

20-27


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Several aspects of the Project were anticipated to require completion of Provincial EA process(es). A single Provincial process coordinated with the required Federal EA process, was selected as the best approach to meet those (or other) needs, as per the following:

 

 

A 230 kV transmission line of approximately 20 km length;

 

 

Diesel generation of between 1 and 5 MW generation;

 

 

Disposition of Crown resources, potentially related Crown lands (such as work on streambeds/shorelands) and effects on Species at Risk; and

 

 

Realignment of a portion of gravel-surfaced Highway 600 to avoid potential land use conflicts.

In parallel with the submission of the Project Description to begin the Federal EA process, Rainy River initiated the Provincial EA process through the submission of a draft Terms of Reference for public comment. A 30-day public comment period on the draft Terms of Reference was held between May 17, 2012 and June 16, 2012. A proposed Terms of Reference was issued for a 30-day public comment period from October 26 to November 26, 2012. A subsequent Amended Proposed Terms of Reference was approved by the Ontario Minister of the Environment on May 15, 2013.

Rainy River Resources has been working closely with the Federal and Provincial approvals agencies to harmonize the Federal and Provincial EA processes and, where possible, align public consultation periods to meet the needs of each Act, while minimizing duplication of effort that can lead to unnecessary project delay. This coordination is directed by the Canada-Ontario Agreement on Environmental Assessment Cooperation, and is led by the Canadian Environmental Assessment Agency and the Provincial Ministry of the Environment. Challenges exist as there is no precedent in Ontario and the two (2) regulatory regimes are very different. In December 2012, the Rainy River Project was selected by the Federal/Provincial Regulatory Reform Working Group as one (1) of a very limited number of projects across Canada to receive enhanced alignment considerations and support from senior government officials. This senior support is expected to assist in maintaining the Project schedule.

The Federally-issued Environmental Impact Statement Guidelines and the Provincially-approved Amended Terms of Reference together set out the framework and requirements for the EA Report. The EA Report is intended to provide Federal authorities with information regarding the

 

 

20-28


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

proposed Rainy River Project in order to assist decision making by the Federal Minister of the Environment regarding the applicability of the Canadian Environmental Assessment Act, 2012. It is also intended to provide sufficient information for the Ontario Minister of the Environment to approve the Rainy River Project pursuant to the Ontario Environmental Assessment Act. The Federal and Provincial government authorities have agreed that a single body of knowledge, will be used for the coordinated EA process.

The EA Report was prepared during 2012 and 2013. At various community and leadership meetings, Rainy River Resources was informed that Aboriginal communities did not have the time nor financial and human resource capacities to adequately review the Rainy River Project EA Report. In order to allow adequate time for the Aboriginal technical review, the draft EA Report (Version 1) was released to thirteen Aboriginal groups on May 17, 2013 eight (8) weeks in advance of the general public and government agencies. Rainy River Resources also committed financial resources to the Aboriginal groups for an independent technical review of the draft EA Report (Version1).

A subsequent draft EA Report (Version 2) was provided for government, Aboriginal group and stakeholder review, and hosted at six (6) public venues to facilitate comments starting on July 19, 2013.

Comments received during the draft EA Report reviews were responded to by Rainy River Resources and, as appropriate, were incorporated into a final EA Report issued on December 2, 2013 for a conformity review, as required by the Canadian Environmental Assessment Act, 2012. It is anticipated that final EA Report (Version 2) will be issued for government, Aboriginal group and stakeholder review, and hosted at public venues to facilitate comments, starting in January 2014.

The Project environmental approvals schedule that has been incorporated into the overall Project schedule includes AMEC’s best estimate of the timeline needed to obtain environmental approvals based on published timelines, discussions with regulatory agencies, professional experience and precedents of other Ontario mining projects. Currently, all major mining projects in Ontario are subjected to the same coordinated Provincial/Federal EA process with the Provincial Individual EA process being a new approach to enhancing inter-governmental

 

 

20-29


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

alignment in Ontario. While there is always a certain level of risk related to major project EA approval timing, the Rainy River Project is subject to a greater confidence level than there would have been prior to the promulgation of the Canadian Environmental Assessment Act, 2012.

Construction of the Rainy River Project cannot proceed until the Federal and Provincial EAs have been approved, and the appropriate regulatory approvals (as described below) have been attained for the Project component being constructed. Environmental approvals to initiate construction must follow after and are dependent on the EA approvals.

 

20.7.2.2 Environmental Approvals

A small number of Federal environmental approvals are anticipated to be required or are potentially required for the construction and operation of the Project as listed in Table 20-6.

Table 20-6: Anticipated Federal Environmental Approvals

 

Permit / License

 

Responsible

Agency

    

Description

Harmful Alteration,

Disruption or Destruction

of Fish Habitat

Fisheries Act

 

 

Fisheries and

Oceans Canada

    

 

Depending on the sensitivity of fish and fish habitat, authorization may potentially be required for the:

 

•  Establishment of the mine rock stockpile(s) and tailings management area;

 

•  Re-alignment of Highway 600 and mine access, creek crossings;

 

•  In water structures such as for fresh water taking;

 

•  Watercourse diversions / re-routing; and/or

 

•  Flow reductions in watercourses supporting fisheries.

Review of Works in Navigable Waters

Navigable Waters

Protection Act

 

Transport

Canada

     For alteration of navigable waters, such as through establishment of crossing(s) over Pinewood River (if determined to be a Navigable Water); or others.

Schedule 2 Listing

Metal Mining Effluent Regulation

Fisheries Act

 

Environment

Canada

     It is expected that the overprinting of waters frequented by fish by tailings and mine rock stockpiles (or other deleterious material) may be necessary and will also require a listing under Schedule 2 of the Federal Metal Mining Effluent Regulation, pursuant to the Fisheries Act.

 

 

20-30


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Note that explosives magazines, manufacturing facilities and transportation of explosives require a Federal permit, pursuant to Sections 6 and 7 of the Explosives Act. It is anticipated that facilities and equipment owned by the licensed explosives contracted will be permitted through the contractor.

A large number of Provincial approvals are expected to be required to construct, operate and eventually reclaim the Rainy River Project. Key legislation related to the Rainy River Project includes the: Ontario Water Resources Act, Environmental Protection Act, Endangered Species Act, Mining Act, Lakes and Rivers Improvement Act, Public Lands Act and Planning Act. Table 20-7 provides a listing of the Provincial approvals anticipated to be required or likely to be required for the construction and operation of the Rainy River Project. In some instances, multiple approvals may be needed of the same type.

Table 20-7: Anticipated Provincial Environmental Approvals

 

Approval/Licence

  

Agency

Responsible

  

Description

Environmental Compliance Approval

– Air and Noise

Environmental Protection Act

  

Ministry of the

Environment

   Approval to discharge air emissions and noise.

Environmental Compliance Approval

– Industrial Sewage Works

Ontario Water Resources Act

  

Ministry of the

Environment

   Approval to treat and discharge effluent such as for: mine/pit water, tailings management area.

Environmental Compliance Approval

– Industrial Sewage Works

Ontario Water Resources Act

  

Ministry of the

Environment

   Approval to treat and discharge effluent (such as for: sewage treatment, oil water separator).

Environmental Compliance Approval

– Waste Disposal Site

Environmental Protection Act

  

Ministry of the

Environment

   Operation of a waste transfer site.

Permit to Take Water

Ontario Water Resources Act

  

Ministry of the

Environment

   Water taking from surface or ground water (open pit and other sources; multiple permits expected to be required).

 

 

20-31


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Approval/Licence

 

Agency Responsible

 

Description

Approval to Commence

Harvesting Operations

(Forestry Resource Licence)

Crown Forest Sustainability Act

 

Ministry of Natural

Resources

 

 

Cutting of merchantable timber on Crown land.

Land Use Permit

Public Lands Act

 

Ministry of Natural

Resources

  Land tenure for facilities constructed on Crown land (such as transmission line).

Species at Risk Net Benefit Permit

Endangered Species Act

 

Ministry of Natural

Resources

  Management of activities related to Species at Risk.

Work Permit or other Approval

Public Lands Act/Lakes and

Rivers Improvement Act

 

Ministry of Natural

Resources

  Work/construction on Crown land, including below the high water mark of local watercourses and construction of dams.

Work Permit / Various Approvals

(highway entrance,

encroachment permit etc.)

Highway Act

 

Ministry of

Transport

  Various engineering approvals, including those related to the relocation of Highway 600.

Closure Plan

Mining Act

 

Ministry of

Northern

Development and

Mines

  For mine construction/production.

An application for a Leave-to-Construct will also be required pursuant to the Ontario Energy Board Act for approval to construct the proposed transmission line.

 

20.8 Preliminary Environmental Impact

A comprehensive assessment of the potential environmental impact of the Rainy River Project, along with proposed mitigation measures and the anticipated significance of the effects, has been developed as part of the EA process. The methodology used has been previously accepted for approval of Ontario mining projects and was approved in the Provincial Terms of Reference.

The effects of the Project on a number of valued ecosystem components (VEC; a particular habitat, an environmental feature, a particular assemblage of plants or animals, a particular species of plant or animal, or an indicator of environmental health) and valued socio-economic components (VSEC; components of the socio-economic environment that are significant in terms of people’s values and quality of life) were assessed, for each project phase.

 

 

20-32


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

For each VEC or VSEC identified, the potential effect is analyzed, mitigation or enhancement proposed and an assessment of significance made. Best professional judgement was used in carrying out the effects analysis, incorporating information from available sources, including opinions and perspectives expressed by the various stakeholders and Aboriginal communities through the EA process. Where appropriate, specific analytical methods and tools have been used to support the effects analysis; including laboratory tests, mass balance calculations, statistical packages and various types of models.

Criteria used to evaluate significance included consideration of magnitude / geographic extent, duration, frequency, and ecological / socio-economic context of each effect, as well as whether or not the effect is likely to occur. The direction of the effect (positive or negative) is also considered for socio-economic effects.

The sections that follow provide an overview of the environmental effects analysis and proposed significance, detailed in the final EA Report.

 

20.9 Effects Analysis

 

20.9.1 Air Quality and Sound

Air quality emissions were modelled to predict Rainy River Project site area air quality. The potential effect associated with air emissions is an increase in the airborne concentrations of key pollutants in the vicinity of the Rainy River Project site, with the potential to adversely affect air quality. With the appropriate mitigation, the magnitude and geographic extent of any effects on air quality are considered to be low while the duration of the effect on air quality is medium-term, with emissions to the atmosphere throughout the operational life of the Rainy River Project site. The effects are readily reversible, as the air quality effects will cease once the mining and ore processing activities cease (anticipated 16 year mine life) upon closure and reclamation. The overall effect of air emissions, including fugitive dusts, is therefore considered to be minor, as they are limited in geographic extent, limited in magnitude, and reversible.

 

 

20-33


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Project-related greenhouse gas emissions will result from onsite fuel combustion and other mining and ore processing activities. The estimated maximum emission from the Rainy River Project is very low, and equivalent to approximately 0.02% of Canada’s 2010 emissions.

Sound emissions will vary over the life of the Rainy River Project from lower levels during construction and early operations phases, and increasing gradually to the projected peak in 2020. Beyond 2020, as the open pit continues to deepen and as the stockpiles provide increased shielding, sound levels will begin to decrease and will decline further once open pit operations cease in about 2026. Sound mitigation measures, such as selection of quieter equipment, are inherent to the current design of the Rainy River Project site and are reflected in the sound model predictions. The modelled sound contours for the Rainy River Project site demonstrate compliance with applicable MOE guidelines.

 

20.9.2 Streamflow, Aquatic Habitats and Species

The Rainy River Project is somewhat unique from an environmental perspective in that there are no lakes located within or adjacent to the main Rainy River Project site. While limited bait fishing does occur within certain project area creeks, the area does not support a significant commercial or recreational fishery. In addition, the creeks present within the Rainy River Project site often encounter zero flow during dry periods.

Project effects are restricted to the minor creeks in the immediate vicinity of the site, including the Loslo Creek / Cowser Municipal Drain, Marr Creek, West Creek, Clark Creek / Teeple Municipal Drain, and the Pinewood River. Development of the Rainy River Project will impact the local creeks and the Pinewood River due to direct habitat displacement (overprinting) and habitat modifications such as channel re-alignment (creeks only); and more indirect pathways such as flow reductions effluent discharge or a combination of the above (creeks and river). The Pinewood River will not be directly altered by any proposed mining works.

Local creeks expected to be directly overprinted by the mine features, in whole or in part, include from east to west:

 

 

Clark Creek / Teeple Municipal Drain;

 

 

West Creek;

 

 

Marr Creek; and

 

 

Loslo Creek / Cowser Municipal Drain.

 

 

20-34


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The remaining upstream portions of these creeks, not overprinted directly by mine facilities or infrastructure, will require flow diversion or interception to avoid the upstream flows from interacting with the developed mine areas.

Potential effects on creek flows and water quality will vary from system to system as various portions of the drainages are overprinted by Project components or incorporated into the Rainy River Project integrated water management system. The tailings management area and all stockpiles will incorporate perimeter ditching to intercept runoff and seepage to enable redirection of the drainage to the Rainy River Project water treatment systems and ensure appropriate water quality standards are met prior to release of excess waters.

For the Pinewood River, the annual change in river flow due to the Rainy River Project development will be a function of the capture of watershed that would otherwise flow directly into the river, less the effect of returning of site excess water being returned to the Pinewood River, either through the constructed wetland or by pipeline further downstream (below the McCallum Creek outlet). The net effect will be to reduce Pinewood River flow as measured below the McCallum Creek outlet by approximately 3.45% during an average flow year during early operation, transitioning to a projected overall net gain in flow in the Pinewood River for an average flow year in later mine life of 0.3%.

A combined aquatic habitat displacement or alteration of approximately 26 ha is anticipated. This will result in a harmful alteration, disruption or destruction of fish habitat. Accordingly, a No Net Loss Plan and compensation strategy to offset unavoidable effects to fish habitats is being developed with associated regulatory agencies in consultation with the local communities. A blended offset strategy of watershed restoration with like for like habitat compensation is proposed. Rainy River Resources has committed to supporting water quality and general habitat improvement activities within the Pinewood River watershed along with development of appropriate compensation efforts focused primarily on the establishment of onsite habitats in ponds and diversions, to offset the Rainy River Project habitat losses. Draft versions of these documents have been provided to Fisheries and Oceans Canada.

 

 

20-35


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

20.9.3 Groundwater

Modelling of the proposed open pit anticipates that the zone of influence, defined by 1 metre of drawdown that will eventually develop from the dewatered open pit, is expected to extend approximately 2.5 to 3.5 km from the edge of the open pit in the base case scenario, by the end of mining.

The predicted reduction in the average groundwater flow contribution to the Pinewood River during mine operations is estimated to be three (3) percent of the mean daily flow for the Pinewood River, as measured below the McCallum Creek outlet. Mitigation measures primarily consist of returning captured groundwater as part of the overall Rainy River Project water discharge to the Pinewood River during the period of mine operations to minimize adverse flow effects to the river, especially during low flow conditions; and accelerating open pit inflow following mine closure, to the extent practicable.

 

20.9.4 Vegetation and Terrestrial Habitat

The primary forest cover types within the natural environment local study area in terms of area extent are:

 

 

Hardwood forest (47.6% coverage);

 

 

Coniferous swamp (18.3% coverage);

 

 

Coniferous forest (9.9% coverage);

 

 

Agricultural land (7.7%); and

 

 

Meadow marsh and shallow marsh (4.6%).

The majority of the Rainy River Project footprint overlaps with the hardwood forest community type (mainly aspen-birch), with an anticipated direct displacement of 1,144 ha of hardwood forest community.

Mitigation measures have been incorporated into site planning, with efforts focused on developing a compact site plan with development, where practical, on lands that have been previously disturbed as a result of past anthropogenic disturbance such as logging or agricultural development.

 

 

20-36


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

20.9.5 Terrestrial and Avian Species

Development of Rainy River Project components will affect both terrestrial and avian species through the direct loss of habitats and sound levels in the local vicinity. Development of the Project will also result in an increased risk of mortality due to collisions with vehicles. Many of the species affected will find suitable habitats adjacent to the Rainy River Project given the homogeneous forest cover of the area and abundance of alternative habitats.

Mitigation measures have been incorporated into site planning, with efforts focused on developing a compact site plan with development, where practical, on lands that have been previously disturbed as a result of past anthropogenic disturbance such as logging or agricultural development. Clearing of habitats will be restricted to periods outside of breeding and nesting seasons for various avian species.

 

20.9.6 Species at Risk

Rainy River Resources has worked collaboratively with the Ministry of Natural Resources on Species at Risk management planning in support of project permitting since 2010. This has included the funding of a collaborative research study along with the Ministry of Natural Resources and Trent University.

No locally significant plant communities have been identified, although two (2) provincially rare plant species were found.

A number of mitigation measures will be employed as part of Rainy River Project development and operation to reduce potential adverse impacts to the species. These measures include:

 

 

Placement of project components and development of a compact project footprint, in consultation with the Ministry of Natural Resources, to minimize the number of habitat locations that are affected by project components; and

 

 

Habitat compensation (for Eastern Whip-poor-will) and active protection of known suitable habitats will encourage use by affected individuals.

 

 

20-37


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

20.9.7 Traditional Land Use

While the Rainy River Project will be situated on primarily private lands, Rainy River Resources is continuing to work with the First Nations and Métis to ensure protection of Aboriginal treaty rights. TK / TLU consultations have not identified traditional activities within the Rainy River Project area by the Aboriginal communities that have participated thus far in studies, including Naicatchewenin First Nation, Rainy River First Nations, as well as Big Grassy River First Nation. Some study participants have stated that the Rainy River Project was not an area of intensive use in the distant past, but it is understood that traditional activities may have taken place there.

As a result of the First Nation independent review of the draft EA Report (Version 1), the Rainy River Resources has stated that it will remain open to working with communities.

 

20.9.8 Socio-economic

The Rainy River Project has the potential, through the generation of very significant employment and business opportunities, to change or influence the population and demographics of the local and regional communities, principally in a positive manner. These potential changes are particularly important considering recent downturns in the forestry and tourism economies that have plagued the region and resulted in a sustained net loss of residents from the District. Improvements to the employment and business economies will also improve the local and regional tax base. Traffic volumes on local roads and highways will increase with proposed Rainy River Project activities during construction and to a lesser extent during operations and decommissioning. There is also the requirement to re-align Highway 600 and to provide alternate access to Marr Road. The expected traffic changes are within the design capacities of the roads affected.

 

20.9.9 Human Health

Human health can be potentially affected by air and sound emissions and by treated effluents discharged to surface waters, or seepage into groundwater. No such effect is expected as the Rainy River Project will comply with applicable criteria for emissions that are dominantly health-based.

 

20.9.10 Cultural Heritage Resources

Construction of the Rainy River Project might affect archaeological sites through the disturbance and/or removal of soils during construction and/or operation that can potentially contain the remains of archaeological sites. Proposed Rainy River Project facilities are expected to overprint a number of cultural heritage resource sites pending final site design during detailed engineering. Avoidance has been possible for several other archaeological sites identified but is not expected to be practical for the remainder.

 

 

20-38


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The Rainy River Project might also affect late 19th and early 20th century built heritage features. Rainy River Resources has committed to undertaking a mitigation program consisting of an illustrated history of the study area.

 

20.10 Reclamation Approach

Closure of the Rainy River Project site will be governed by the Ontario Mining Act and its associated Regulations and Codes. The Act requires that a Closure Plan be filed for any mining project before the project is undertaken, and that financial assurance be provided before any substantive development takes place to ensure that funds are in place to carry out the Closure Plan.

The objective of closure is to reclaim the mine site area to a naturalized and productive condition when mining ceases. The terms naturalized and productive are interpreted to mean a reclaimed site without infrastructure (unless otherwise negotiated) that, while different from the existing environment, is capable of supporting plant, wildlife and fish communities; and other applicable land uses. A draft Closure Plan is currently in preparation that is anticipated to be issued for government and Aboriginal comment during the first quarter of 2014.

It is expected that the primary phase of active reclamation at the Rainy River Project will take approximately two (2) years after operations cease. Thereafter, the site will be held in care and maintenance until the open pit is fully flooded. Once the pit is flooded, an additional shorter period of active reclamation will occur to remove associated remaining project elements. Environmental monitoring and potentially effluent quality management will occur in accordance with the Closure Plan prepared and filed pursuant to the Mining Act.

 

20.10.1 Open Pit and Underground Mine

Both the open pit and underground mine will flood naturally once dewatering activities cease. The open pit will be flooded to create a pit lake either passively through natural groundwater entry and precipitation inputs; or by active enhanced flooding of the open pit, using water pumped from an alternate source such as seasonal fresh water inputs. Flooding of the underground and open pit mine to surface is expected to take approximately 72 years using a moderately enhanced, flooding process. Consultation is proposed to determine the preferred flooding approach.

 

 

20-39


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Other measures to be taken to reclaim the open pit progressively or at closure may, or are likely to include:

 

 

Remove all infrastructure and equipment within the open pit and underground mine and clean up any petroleum hydrocarbons and/or explosives;

 

 

Shape and revegetate overburden pit slopes to a stable condition and to facilitate riparian habitats along the pit lake margins;

 

 

Block the entrance to the open pit and install a boulder or traditional security fence around the pit perimeter during or following active mining operations to ensure safety while the pit is flooding; and

 

 

Develop a spillway, if needed, to allow the pit lake to eventually overflow into the Pinewood River.

Entrances to the underground mine will be blocked to ensure long term security.

 

20.10.2 Stockpiles

Progressive rehabilitation of mine rock and overburden stockpiles will be undertaken, where practical, once the maximum height of each stockpile has been reached and/or as each lift is completed, to minimize the amount of reclamation required at closure. All stockpiles will be re-shaped as necessary and stabilized if needed.

The overburden stockpile will be revegetated progressively, with final stabilization and revegetation occurring after overburden has been extracted for site reclamation.

The west mine rock stockpile will contain non-potentially acid generating mine rock. Acid rock drainage / metal leaching is not of concern, so Rainy River Resources proposes to cover the stockpile with a layer of overburden and revegetate.

 

 

20-40


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

A multi-layered cover is proposed for the east mine rock stockpile as it will contain potentially acid generating mine rock. Encapsulation is proposed with a long term goal of controlling acid rock drainage. The side slopes will be covered progressively by a layer of compacted clay till to shed water, topped by a layer of non-potentially acid generating mine rock to consume oxygen, another layer of compacted clay till, followed by a layer of clay till and a growth media to enable revegetation. The flat portion of the stockpile will have a similar cover, but will not include the lowest layer of clay till. Should a temporarily closure or early closure occur, the cover will be completed to ensure acid rock drainage / metal leaching is properly managed.

Rainy River Resources proposed to process all stockpiled ore during operation, therefore reclamation of the low grade or run of mine (high grade) stockpile should not be required. If necessary, the stockpiles will likely be reclaimed in a manner similar to that proposed for the east mine rock stockpile at early or final closure.

Revegetation will occur through seeding, hydroseeding and/or hand planting of tree seedlings as appropriate, to expedite the colonization by indigenous plant species. Investigations will be completed to determine the feasibility of establishing specific wildlife habitats, such as those that might be used by Species at Risk, following closure. The investigations will also determine whether any amendments are required to the native till (overburden) to improve its suitability to provide a base for revegetation.

 

20.10.3 Tailings Management Area

The principal concerns associated with closure of the tailings management area are long term slope stability, erosion control, drainage, vegetation cover and appearance, as well as prevention of acid rock drainage and metals leaching from the tailings. The tailings management area development plan currently provides for a water and overburden cover at closure to restrict oxygen contact with the tailings surface. Overflow spillway(s) will be developed or deepened to ensure efficient drainage of excess runoff.

 

20.10.4 Aggregate Sources

If quarries or pits are developed as aggregate sources during the construction and operation phases, these will be reclaimed according to provincial approvals and standards, which may include natural flooding to create pond features.

 

 

20-41


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

20.10.5 Buildings, Machinery, Equipment and Infrastructure

A dedicated onsite demolition landfill is expected to be developed for the disposal of non-hazardous demolition wastes (such as concrete, steel, wallboard and other inert materials) generated by mine closure. It is expected that this demolition landfill will be developed within the east mine rock stockpile.

Salvageable machinery, equipment and other materials will be dismantled and taken off site for sale or re-use if economically feasible, or cleaned of oil and grease where appropriate and deposited within the onsite demolition landfill. Gearboxes or other equipment containing hydrocarbons that cannot be readily cleaned will be removed from equipment and machinery and trucked offsite for disposal at a licensed facility.

All above grade concrete structures will be broken up and demolished to near grade elevation. Concrete structures and below grade facilities (if any) will be infilled if needed. Affected areas will be contoured, covered with overburden as needed and revegetated.

 

20.10.6 Petroleum Products, Chemicals and Explosives

All petroleum products and chemicals will ultimately be removed from the site. Empty tanks will be sold as scrap, re-used off site, or cleaned to remove any residual fuel / chemicals and deposited within the demolition landfill.

An environmental site investigation will be conducted at the end of operations or early in the closure phase. Soil found to exceed acceptable criteria will be remediated onsite or transported off site to an approved disposal facility.

Any explosives will be depleted towards the end of operations. Any remaining explosives will be either detonated on site or hauled offsite by an authorized transportation company.

 

20.10.7 Roads, Pipelines and Power Distribution

Site roads may be scarified when no longer needed to support final reclamation, long term site management and environmental monitoring, assuming they are not required to support some other development on the site. Safety berms, if any, along the perimeter of haul roads will be re-shaped to near grade. Culverts will be removed and roads will be breached at the culvert locations on site to allow for natural drainage.

 

 

20-42


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Pipelines or pipeline sections will either be sealed and left in place; or purged if needed, dismantled and disposed of in the onsite demolition landfill.

Onsite power distribution lines and associated materials that have no salvage value will be dismantled and deposited in the demolition landfill. Other power equipment and materials will be taken off site for sale or re-use.

 

20.10.8 Site Drainage and Water Structures

The new alignment for the West Creek will naturalize over the life of the mine and will become the permanent creek channel, unless it is determined during closure planning that directing West Creek through part of its original route and on into the open pit is preferred.

The Clark Creek diversion will remain in place to continue to divert drainage away from the east mine rock stockpile.

The pattern of general site drainage will remain in place at closure, with the exception of the removal of culverts at water crossings during site road reclamation activities. Water intake structure(s) at the Pinewood River (or other waterbodies if any) will be reclaimed by removing any structures and mechanical components for disposal in the demolition landfill.

 

20.10.9 Waste Management

At the end of reclamation activities, the onsite closure landfill will be capped and revegetated in a manner consistent with the remainder of the site and environmental approval requirements.

 

20.10.10 Offsite Facilities

Highway 600 will remain in its re-aligned form and will continue to provide local access. The re-aligned gravel-surfaced Highway 600 water crossing will remain in place after mine closure.

The East Access Road constructed to support the Rainy River Project development is expected to remain in place.

 

 

20-43


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

It is expected that the 230 kV transmission line constructed to support the Rainy River Project operations will not be required by other local users and will be removed at closure. The option remains to transfer the transmission line to another owner should demand exist at Rainy River Project closure. Assuming reclamation is required, electrical equipment will be removed and recycled / re-used or disposed of. Poles will be removed or cut at grade, and either re-used or disposed of.

Closure costs have been prepared based on this approach and are included in the sustaining capital and financial analysis sections of this study (Chapter 21 and 22, respectively).

 

 

20-44


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

21. CAPITAL AND OPERATING COSTS

 

21.1 Capital Costs – Introduction

The capital and operating costs are based on the construction of a greenfield open pit/underground mine and process plant facility having a nominal daily treatment capacity of 21,000 tpd. The capital cost estimate related to the open pit mine, concentrator and site infrastructure was developed by BBA and Merit Consultants. AMC Consultants estimated the costs related to the underground mining operation which were included only in the sustaining capital costs. AMEC provided the tailings and water management area material quantities, the water treatment plant costs and site closure costs. The site closure costs and water treatment costs are included only in the sustaining capital costs. BBA and Merit Consultants consolidated the cost information to determine the overall Project capital costs.

The overall capital developed in the Feasibility Study meet the American Association of Cost Engineers (“AACE”) Class 3 requirement of an accuracy range between -10% and +15% of the final Project cost. The capital cost estimate of this Feasibility Study forms the basis for overall project budget authorization and funding. It is the “Control Estimate” against which subsequent phases of the Project will be compared.

 

21.1.1 Assumptions

The capital cost estimate provides a common basis for classifying all types of facilities and processes and primarily classifies cost estimates based on a measurable degree of engineering completion and prices obtained from vendors. In addition, the capital cost estimate was conducted on the following assumptions:

 

 

Reflects general accepted practices in the cost engineering profession;

 

 

Assumes that contracts will be awarded to reputable contractors on a lump sum basis (the contractor is required to submit a total and global price instead of bidding on individual items) and an open shop environment for every trade except heavy earthwork and mining pre-development;

 

 

Heavy earthwork will be awarded to reputable contractors on a unit cost basis;

 

 

Open pit mine pre-development will be executed by New Gold;

 

 

All costs are expressed in constant Q4 2013 Canadian dollars (“CAD”);

 

 

21-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

Exchange rate to the US Dollar (“USD”) is 0.95 to CAD $1.00;

 

 

Exchange rate to the EURO is 0.695 to CAD $1.00;

 

 

Taxes are not included;

 

 

The use of overburden and NPAG waste rock generated during the mine pre-stripping will be maximized for sourcing backfill material;

 

 

Other required backfill materials will be available from the nearby borrow pit owned by New Gold;

 

 

Bulk earthworks and haulage road construction will be performed by crews assigned to the mine pre-stripping operation;

 

 

Soil conditions will not require special foundation designs such as piling other than at the reclaim tunnel exit (as established from geotechnical data and from foundation design recommendations by AMEC);

 

 

Costs will be capitalized until commercial production is achieved (30 days at an average of 60% of production capacity);

 

 

All excavated material will be disposed on-site; and

 

 

The Project will adhere to the schedule in Chapter 24.

 

21.1.2 Exclusions

The following items are not included in the capital cost estimate:

 

 

Inflation and escalation;

 

 

Costs associated with hedging against currency fluctuations;

 

 

All taxes, duties and levies;

 

 

Working capital; and

 

 

Project financing costs including interest expense, fees, commissions, etc.

 

21.2 Capital Cost Summary

The pre-production (initial) capital cost and contingency for the Project is estimated to be $931.4M, including a $73.3M contingency allocation. Total sustaining capital costs are estimated to be $366.3M. Working capital requirements, to cover the period between commission and first metal sales, and project closure bonding requirements are assumed to be covered by New Gold’s current operations and are not included in the cost estimate. Land acquisition, permitting,

 

 

21-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

licensing and project financing costs are included in the Owner’s Costs. The Project capital cost (pre-production and sustaining) summary is outlined in Table 21-1. The capital cost breakdown descriptions are outlined in the subsequent sections.

Table 21-1: Project Capital Cost Summary

 

Area Description

   Pre-Production
Capital Costs ($M)
     Sustaining Capital
Costs ($M)
 

Overhead Power Line

     10.2      

Highway 600 Realignment

     12.4      

Open Pit Overburden Pre-Stripping

     39.3      

Open Pit Waste Removal and Ore Stockpiling

     45.1      

Open Pit Mining Equipment

     85.1         74.1   

Mobile Equipment3

        5.2   

Underground Mine Development Capital1

        110.5   

Underground Mine Sustaining Capital2

        138.5   

Site Development

     117.2         4.0   

Process Facilities

     312.8      

Tailings, Water Management and Treatment

     50.0         40.5   

Fish Habitat Compensation Costs

        2.0   

Chapple Township Compensation

        2.1   

Equipment Salvage Value

        (60.5

Reclamation and Closure Costs

        49.9   
  

 

 

    

Direct Costs Subtotal

     672.1      
  

 

 

    

Indirect Costs (excluding Owner’s Cost)

     106.3      

Owner’s Cost

     79.7      
  

 

 

    

Indirect Costs Subtotal

     186.0      
  

 

 

    

Contingency

     73.3      
  

 

 

    

 

 

 

Total Capital

     931.4         366.3   
  

 

 

    

 

 

 

 

1. 

Funded through internal cash flows, this is the capital required in the development phase of the underground mine, consisting of equipment and infrastructure, as well as vertical and horizontal development.

2. 

Funded through internal cash flows, this is the sustaining capital required for the underground mine, consisting of equipment and infrastructure, as well as vertical and horizontal development.

3. 

Mobile equipment includes equipment for both the process plant and surface operations.

 

 

21-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

21.3 Basis of Estimate

The capital pre-production direct costs can also be divided into the following disciplines: mining, civil/earthworks, concrete, structural, architectural, mechanical, piping, electrical automation / communications and labour. Each discipline is calculated using multiple rates, costs and units for each type of concrete, pipe, equipment, labour, etc. The total costs by discipline are shown in Table 21-2.

Table 21-2: Direct Costs by Discipline

 

Area Description

   Pre-Production
Capital Costs ($M)
 

Mining

     169.5   

Civil/Earthworks

     83.3   

Concrete

     67.6   

Structural

     42.1   

Architectural

     18.1   

Mechanical

     172.7   

Piping

     50.0   

Electrical

     52.2   

Automation/Telecommunication

     16.5   
  

 

 

 

Total Cost

     672.1   
  

 

 

 

Mining

Mining costs include overburden pre-stripping, open pit waste removal, ore stockpiling and mining equipment and total $169.5M. All mining equipment cost estimates are based on a mining fleet owned, operated and maintained by New Gold. Further detail is provided in Sections 21.4.4, 21.4.5 and 21.4.6.

Civil/Earthworks

Earthwork quantities were estimated from drawings, topographical data and geotechnical information. Budgetary quotations were obtained from five (5) different potential contractors. After completion of a commercial analysis, a quote was selected as the basis for this estimate. The total civil/earthworks direct costs is $83.3M. Various total quantities are presented in Table 21-3.

 

 

21-4


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 21-3: Civil/Earthwork Quantities

 

Quantities

       Units       Value  

Site Preparation (Clearing & Grubbing)

   m3     10,898,000   

Site Stripping

   m3     542,000   

Excavation

   m3     1,316,000   

Backfill

   m3     4,111,000   

Slope Protections

   m3     268,000   

Geotextile Liners

   m2     259,000   

Concrete

Designs from basic engineering were used to develop the concrete and embedded steel quantities. Unit rates, including formwork and rebar, were estimated from similar projects. The total direct cost for concrete works is $67.6M. Various total quantities are presented in Table 21-4.

Table 21-4: Concrete Quantities

 

Quantities

       Units       Value  

Concrete

   m3     40,700   

Embedded Metals

   kg     48,122   

Anchor Bolts

   kg     147,321   

Damproofing, Insulation

   m2     3,546   

Structural

Preliminary design sketches were used to develop the structural steel quantities. Material was priced from the current steel market values and benchmarked against current projects. The total direct costs for structural and steel works is $42.1M. Various total quantities are presented in Table 21-5.

Table 21-5: Structural Quantities

 

Quantities

       Units       Value  

Steel

   t     5,603   

Decking

   m2     19,051   

Handrails

   m     4,090   

Structural Erection

   hours     167,990   

 

 

21-5


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Architectural

Siding and roofing quantities were estimated from the General Arrangement (“GA”) drawings. Pricing was based on Merit Consultants’ references on recent data from similar projects. The total direct cost for architectural works is $18.1M. Various total quantities are presented in Table 21-6.

Table 21-6: Architectural Quantities

 

Quantities

       Units       Value  

Roofing

   m2     11,187   

Siding

   m2     21,496   

Masonry Block Walls

   m2     3,743   

Architectural Erection

   hours     62,568   

Mechanical

Full specifications were issued and firm price quotations were obtained from vendors for the following major equipment: gyratory crusher, apron feeders, SAG mill, ball mill, scalping screen, pebble crusher. For process and mechanical equipment packages, equipment datasheets and summary specifications were prepared and budget pricing was obtained from vendors. For packages of low monetary value, pricing was obtained from BBA’s recent project database. A detailed equipment list was developed with equipment sizes, capacities, motor power, etc.

A platework list was developed with sizing, weights, and surface areas including lining requirements. A heating, ventilation and air conditioning (“HVAC”) equipment list was developed and fire protection and HVAC material take-offs (“MTOs”) were taken from general arrangement drawings. The total mechanical supply and installation direct cost is $172.7M, total mechanical installation hours are 253,612 and the total equipment pre-purchase cost is $125.4M.

Piping

Complete piping diagrams were prepared. Pipe lining requirements were also categorized. Lengths for each line shown on the piping diagrams were determined from layout drawings. Material pricing for carbon steel and rubber-lined piping was obtained from supplier proposals. The total direct cost for piping works is $50M. Various quantities are shown in Table 21-7.

 

 

21-6


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 21-7: Piping Quantities

 

Quantities

       Units        Value  

Carbon Steel (rubber lined)

   m      1,899   

Carbon Steel (standard)

   m      24,224   

Ductile Iron

   m      2,158   

Fiberglass Reinforced Plastic

   m      19   

High Density Polyethylene

   m      42,289   

Polyvinylchloride

   m      2,146   

Stainless Steel

   m      4,396   

Piping Insulation

   m      19,222   

Total Small Bore Piping

   m      21,895   

Total Large Bore Piping

   m      55,236   

Total Piping and Insulation Installed

   hours      260,100   

Electrical

An equipment list, including capacities and sizing, was developed from the single line diagrams. MTO for electrical bulk quantities were derived from cable schedules and runs, including cable tray routing layouts. Datasheets were prepared for all major electrical equipment and components and budget pricing was obtained from vendors. For less costly electrical equipment, BBA’s historical cost data was used. The total direct cost for electrical works is $52.2M. Various quantities are shown in Table 21-8.

Table 21-8: Electrical Quantities

 

Quantities

       Units        Value  

Cable

   m      108,380   

Cable Trays

   m      5,877   

Total Electrical Installation

   hours      103,539   

Automation/Telecommunications

A detailed instrumentation list was developed from the process flow diagrams. An allowance for communications for the process buildings is included in the capital cost estimate. The total direct cost for Automation/Telecommunications is $16.5M and total installation hours are 52,126.

 

 

21-7


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Construction Labour

Each discipline mentioned above includes an amalgamation of costs and rates for different types of labour. The total labour of 2.1 million hours was estimated and represents 42% of the total direct costs.

All estimated costs for labour are based on ten (10) hours per day, seven (7) days per week, for a total of 70 hours worked per week. Employee rotations of three (3) weeks of work and one (1) week of rest is expected. There is no allowance for evening shifts except for the mine pre-development which will be executed by New Gold’s mining crews.

Separate methodologies for bulk earthwork and other trades were used to determine the hourly construction crew rates used in this estimate.

For bulk earthworks, budgetary quotations were obtained from qualified contractors. These quotes were developed by the contractors from MTOs generated during the Feasibility Study. After a commercial analysis was conducted, a quote was selected as the pricing basis for the estimate. The crew rate for every work area and work element, including the cost of operation for heavy machinery, was calculated based on the selected quote.

For the other trades, a general contractor was contacted to update the single combined crew rate based on non-building trades union that was developed in the 2013 Feasibility Study. In order to take into account potential shortages of qualified non-building trade tradesmen, a single building trade average rate was developed and combined with the non-building trade rate in a ratio of 80% : 20% (non-building trade, non-union workers : building trade, unions workers).

The average crew rates are built from four (4) components as follows:

 

1. The direct cost is calculated from the rates of direct labour, such as: labourers, apprentices, journeymen and lead-hands, foremen, general foremen, and superintendents;

 

2. The indirect cost is calculated from the rates of supervisors, i.e., the contractor’s project manager, engineers, quality control crew, planners, and secretaries;

 

3. Living Out Allowance estimated at $13.75 per man-hour;

 

4. Contractor construction equipment costs are estimated at 15% of the total crew rate for mechanical and piping trades, and at 12% for other trades.

 

 

21-8


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

For non-building trade union workers, the direct and indirect cost components are calculated on an assumption of 70 hours per week, considering 40 hours at regular rate and 30 hours applying an overtime multiplier of 1.5 to the regular rate. General foremen and superintendent rates are calculated based on a 73.5 hour week, with 40 hours at regular rate and 33.5 hours at overtime rate (1.5 times the regular rate). Both the direct and indirect costs components include provisions for small tools, insurance, overhead, and profit and travel turnaround costs. The contractor’s direct and indirect personnel are estimated to use respectively 73% and 27% of the construction effort, yielding a rate of $129/hour.

For building trade union workers, the direct and indirect cost components are calculated on the same rotation of 73.5 hours per week and 40 hours at regular rate; however, an overtime multiplier of 2 is applied to the remaining 33.5 hours. Again, this includes provisions for small tools, insurance, overhead and profit, travel allowance, and retention premium, yielding a rate of $149/hour.

Both hourly labour rates were combined in the 80% : 20% ratio (non-building trade, non-union workers: building trade, unions workers) to obtain an average rate of $132/hour.

Productivity

Labour productivity is often the greatest risk factor, followed closely by uncertainties in cost and scheduling. The two (2) most important measures of labour productivity are:

 

1. The effectiveness with which labour is used in the construction process; and

 

2. The relative efficiency of labour at a given time and place.

 

 

21-9


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Important factors affecting productivity on a construction site (such as site location, labour turnover, health and safety consideration, weather conditions, supervision, etc.) were considered to calculate the labour productivity factors shown in Table 21-9:

Table 21-9: Labour Productivity Factors

 

Calculated Productivity Loss Factor

 

Trade

   Factor  

Earthwork

     1.00   

Concrete

     1.15   

Structural Steel

     1.20   

Architectural

     1.25   

Mechanical

     1.12   

Piping

     1.14   

Electrical

     1.45   

Automation/Telecom

     1.45   

The productivity loss factors are applied on the installation direct labour hours and evaluated from the following first principles:

 

 

Earthworks is based on multiple contractor quotes including all the appropriate factors;

 

 

Concrete is based on contractor quotes including all appropriate factors;

 

 

Structural steel and architectural are based on BBA’s and Merit’s experience for similar projects;

 

 

Mechanical and piping are based on highly skilled trades personnel and most works to be performed indoors in enclosed areas and buildings; and

 

 

Electrical and automation are based on National Electrical Contractors Association (“NECA”) Class 4 electrical labour installation manhours with high voltage works outdoors in elevated work situations.

Winter conditions expected between December 1st and March 31st were taken into consideration within the aforementioned productivity factors and were also considered in the first year for civil, concrete and steel works, as indicated in the Project Execution Schedule presented in Chapter 24 of this Study.

 

 

21-10


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

21.4 Pre-Production Capital Costs

 

21.4.1 Introduction

The pre-production costs total $931M, with $672M in direct costs, $186M in indirect costs and $73M in contingency. The pre-production costs represent the expected expenditure incurred during the pre-production period (2015 and 2016).

 

21.4.2 Overhead Power Line

The cost of the high voltage power line from the local power grid was estimated from budgetary quotations reviewed by SanZoe Consulting and is included in the capital cost estimate. The plant will be fed through a new 230 kV power line, 18 km long and will be connected to an existing 230 kV line on Hydro One’s provincial grid. A conceptual line routing has been established and included in the Environmental permitting documentation. The right-of-way of this route falls within the claims owned by New Gold. A more precise routing will be achieved during the design phase of the Turnkey contract that will be awarded for the design and building of the power line. The estimated total is $10.2M CAD including the contractor cost, commissioning, connection cost recovery agreement and other consulting fees and expenses. The total is exclusive of property costs and permits that have been included in the Owner’s Costs. The substation, metering, metering communications and commissioning of metering communications or protection and control systems are excluded from the total and part of the substation cost that is included in the site development total.

 

21.4.3 Highway 600 Re-alignment

TBT Engineering provided engineering input for the Highway 600 realignment to meet the Ministry of Transportation requirements. Approximately 4.9 km of existing local roads require upgrading and a 6.3 km section of the highway needs to be rebuilt as it passes through the Project site. The cost of the Highway 600 realignment was estimated by Merit based on bulk earthwork quantities provided by TBT Engineering including, rock supply, backfill quantities, over 200,000m3 of excavated material and 0.3 km2 of clearing and grubbing. The estimated total is $12.4M and includes engineering, contract administration, clearing, grubbing, earth and rock excavation.

 

 

21-11


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

21.4.4 Open Pit Overburden Pre-Stripping, Waste Removal and Ore Stockpiling

The open pit mining pre-production costs for waste removal and ore stockpiling are estimated to be $45.1M and the pre-production costs for overburden pre-stripping are estimated to be $39.3M. The initial cost during the pre-production phase totals $84.4M. More specifically, the costs include:

 

 

Equipment operating costs;

 

 

Fuel costs;

 

 

Blasting costs, including the supplier service and maintenance fees;

 

 

Hourly labour (e.g. mining fleet operators) and salaried staff costs for production, maintenance, engineering and the geology department; and

 

 

Other costs include dewatering, pre-split, consultant fees, software licence, etc.

 

21.4.5 Open Pit Mining Equipment

The open pit equipment pre-production capital cost is $85.1M as presented in Table 21-10. The total cost includes equipment pre-purchased in 2014, 2015 and 2016 and a 10% down payment of pre-purchased equipment to be delivered in 2017.

 

 

21-12


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 21-10: Open Pit Mine Equipment Capital Cost

 

     Pre-Production Period

Equipment

   2015    2016    Total

Haul Truck Fleet

        

Haul Truck

   6    1    7

Shovel Fleet

        

Hydraulic Shovel (Diesel)

   2       2

Drill Fleet

        

Blastholes Drill

   1    1    2

DTH Drill (Reverse Circulation Sample, Pre-Split)

   2       2

Support Fleet

        

Wheel Loader

   1       1

Motor Grader

   1    1    2

Track-Dozer

   3    1    4

Track-Dozer (dyke construction and site rehabilitation)

   1       1

Auxiliary Fleet

        

Water Truck

   1       1

Water Truck

   1       1

Fuel/Lube Truck

   2       2

Boom Truck

   1       1

Wheel Loader (Used)

   1       1

Tow Haul Truck (Used)

   1       1

Hydraulic Crane, truck-mounted

   1       1

Dewatering Pump

   1    1    2

Mobile Pump

   2       2

Service Truck

   1       1

Tire Changer, truck-mounted

   1       1

Mini Bus

   1       1

Pick-up Truck Crew Cab

   6    6    12

Stemming Loader

   1       1

Aggregate Plan

   1       1

Lighting Tower

   4       4

Other Equipment

        

Geotech Monitoring Equipment

   1       1

Dispatch system

   1       1

Total Open Pit Mine Equipment Costs

         $85.1 M

 

 

21-13


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Mining equipment quantities and costs have been developed based on the mine plan presented in Chapter 16. Mining equipment costs are based on vendor quotes requested during this Feasibility Study and from BBA’s recently updated database of vendor pricing. Contrary to the 2013 Feasibility Study’s approach of lease-to-own, this updated Feasibility Study has assumed that New Gold will not finance the equipment purchases.

The capital cost for the open pit mining equipment is calculated on the basis of a 10% down payment on award and the balance is paid on delivery. Payments incurred during pre-production Years -2 and -1 are included in the pre-production capital cost.

For this Study, it is assumed that mine maintenance and service facilities will be built during the pre-production period. These installations will include a truck fueling station, a permanent truck wash station with mud settling basins and a permanent truck shop facility for mine equipment maintenance consisting of a six (6) bay garage and shops.

 

21.4.6 Site Development and Process Facilities

Site development costs and process facilities costs and presented in Table 21-11.

Table 21-11: Site Development and Process Facilities Direct Costs

 

Area Description

   Pre-Production
Capital Costs ($M)
 

Site Utilities – Water

     24.0   

Site Utilities – Power

     28.5   

Site Infrastructure and Facilities

     64.7   
  

 

 

 

Site Development Total

     117.2   
  

 

 

 

Process Facilities – Crushing

     68.3   

Process Facilities – Grinding

     104.2   

Process Facilities – Gravity, Thickening, Leaching, CIP

     119.6   

Process Facilities – Refining

     48.1   

Process Facilities – Reagents

     8.2   

Process Facilities – Other

     4.4   
  

 

 

 

Process Facilities Total

     312.8   
  

 

 

 

 

 

21-14


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Site development costs total $117.2M and include expenses for site utilities such as fresh and fire water systems, mine rock pond, stockpile pond and sedimentation ponds, control room, unit substation and distribution, etc. Site development also includes costs for site infrastructure and facilities such as administration buildings, laboratories, shops and other various buildings. Site development costs include construction for 6.7 km of the East Access Road. Infrastructure has been estimated by BBA based on the developed site plan.

Process facilities costs total $312.8M and include equipment costs, reagent storage costs, common mechanical services and electrical unit substation costs.

The design of the crusher area, the crushed ore stockpile area and the concentrator area is based on BBA’s basic engineering work undertaken between June 2013 and October 2013. The site plan and GA drawings developed during this period have been used to estimate the MTOs for all building materials and earthwork requirements.

Equipment costs have been estimated using budgetary proposals obtained from vendors for most process equipment. For a number of the major process equipment, firm price quotations were obtained during the basic engineering and incorporated into the estimate. For the remaining process and mechanical equipment packages, equipment datasheets and summary specifications were prepared and budget pricing was obtained from vendors.

Information obtained during the interim basic engineering work has been integrated into a detailed equipment list with equipment sizes, capacities, motor power, etc.

 

21.4.7 Tailings, Water Management and Treatment

The total cost for the tailings, water management and water treatment is $50M. The pre-production costs include the Tailings Management Area, Water Management Pond, Discharge Pond, constructed wetland, Teeple Road Dam construction, the tailings slurry pipeline and the tailings water reclaim system (including the water discharge line from the Water Management Pond to Pinewood river). The West Creek Dam, Mine Rock Pond, Stockpile Pond, collection ponds, sedimentation ponds and Clark Creek Diversion are captured in the Site Development Costs in Section 21.4.6.

 

 

21-15


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

21.4.8 Indirect Costs

Indirect Costs were estimated jointly by BBA and New Gold and are divided into several categories as shown in Table 21-12.

Table 21-12: Indirect Costs

 

Indirect Costs

   Millions ($ M)  

Engineering Procurement and Construction Management (“EPCM”)

     50.8   

Pre-Operation Verification (“POV”)

     3.0   

Temporary Construction Facilities & Services

     10.3   

Health, Safety, Security

     3.0   

External Consultants & Professional Services (Third Parties)

     10.0   

Start-up and Commissioning Services

     2.6   

Freight & Logistics, Off-site Warehousing & Handling

     13.8   

Spares Parts

     10.1   

First Fill

     2.9   

Owner’s Cost

     79.7   
  

 

 

 

Total Indirect Costs

     186.2   
  

 

 

 

Engineering Procurement and Construction Management (“EPCM”)

EPCM service costs were developed based on BBA’s reference data for projects of similar size and schedule. Costs were established based on the number of required hours per task on a defined scope of deliverables and charged using BBA’s hourly rate per required specialty. The total EPCM cost is $50.8M.

The overall percentage ratio on Directs (excluding mining costs) for EPCM costs are as follows:

 

 

Engineering 4% of direct costs;

 

 

Project Management 1.25% of direct costs;

 

 

Procurement 0.4% of direct costs; and

 

 

Construction Management 4.5% of direct costs.

 

 

21-16


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Pre-Operation Verification (“POV”)

POV (pre-commissioning) costs are included in the estimate for the preparation of the detailed commissioning and process plant start-up procedures.

These costs include the following categories:

 

 

POV manager salary;

 

 

Preparation of commissioning plan;

 

 

Electrical pre-commissioning;

 

 

Senior minerals engineer salary;

 

 

Senior mechanical engineer salary;

 

 

Construction and Pre-commissioning support (programmable logic controller (“PLC”) programmers);

 

 

Commissioning and Start-up support; and

 

 

Travel and living expenses.

The total POV cost is $3.0M.

Temporary Construction Facilities & Services

Construction operation costs include the construction and maintenance of temporary worker facilities required during the Project’s construction period. An itemized list with budget allowances was developed by BBA which includes the costs for site distribution of temporary construction power, access roads to the temporary construction facilities, a telecommunication tower and general communications, and other related equipment. A monthly fee of $15,000 over a period of 24 months was included for the construction management team requirements to connect to the Owner’s network (phone, internet, etc.).

Construction workers housing on site was excluded from the capital cost estimate. A provision for Living Out Allowance (“LOA”) and travel costs of $13.75/hour were included instead as part of the labour rate for all trades.

The total cost of temporary construction facilities and services cost is $10.3M.

 

 

21-17


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

External Consultants & Professional Services (Third Parties)

Cost of sub-consultants and other third parties were estimated based on projects of similar size and are included in the Capital Cost Estimate. Third party costs amount to $10M and can be divided into external consultants and professional services.

Third party costs for external consultants were broken down as follows:

 

 

Outside engineering consultants (undefined): $758,500;

 

 

Engineering and quality surveillance for the Highway 600 Realignment (based on a cost estimate provided by TBT Engineering): $1.3M;

 

 

Engineering and quality surveillance for the East Access Road construction: (based on a cost estimate provided by TBT Engineering): $536 K; and

 

 

Engineering services for water management/geotechnical (based on a cost estimate provided by AMEC): $5.4M.

Third party costs for professional services were broken down as follows:

 

 

Labour relation management assistance (based on a provision of 200 hours): $37,000;

 

 

Water treatment testing services (provision): $50,000; and

 

 

Site surveying services (based on 176 person-weeks of site surveying team): $1.7M.

Start-up and Commissioning Services

Start-up and commissioning costs were estimated based on projects of similar size and include specialist services required to assist New Gold in the final acceptance of the work and plant start-up. Costs also include an allocation of construction manpower resources for miscellaneous commissioning adjustments. The total cost of start-up and commissioning services is $2.6M.

Freight and Logistics, Off-Site Warehousing and Handling

A freight forwarder provided a quote for equipment freight costs. The quote was approximately 6.75% of the equipment purchase cost. It was assumed that most major mechanical and electrical equipment will be stored in an off-site location within approximately a day of travel from the storage area to the site. The total cost of freight and logistics, off-site warehousing and material handling is $13.8M.

 

 

21-18


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Spare Parts

Costs related to construction and commissioning spare parts were estimated at $10.1M and broken down into the following categories:

 

 

Capital spares based on a detailed spare parts list: $6.6M (5.4% of total equipment purchase cost);

 

 

2-year operating spares $2.2M (1.8% of total equipment purchase cost); and

 

 

Mining fleet spare parts $1.3M (1% of total equipment purchase cost).

First Fill

A detailed list and costs for grinding media, chemicals and lubricants is included in the capital cost estimate. First fills amount to a total cost of $2.9M.

 

21.4.9 Owner’s Costs

New Gold prepared an itemized list with budget allowances for the Owner’s Costs. Owner’s Costs total $79.7M and include items such as, but not limited to: administration and management personnel, project management team personnel, housing, construction insurance, purchasing costs, environmental expenses and training. Plant operating and maintenance personnel hired during the pre-production period were also included in Owner’s costs. Operating costs are capitalized within the Owner’s costs until commercial production is achieved, which is defined as 30 days at an average of 60% production capacity.

 

21.4.10 Contingency

Contingency provides an allowance for undeveloped details within the scope of work. It does not account for labour disruptions, weather-related impediments, changes to the Project’s scope, price escalation or currency fluctuations. The value of the contingency, $73.3M, is expected to be spent during the life of the project.

Contingency calculations on discipline work categories and labour totals was performed by the Project’s estimator. The Project’s estimator used knowledge of the actual project engineering completion to date serving as the basis to establish the contingency percentages, following established industry guidelines for an AACE Class 3 estimate. The outcome of the contingency calculation yields an overall percentage of 12% on the total direct and indirect costs. No

 

 

21-19


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

contingency was calculated on the mining and Owner’s costs as these have contingencies built into their totals. Typical contingency for AACE Class 3 estimates range between 10% and 15% of direct and indirect costs, depending on engineering completion.

Material and equipment costs were meticulously developed and provide a high level of confidence in the estimate. Installation productivities were based on past experience and input from contractors. The quantities provided by the engineers are in the expected range for a plant of this size and capacity.

 

21.5 Sustaining Capital Costs

 

21.5.1 Introduction

The total sustaining capital cost is $366M. This is the estimated expense required to maintain operations throughout the production life. Sustaining capital costs include open pit mining equipment, surface and process plant mobile equipment, underground mining and development costs, fencing, tailings and water management, compensation costs, reclamation and closure costs.

 

21.5.2 Open Pit Mine Equipment

Completion of payments in Year 1 (2017) and subsequent equipment purchases are considered to be a sustaining capital cost. A total sustaining cost of $74.1M is expected for open pit mining equipment. The total cost is inclusive of a 10% equipment down payment disbursed one year prior to utilization/commissioning in addition to the remaining payments.

 

 

21-20


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The sustaining open pit mining equipment are shown in Table 21-13:

Table 21-13: Sustaining Open Pit Mine Equipment

 

Sustaining Mining Equipment

   Production Period
     2017    2018    2019    2020    Total

Haul Truck Fleet

              

Haul Truck

   6    6    2    1    15

Shovel Fleet

              

Hydraulic Shovel (Electric)

   1             1

Drill Fleet

              

Blastholes Drill

   1             1

Support Fleet

              

Motor Grader

   1             1

Track-Dozer

   1             1

Wheel-Dozer

   1             1

Auxiliary Fleet

              

Compactor

   1             1

Boom Truck

   1             1

Wheel Loader (Used)

            1    1

Mobile Pump

   2             2

Mini Bus

   1             1

Stemming Loader

            1    1

Cable Reeler (Used)

   1             1

Lighting Tower

   2             2

Total Open Pit Mine Equipment Costs

               $74.1 M

 

21.5.3 Mobile Equipment

Sustaining capital for the process plant includes an allowance of $5.2M for mobile and shop equipment. Half the allowance will be spent in Year 5 and the balance will be spent in Year 10. The mobile equipment include items for surface work (general and administrative) and process plant such as aerial work platforms, fork lifts, pick-up trucks, service trucks, wheel loader and portable diesel welders.

 

 

21-21


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

21.5.4 Site Development

A provision of $4.0M for project security fencing is included and will be paid in $1.0M installments for the first four (4) years of the mine life (2017-2020).

 

21.5.5 Underground Mine

The capital costs for the underground mine were estimated based on first principle work-ups of all key mining activities using a detailed cost model developed by AMC. It is estimated that $249.1M in capital will be required to build and sustain the Underground mine. This covers all capital development, mobile and stationary equipment purchases and rebuilds, capitalized pre-production development, and contracted construction. Construction costs include the underground workshop, backfill station, ancillary installations, portal construction, primary electrical distribution, dewatering, and primary ventilation equipment. A contingency representing 8.4% of the total underground capital cost estimate is included.

The underground capital cost estimate is compiled based on the following key points:

 

 

Budget quotations for all major mobile and fixed plant equipment obtained from vendors;

 

 

All mine operating costs during the pre-production period (Years 2015 – 2016) are capitalized;

 

 

Drawings and construction cost estimates for the underground workshop, ancillary installations, portal construction, electrical, dewatering, and ventilation systems have been estimated by Nordmin Engineering;

 

 

Lateral capital development and capitalized operating expenses are developed from first principle work-ups;

 

 

Raise development will be executed by a contractor. Unit costs for these activities (including labour) were obtained from contractor budget quotes. Contractor quotes do not include fuel, power, support equipment, and waste removal. These are considered as Owner’s Costs and have been estimated from first principle work-ups;

 

 

All capital development and mine operating activities during the first three years (2015 –2017) are to be completed by a contract workforce. Labour rates in these years include contractor premiums. All lateral capital development and mine operating activities are to be completed by New Gold in the following years (2018 – 2026); and

 

 

21-22


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

The contingency of $20.9M represents 8.4% of the total underground capital cost estimate. This includes a 10% contingency on underground mining costs, 15% contingency on fixed plant purchases and fixed plant sustaining costs, 15% contingency on construction costs, and a 10% contingency on capital indirect costs. Considering the use of actual supplier quotes, no contingency is applied to any purchases of new mobile mining equipment and equipment rebuilds/replacements.

The total underground mining capital requirement is estimated to be $249.1M. Table 21-14 shows the annual capital requirements for the underground mine. The capital requirements are also shown by cost item in Table 21-15 :

Table 21-14: Life of Mine Underground Capital Costs

 

Year

   Annual Capital
Costs ($M)
 

2017

     50.7   

2018

     59.9   

2019

     30.7   

2020

     25.7   

2021

     11.9   

2022

     9.6   

2023

     13.1   

2024

     19.7   

2025

     16.1   

2026

     5.6   

2027

     2.8   

2028

     3.4   
  

 

 

 

Total

     249.1   
  

 

 

 

 

 

21-23


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 21-15 : Underground Capital Cost Breakdown

 

Item

   Total Cost ($M)      Percentage of Total  

Capital Development

     88.1         35.4

Equipment Purchases – Mobile and Fixed Plant

     47.5         19.1

Sustaining Capital – Plant & Equipment

     38.5         15.5

Capitalized Pre-Production Development

     31.1         12.5

Contracted Construction Costs

     13.0         5.2

Project Indirects

     9.7         3.9

Contingency

     20.9         8.4
  

 

 

    

 

 

 

Total

     249.1         100.0
  

 

 

    

 

 

 

Capital development includes the main decline, internal production ramps, ventilation raises, ventilation accesses, main pump station, development for the underground workshop, CAF plant and ancillary installations, i.e., explosive storage facilities, wash bay, and refuge stations. Capital development costs are summarized in Table 21-16.

Table 21-16: Underground Capital Development Costs

 

Year

   Lateral
Development ($M)
     Vertical
Raising ($M)
     Total ($M)  

2017

     3.9         0.0         3.9   

2018

     13.1         3.3         16.4   

2019

     12.0         4.1         16.1   

2020

     14.1         1.3         15.3   

2024

     6.5         0.1         6.7   

2022

     4.8         0.0         4.8   

2023

     5.3         0.1         5.4   

2024

     7.6         0.2         7.8   

2025

     7.9         0.3         8.2   

2026

     3.0         0.0         3.0   

2027

     0.5         0.0         0.5   

2028

     0.0         0.0         0.0   
  

 

 

    

 

 

    

 

 

 

Total

     78.7         9.5         88.1   
  

 

 

    

 

 

    

 

 

 

 

 

21-24


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The quantity and total cost of mobile equipment required for the underground mine are summarized in Table 21-17. Equipment purchases are scheduled based on the planned build-up of mine development and production rates. Rebuild and replacement schedules of mobile mine equipment are calculated based on annual equipment operating hours.

Table 21-17: Underground Equipment Purchases – Mobile

 

Equipment Type

   Quantity      Total Cost ($M)  

Drill Jumbo, 2-Boom

     3         3.70   

Drill Longhole

     2         2.18   

Haulage Truck, 45 Tonne

     6         8.95   

LHD, 7.2m3 with Remote

     4         5.84   

Bolter

     2         1.97   

Lubrication Service Truck

     2         1.26   

Boom Truck

     1         0.34   

Scissor Lift

     1         0.42   

Face Charger, Explosives

     2         0.84   

Pneumatic Cartridge Loader

     1         0.01   

Pneumatic ANFO Loader

     1         0.01   

Blasting Utility

     1         0.08   

Shotcrete Sprayer

     1         0.46   

Personnel Carrier

     3         0.24   

Transmixer

     1         0.48   

Motor Grader

     1         0.40   

Utility Platform Lift

     1         0.47   

Fork Lift

     1         0.11   
  

 

 

    

 

 

 

Total

     34         27.74   
  

 

 

    

 

 

 

The Underground mine fixed plant includes primary and secondary ventilation fans, heaters, emergency egress system, dewatering equipment (pumps, piping, couplings, brackets, and support), workshop, electrical infrastructure (power distribution systems, cabling, controls and instrumentation, utilities, switches, and compressors), backfill system (grout tank and pump, grizzly, and rock box), and mine rescue equipment. Fixed plant costs are summarized in Table 21-18. Fixed plant sustaining costs are estimated at 10% of the initial purchase costs.

 

 

21-25


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 21-18: Underground Equipment Purchases—Fixed Plant

 

Fixed Plant Equipment

   Total Cost
($M)
 

Ventilation and Egress

     6.53   

Dewatering Equipment

     3.00   

Electrical Infrastructure

     7.49   

Workshop, Services and Mine Rescue

     2.06   

Backfill System

     0.66   
  

 

 

 

Total

     19.76   
  

 

 

 

Pre-production period operating costs are capitalized during 2017 and 2018 and include mining labour, maintenance, power, heating, non-capital stope development, technical services, and operational planning.

Underground mine construction costs include civil, structural, mechanical and electrical installations, contract labour, and owner costs. These are grouped into the following cost items and are summarized in Table 21-19.

 

 

Underground Infrastructure and Foundations – including alimak support structure, portal substation, and fresh and return air raise foundations;

 

 

Underground Workshop, CAF Backfill Station and Ancillary Installations – including structural costs of the maintenance bay, sump bays, backfill station support, fuel bay, cranes and hoists;

 

 

Portal Entry and Infrastructure – including portal building foundations, excavation, backfill, and ground support; and

 

 

Owners Costs – including detailed design engineering, consulting engineering, field engineering, and site closure.

 

 

21-26


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 21-19: Contracted Construction Costs

 

Contracted Construction Costs

   Total Cost
($M)
 

Underground Infrastructure and Foundations

     2.01   

Underground Workshop, CAF Backfill and Ancillary Installations

     5.40   

Portal Entry and Infrastructure

     0.64   

Owners Costs

     4.99   
  

 

 

 

Total

     13.03   
  

 

 

 

Project indirect costs are estimated at $9.7M and include freight, capital spares, commissioning, contractor supervision and training, and mobilization and demobilization.

 

21.5.6 Tailings Water Management and Treatment

Approximately $40.5M in sustaining capital is allocated for the tailings dams, water management infrastructure and a water treatment plant.

The main components of sustaining capital related to the TMA and water management include:

 

 

Phased construction of TMA dams based on the tailings management strategy developed by AMEC;

 

 

The construction of an artificial wetland; and

 

 

An additional tailings pump booster station and tailings pipeline.

The estimated cost to design, construct, install and commission the facilities for the water treatment plant (AMEC 2013) is $12.1M. This amount covers the direct field costs of executing the project, plus the indirect costs associated with design, construction and commissioning. Escalation of material and equipment costs has not been included in the estimate; however, a $1.6M contingency was applied. Mechanical equipment such as reactors, agitators, in-line lime silo, dosing systems, acid storage tank, a process water pumphouse and other minor equipment are included in the estimate. A 12 x 16 m building is required for the control room, electrical room and for housing of certain pieces of mechanical equipment such as the reagent pumps. Direct costs also include 323 m3 of concrete, 1,500 m of piping and other various costs pertaining to automation, civil/architectural, electrical and structural/miscellaneous steel. The cost for construction of a settling pond dam inside the Water Management Pond is also included.

 

 

21-27


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

21.5.7 Fish Habitat Compensation Costs

Fish habitat compensation costs were provided by AMEC and total $1.99M. This cost includes onsite fish habitat for diversion channels and ponds and offsite watershed restoration works (livestock fencing and offline water).

 

21.5.8 Chapple Township Compensation Costs

Chapple Township compensation costs were provided by New Gold and total $2.1M. This cost includes Official Planning Amendment/Zoning By-Law Amendment (“OPA/ZBLA”), water pipeline easement compensation and 10.1 km of road closure compensation.

 

21.5.9 Salvage Value

Total equipment salvage value was calculated to be $60.5M and is credited partially during Year 10 (2026) once the open pit has finished and in Year 14 (2030) at the end of the Project. An estimate salvage value percentage was applied to the initial equipment value.

Year 10

After the open pit is depleted, open pit mining equipment not required for stockpile reclamation will be sold for a total estimated salvage value of $30.2M.

Year 14

At the end of the mine life, remaining equipment will be sold for a total estimated salvage value of $30.3M. The major equipment include the SAG and ball mill (including motors), primary crusher, pebble crusher and apron feeders along with the balance of the plant equipment.

 

21.5.10 Reclamation and Closure Costs

Reclamation costs are estimated to be $20.5M and closure costs are estimated to be $29.4M for a total of $49.9M, provided by AMEC. Closure and reclamation costs include monitoring inspection program, engineering, contracts, supervision, reporting, removal of 230 kV transmission line and poles, drainage works, site ponds, stockpiles reclamation, buildings, remote services, tanks, roads, etc.

 

 

21-28


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

21.6 Operating Costs

 

21.6.1 Introduction

Operating costs were calculated based on open pit and underground mining, processing, refining, transport and general and administrative costs. Operating costs and any revenue from production incurred during the pre-production period until commercial production is achieved have been capitalized within New Gold’s Owner’s costs. A summary of the overall Project operating costs per year for each area is shown in Figure 21-1, Table 21-20 and Table 21-21.

LOGO

Figure 21-1: Project Operating Costs

 

 

21-29


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 21-20: Annual Project Operating Cost Summary ($/t milled)

 

     2017      2018      2019      2020      2021      2022      2023      2024      2025      2026      2027      2028      2029      2030      TOT  

Open Pit Mine

     12.35         14.32         16.23         16.63         17.18         16.91         12.77         9.15         3.65         1.21         1.35         1.38         1.29         1.30         9.22   

Underground Mine

     0.00         0.00         4.16         4.09         5.62         6.00         6.05         5.81         5.74         6.17         4.26         1.33         0.00         0.00         3.63   

Process Plant

     9.13         9.27         9.27         9.07         9.16         9.33         9.24         9.33         9.26         9.24         9.36         9.28         9.21         9.38         9.25   

General & Administration

     1.65         1.62         1.60         1.60         1.60         1.58         1.58         1.58         1.57         1.51         1.51         1.36         1.35         1.38         1.54   

Refining & Transport

     0.14         0.14         0.18         0.17         0.20         0.19         0.16         0.15         0.13         0.09         0.10         0.10         0.08         0.09         0.14   

Royalties

     0.07         0.07         0.20         0.21         0.12         0.28         0.26         0.53         2.39         0.77         0.22         0.09         0.07         0.58         0.41   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

TOTAL

     23.34         25.43         31.65         31.77         33.88         34.29         30.07         26.56         22.74         18.99         16.82         13.53         12.00         12.73         24.19   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Table 21-21: Annual Project Operating Cost Summary ($M)

 

     2017      2018      2019      2020      2021      2022      2023      2024      2025      2026      2027      2028      2029      2030      TOT  

Open Pit Mine

     93.1         109.8         124.4         127.4         131.7         129.6         97.9         70.1         28.0         9.3         10.4         10.5         9.9         5.7         957.8   

Underground Mine

     0.0         0.0         31.9         31.3         43.1         46.0         46.4         44.5         44.0         47.3         32.7         10.1         0.0         0.0         377.2   

Process Plant

     68.8         71.1         71.1         69.5         70.2         71.5         70.9         71.6         71.0         70.8         71.7         70.9         70.6         41.4         961.0   

General & Administration

     12.5         12.4         12.3         12.3         12.3         12.1         12.1         12.1         12.1         11.6         11.5         10.4         10.4         6.1         160.0   

Refining & Transport

     1.1         1.1         1.4         1.3         1.5         1.5         1.2         1.2         1.0         0.7         0.8         0.7         0.6         0.4         14.4   

Royalties

     0.5         0.6         1.6         1.6         0.9         2.1         2.0         4.1         18.3         5.9         1.7         0.7         0.5         2.6         43.1   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

TOTAL

     175.9         194.9         242.6         243.5         259.7         262.9         230.5         203.5         174.3         145.5         128.8         103.4         91.9         56.1         2,513.6   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

 

 

21-30


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 21-22 provides a summary of the average cash costs per tonne milled and ounce of gold over the LOM. Operating cash costs, including silver credits and royalties for the LOM total USD $663/oz. Au. All in sustaining cash costs, including silver credits and royalties for the LOM total USD $765/oz. Au.

Table 21-22: Project Cash Cost Summary

 

Area

   Year 1 – 9
Cash  Cost
(USD/oz.)
     LOM Cash
Cost

(USD/oz.)
 

Open Pit Mining (Waste + Rock +

     390         373   

Overburden + Stockpile Rehandling)1

     

Underground Mining (Cut & Fill)2

     

Processing

     207         268   

General & Administration

     36         45   

Refining and Transportation

     4         4   

Royalty Payments

     10         12   
  

 

 

    

 

 

 

Subtotal Costs

     646         702   
  

 

 

    

 

 

 

Silver by-Product Sales

     -33         -39   
  

 

 

    

 

 

 

Total Costs Net Silver

     613         663   
  

 

 

    

 

 

 

Sustaining Capital

     123         102   
  

 

 

    

 

 

 

All-in Sustaining Cash Costs

     736         765   
  

 

 

    

 

 

 

 

1.

Equivalent to $2.04/t mined, (excluding stockpile rehandling costs of $1.34/t mined).

2.

Equivalent to $90.10/t mined.

The cash costs per ounce of gold vary significantly, depending on the feed grade, mine strip ratio and the amount of stockpiling. The annual fluctuation of operating costs per ounce of gold produced can be seen in Figure 21-2. It should be noted that, due to the processing of stockpile material, the overall operating costs per ounce increase substantially during the later years with gold grades ranging from 0.3 to 0.6 g/t Au.

 

 

21-31


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 21-2: Annual Operating Cash Costs (USD/oz. Au) with Silver Credit

 

21.6.2 Power and Fuel

The cost of electrical power for the Project was determined to be $0.065/kWh. This includes a reduction for the Northern Industrial Rebate Program and is a projected 2014 rate based on historical rates from 2006 to 2013. The cost of propane and diesel, $0.50/L and $0.95/L, respectively was provided by local suppliers and used for cost calculations.

 

21.6.3 Total Employees

The number of employees during the production period (Years 1-14) consists of personnel from the open pit mine, underground mine, process plant and general and administrative. While the process plant and general and administrative employees remain constant through the mine life, the open pit and underground mine employees vary per year, as shown in Figure 21-3.

 

 

21-32


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 21-3: Total Personnel

The total personnel for the Rainy River Project peaks in Year 5 (2021) at 606 employees as shown in Table 21-23.

Table 21-23: Project Peak Personnel

 

Area

   Project Peak
(Year 5)
 

Open Pit Mine

     311   

Underground Mine

     172   

Process Plant

     91   

General and Administrative

     29   
  

 

 

 

Total

     606   
  

 

 

 

 

21.6.4 Open Pit Operating Costs

Mine operating costs were estimated by BBA using the equipment list and manpower requirements based on the mine plan presented in Chapter 16. The mining operating costs include all costs related to ore extraction, waste, and overburden material and rehandling of the stockpiled material. All open pit mine production costs incurred during the pre-production phase of the Project will be capitalized. The open pit mining production period is from Year 1 to Year 9. Stockpile rehandling occurs from Year 9 until the end of the mine life (Year 14).

 

 

21-33


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 21-24 presents the total open pit mining cost summary for pre-production, production, and stockpile rehandling periods.

Table 21-24: Open-Pit Mining Cost Summary Per Period

 

     Units    Pre-Production
(Years -2 and  -1)
   Production
(Year 1 to 9)
   Pre-Production
and Production
(Year -2 to Year 9)
   Stockpile
Rehandling

(Years 9 to  14)

Mining Cost for

              

Rock (Ore, Waste)

   $/t mined    2.11    2.11    2.11   

Mining Cost for Overburden

   $/t mined    1.54    1.52    1.53   

Total Mining Cost

   $/t mined    1.81    2.04    2.02   

Rehandling Cost

   $/t mined             1.34

The open-pit mine operating cost is presented by cost area in Table 21-25. The average operating cost over the LOM is $2.04 per tonne of material mined, including pre-production capitalized costs or $2.02 per tonne of material mined excluding pre-production capitalized costs.

Table 21-25: Open Pit Mine Operating Cost Breakdown

 

Cost Area

   LOM
Operating

Cost ($M)
     Operating Cost
($/t mined)
 

Equipment Maintenance

   $ 328.5       $ 0.67   

Equipment Fuel and Electricity

   $ 269.7       $ 0.55   

Blasting

   $ 152.5       $ 0.31   

Personnel

   $ 238.7       $ 0.49   

Services

   $ 5.0       $ 0.01   
  

 

 

    

 

 

 

Total Open Pit Operating Cost1

   $ 994.4       $ 2.02   
  

 

 

    

 

 

 

Stockpile Rehandling

   $ 50.4       $ 1.34   

 

1.

Total Mine Opex includes capitalized pre-production costs. Mine Opex during production years is $2.04/t mined and $1.81/t mined during pre-production years.

 

 

21-34


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Equipment Maintenance

Equipment operating costs were developed from vendor quotations. Other sources of information include an internal database of similar projects. It includes maintenance (e.g. repairs, spare parts, bucket repairs), chains, ground engaging tools grease and oil, tires, truck liners, drilling tools and accessories, etc. The total cost was compiled based on a cost per hour of operation for each type of equipment. Equipment maintenance costs exclude the cost of maintenance personnel, fuel, and electricity as they were calculated separately. Equipment maintenance over the LOM is $328.5M or $0.67/t milled.

Equipment Fuel and Electricity

Diesel fuel is used to operate mine trucks, hydraulic diesel shovels, loaders, dozers, and other smaller mine equipment. Yearly fuel consumption was estimated according to the annual operating hours, based on equipment specifications and truck haulage profiles. Electrical power is supplied to the open pit by a power distribution loop and is used to operate the electric hydraulic shovel. Yearly power consumption was estimated according to the annual operating hours, equipment specifications, and equipment utilization. Equipment fuel and electricity is $269.7M over the LOM or $0.55/t milled.

Blasting

Blasting costs for ore and waste rock have been estimated based on parameters and powder factors presented in Chapter 16. Blasting costs were estimated based on the blast pattern for required fragmentation and annual tonnage in both ore and waste. The blasting unit costs were derived from vendor quotations.

Emulsion costs were estimated at $0.29/t for ore and $0.23/t for waste rock, based on a unit cost of $82.20 per 100 kg of emulsion. It is assumed that 20% of the waste will be drilled using the ore pattern. Blasting costs also include accessories and contractor labour costs for mixing, delivering explosives to the blast holes, and loading explosives into the blast holes. Pre-splitting blasting costs are considered in the estimation of total blasting costs. Total blasting costs over the LOM are $152.5M or $0.31/t milled.

 

 

21-35


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Personnel

Labour requirements have been estimated on an annual basis to support the mine plan developed in this study. Mine salaried and hourly personnel positions with corresponding headcounts were presented in Chapter 16. Salaried and hourly personnel base salaries were provided by New Gold and included: a short-term incentive bonus, a long term incentive bonus, employment insurance, Canada pension plan, medical, workplace safety and insurance board and company pension fund factors. The combined burdens for the salaried personnel varied by position, averaging 31.5%. Total personnel costs including burden is $238.7M or $0.49/t milled.

Services

Service costs include items such as consultant fees, software licences, an allowance for mine dewatering, dispatch system licence, and survey and monitoring equipment. Services represent $5M over the LOM or $0.01/t milled.

Stockpile Re-handling

After depletion of the Open Pit, the mill will be fed at 21,000 tpd using the low-grade stockpiled material. The operating cost estimate for rehandling is $50.4M or $1.34/tonne of reclaimed ore material ($0.50/t milled LOM) for the transportation of the stockpiled material from the stockpile to the crusher. This cost includes the equipment maintenance, fuel, and the labour required for maintenance and operations.

 

21.6.5 Underground Operating Costs

The total operating cost for the underground mine is estimated to be $377M, or $90.10 per tonne of ore mined (average), and includes the costs of all key mine operating activities from the onset of production (2017) to the end of the mine life (2026).

The estimation of underground mine operating costs is based on a first principles work-up of all key mining activities, using the following inputs:

 

 

Mine design and method;

 

 

Production and development schedule;

 

 

Power and ventilation requirements; and

 

 

Waste and backfill schedule.

 

 

21-36


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The operating costs are divided into key mining activities as shown in Table 21-26.

Table 21-26: LOM Underground Operating Costs by Activity

 

Operating Costs

   Total LOM Cost
($M)
     Average LOM Cost
($ / tonne mined)
 

Waste Development

     28.9         6.90   

Ore Development

     35.9         8.57   

LH Stoping

     48.8         11.65   

Backfill

     27.2         6.49   

Mine Maintenance

     14.7         3.51   

Mine General

     57.0         13.61   

Labour

     164.8         39.36   
  

 

 

    

 

 

 

Total

     377.2         90.10   
  

 

 

    

 

 

 

Associated cost areas include equipment operating, explosive and fuel consumption, consumables (ground support and backfill) and services requirement (ventilation, cabling, and piping).

Equipment selection and operating costs are based on mine activities and workups of required operating hours, productivity and cycle times, availability/utilization, and fuel consumption. The operating costs for all major mobile equipment were obtained from vendor quotes and benchmarked against AMC’s cost database for similar recent projects. Ancillary equipment utilization and costs are calculated based on projected usage to complete general mine tasks.

The unit costs of all major consumables, including explosives, ground support, pipes, and ventilation ducting, have been obtained from vendor quotes. The unit costs of power, propane, cement, and diesel were provided by New Gold.

Mine Maintenance costs include fixed plant and electrical maintenance, maintenance overheads, and shop consumables. The Mine General and Mine Maintenance costs are developed based on industry experience and benchmarked against similar projects in the region.

Manpower requirements and labour rates, including benefits and burdens, were developed in consultation with New Gold. The manpower build-up is estimated based on mine activities and

 

 

21-37


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

mobile equipment quantities. All underground mine operating activities during the first three (3) years are proposed to be completed by a contracted workforce. Labour rates in these years include a 22% contractor premium. After the initial three (3) years, all underground mine operating activities will be undertaken by New Gold and hence, no contractor premiums are applied after production begins.

Mine General

Mine General costs include power consuming items include primary and secondary ventilation fans, mobile drilling equipment, dewatering pumps, workshop services, and the underground CAF plant. Propane heating costs are based on the scheduled total mine airflow which increases annually in tandem with development and production activity until steady state production, 1,500 tpd, is achieved. The breakdown of Mine General costs is presented in Table 21-27.

Table 21-27: Underground Operating Costs – Mine General Area

 

Mine General

   Total LOM Cost
($M)
     Average LOM Cost
($ / tonne mined)
 

Power

     23.2         5.53   

Heating

     13.0         3.11   

Support Equipment

     6.4         1.52   

Technical Service Consumables

     1.3         0.30   

Mine General Consumables

     2.1         0.50   

Personnel Safety Equipment

     0.6         0.15   

Freight

     1.8         0.42   

Definition Drilling

     8.7         2.08   
  

 

 

    

 

 

 

Total

     57.0         13.61   
  

 

 

    

 

 

 

 

21.6.6 Process Plant

Process plant operating costs were calculated for 14 years of operation. The operating costs are based on metallurgical testwork, the mine plan, a recent salary survey, literature, and recent supplier quotations. The average LOM processing operating costs were determined to be $9.25/t milled at approximately 21,000 tpd. The yearly tonnages from the mine plan vary and were used to obtain the operating costs.

 

 

21-38


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Operating costs during ramp-up/commissioning (up to 60% of 21,000 tpd production) were included in the capital expenditures as Owner’s Costs (Section 21.4.9).

The average operating cost includes reagents, consumables, grinding media, personnel (including contractors), electrical power, propane, and maintenance parts. The consumables include spare parts, grinding media and liner, and screen components. A breakdown of the average processing operating costs can be seen in Table 21-28.

Table 21-28: Processing Operating Cost Breakdown

 

Cost Area

   LOM Operating
Cost
($M)
     Operating
Cost
($/t milled)
 

Reagents

     187.4         1.80   

Spare Parts/Maintenance

     65.3         0.63   

Liners and Screen Components

     49.0         0.48   

Grinding Media

     155.7         1.50   

Personnel

     139.3         1.34   

Electrical Power

     288.3         2.77   

Propane

     10.6         0.10   

Transportation (reagents, media)

     57.7         0.56   

Water Treatment

     7.7         0.07   
  

 

 

    

 

 

 

Total

     961.0         9.25   
  

 

 

    

 

 

 

It can be seen that the main cost areas for the process plant are the electrical power, grinding media, and reagents. The majority of the reagent costs are associated with cyanide leaching and cyanide destruction.

Reagents

The reagent consumptions were estimated based on testwork, industrial references, literature and assumed operational practice. The individual reagent costs ($/t reagent) were established through vendor quotations and comparison with prices at reference sites. Reagents represent approximately 20% of the total process operating cost at $187.4M or 1.80 $/t milled.

 

 

21-39


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Spare Parts / Maintenance

Vendors provided yearly quotes for various spare parts and the estimated required maintenance. Spare parts / maintenance represent approximately 7% of the total process operating cost at $65.3M or $0.63/t milled.

Liners and Screen Components

Liner and screen components were calculated based on vendor quotes for the estimated parts cost and their expected wear life, provided in months. Liners and screen components represent approximately 5% of the total process operating cost at $49.0M or $0.48/t milled.

Grinding Media

The annual cost for grinding media for the SAG and ball mill were estimated based on the expected media consumption (g/kWh) and the cost per tonne of steel media. The individual media costs ($/tonne steel media) were established through vendor quotations and comparison with prices at reference sites. Grinding media represents approximately 16% of the total process operating cost at $155.7M or $1.50/t milled.

Personnel

The personnel costs incorporate requirements for plant management, metallurgy, operations, maintenance, site services, assay lab and contractor allowance. The individual personnel are divided into their respective positions and their salaries were provided by New Gold. It was assumed that contractors would be used for crusher and liner changes.

There are a total of 91 employees accounted for in the process operating costs, 78 employees in the process plant and 13 employees in the assay lab.

The personnel costs represent approximately 15% of the total process operating cost at $139.3M or $1.34/t milled.

Electrical Power

The respective power required for the SAG and ball mill were calculated based on the material hardness (A x b value) for the SAG mill and the BWi of the ball mill. The power consumption of all the major equipment was calculated using the electrical load list and mechanical equipment list.

 

 

21-40


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The process plant energy consumption was estimated from the equipment running loads and the SAG and ball mill grinding energy requirements. Various factors (efficiency, load, diversity, and annual factors) were applied to adjust for equipment motor efficiency, the power used versus installed, the synchronous operation of equipment and average on-line time in the plant and throughout the year.

The SAG mill specific energy (kWh/t) was estimated from the analyzed relationship derived from testwork between the A x b value and the SAG motor input specific energy as determined by JK SimMet. The ball mill specific energy (kWh/t) was calculated from the BWI and the Bond formula, assuming the ball mill will grind the rock from 2,800 µm to 75 µm. The A x b and BWi values were estimated for each year based on testwork and the mine plan. The specific energies were converted to an annual power demand (GWh) based on efficiency factors and the varying milled tonnage per year.

The electrical power costs represents approximately 30% of the total process operating costs at $288.3M or $2.77/t milled.

Propane

The propane consumption includes requirements for the crusher, concentrator, process and boiler. The propane costs represent approximately 1% of the total process operating costs at $10.6M or $0.10/t milled.

Transportation (Reagents, Media)

Transportation costs were provided by vendor quotes and displayed separately in the process operating cost to allow a better comparison of reagent and grinding media prices. The transportation costs represent approximately 6% of the total process operating costs at $57.7M or $0.56/t milled.

 

 

21-41


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Water Treatment Plant

An annual cost of $734k was calculated by AMEC for operating the water treatment plant starting in Year 5 until the end of the mine life. The water treatment plant costs represent approximately 1% of the process operating costs at $7.7M or $0.07/t milled.

 

21.6.7 G&A Costs

General and Administrative (“G&A”) costs are expenses not directly related to the production of goods and encompass items not included in mining, processing, refining, and transportation costs. These costs are based on the client’s recommendations, similar sized operations, and BBA’s in-house database.

The G&A costs were calculated for 14 years of operation and with an average cost of $1.54/tonne milled. This cost includes:

 

 

Human Resources;

 

 

Site Administration, Insurance and Management;

 

 

Infrastructure Power;

 

 

Health and Safety Supplies;

 

 

First Nations Participation Agreement Payments;

 

 

Security and Paramedic Services;

 

 

Environmental Costs;

 

 

G&A Personnel;

 

 

Information Technology (“IT”); and

 

 

Training.

The labour costs include the twenty-nine (29) employees required for G&A, including nineteen (19) staff members and ten (10) hourly employees. In general, the management and administrative staff will work 40 hours per week on day shift. Warehousing personnel will work a 12-hour shift per day to support the 24 hours of required daily operations. The labour cost represents 25% of the G&A costs. Infrastructure electricity accounts for approximately 21% and site administration, maintenance and insurance represent approximately 28% of the G&A costs. The breakdown is shown in Table 21-29.

 

 

21-42


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 21-29: Average General and Administrative Costs

 

Cost Area

   LOM Operating
Cost
($M)
     Operating Cost
($/t milled)
 

Infrastructure Electricity

     34.1         0.33   

Site Admin., Insurance and Maintenance

     45.1         0.43   

Health and Safety

     7.5         0.07   

Environment

     6.9         0.07   

Human Resources

     11.0         0.11   

IT and Telecommunications

     10.2         0.10   

Personnel

     39.5         0.38   

First Nations Participation Agreement Payments

     5.7         0.06   
  

 

 

    

 

 

 

Total

     160.0         1.54   
  

 

 

    

 

 

 

 

21.6.8 Royalties

The annual royalty costs are based on the Feasibility Study mine design and production profile, along with the terms of the individual royalty agreements for each property, which in turn relate to a limited portion of the reserves. Royalty costs are based on a gold price of USD $1,300 per ounce of gold and USD $22 per ounce of silver. Over the life of the Project, approximately $43M in royalties is expected to be paid.

 

21.6.9 Transportation and Refining

A weekly shipment of doré bars containing approximately 38% gold and 62% silver will be transported to a refinery. A flat rate transportation cost will be incurred by the refinery in addition to a cost by weight and a variable liability fee. A treatment cost per troy ounce of material shipped to the refinery will also be charged. New Gold will be paid for a set recovery of the assayed content. Over the LOM, a transport and refining cost of $14.4M or $0.14/t milled is estimated and this is based on a budgetary quotation obtained from a North American gold refinery.

 

 

21-43


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

22. ECONOMIC ANALYSIS

 

22.1 Introduction

A financial analysis for the Rainy River Project was carried out using a discounted cash flow approach on a pre-tax and after-tax basis. The internal rate of return (“IRR”) on the total investment was calculated based on the assumption that no debt financing is required for the project. The Net Present Value (“NPV”) was calculated from the cash flow generated by the project based on a discount rate of 5%. The payback period based on the undiscounted annual cash flow of the project was also indicated as a financial measure. Furthermore, a sensitivity analysis was performed for the pre-tax base case to assess the impact of variations of the project capital costs, annual operating costs, price of gold/silver and USD/CAD exchange rate.

The results of the economic analysis summarized below represent forward-looking information as defined under Canadian securities law. Actual results may differ materially from those expressed or implied by forward-looking information. The reader should refer to the Cautionary Note with respect to Forward Looking Information at the front of this Report for more information regarding forward-looking statements, including material assumptions (in addition to those discussed in this section and elsewhere in this Report) and risks, uncertainties and other factors that could cause actual results to differ materially from those expressed or implied in this section (and elsewhere in the Report).

 

22.2 Methods, Assumptions and Basis

The Economic Analysis was performed using the following assumptions and basis:

 

 

The Project NPV was determined on a pre-tax and after-tax basis with discounting to the start of Year -2 (2015), which marks the first year of project construction. Project expenses incurred in Year -3 (2014) are treated in the cashflow model as occurring at the start of Year -2;

 

 

Cashflows are assumed to occur mid-period;

 

 

The Project Executive Schedule developed in the Feasibility Study (Chapter 24) is used and takes into consideration key project milestones;

 

 

The Financial Analysis was performed for the Open Pit and Underground Proven and Probable Mineral Reserves estimated in this Study;

 

 

22-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

Commercial production start-up is scheduled to begin in the first quarter (Q1) of 2017. Operations are estimated to span over a period of approximately 14 years;

 

 

The base case gold and silver prices are USD $1,300/oz. and USD $22/oz., respectively;

 

 

The United States to Canadian dollar exchange rate has been assumed to be USD $0.95:CAD $1.00 during preproduction and operation years;

 

 

All cost and sales estimates are in constant Q4 2013 Canadian dollars, with no inflation or escalation factors taken into account;

 

 

All gold and silver is sold in the same year it is produced;

 

 

All project related payments and disbursements incurred prior to the effective date of this Report are considered as sunk costs. Disbursements projected after the effective date of this Report, but before the start of construction, are considered to take place in the pre-production period;

 

 

Details of capital and operating costs are provided in Chapter 21 “Capital and Operating Costs”;

 

 

All values shown are post payment of royalties. Total royalty payments over the LOM are $28.6M NPI/NSR (net profit interest / net smelter return) and $14.5M other;

 

 

The financial analysis does not include working capital for the period between commissioning and first metal sales, or closure plan bonding requirements. It is assumed that these items are covered in the cashflow from New Gold’s operating mines;

 

 

Final rehabilitation and closure costs will be incurred after production Year 14;

 

 

After-tax results were provided by New Gold. BBA has not verified this work;

 

 

After-tax figures assume a combined income tax rate of 25% with 2.7% corporate minimum tax, a mining tax of 10% of taxable mining profits over $500,000 and an allocation of corporate tax attributes among New Gold’s operations; and

 

 

All dollars are in Canadian, unless specifically noted.

The general assumptions used for this financial model are summarized in Table 22-1, Table 22-2 and Table 22-3.

 

 

22-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 22-1: Financial Model Criteria and Production Summary1,2

 

Area

   Units    LOM
Annual
Average
     Year 1-9
Annual
Average
     LOM
Total
 

Gold Price

   USD/oz      1,300         1,300         1,300   

Silver Price

   USD/oz      22         22         22   

Ore Milled (OP & UG)

   Mt      7.67         7.65         104.28   

Open Pit Waste Mined

   Mt      23.44         32.96         318.18   

Strip Ratio (Waste: Ore)

   —        3.18         3.00         3.18   

Blended Gold Grade

   g/t      1.12         1.44         1.12   

Blended Silver Grade

   g/t      2.80         3.07         2.80   

Gold Recoveries

   %      90.61         91.89         90.61   

Silver Recoveries

   %      64.05         64.15         64.05   

Gold Recovered

   koz      251         325         3,402   

Silver Recovered

   koz      442         480         6,004   

Exchange Rate

   CAD:USD      0.95         0.95         0.95   

Discount Rate

   %      5         5         5   

Initial Capital Cost

   $ M      —           —           931.58   

Sustaining Capital

   $ M      26.99         41.90         366.34   

Life of Mine

   years      —           —           13.6   

 

1.

Year 1 starts from commercial production (excluding pre-production).

2.

Table excludes 0.4 Mt of material milled in the pre-production period.

Table 22-2: Operating Costs and Cash Costs over the LOM

 

Area

   LOM Total
($M)
     $ per tonne
milled (LOM)
     USD per gold
ounce
produced
(LOM)
 

Open Pit Mining (Waste + Rock + Stockpile)

     958         9.22         373   

Under Ground Mining (Cut & Fill)

     377         3.63      

Processing

     961         9.25         268   

General & Administration

     160         1.54         45   

Refining and Transportation

     14         0.14         4   

Royalty Payments

     43         0.41         12   
  

 

 

    

 

 

    

 

 

 

Subtotal Costs

     2,514         24.19         702   
  

 

 

    

 

 

    

 

 

 

Silver by-Product Sales

     -139         -1.34         -39   
  

 

 

    

 

 

    

 

 

 

Total Costs Net Silver

     2,375         22.86         663   
  

 

 

    

 

 

    

 

 

 

Sustaining Capital

     366         3.53         102   
  

 

 

    

 

 

    

 

 

 

All-in Sustaining Cash Costs

     2,741         26.38         765   
  

 

 

    

 

 

    

 

 

 

 

 

22-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 22-3: Capital Costs over the LOM (M $CAD)

 

Description

   Capital Costs
($M)
 

Initial Direct Costs

     672   

Initial Indirects

     186   

Initial Contingency

     73   
  

 

 

 

Total Pre-Production Capital Costs

     931   
  

 

 

 

Sustaining Capital

     366   
  

 

 

 

Total LOM Capital Costs

     1,297   
  

 

 

 

 

22.3 Royalties

The annual royalty costs were calculated by New Gold and are based on the conceptual Open Pit and Underground mine design and production profiles developed by BBA and AMC, along with the terms of the individual royalty agreements, which in turn relate to a limited portion of the reserves. Royalty costs are based on a gold price of USD$1,300 per ounce of gold and USD$22 per ounce of silver. Over the life of the Project, approximately $43.1M in royalties is expected to be paid based on the base case metal prices and project assumptions, with $28.6M NPI/NSR (net profit interest / net smelter return, respectively) and $14.5M in other royalties.

 

22.4 Salvage Value

Total equipment salvage value was calculated to be $60.5M and is credited partially during Year 10 (2026) once the open pit is depleted, and in Year 14 (2030), at the end of the Project. In Year 10, the open pit mining equipment not being used for stockpile reclamation will be sold for a total estimated salvage value of $30.2M. In year 14, at the end of the mine life, the remaining mine and process plant equipment will be sold for a total estimated salvage value of $30.3M. Major equipment includes the SAG and ball mills (including motors), primary crusher, pebble crusher and apron feeders, along with the balance of the plant equipment.

 

22.5 Taxation

The tax rate calculations and taxation assumptions used in the after-tax NPV calculations are summarized below.

The federal government imposes income tax on mining income at the same rate that applies to other types of income. The federal rate applicable to resource profits is 15%. Ontario’s taxation

 

 

22-4


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

of the resource sector is generally harmonized to the federal system. The provincial corporate income tax rate applicable to mining income is 10%. A combined rate of 25% is used in the model to compute the federal and provincial tax liability in respect of the Rainy River Project. In addition, in the earlier years of the project, the Ontario Corporate Minimum Tax has been computed at a rate of 2.7%. All deductions and rates are based on currently enacted legislation. In addition, Ontario’s Mining Tax Act is levied at a rate of 10% on annual taxable profits in excess of $500,000.

The federal and provincial tax legislation provides a number of deductions, allowances, and credits that are specifically available to taxpayers engaged in qualifying mining activities. The most notable of these deductions are Canadian Exploration Expenditures (“CEE”), Canadian Development Expenses (“CDE”), and capital costs eligible for Class 41 of the capital cost allowance system. Because these deductions and allowances are only available when incurred, a high-level assumption was made with regard to the allocation of expenditures between the three categories in the life-of-mine model.

Similarly, the Ontario Mining Tax Act provides a number of deductions in arriving at taxable profits, the key ones being allowance for Exploration and Development Expenditures, Depreciation Allowance and Processing allowance. Since these deductions depend on when the expenses are incurred and the degree of processing that occurs in Canada, a number of high level assumptions are made with regards to the allocation and timing of expenditures for the depreciation allowance calculation. A general assumption regarding the processing allowance has been made and it has been assumed that Rainy River will qualify for a minimum 15% processing allowance.

Rainy River Resources Limited is a 100% subsidiary of New Gold Inc. (“New Gold”). New Gold is intending to implement tax planning strategies that will allow it access to Rainy River’s tax attributes, with the overall goal of maximizing the overall profitability of New Gold’s Canadian operations as a whole, as opposed to any one operation or project. Part of New Gold’s growth strategy, including the successful acquisition of Rainy River Resources in 2013, has been to build its business in jurisdictions where it already has an established presence. One of the many benefits of this approach is that it enables the company to manage its business in a tax-efficient manner. In the case of Rainy River, New Gold plans to implement tax planning strategies that

 

 

22-5


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

would allow it to realize tax synergies by utilizing a portion of the tax attributes that have been, and will continue to be generated in the corporate entity holding the company’s portfolio of Canadian assets. Currently, the company’s primary objective is to maximize the cash flow generation of its New Afton Mine in Kamloops, British Columbia, with any remaining tax attributes planned to be used to maximize Rainy River’s future after-tax cash flow. As New Gold’s focus in such allocation will be to maximize the company’s overall profitability rather than that of any one operation or project, this will remain a dynamic process.

At the end of 2012, on a combined basis, the New Gold corporate entity had over $900 million in Canadian Exploration Expenditures, Canadian Development Expenditures and Class 41 capital cost allowance, as well as over $100 million in net operating losses. These totals exclude those attributes specifically related to the Blackwater project. In addition, the company’s annual corporate administration expenses are approximately $30 million and its annual interest expenses are $52 million, both of which can be combined with the above noted attributes to shelter taxable profits from one or both of New Afton and Rainy River going forward. New Gold intends to implement tax planning strategies that would allow it the flexibility to access the existing tax attributes of Rainy River Resources and utilize them in a manner which would maximize New Gold’s overall profitability.

 

22.6 Financial Analysis Summary

A discount rate of 5% was applied to the cash flow to derive the Project’s NPV on a pre-tax and after-tax basis. The summary of the financial evaluation for the Project’s base case is presented in Table 22-4.

Table 22-4: Financial Analysis Summary (Pre-tax and After-tax)

 

Description

   Base Case      Units  
LOGO    

Net Present Value (0% disc)

     983         $M   
 

Net Present Value (5% disc)

     462         $M   
 

Internal Rate of Return

     13.1             
 

Simple Payback Period1

     5.4         Years   
LOGO    

Net Present Value (0% disc)

     774         $M   
 

Net Present Value (5% disc)

     330         $M   
 

Internal Rate of Return

     11.3             
 

Simple Payback Period1

     5.5         Years   

 

1.

Payback period starts from commercial production using undiscounted cash flows.

 

 

22-6


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The pre-tax base case financial model resulted in an internal rate of return of 13.1%, a NPV of $986M with a discount rate of 0%, and a NPV of $462M with a discount rate of 5%. The simple payback period is 5.4 years. On an after-tax basis, the base case financial model resulted in an internal rate of return of 11.3% and a NPV of $774M with a discount rate of 0%, and a NPV of $330M with a discount rate of 5%. The simple payback period is 5.5 years. Figure 22-1 shows the gold production, cash costs and the all in cash costs. The all-in cash costs in Years 10 (2026) and 14 (2030) include a credit for the estimated equipment salvage values. The Year 10 salvage credit consists of the sale of all mine equipment not required for the stockpile reclamation operation. The Year 14 salvage credit consists of the sale of all remaining mine and process plant equipment at the end of the life of mine.

LOGO

Figure 22-1: Life-of-Mine Cash Flow Projection

The summary of the Rainy River Project discounted cash flow financial model (pre-tax and after tax) is presented in Table 22-5.

 

 

22-7


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 22-5: Rainy River Financial Model Summary (CAD$)

LOGO

 

 

22-6


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

 

 

22-7


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Figure 22-2 shows the Project’s cumulative cash flows projected for the mine life on a pre-tax and after-tax basis.

LOGO

Figure 22-2: Life-of-Mine Cash Flow Projection (Pre-tax and After-tax, discount rate: 5%)

 

22.7 Sensitivity Analysis

A financial sensitivity analysis was conducted on the Project’s base case cash flow NPV and IRR for variations in capital expenditures, operational expenditures, metal recoveries and metal prices. Table 22-6 shows the pre-tax and after-tax NPV (in CAD$) and IRR sensitivity to varying metal prices and exchange rates. The results are also presented in USD$ in Table 22-7. The royalty payments were assumed to be constant (equivalent to the base case) for the sensitivity analysis.

 

 

22-8


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 22-6: Sensitivity Results for Metal Price and Exchange Rate Variations (CAD $M)

 

Gold
Price
(USD$ /
ounce)
    Silver
Price
(USD$ /
ounce)
    Exchange
Rate
(USD$:CAD$)
    NPV at 5%
Discount Rate
(CAD$ million)
    IRR
(%)
    Payback Period
(years)
 
      Pre-Tax     After-Tax     Pre-Tax     After-
Tax
    Pre-Tax     After-
Tax
 
  1,150        20        0.93        147        107        7.8        7.1        6.8        6.8   
  1,300        22        0.95        462        330        13.1        11.3        5.4        5.5   
  1,450        24        0.97        763        536        17.6        14.9        4.3        4.4   
  1,600        26        1.00        1,013        706        21.1        17.8        3.6        3.8   

Table 22-7: Sensitivity Results for Metal Price and Exchange Rate Variations (USD $M)

 

Gold
Price
(USD$ /
ounce)
    Silver
Price
(USD$ /
ounce)
    Exchange
Rate
(USD$:CAD$)
    NPV at 5%
Discount Rate
(USD$ million)
    IRR
(%)
    Payback Period
(years)
 
      Pre-Tax     After-Tax     Pre-Tax     After-
Tax
    Pre-Tax     After-
Tax
 
  1,150        20        0.93        138        100        7.8        7.1        6.8        6.8   
  1,300        22        0.95        438        314        13.1        11.3        5.4        5.5   
  1,450        24        0.97        738        520        17.6        14.9        4.3        4.4   
  1,600        26        1.00        1,009        706        21.1        17.8        3.6        3.8   

The pre-tax sensitivity analysis for Project capital costs, operating costs and metal recovery is summarized in the following table.

Table 22-8: Selected Sensitivities, Pre-Tax NPV at 5% Discount Rate (CAD $M)

 

      Sensitivities  

Description

   -30%     -20%     -10%      0%      10%      20%     30%  

LOM Capital Expenditures

     818        699        581         462         343         225        106   

LOM Operating Expenditures

     975        804        633         462         291         120        (51

Gold Price

     (525     (196     133         462         791         1120        1449   

Silver Price

     434        443        453         462         471         481        490   

USD Foreign Exchange Rate

     1477        1139        800         462         124         (215     (553

Open Pit Mining Costs

     742        649        555         462         369         275        182   

Underground Mining Costs

     594        550        506         462         418         374        330   

Processing Costs

     656        591        527         462         397         333        268   

 

 

22-9


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The results of the financial sensitivity analysis are graphed in Figure 22-3. It can be seen that the Project financials are most sensitive to the gold price and foreign exchange rate.

LOGO

Figure 22-3: Sensitivity of the Net Present Value (Pre-tax) to Selected Financial Variables

 

 

22-10


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

23. ADJACENT PROPERTIES

 

23.1 Introduction

Seven (7) properties in the exploration stage are located adjacent to or near the Rainy River Project property. Bayfield Ventures Corp. (TSX-V:BYV) holds three (3) of the properties, known as the B Block, C Block and Burns Block. Coventry Resources Inc. (TSX-V:CYY) holds three (3) of the properties, known as the Pattullo, Nelles and Blue properties. King’s Bay Gold Corp. (TSX-V:KBG) holds the seventh property, being a single continuous land package contiguous with the most northerly portion of the Rainy River Project property. The closest Canadian operating mines are the Lac des Iles; palladium, nickel, gold and copper mine, owned by North American Palladium Ltd. (TSX:PDL) and Goldcorp’s (TSX:G) Red Lake mine complex. Both projects are approximately 400 km from the Rainy River Project.

The following information was obtained from public sources, and neither New Gold nor BBA has verified its accuracy. The information provided in the following section is not a reflection of the mineralization of the Rainy River Project property.

Bayfield Ventures Corp.

Bayfield Ventures Corp. (“Bayfield”) is exploring for gold and silver in the Rainy River district and owns a 100% interest in mineral rights to three (3) properties adjacent to the Rainy River Project property. These consist of the B Block, C Block and the Burns Block.

The Burns Block is an 80 acres parcel of land directly east of the ODM Zone and west of the newly discovered Intrepid Zone, which is completely surrounded by properties either owned by, or optioned to New Gold (both surface and mineral rights). New Gold also owns a 100% interest in the surface rights to the Burns Block.

On January 14th, 2014, Bayfield issued a press release: “Bayfield Announces Maiden NI 43-101 Technical Report and Mineral Resource Estimate on Burns Block Rainy River Gold-Silver Project, NW Ontario”. The press release stated combined Indicated mineral resources from both potential open pit and underground mineralization to be 60 koz. Au and 686 koz. Ag and 151 koz. and 1,563 koz Ag of Inferred resources. An NI 43-101 compliant technical report for the Burns Block entitled “Burns Block National Instrument 43-101 Compliant Technical Report” was filed on SEDAR on January 23, 2014.

 

 

23-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Bayfield also published a NI 43-101 technical report in March 2007 on its Tait Gold project located 3 km southwest of the Rainy River project over which Bayfield held an option. That option was subsequently allowed to lapse and the property has been returned to the original mineral rights owner.

Coventry Resources Inc.

Coventry Resources Inc. (“Coventry”) has a gold exploration project in the Rainy River District comprised of three (3) properties to the west of the western perimeter of the Rainy River Project, known as the Pattullo, Nelles and Blue properties.

Coventry holds patented claims optioned by landholders, staked unpatented claims and unpatented claims optioned by third parties. Within the next seven (7) years, Coventry Resources is entitled to earn a 100% interest in the mineral rights on all leased areas (132.7 km2).

King’s Bay Gold Corp.

King’s Bay Gold Corp. (“King’s Bay”) is exploring for gold in the Kenora Mining District in Northern Ontario. King’s Bay owns a 100% interest (both surface and mineral rights) to the Menary gold projects representing 18 claims (2,238 hectares) approximately 20 km southeast of the town of Nestor Falls, Ontario and approximately 15 km northeast of the Rainy River project.

 

 

23-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

24. OTHER RELEVANT DATA AND INFORMATION

 

24.1 Project Execution

The Project Execution Strategy was developed for the Rainy River Project Feasibility Study (FS) based on the latest FS information available and industry best practices. It is intended to describe the strategy for moving forward on engineering, procurement, construction and environmental activities. The Execution Strategy ensures that the core elements of New Gold’s Corporate Objectives regarding the inter-relationship between the stakeholders, community, First Nations and project development are maintained from the mineral exploration stage through the construction phase.

The core elements of New Gold’s Corporate Objectives integrate the following commitments into the strategy:

 

 

Human Rights;

 

 

Project Due Diligence and Pre-Engagement;

 

 

Community and Aboriginal Engagement and Enhancement;

 

 

Human Resource Development;

 

 

Environmental Integrity and Performance, and

 

 

Health and Safety Performance.

 

24.2 Health, Safety, Environmental and Security

A fully integrated Health, Safety and Environmental (“HSE”) program will be implemented to help achieve a “zero-harm” goal. HSE practices include: alignment with site contractors on safety training, occupational health and hygiene, hazard and risk awareness, safe systems of work, and job safety analysis. A 24-hour staffed site security program will be supplied during the initial field mobilization in 2015.

 

24.3 Hazardous Waste Management

Specific procedures for waste management and spill response will be implemented for the construction period. These procedures will cover compliance, auditing and reporting requirements. Procedures regarding on-going cleanup and rubbish removal, as well as safe handling, storage and disposal of batteries, fuels, oil and hazardous materials, will be

 

 

24-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

established and observed for the duration of the construction phase. Waste will be recycled to the extent feasible. Ongoing dust suppression and rain water management programs will also be established and observed for the duration of the construction phase. Specific procedures and storage areas will be designated for construction waste prior to recycling or removal from the plant. Solid waste will be disposed of in designated pits. New Gold plans to operate the Project in accordance with the International Cyanide Management Code.

 

24.4 Execution Strategy

Under the direction of a Construction Management (“CM”) team, field construction contractors will commence work once engineering tasks are well advanced and long lead times for the delivery of major equipment are confirmed.

Remaining basic engineering and detailed engineering begins early in the Project. Construction work packages will be issued on a fixed-price basis dependent on the level of engineering progress. Otherwise, construction work packages will be based on a unit price structure incorporating calculated quantities and an estimated budget or target price. Contract packages will be designed for cost and schedule efficiency.

 

24.5 Management Procedures

The Project Team (the “Team”) including the Owner, project management team, engineers and construction managers are responsible for bringing the Project in on time and within budget.

Figure 24-1 shows the Project Management Organization Chart envisaged as the Project moves into detailed engineering, procurement and construction.

 

 

24-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 24-1: Project Management Organization Chart

 

 

24-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

24.6 EPCM Project Controls and Reporting

Project Controls will be implemented to provide the project management and the Owner with timely, updated reports on the project status for analysis and control, ensure that the project scope is completed on time and within budget including; budgeting, incurred cost, actual cumulative capital cost, final cost forecasts, reasons for variances, and monthly cash flows. The periodically updated information will include updates of scope, budget, commitments, schedule, and trends.

Baseline Definition

At the start of basic definition phase, the EPCM contractor will assemble a task force of experienced project personnel who will complete documentation for the “Baseline Definition”. This documentation will include:

 

 

Project execution plan;

 

 

Project schedule;

 

 

Project cost estimate;

 

 

Project control budget;

 

 

List of engineering deliverables;

 

 

Project Manpower Forecasting and Leveling (“MFL”);

 

 

Project Manual including project instructions.

Scope and Engineering Management

Once the Baseline Definition is completed, the project enters the execution phase and any variations will be documented through coordination meetings and various types of reviews. Engineering Deliverables will be progressed on a monthly basis, earned value and forecast hours to complete calculated.

Cost and Change Management

Once the budget structure and the baseline schedule have been completed and approved by the project management team and the Owner, the baseline budget will be developed and serve as reference for project cost control and management. Change management will include tracking all changes through the use of trends and project change notices.

 

 

24-4


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Document Management

The EPCM contractor will put in place a Document Management system that will consist of controlling the document reception and distribution for tender, purchase, construction and review.

Project Status Report

Monthly and weekly reporting will be established as a standard tool to track and monitor progress and budget.

 

24.7 Project Scheduling

Along with the FS, the Project will produce a detailed project schedule that will become the ‘Baseline Schedule’. The overall Project Schedule (“Schedule”) identifies the preferred critical sequences and target milestone dates that need to be managed for the Project to be executed successfully. The detailed schedules track the planned and actual progress throughout the duration of the Project using information provided by the engineering groups, contractors, suppliers, the field management staff and the Owner.

The 22-month project construction duration assumes commencement of field activities in January 2015 and mechanical completion in November 2016. The detailed engineering is scheduled to start in January 2014 to allow sufficient progress to award fixed-price construction contracts. The purchase of major process equipment is assumed to be completed in January 2014 to allow the detailed design of buildings and infrastructures.

The January start schedule specifically takes into account 2014/2015 winter work for activities such as bulk earthworks and concrete placement that could have significant cost impact. These activities were deferred to 2015 without impact to the Mechanical Completion date to mitigate such costs.

The Feasibility Study Project Schedule reflects the Environmental Assessment approval and permits in place to enable commencement of construction activities in January 2015. Detailed engineering is expected to achieve substantial completion in the second quarter (Q2) of 2015, which will facilitate the Project Team’s ability to maximize Lump Sum Construction Contracts.

The key Project milestones are summarized in Figure 24-2.

 

 

24-5


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 24-2: Project Milestones

 

 

24-6


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

After acceptance of the FS and the associated trade-off studies, the implementation of the Project Schedule will begin by ordering outstanding long-lead capital equipment items critical to engineering design. At the same time, detail engineering and remaining basic engineering for the plant and infrastructure will start.

 

24.8 Procurement and Contracts

Purchasing and Expediting Strategy

The EPCM procurement group will provide capital equipment procurement, supplier drawing expediting and coordinate equipment inspection. The procurement group will manage the bidding cycle for equipment and materials to be supplied by the Owner to the contractors. Standard procurement terms and conditions approved for the Project will be utilized for all equipment and materials Purchase Orders. Suppliers will be selected based on location, quality, price, delivery and support service.

 

24.9 Site Development

Highway 600

Construction of Highway 600 will be the subject of a specific road contract. The East Access Road will be included in the major civil contract.

230 kV Overhead Line

The construction of the 230 kV power line will be contracted to a specialized contractor on a design-build basis.

 

24.10 Construction

 

24.10.1 Construction Management Responsibilities

The CM group will be responsible for the management of the construction site under the authority of the EPCM Project Manager. The Construction Manager will be responsible for effectively planning, organizing, and managing the construction quality, safety, budget, and scheduling objectives of the Project.

The CM Field Engineering Team will employ independent Quality Assurance specialists, qualified to CSA, to ensure the implementation and success of the contractor’s quality control.

 

 

24-7


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

24.10.2 Construction Power

The contractors present in the initial phase of the construction will be expected to be self-sufficient in terms of construction electrical power. The main substation at the site and adjoining 230 kV OHL will be constructed by mid-2015. It is anticipated that 230 kV power will be available in July 2015. Pre-commissioning and commissioning of electrical distribution power lines and equipment will commence thereafter. From August 2015, this will supply power to all mine equipment and peak construction power loads for the balance of the construction phase.

The emergency power generators planned for the primary crusher and the process plant will be purchased early and used for operations of the remote water pump house at the Pinewood/McCallum junction. This pump house has to be operational early in the construction schedule in order to pump fresh water to fill up the WMP. The water stored in the WMP is required for plant start-up.

 

24.10.3 Construction Labour Requirement

The RRP construction schedule has been based on a 70-hour work week with some double-shifts, as required. Crew rotations are planned to be three (3) weeks on site and one (1) week off site.

Approximately 1,670,000 man-hours of direct construction labour are anticipated during project construction, excluding mine pre-development and engineering. Construction manpower is expected to peak at approximately 447 direct construction workers on site, as shown in Figure 24-3. The double-peak curve is a reflection of the slowdown of construction work planned for the winter of 2015-2016. The slowdown reflects the project schedule objective, while reducing the expenses related to winter concrete work.

 

 

24-8


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

LOGO

Figure 24-3: Monthly Construction Manpower Graph

 

24.11 Process Facilities

 

24.11.1 Critical Path and Installation Methodology

The Schedule has been presented in association with the established Project Work Breakdown Structure (“WBS”) that defines the elements of project scope, each of which can stand alone with estimate, cost, schedule and accountability.

There is one critical path where there is zero float. It currently runs through the mechanical completion of the SAG mill.

Primary Crusher Installation

Once the foundations for the primary crusher are completed, the MSE retaining walls will be constructed concurrently with the structural and general backfill, as well as the mine truck ramp. The mine truck ramp will be constructed using mine overburden and waste rock, which will be delivered to the crusher area via the mine trucks. This work will be completed by the fourth quarter (Q4) of 2015.

 

 

24-9


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Mill Installations Including Operating Floors

It has been recommended to install the complete operating floor before the mills are installed. This step will eliminate the need to construct temporary platforms around the mill foundations to enable surveying and assembly of the various shells and head sections.

 

24.12 Tailings Management Area (“TMA”) Earthworks

The TMA will be constructed in staged lifts throughout the mine life. Construction of the TMA and Water Management Pond (“WMP”) will commence two (2) years prior to mill start-up to ensure sufficient water collection from spring freshets and water sources for use in the mill process.

Construction is constrained by work that restricts the placement of certain general and rock fills to the warm and dry months of the year. The phased completion of the TMA has been scheduled accordingly, governed in part by the engineer’s quality specifications that will determine the “no-build” restrictions during the winter.

Initial construction of the TMA will begin with the water management pond and the southwest starter dam. Materials for construction will be supplied from the open pit pre-stripping development. An on-site quarry will also be used to supply appropriately sized aggregates.

 

24.13 Commissioning

The EPCM team will be responsible for the installation of facilities, with the exception of all mining activities until mechanical completion.

The Sequence of System Commissioning is vital to shifting the construction schedule from general area completion to more specific system completion to suit the commissioning and start-up of the entire facility.

During the latter part of engineering, the Owner and the CM/Pre-Commissioning team will develop a commissioning plan. The systems will be identified and scheduled for delivery by priority. Packages will be assembled for each system that must be commissioned to include all sign-off and test documentation, drawings and supplier information.

As the various systems are completed and determined by the Construction Management team to be free of deficiencies that would prevent safe operation, they will be transferred to the Pre-Commissioning

 

 

24-10


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

team for dry and wet commissioning. The Pre-Commissioning team will consist of EPCM staff, plant operators and maintenance staff and will enlist the help of suppliers, contractors, engineers and construction management personnel, as needed, to dry run and then wet run the systems until they are finally accepted by the Owner’s operations management for the commencement of ramp-up. The transfer of systems will be formally documented and will include all mechanical/electrical testing documents and supplier information.

 

24.14 Mechanical Completion

Mechanical Completion is a term used with contractors, and often defined in contracts to designate the point at which the contractor is considered to have completed his work such that the Owner may operate the facility in a safe manner. The facility may not be completely finished at such time; however, mechanical completion may pertain to a building or a system, for example the fresh water system. Mechanical Completion is often descriptive of Substantial Completion at which time a full punch list of deficiencies remaining is developed by the contractor, the Construction Management team and the Owner, and used to measure the progress to Final Completion. This period in the Project represents the greatest safety risk as the push to complete construction interfaces with the first energization of facilities and equipment. However, before this point is reached, procedures will be established such that electrical lockout is ensured, hazards identified, and communication protocols established.

 

24.15 Risk Management

The formal risk management program began during the initial feasibility study phase, and will continue through to commissioning. The project team will review all aspects of the Project throughout the developmental stage, inclusive of environmental, technical, health and safety, community, business and project delivery issues. These reviews will identify the relevant risks and or opportunities associated with this Project, assess those risks and opportunities against the outcome objectives and determine the best way to eliminate or control those risks or take advantage of opportunities that may present themselves.

 

 

24-11


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

25. INTERPRETATION AND CONCLUSIONS

This Feasibility Study indicates that the Rainy River Project can support a 19,500 tpd open pit and a 1,500 tpd underground mine. Support is based on the total direct processing of Proven and Probable Mineral Reserves of 66.9 Mt grading 1.54 g/t Au and 3.26 g/t Ag, and 37.4 Mt of stockpile Proven and Probable Mineral Reserves grading 0.38 g/t Au and 1.99 g/t Ag. The QP’s have read the following conclusions and made the following interpretations:

 

25.1 Sampling Method, Approach and Analyses

Rainy River used industry best practices to collect, handle and assay core samples collected during the period from 2005 to 2013. All drilling and sampling was conducted by appropriately qualified personnel under the direct supervision of appropriately qualified geologists.

Rainy River has partly relied on the internal quality control measures of the accredited laboratory; however, they have also implemented external analytical quality control measures, consisting of inserting control samples (blanks and certified reference material, and field duplicates) with each batch of core drilling samples submitted for assaying.

In the opinion of SRK, the field sampling and assaying procedures used by Rainy River meet industry best practices.

 

25.2 Data Verification

The gold grades can be reasonably reproduced, suggesting that the assay results reported by the primary assay laboratories are sufficiently reliable for the resource estimation used in this Feasibility Study.

Upon completion of the validation procedures, SRK concludes that the digital database for the Rainy River Project is also reliable for resource estimation.

 

 

25-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

25.3 Mineral Resources

SRK reviewed and audited the exploration data available for the Rainy River Project as well as the exploration methodologies adopted to generate this data. Exploration work is professionally managed and procedures are adopted that generally meet accepted industry best practices. SRK is of the opinion that the exploration data are sufficiently reliable to interpret with confidence the boundaries of the gold-rich sulphide mineralization and support evaluation and classification of mineral resources in accordance with generally accepted CIM Estimation of Mineral Resource and Mineral Reserve Best Practices Guidelines and CIM Definition Standards for Mineral Resources and Mineral Reserves.

The drilling database includes information from 1,665 core boreholes (742,424 m), which includes 230 boreholes (79,575 m) drilled within the Intrepid Zone during the period from 1996 to August 16, 2013, which has been added since the previous October 2012 mineral resource model. The mineral resource statement effective November 2, 2013 is shown in Table 25-1.

SRK considers the mineral resource model document herein to be sufficiently reliable to support engineering and design studies to evaluate the viability of a mining project at a feasibility level.

 

 

25-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 25-1: Mineral Resource Statement, Rainy River Gold Project, Ontario,

SRK Consulting, November 2, 20131,2,3,4,5

 

     Quantity
‘000t
     Grade      Metal  

Category

      Au
gpt
     Ag
gpt
     Au
‘000 oz
     Ag
‘000 oz
 

Direct Processing Material

              

Open Pit2

              

Measured

     20,282         1.45         1.93         947         1,261   

Indicated

     80,411         1.35         2.55         3,486         6,584   

O/P Measured & Indicated

     100,693         1.37         2.42         4,433         7,846   

Inferred

     9,388         0.97         2.28         292         687   

Underground2

              

Measured

     89         4.95         2.75         14         8   

Indicated

     5,469         4.53         11.34         796         1,994   

Measured & Indicated

     5,558         4.53         11.20         810         2,002   

Inferred

     2,641         4.46         8.30         379         707   

Stockpile Material3

              

Open Pit

              

Measured

     6,294         0.37         1.29         74         262   

Indicated

     64,816         0.44         2.17         919         4,526   

Measured & Indicated

     71,110         0.43         2.09         993         4,788   

Inferred

     8,626         0.37         1.16         102         323   

Combined Direct Processing and Stockpile Mineral Resources

              

Measured

     26,665         1.21         1.79         1,035         1,531   

Indicated

     150,696         1.07         2.70         5,202         13,104   

Measured and Indicated

     177,361         1.09         2.57         6,236         14,635   

Inferred

     20,655         1.16         2.58         773         1,717   

 

1 

Mineral resources are reported in relation to conceptual pit shells which are limited to 150m below sea level and are inclusive of the Intrepid Zone.

2 

Open pit mineral resources are reported at a cut-off grade of 0.30 g/t gold, underground mineral resources are reported at a cut-off grade of 2.50 g/t gold based on a gold price of US$1,400 per ounce, a silver price of US$24.00 per ounce, a foreign exchange rate of C$1.10 to US$1.00, gold recovery of 88% for open pit resources, 90% for underground resources and a silver recovery at 75% for all mineral resources.

3 

Direct processing material is defined as mineralization above a cut-off of 0.45 g/t gold and likely to be mined and processed directly.

4 

Stockpile material includes all material within conceptual open pit shells above a cut-off of 0.30 g/t gold and below a 0.45 g/t gold cut-off as well as material within the CAP zone (code 500) that is suitable for stockpiling and future processing based on average metallurgical recoveries of 88% gold and 75% silver.

5 

Qualified Persons – The mineral resource statement was prepared by Dorota El-Rassi, P.Eng. (APEO #100012348) and Glen Cole (APGO #1416) from SRK Consulting (Canada) Inc., both Independent “Qualified Persons” as that term is defined in Canadian National Instrument 43-101.

 

 

25-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

A comparison between the October 2012 and the November 2013 Mineral Resource Statements is shown in Table 25-2. The reduction in Measured and Indicated Open Pit Mineral Resources grade is primarily due to the increase in block size in 2013 and the reduction in reporting cut-off grade. The reduction in Inferred resources is due to a difference in mineral resource reporting methodology in relation to a conceptual pit shell. The increase in the Underground Mineral Resources is primarily due to the addition of the Intrepid Zone to the Mineral Resource Statement.

Table 25-2: Comparison of October 2012 and November 2013 Mineral Resource Statements

 

     Quantity     Grade (g/t)     Contained Metal (oz.)  

Classification

   (tonnes)     Gold     Silver       Gold         Silver    

Open Pit

          

Measured

     -4     -10     -6     -13     -9

Indicated

     +15     -12     -11     0     +3

Measured & Indicated

     +11     -13     -9     -2     1

Inferred

     -81     -6     -22     -82     -85

Underground

          

Measured

     +1     +0     +0     +0     +0

Indicated

     +32     +1     +85     +33     +144

Measured & Indicated

     +31     +1     +85     +32     +143

Inferred

     +194     +7     +79     +216     +428

 

25.4 Sampling Preparation, Analysis and Security

Rainy River personnel used care in the collection and management of field and assaying exploration data. In addition, the sampling preparation, security and analytical procedures used by Rainy River are consistent with generally accepted industry best practices and are therefore adequate.

 

25.5 Mining Methods and Reserves

The combined open pit and underground mine mineral reserves are summarized in Table 25-3. This summary is reported at two (2) gold equivalent cut-off grades. Open pit mineral reserves are reported at a cut-off grade of 0.30 g/t Au eq., whereas underground quantities are reported at a cut-off grade of 3.5 g/t Au eq. The summary of mineral reserves includes both dilution and mining recovery factors.

 

 

25-4


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Table 25-3: Open Pit and Underground Proven and Probable Mineral Reserves1,2,3,4,5,6

 

Mineral Reserves Category

   Tonnage
(‘000 t)
     Au Grade
(g/t)
     Ag Grade
(g/t)
     Contained
Metal Au (koz)
     Contained
Metal Ag (koz)
 

Direct Processing Material

  

Open Pit

              

Proven

     15,839         1.47         2.04         746         1,038   

Probable

     46,866         1.26         3.05         1,896         4,594   

Underground

              

Proven

     —           —           —           —           —     

Probable

     4,187         4.96         10.31         668         1,388   

Total Direct Processing Material

     66,892         1.54         3.26         3,311         7,021   

Stockpile Material

              

Open Pit

              

Proven

     6,843         0.38         1.51         84         332   

Probable

     30,541         0.39         2.10         378         2,058   

Total Stockpile Material

     37,384         0.38         1.99         462         2,390   

Combined Direct Processing and Stockpile Material

              

Open Pit

              

Proven

     22,681         1.14         1.88         830         1,370   

Probable

     77,407         0.91         2.67         2,275         6,652   

Total

     100,088         0.96         2.49         3,105         8,022   

Underground

              

Proven

     —           —           —           —           —     

Probable

     4,187         4.96         10.31         668         1,388   

Total

     4,187         4.96         10.31         668         1,388   

Total Combined

              

Proven

     22,681         1.14         1.88         830         1,370   

Probable

     81,594         1.12         3.06         2,943         8,040   

TOTAL

     104,275         1.13         2.81         3,773         9,410   

 

1. 

Open pit mineral reserves have been estimated using an optimized pit shell based on metal prices of USD $800 per ounce gold and USD $25 per ounce silver, a foreign exchange rate of CAD $1.05 to USD $1.00, gold recovery of 89.9% (non-CAP zone) and 74.3% (CAP zone) and a silver recovery of 67.1% (non-CAP zone) and 69.5% (CAP zone). The cut-off grade is based on a gold price of USD $1,200. Underground reserves have been estimated from mining shapes generated using a cut-off grade of 3.5 g/t gold-equivalent. Development material from stope access drives above a cut-off grade of 1.5 g/t gold-equivalent is also assumed to be sent to the mill for processing. Underground breakeven cut-off grade calculated at 2.75 g/t gold-equivalent based on metal prices of USD $1,300 per ounce gold and USD $22 per ounce silver, a foreign exchange rate of CAD $1.05 to USD $1.00, gold recovery of 95% and a silver recovery of 75%.

2. 

Open pit reserves have been estimated using a dilution of 4% at 0.21 g/t Au and 1.19 g/t Ag. An average dilution of 11.7% for the underground stoping (8.3% total underground, inclusive of development ore), which includes dilution from both overbreak and backfill. Open pit and underground reserves have been estimated using a mine recovery of 95% and 96.5%, respectively.

3. 

Open pit direct processing material is defined as mineralization likely to be mined and processed directly and above a variable cut-off grade ranging from 0.3-0.7 g/t.

4. 

Stockpile material includes all material within designed open pit between variable cut-offs described above in Note 3, as well as material within the CAP zone (code 500) that is suitable for stockpiling and future processing.

5. 

Mineral Reserves for the open pit are derived from the resource model effective November 2, 2013. Models for the underground reserves were derived from the August 2013 and September 2013 models for the main ODM zone and Intrepid Zone, respectively. Models were prepared by Dorota El-Rassi, P.Eng. (APEO #100012348) and Glen Cole, P.Geo. (APGO #1416), of SRK, both independent “Qualified Persons” as that term is defined in Canadian National Instrument 43-101. The combined mineral resource statement, including the Intrepid Zone, was provided to BBA on November 2, 2013. Rainy River’s exploration program in Richardson Township is being supervised by Mark A. Petersen, (AIPG Certified Professional Geologist #10563), Vice President, Exploration for New Gold and a “Qualified Person” as defined in Canadian National Instrument 43-101. New Gold continues to implement a rigorous QA/QC program to ensure best practices in drill core sampling, analysis and data management.

6. 

Qualified persons -The open pit portion of the mineral reserve statement was prepared under the supervision of Patrice Live (OIQ #38991) of BBA, and the underground portion of the mineral reserve statement was prepared by Colm Keogh, P.Eng. (APEGBC #37433) of AMC Mining Consultants (Canada) Ltd., both independent “Qualified Persons” as that term is defined in Canadian National Instrument 43-101.

 

 

25-5


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Open Pit Mining

Conventional open pit mining has been chosen as the primary method to extract the Rainy River deposit because of the deposit’s geometry and proximity to the surface. The primary equipment fleet at the peak of operations consists of: three (3) hydraulic shovels (2 x 26 m3, 1 x 29 m3), one (1) wheel loader (18 m3), 22 haul trucks (220 t class), three (3) DTH drills (8.5”) and a fleet of support equipment. Operating bench heights of 10 m have been planned for mining operations. Over the life of the mine, a total of 318.2 Mt of waste rock and 73.6 Mt of overburden will be moved. The operational open pit stripping ratio, excluding waste and overburden stripping during the development phase is 3.5:1.0. It is anticipated that all overburden will be removed within the first seven (7) years of mine operation. Mined waste and overburden will be stored in nearby stockpiles or used in dam construction activities associated with the Tailings Management Area (TMA) or blended in cement and used as backfill material for the underground mine.

The LOM mining operating cost is estimated at $2.04/t mined (including waste, ore and overburden). Open pit mining operating costs include costs for the fleet of primary, support and auxiliary equipment, maintenance, electricity and fuel costs, hourly labour and salaried personnel, blasting costs and services. The mine mobile fleet unit operating cost is based on both suppliers data requested during the Feasibility Study and from BBA’s recently updated database. At the peak of open pit mining, a workforce of 318 persons (staff and hourly employees) will be required.

Underground Mining

The proposed underground mine design supports the extraction of 1,500 t/d of ore by longitudinal longhole open stoping (“LHOS”), a mining technique suitable for the geometry and ground conditions of the Rainy River underground resources. Backfilling with cemented aggregate fill (“CAF”) is a significant aspect of the project with respect to maximization of both resource recovery and mining productivity. Modern trackless equipment will be employed in the majority of mining activities.

A main decline from a surface portal located to the east of the open pit will be used to access the mine. A fleet of 7 m3 Load Haul Dump trucks (“LHDs”) and 45-tonne trucks will be used for material loading and transport from the various underground working areas through an internal ramp system that connects all levels to the main decline. Loading will occur in close proximity to the stoping areas and ore will be hauled directly to a surface coarse ore stockpile adjacent to the portal.

 

 

25-6


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

An extensive underground development program that attains a peak of 560 m/month of jumbo advance is required to develop and maintain access to adequate resources to sustain 1,500 tpd of ore production. The ramp-up period to full production will require five (5) years from the onset of mine development. Waste generated through infrastructure development will be disposed of in underground stopes whenever operationally practical, however, an estimated excess of 1.80 Mt must be hauled to the surface waste stockpile over the life of mine.

Key mine infrastructure includes a backfill delivery raise that terminates at an underground truck loading station, a cement storage and grout mixing facility, two (2) main dewatering stations, an equipment maintenance facility, electrical substations, and other smaller, ancillary installations. Permanent fans located on surface will provide fresh air to the mine. A propane air heating system will be used during the winter months.

The LOM average underground operating cost has been estimated to be $90.10 /t ore mined. Underground mining costs include labour, mine general costs, LH stoping, ore development, waste development, backfill and mine maintenance. A maximum of 176 people will be required in Year 5 (2021) and 168 people in the Project peak year (Year 5, 2021).

 

25.6 Metallurgy, Processing and General & Administrative

The results from the SGS testwork program are the basis for the mineral reserve estimate and Feasibility Study. Based on a trade-off study, it was determined that the whole rock leaching option with gravity separation was the most economic alternative and was therefore used as the basis for the original 2013 Feasibility Study and for this Feasibility Study. The main reasons for this selection were the significant amount of energy associated with regrinding the flotation concentrate and the high cyanide consumption in the flotation concentrate leaching, in addition to risk associated with ultrafine grinding of this material. All subsequent testwork was based on cyanide leaching of the gravity tailings.

An extensive grinding testwork campaign has allowed for definition of the overall hardness of each zone and indicated that there are several portions of the deposit that will have high energy requirements and this is reflected in the design of the process plant.

 

 

25-7


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The design A x b value is 24.2, which corresponds to the 80th percentile of the testwork data, weighted by zone. The strong correlation between the four (4) methods and consultant used to size the grinding circuit provides a good level of confidence in the sizing of the SAG and ball mills. The grind size chosen for this study was 75 µm, based on a cost versus revenue study performed by BBA.

The process circuit is designed for a throughput of 21,000 tpd and will incorporate primary crushing, semi-autogenous milling with pebble crushing of the oversized material, ball milling, gravity and cyanide leach, followed by gold and silver recovery by carbon-in-pulp (CIP), cyanide destruction system, stripping and electrowinning of the pregnant strip solution.

The process is expected to yield an overall gold recovery including solution losses of approximately 0.6% (average), ranging from 90-91% (LOM: 90.6%), and a silver recovery including solution losses of approximately 2-3%, ranging from 63-65% over the life of mine (LOM: 64.1%). It is anticipated that, over a mine life of 14 years, approximately 3,402 koz. of gold and 6,004 koz. of silver will be produced.

The average life-of-mine processing operating costs were determined to be $9.25 per tonne milled. The operating costs are based on metallurgical testwork, the mine plan, New Gold salary compensation/benefit guidelines, and recent supplier quotations. The operating costs include reagents, consumables, grinding media, personnel (including contractors), electrical power, and propane. A full personnel list has been developed and it is expected that 91 people will be required for the processing plant. This number is not expected to vary significantly over the life-of-mine.

The average life-of-mine General and Administrative (“G&A”) operating costs were determined to be $1.54 per tonne milled. The operating costs include Human Resources, Site Administration, Management and Insurance, Infrastructure Power, Health and Safety Supplies, First Nations Participation Agreement Payments, Security and Paramedic Services, Environmental Costs, Personnel, Information Technology (“IT”) and Training. A full personnel list has been developed and it is expected that 29 people will be required for G&A. This number is not expected to vary significantly over the life-of-mine.

 

 

25-8


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

25.7 Infrastructure

 

Buildings

The main administration building will be located at the entrance of the mine site and will house administration and safety/security staff only.

The mine garage will have a total of six (6) maintenance bays, including two (2) bays for auxiliary vehicles and one (1) bay dedicated for welding. The truck wash facility will be accessible from outside the building through two (2) garage doors.

The mine office will be located next to the truck shop and will house the mine, maintenance and mine engineering office staff. The process plant office will be located on the west side of the process building between the leach tanks and the pre-leach thickener and will be connected to the main building via a short corridor.

Roads

Mine haul roads will be built at the start of the Project and will remain in use for the duration of the mine life. Site access roads to the tailings management area and to the explosives plant are already existing roads which will be enlarged and resurfaced with crushed stone.

Based on the findings of the TBT study, the preferred alignment for rerouting Highway 600 around the proposed development area optimizes the use of existing road easements and is the preference of both the Township of Chapple and Rainy River Resources. Access to Marr Road will be provided via Korpi Road and the new East Access Road.

Tailings Management and Dam Design

The total volume of tailings produced over the mine life will be approximately 75 Mm3 at a deposited dry density of 1.4 t/m3, and its location to the northwest of the open pit was selected in consideration of the topography, location of the pit and watershed boundaries, availability of dam construction materials and suitability for a flooded water cover for closure.

The water management system developed by AMEC is designed to: generate a reliable water source for process plant operations and ancillary uses while optimizing the quantity and quality of site effluents released to the environment. Water will be recycled from various manmade ponds for process water, in order to minimize the volume of fresh water to be taken from local watercourses. The system has been designed to ensure a reliable water supply at all times of the year and to allow for contingencies, such as dry years.

 

 

25-9


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

The system includes five (5) constructed ponds for water management, in addition to sediment control ponds and a primary freshwater source. A constructed wetland is proposed downstream of the TMA and may act as part of the site effluent treatment system.

Electricity

The total power demand of the Project was determined to be approximately 58 MW based on the estimated connected load, running load and running power. Electricity will be supplied by a proposed new 17 km long 230 kV power line to be built and subsequently connected to the existing 230 kV Hydro One line connecting Fort Frances and Kenora.

 

25.8 Environmental Permitting

The process of environmental permitting is well understood and a preliminary schedule outlining the critical steps has been developed in this study and has been integrated into the preliminary Project execution schedule. The obtaining of environmental approvals is on the Project’s critical path and no construction activities can commence until the required permits and authorizations are obtained.

There is considerable environmental baseline information currently available regarding the site and the surrounding area, compiled through extensive field investigations conducted over a 5-year period. Based on the information available to-date, there are no environmental aspects that are considered to be limiting to the Project’s development, as the Project design has considered appropriate environmental mitigation measures including avoidance of critical areas as practical.

 

25.9 Financial Analysis

The initial capital cost of the Project is estimated to be $931M; with a sustaining capital of $366M. The life-of-mine all-in sustaining cash cost is USD $765/oz. Au, including silver credits and royalty payments. The life-of-mine operating cash cost is USD $663/oz. The pre-tax Project NPV is estimated to be $462M using a discount rate of 5% and an after-tax NPV of $330M using a discount rate of 5%. The Project’s pre-tax internal rate of return (IRR) is estimated to be 13.1% and the pre-tax payback period of the Project is 5.4 years.

 

 

25-10


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

New Gold compiled the taxation calculations for the Project. The federal rate applicable to resource profits is 15%. Ontario’s taxation of the resource sector is generally harmonized to the federal system. The provincial corporate income tax rate applicable to mining income is 10%. A combined rate of 25% is used in the model to compute the federal and provincial tax liability in respect of the Rainy River Project. As well, in the earlier years of the project, the Ontario Corporate Minimum Tax was computed at a rate of 2.7%. All deductions and rates are based on currently enacted legislation. In addition, Ontario’s Mining Tax Act is levied at a rate of 10% on annual taxable profits in excess of $500,000.

After tax NPV is estimated to be $330M using a discount rate of 5%. The Project IRR (after tax) is estimated to be 11.3% and the simple after tax payback period is 5.5 years.

The pre-tax discounted sensitivity analysis indicates that positive project returns can be achieved over the likely range of variation in capital costs (± 30%), operating costs (-30% / +27%), gold prices (-14% / +30%), and a USD foreign exchange rate (-14% / +30%). The project financials are most sensitive to metal price and metal recovery.

 

25.10 Conclusion

Based on the information available and degree of development of the Project as of the effective date of this Report, it is BBA’s opinion that the Rainy River Project is sufficiently robust, both technically and financially, to warrant proceeding to the next stage of project development, consisting of final design and Detailed Engineering. This conclusion is based on the recommendations and work plan as presented in Chapter 26. However, the final decision to proceed with a construction of a mining operation at the Rainy River Project site is at the discretion of New Gold.

 

 

25-11


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

26. RECOMMENDATIONS

BBA recommends that New Gold proceed with the detailed engineering phase based on the results of this updated Feasibility Study and the Project risks/opportunities identified. However the decision to proceed with a mining operation on the Rainy River Project is at the discretion of New Gold. The suggested work program includes the following components:

 

 

Continuation of open pit and underground mine design optimization;

 

   

Consideration of an underground mining test program within the Intrepid Zone;

 

 

Procurement of long lead time mining and process equipment;

 

 

Continuation of preparatory work to secure electrical power and procurement of long lead time electrical equipment;

 

 

Continuation of key personnel recruitment;

 

 

Continuation of coordinated environmental assessment process;

 

 

Continuation of First Nation, Métis and public consultations;

 

 

Continuation of hydrogeological studies in specific areas;

 

 

Secure required permits and authorizations from government and regulatory agencies;

 

 

Continuation of value and detailed engineering activities; and

 

 

Construction of the Project (following appropriate approvals).

 

26.1 Proposed 2014 Work Program Budget

In order to advance the Project according to the proposed schedule and this feasibility study, the 2014 budgeted costs for initiation of key project activities are estimated at approximately US $104 M, as shown in Table 26-1.

Table 26-1: Budget for 2014 (US dollars)

 

Activity

   Cost (US $ M)  

Capitalized exploration and condemnation drilling

     14.0   

Property, plant and equipment payments

     60.0   

Detailed engineering and studies

     20.0   

Permitting and environmental monitoring

     10.0   
  

 

 

 

Total

     104.0   
  

 

 

 

 

 

26-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

As of the effective date of this report, New Gold has already budgeted, authorized and initiated a considerable amount of the recommended work as stated in their press release dated February 6, 2014 “New Gold Finishes 2013 with Lowest Costs in its History, Increase Gold Reserves by 127 Percent per Share and Provides 2014 Guidance with Even Lower Costs”

BBA has reviewed New Gold’s 2014 proposal for detailed engineering work, permitting and exploration activities on the Rainy River Project property and considers that the program budget is reasonable. BBA recommends that New Gold implement the program as in order to maintain the proposed Project schedule as described within this Feasibility Study. It should be noted that initiation of these proposed activities and the overall budget are subject to funding, permitting or other matters that may cause the proposed program to be altered in the normal course of New Gold’s business activities, or alterations which may affect the program as a result of the activities themselves. The reader should refer to the Cautionary Note with respect to Forward Looking Information at the front of this Report for more information regarding forward-looking statements, including material assumptions (in addition to those discussed in this section and elsewhere in this Report) and risks, uncertainties and other factors that could cause actual results to differ materially from those expressed or implied in this section (and elsewhere in the Report).

 

26.2 2014 Detailed Recommendations

During the completion of the Feasibility Study, a large amount of work has been completed to bring the various aspects of the Project to its current stage (February 2014). Further development of the Rainy River Project property should address key risks and opportunities that have been identified through the Feasibility Study work program.

Geology and Exploration

 

 

Additional drilling is required to infill the remnant gaps in the drilling data with the potential to increase the mineral resources; infill areas of inferred resources to improve resource classification; and test the lateral and depth extensions of the gold mineralization;

 

 

Geological studies aimed at improving the understanding of the geological and structural setting of the deposit particularly within the silver-enriched zones and the mafic-hosted nickel-copper rich zones, followed by revised 3D modeling;

 

 

26-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

SRK supports and understands New Gold’s wish to consolidate and re-interpret currently available data with the objective to optimize data extraction and knowledge to help guide future local exploration and regional exploration efforts: and

 

 

Condemnation drilling to support mine infrastructure design.

New Gold has budgeted approximately US $14 M for exploration related activities to test the potential of the company’s land package in 2014. The program is scheduled to include 35,000 to 40,000 metres of exploration drilling of which approximately 70% will be dedicated to testing new targets around known ore bodies and along newly recognized district trends. The remaining 30% of the drilling is for completion of condemnation drilling within the immediate project development area. This proposed condemnation/exploration drilling program is considered to be aligned with the recommendations of this Study.

Open Pit and Underground Mining

 

 

To review the current overburden material stockpiling approach;

 

 

Revisit the elevated open pit cut-off grade strategy using the current mill throughput and mining method to maximize the positive NPV impact;

 

 

Continue with value engineering initiatives;

 

 

To review the open pit slope as more data is collected and available;

 

 

To develop a detailed operational mine plan for pre-production and for the first two (2) years of operation;

 

 

Consider an underground bulk sample program within the Intrepid Zone to validate ground conditions, operating assumptions, grade distribution, and to reduce the level of uncertainty associated with the future larger scale investment in mine development. Consideration should be given to commencing this program earlier than the current scheduled start of underground activity in 2017;

 

 

Further optimization of the underground mine design and schedule should be undertaken following the test mining program; and

 

 

Underground cut-off grade optimization work should be undertaken in tandem with the mine design optimization work.

AMC estimates that $30M would be sufficient funds for the bulk sample program work that includes:

 

 

26-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

Portal entry construction.

 

 

2900 m of lateral development under contract, of which nearly 500 m would be within mineralized horizons. A 100 m waste drift to permit definition drilling has also been provided.

 

 

208 m of raise development for ventilation and secondary egress.

 

 

All stationary equipment including fans, dewatering equipment, electrical distribution and refuges.

 

 

5000 m of definition drilling.

 

 

Owner’s costs and a 15% contingency have been included in the $30M estimate. It should be noted that costs for the work described above have been included in the mine-wide underground development capital estimate (Section 21).

Open Pit Geotechnical Design

The design specifications for Zone 3, the north wall of the ODM/17 are primarily based on the geotechnical drilling in Zone 1 (south wall) of the ODM/17, with confirmation from the televiewer data of the exploration boreholes in the central core of the pit, and are adequate for this level of study. It is recommended however to confirm variation in the dip of the controlling foliation set from east to west and north to south with either:

 

 

Additional televiewer surveys or;

 

 

Two (2) additional boreholes either side of the pit centre towards the north.

Underground Geotechnical Design

 

 

The main underground zones of the ODM/17 have been investigated with three (3) geotechnical boreholes and supplemented with televiewer surveys from exploration boreholes in the central zone. The level of information is adequate for the present Study, however, it is recommended that further investigations are performed in line with other geotechnical bedrock drilling;

 

 

All further exploration cores should be photographed prior to splitting and logged to record rock quality designation (“RQD”) values. This information is significantly useful to supplement any directed geotechnical program;

 

 

The underground water inflow estimates and sump design should be updated in the next phase of work to consider inflow from the open pit into the stopes.

 

 

26-4


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

Geotechnical investigation should be performed for the portal location and for the first 300 m of the ramp;

 

 

Geotechnical investigation should be performed for all major raises from surface to the underground mine. This should be in the form of geotechnical pilot holes for the main ventilation shafts and backfill raise;

 

 

Variance in the open pit and underground mining geometry due to changes in the cut-off grade should be investigated as to their impact on infrastructure through rock mechanics and hydrogeological studies; and

 

 

It is recommended that once the ramp has reached a depth approaching 500 m, that in-situ stress over coring tests are performed preferably at two locations separated vertically by 100 m to 150m.

Metallurgical Testing and Processing

 

 

Hydraulic testing for the final confirmation of tailings pumping characteristics and thickener settling characteristics;

 

 

Continue with value engineering initiatives;

 

 

Additional testwork for thickener sizing and flocculant dosages to optimize sizing of thickeners and flocculant system;

 

 

Additional testwork for equipment sizing, as required;

 

 

Investigate the design circulating load for the ball mill circuit to potentially improve grinding efficiency.

Infrastructure

 

 

Continue with value engineering initiatives;

 

 

Prepare a site material balance by month to confirm usage and source of material for roads, backfill and aggregates; complete the assessment of available quantity of material from the former MOT borrow pit;

 

 

Submit application for electrical power to IESO Ontario.

Environmental and Tailings Management

 

 

Environmental assessment(s) and consultation/engagement activities should proceed with the objective of gaining environmental approval for the Project in line with the overall Project schedule;

 

 

26-5


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

 

Geochemical characterization should continue as the processing and mining plans are detailed, with modification to the mineral waste management plan as appropriate;

 

 

Estimated reclamation costs and bonding requirements should be reassessed in the next phase of development as more detailed engineering designs become available;

 

 

The design of the water treatment plant at the TMA should be optimized during detailed design (Section 18.9.2);

 

 

Supplemental geotechnical site investigations at the dam sites are required to better define the foundation conditions for construction material quantity estimation, particularly for the west dam of the TMA. Shallow or exposed bedrock foundations may require treatment based on the rock quality; and

Additional work should be carried out for delineation and characterization of local clay borrow areas and the mine waste overburden suitable for dam construction

 

 

26-6


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

27. REFERENCES

AMEC, 2011. Rainy River Project, 2011 Wildlife Baseline Study.

AMEC, 2012. Estimated Groundwater Seepage into Proposed Underground Mine Workings at the Rainy River Gold Project. Technical Memorandum for Rainy River Resources Ltd. Submitted November 15, 2012.

AMEC, 2012A. Rainy River Gold Project - Site Investigations. Report - Rock Mechanics Site Investigation/Joint Mapping and Rock Mass Characteristics (TC113921) version Draft. Document prepared by AMEC Environment & Infrastructure, submitted to Rainy River Resources Ltd. on May 4, 2012.

AMEC, 2012a. Overburden Material Delineation, Rainy River Gold Project - Feasibility Study. Technical Memorandum TC121506 prepared by AMEC Environment & Infrastructure, submitted to Rainy River Resources Ltd., November 2, 2012.

AMEC, 2012B. Rainy River Gold Project - Site Investigations. Preliminary Summary – Preliminary Rock Mechanics Overview (TC113921) Version 1. Document prepared by AMEC Environment & Infrastructure, submitted to Rainy River Resources Ltd. on July 27, 2012.

AMEC, 2012C and 2012c. Rainy River Gold Project - Site Investigations. Report - 2011 Geotechnical and Hydrogeological Investigation Report (TC113921) Vversion 3. Document prepared by AMEC Environment & Infrastructure, submitted to Rainy River Resources Ltd. on August 8, 2012.

AMEC, 2012D. Rainy River Resources Limited - Rainy River Feasibility Study Rock Mechanics Site Investigation Laboratory Testing Of Intact Rock Core (Draft - TC113921) Document Prepared by AMEC Environment & Infrastructure. Submitted to Rainy River Resources Ltd. on August 17, 2012.

AMEC, 2012E. Rainy River Gold Project - Feasibility Study. Drawing - Pit Design Zone Recommendations -Pit Shell (TC121506). Document prepared by AMEC Environment & Infrastructure, submitted to BBA on October 3, 2012.

AMEC, 2012F and 2012f. Rainy River Gold Project - Feasibility Study. Open Pit Overburden Slope Design Considerations (TC121506) Vversion 3. Document prepared by AMEC Environment & Infrastructure, submitted to Rainy River Resources Ltd. on October 31, 2012.

AMEC, 2012G. 2012 Hydrogeological Baseline Study (TC111504), Rainy River Gold Project, Rainy River Resources Limited, Draft report, prepared by AMEC Environment & Infrastructure, submitted to Rainy River Resources Ltd. on December 17, 2012.

AMEC, 2012H. Rainy River Aquatic Resources 2011 Baseline Investigation.

AMEC. 2012I. Rainy River Project, 2011 Wildlife Baseline Study.

 

 

27-1


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

AMEC. 2012J. Rainy River Project, 2011 Species at Risk Report.

AMEC. 2012K. Rainy River Project, 2012 Terrestrial Baseline Study.

AMEC. 2012L. Rainy River Project, 2012 Species at Risk Report.

AMEC, 2013A. Rainy River Underground Ground Support Recommendations Memo (Draft - TC121506) Document prepared by AMEC Environment & Infrastructure. Submitted to Rainy River Resources Ltd. and Golder Associates Limited, March 2013.

AMEC, 2013a. Geotechnical and Hydrogeological Site Investigations, Rainy River Gold Project. Report TC113921.100 by AMEC Environment & Infrastructure, submitted to Rainy River Resources Ltd., February 26, 2013.

AMEC, 2013B. Rainy River Cemented Rockfill Feasibility Study Test Program - Interim Report (Draft – TC121506). Document prepared by AMEC Environment & Infrastructure, Submitted to Rainy River Resources Ltd., April 2013.

AMEC, 2013b. Geotechnical Recommendations for Plant Site Foundations Rainy River Gold Project - Feasibility Study. Report TC121506.100.6 prepared by AMEC Environment & Infrastructure, submitted to Rainy River Resources Ltd., January 17, 2013.

AMEC, 2013C. Rainy River Resources Limited – Rainy River Feasibility Study Construction Aggregate Source Assessment (Draft – TC121506). Document prepared by AMEC Environment & Infrastructure, submitted to Rainy River Resources Ltd., April 2013.

AMEC, 2013c. Geotechnical Design of the Tailings, Mine Waste and Water Management Facilities – Rainy River Gold Project Feasibility Study. Draft Report TC121506.100.23 by AMEC Environment and Infrastructure, submitted to Rainy River Resources Ltd., April, 2013.

AMEC, 2013D. Rainy River Resources Limited - Rainy River Feasibility Study Rock Mechanics Site Investigation Laboratory Testing of Intact Rock Core (Final - TC113921) Document prepared by AMEC Environment & Infrastructure. Submitted to Rainy River Resources Ltd., April 2013.

AMEC, 2013d. Proposed clay test embankment program, Rainy River Gold Project - Feasibility Study. Technical Memorandum TC121506 prepared by AMEC Environment & Infrastructure, submitted to Rainy River Resources Ltd., January 12, 2013.

AMEC, 2013E. Rainy River Resources Limited - Rainy River Feasibility Rock Mass Characterization Summary Of Geomechanical Site Investigation Program 2012 (Final - TC113921). Document prepared by AMEC Environment & Infrastructure, submitted to Rainy River Resources Ltd., April 2013.

AMEC, 2013e. Water Management Plan – Rainy River Gold Project Feasibility Study. Report TC121506.100.33 by AMEC Environment and Infrastructure, submitted to Rainy River Resources Ltd., April, 2013.

 

 

27-2


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

AMEC, 2013F. Rainy River Resources Limited - Rainy River Feasibility Rock Mechanics Open Pit Stability Analysis Report (Final – TC121506). Document prepared by AMEC Environment & Infrastructure, submitted to Rainy River Resources Ltd., May 2013.

AMEC, 2013G. Rainy River Resources Limited - Rainy River Feasibility Rock Mechanics Underground Mine Design Report (Final – TC121506). Document prepared by AMEC Environment & Infrastructure, submitted to Rainy River Resources Ltd., May 2013.

AMEC 2013h. Treatability Tests for Cd and Zn Removal Rainy River Gold, dated April 2013.

AMEC 2013i. Rainy River Gold Project Feasibility Study: Water Management Pond, dated May 2013.

AMEC 2013j. Rainy River Project – Feasibility Level Treatment Plant Design, in progress.

AMEC 2013k Clay borrow assessment in Water Management Pond area (Doc3098004—004000-A1-ETR-0001-AA)

AMEC, 2013l. Water Management Plan – Rainy River Gold Project Feasibility Study. Report by AMEC Environment and Infrastructure, submitted to Rainy River Resources Ltd., October, 2013.

AMEC. 2013m. Rainy River Project, Climate, Air Quality and Sound Baseline Study.

AMEC. 2013n. Rainy River Project, Socio-economic Baseline Report.

AMEC. 2013o. Rainy River Project, 2012 Aquatic Resources Baseline Report.

AMEC. 2013p. Rainy River Project, Hydrogeology Baseline Report.

AMEC. 2013q. Rainy River Project, Report on Metal Leaching and Acid Rock Drainage Characterization of Mine Rock and Tailings.

AMEC 2013r. Rainy River Project. 2013 Aquatic Resources Baseline Report.

AMEC. 2013s. Rainy River Project. 2013 Species at Risk Report.

AMEC. 2013t. Rainy River Project. 2013 Terrestrial Baseline Study: Bats.

AMEC. 2013u. Rainy River Project. 2013 Fish and Fish Habitat Existing Conditions for Highway 600 Realignment.

AMEC. 2014v. Rainy River Cemented Rockfill Feasibility Study Test Program, Document prepared by AMEC Environment & Infrastructure, submitted to Rainy River Resources, August 2013.

AMEC, 2014Z. New Gold Inc. – Rainy River Project – Underground Rock Mechanics Mine Design Review for the Intrepid Zone and Optimization of the ODM., Document Prepared by AMEC Environment & Infrastructure, submitted to New Gold Inc., February 2014.

 

 

27-3


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Archibald, J.F., 2012. UCS Testing of Rainy River Project Rock Materials. Queen’s University at Kingston. Dated May 27, 2012.

Averill, S., 2008. Description of the Rainy River Project Geology and Mineralization. Internal unpublished report of Rainy River Resources Ltd. 2008.

Ayres, L. D., 1997. A Volcanological Investigations of Rock Units, Structures and Gold Mineralization, Rainy River Project for Nuinsco Resources Ltd., 43 pages. 1997.

Barnett, P.J., 1992. Quaternary Geology of Ontario, in Geology of Ontario. Ontario Geological Survey, Special Volume 4, Part 2, p. 1011-1088. 1992.

Barton, N., Lien, R. and Lunde, J., 1974. Engineering Classification of Rock Masses for the Design of Tunnel Support. Rock Mechanics. p. 186-236. May 6, 1974.

Bieniawski, Z.T., 1989. Engineering Rock Mass Classifications. New York, Wiley. 1989.

BBA, 2013. 3098007-AD0000-33-KCA-0001-02 – Capital Expenditure Estimate: 21,000 TPD Operation. Owner’s Cost Revised. December 18, 2013.

BBA, 2013. 3098007-AD0000-32-JS1-0001-00 – Preliminary EPCM Schedule. Issued for Feasibility Update Study. December 17, 2013.

BBA, 2013. 3098007-AD0000-4M-KCB-0001-00 – Open Pit Mining Operating Costs: 21,000 TPD Operation. Issued for Feasibility Update Study. December 16, 2013.

BBA, 2013. 3098007-AD0000-33-KCA-0003-00 – Basis of Estimate: Escalation Cost Calculation. Issued for Feasibility Update Study. December 13, 2013.

BBA, 2013. 3098007-000000-33-EAN-0001-00 – Construction Camp Versus LOA Trade-Off Study. Issued for Feasibility Update Study. December 13, 2013.

BBA, 2013. 3098007-000000-40-ELI-0001-00 – Detailed Personnel List. Final for Feasibility Update Study. December 4, 2013.

BBA, 2013. 3098007-AD0000-49-KCB-0001-00 – Process Operating Costs: 21,000 TPD Operation. Final for Feasibility Update Study. December 2, 2013.

BBA, 2013. 3098007-AD0000-49-KCB-0002-00 – General and Administrative Costs: 21,000 TPD Operation. Final for Feasibility Update Study. December 2, 2013.

BBA, 2013. 3098007-000000-47-ENC-0001-00 – Calculation Note: Power Demand. Final for Feasibility Update Study. November 29, 2013.

BBA, 2013. 3098007-AD0000-33-AGO-0001-AB – Project Instruction: Cost Escalation Evaluation. Issued for Client Approval. November 27, 2013.

BBA, 2013. 3098007-003210-40-EAN-0001-AA – Technical Note: Evaluation of the Roofing Cost on the Grinding Building. Issued for Comments. November 18, 2013.

 

 

27-4


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

BBA, 2013. 3098007-000000-45-ELI-0001-AA – Mechanical Equipment List. Issued for Coordination. November 15, 2013.

BBA, 2013. 3098007-003000-49-EAN-0001-AB – Analysis: Pre-Detox Thickener Trade-Off Study. Issued for Client Approval. October 21, 2013.

BBA, 2013. 3098007-000000-4M-ERA-0002-00 – Technical Memorandum: Electric and Diesel Shovel Comparison. For Final Issue. October 16, 2013.

BBA, 2013. 3098003-000000-49-ETR-0002-00 -Technical Report – Metallurgical Audit Follow Up. Final Issue. April 4, 2013.

BBA, 2013. 3098003-000000-49-EAN-0001-00 – Technical Report: Gravity/Leaching Gold and Silver Recovery Curves. Final Issue. April 4, 2013.

BBA, 2013. 3098003-004611-40-EAN-0001-01 – Technical Report: CIP and Stripping Circuit Sizing. Final Issue. April 4, 2013.

BBA, 2013. 3098003-000000-49-ETR-0001-01 – Estimated Mill Power Requirements From Grinding Simulations. Final Issue. April 5, 2013.

BBA, 2012. 3098003-004000-40-ETR-0001-00 – Review of Potential Thermal Energy Sources. December 10, 2012.

BBA, 2012. 3098003-004610-40-EAN-0002-00 – Technical Report: Bulk Liquid Oxygen versus On-Site Oxygen Generation. November 23, 2012.

BBA, 2012. 3098003-004000-40-EAN-0001-00 – Water Cooling Systems. November 23, 2012.

BBA, 2012. 3098003-004130-47-EAN-0001-00 – Technical Report: Mill Drive System Comparison. October 31, 2012.

BBA, 2012. 3098003-004610-40-EAN-0001-00 – Technical Report: O2 vs. Air. October 25, 2012.

BBA, 2012. 3098003-AD0000-30-CME-0001-00 – Technical Report: The Comparison of the Flotation Concentrate Leach Option to the Whole Ore Leach Option. April 24, 2012.

BBA, 2013. NI 34-101 Feasibility Study of the Rainy River Gold Project, Ontario, Canada : Re- addressed to New Gold. July 31, 2013.

BBA, 2013. NI 43-101 Feasibility Study of the Rainy River Gold Project, Ontario, Canada. May 23, 2013.

BBA, 2012. NI 43-101 Preliminary Economic Assessment Update of the Rainy River Gold Property, Ontario, Canada. October 12, 2012.

Blackburn, C.E., 1976. Geology of the Off Lake – Burditt Lake area, District of Rainy River, Ontario Division of Mines, Geoscience Report 140, 62 pages accompanied by Map 2325 at 1 inch to 1 mile scale. 1976.

 

 

27-5


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Bloom, 2011. Comparison of Assays at Acurassay and ALS Laboratories. Prepared for Rainy River Resources Ltd., by Analytical Solutions Ltd., dated December 16, 2011.

Botz, M.M, Mudder, T.I., Akcil, A.U., 2005. Cyanide Treatment: Physical, Chemical and Biological Processes. 2005.

Caracle Creek International Consulting Inc., 2008. Independent Technical Report for the Rainy River Property in North-Western Ontario, Canada prepared for Rainy River Resources Ltd., Public document filed on SEDAR, 88 pages. April 30, 2008.

Clark, W., 2012. Power Cost Projections memo prepared for Rainy River Resources Ltd., by SanZoe Consulting Inc., dated October 2012.

Compass International Consultants Inc. 2013. Global Construction Cost and Reference Yearbook 13th Edition. Publisher Compass International Consultants Inc., Morrisville PA USA, Copyright 2005-2013.

Coulson, A.L., 2009. Investigation of the Pre to Post Peak Strength State and Behaviour of Confined Rock Masses Using Mine Induced Microseismicity. PhD Thesis submitted to University of Toronto, 2009 pp 457.

Cundiff, M., 2013. Auditor Report. Rainy River Feasibility Study Independent Review. Feasibility Planning and Schedule. February 9, 2013.

Delkor Solid Solutions, 2012. Delkor Linear Screens Selection. September 14, 2012.

Delkor Solid Solutions, 2012. Thickening of Rainy River Pre-Leach and Pre-Detox. September 14, 2012.

Diederichs, M.S., Coulson, A., Falmagne, V., Rizkalla, M. and Simser, B., 2002. Application of Rock Damage Limits to Pillar Analysis at Brunswick Mine. In Proc. 4th North Am. Rock. Mech. Symp., NARMS ’02, Mining and Tunneling Innovations and Opportunities, Toronto, 2: 1325-1332. July 8-10, 2002.

Dubé, B., Gosselin, P., Hannington, M, Galley, A., 2007. Gold-rich Volcanogenic Massive Sulphide Deposits. Geological Survey of Canada. 2007.

FLSmidth Inc., 2012. Bond Crushability Index Testing. Report prepared for Rainy River Resources Ltd., dated December 2011.

FLSmidth Inc., 2012. Bond Crushability Index Testing. Report prepared for Rainy River Resources Ltd., dated May 2012.

FLSmidth Inc., 2012. Sedimentation Tests on Pre-Leach and Post-Leach Process Samples for Remaining Mine Life and Starter Pit. Report prepared for BBA-Rainy River Project, dated August 2012.

 

 

27-6


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

FLSmidth Inc., Knelson, 2012. Gravity Modeling Report, Report Prepared for Paolo Toscano (Rainy River Resources), dated July 10, 2012.

Golder Associates Ltd., 2013. Underground Mine Design for the Rainy River Gold Project Feasibility Study. Report prepared for Rainy River Resources Ltd., 150 pages,. d8ated May 8, 2013.

Hadjigeorgiou, J., Leclair, J.G. and Potvin, Y., 1995. An Update of the Stability Graph Method for Open Stope Design. 97th CIM-AGM Rock Mechanics and Strata Control Session, Halifax, Nova Scotia. 1995.

Hannington, M.D., Poulsen, K.H., Thompson, J.F.H., and Sillitoe, R.H.,1999, 1999. Volcanogenic Gold in Massive Sulfide Environment: Reviews in Economic Geology, v. 8, p. 325-356. 1999.

Herget, G., 1986. Changes in Ground Stresses with Depth in the Canadian Shield. In Proc. of the Int. Symp. on Rock Stress and Rock Stress Measurements, Stockholm, p. 61-68. 1986.

Hoek, E., Kaiser, P.K. and Bawden, W.F., 1995. Support of Underground Excavations in Hard Rock Rotterdam: Balkema. 215 pages. 1995.

Hrabi, B. and Vos, I., 2010. Rainy River Structural Study Interim Results, Northwestern Ontario. Internal presentation by SRK Consulting (Canada) presented to Rainy River personnel, June 2010.

Johns, G.W., 1988. Precambrian Geology of the Rainy River area, District of Rainy River, Ontario Geological Survey, Map P. 3110 scale 1:50,000 in OGS Miscellaneous Paper 137, p. 45-48. 1988.

Kajmowicz, G., 2009. Quality Control Report for Rainy River Resources in 2008. Prepared by Accurassay Laboratories. Internal report for Rainy River Resources Ltd., 17 pages. January 2009.

Knorr, B and Allen, J. Selection Criteria for Stirred Milling Technologies. Metso Minerals Industries.

Klohn Crippen Berger, 2011a. Preliminary Open Pit Stability Assessment, Project M09559A06. January 2011.

Klohn Crippen Berger, 2011b. Rainy River Project. Geochemical Baseline Report 2008-2010.

Klohn Crippen Berger, 2011c. Geochemical Baseline Report 2008 to 2010.

Klohn Cripper Berger, 2011d. Rainy River Project Species at Risk Baseline Report 2008-2010.

Leggitt, B., 2013. Auditor Report. Rainy River Feasibility Study Independent Review. Project Execution Section 24. February 10, 2013.

 

 

27-7


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Mackie, B., Puritch, E. and Jones, P. 2003. Rainy River Project, Exploration Summary and Mineral Resource Estimate for the #17 Zone, prepared for Nuinsco Resources Ltd. 2003.

Major, K., 2013. Auditor Report. Rainy River Feasibility Study – Independent Review. Metallurgy and Process Plant. February 9, 2013.

Martin, C.D., Kaiser,P.K., and McCreath, D.R., 1999. Hoek-Brown Parameters for Predicting Depth of Brittle Failure Around Tunnels. Can. Geotech. J., 36(1):136-151. 1999.

McTavish, S., 2013. Rainy River PDRI Report. April 2013.

Merit, 2013, Labour Survey documentation - CLAC and Ontario Construction Outlook October 2013.

Metso, Basics in Minerals Processing.

Metso, 2011. Metso Stirred Milling: Vertimill and Stirred Media Detritors, presented to BBA on August 19, 2011.

Metso, 2011. Special Jar Mill Grindability Test. Stirred Media Detritor Lab Test. Presented to BBA in October 2011.

Metso, 2012. Impact Crushability/Bond Work Index Test Results. Various dates, 2012.

McCarthy, P.L., 1993. “Economics of Narrow Vein Mining.” Proceedings for Narrow Vein Mining Seminar, Victoria, Australia. 1993.

Mine Cost Database (2013) available by subscription at: http://calc2011.costs.infomine.com/projects/project.aspx?pid=818 accessed February 15, 2013.

Morell, S. A Method for Predicting the Specific Energy of Comminution Circuits and Assessing Their Energy Utilization Efficiency.

Nesset, J.E., Radziszewski, P., Hardie, C., Leroux, D., 2006. Assessing the Performance and Efficiency of Fine Grinding Technologies. Proceedings of the 38th Annual Canadian Mineral Processors Conference – 2006.

National Electrical Contractors Association Inc. (NECA) – The NECA Manual of Labour Units 2003-2004, Copyright 2003, necanet.org.

Nickson, S.N., 1992. Cable Support Guidelines for Underground Hard Rock Mine Operations. MASc. thesis, Dept. Min. & Min. Pro., University of British Columbia. 1992.

Ontario Geological Survey 1990 Airborne Electromagnetic and Total Intensity Magnetic Survey, Rainy River area, Ontario Geological Survey, Maps 81513 and 81521, Scale 1:20,000. 1990.

 

 

27-8


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Ontario Ministry of Labour 2013. Ontario Occupational Health and Safety Act, Part 183.1(3) Available at: http://www.e-laws.gov.on.ca/html/regs/english/elaws_regs_900854_e.htm. accessed December 3, 2012.

Ontario Ministry of Northern Development, Northern Industrial Electricity Rate Program, Version 1.0, September 2010.

Ontario Occupational Health and Safety Act, Part 183.1(3) Available at: http://www.e-laws.gov.on.ca/html/regs/english/elaws_regs_900854_e.htm accessed: December 3, 2012.

Orway Mineral Consultants (OMC). Dewan, R., 2013. Rainy River Gold Project 15 MW SAG Mill and Ball Mill Evaluation, January 24, 2013.

Outotec, Ho, D., 2012. Gold Pre-Leach and Pre-Detox Thickening Testwork Report, Prepared for Paolo Toscano (Rainy River Resources), August 9, 2012.

Ovalle, A., 2013. Auditor Report. Rainy River Feasibility Study – Independent Review. Underground Mining. February 12, 2013.

Page, S. John. 1999. Estimator’s Piping Man-Hour Manual Fifth Editio, Gulf Pprofessional Publishing Ccompany, Houston TX USA , Bibliographical references and index ISBN 0-88415-259-6.

Pakalnis, R., 2002. Empirical Design Methods – UBC Geomechanics An Update. In Proc. of 5th North American Rock Mechanics Symposium, “Mining and Tunnelling Innovation and Opportunities”, NARMS-TAC 2002, p. 203-210. 2002.

Percival, J.A., Sanborn-Barrie, M., Skulski, T., Stott, G.M., Helmstaedt, H., and White, D.J., 2006. Tectonic evolution of the western Superior Province from NATMAP and Lithoprobe studies. Canadian Journal of Earth Sciences, v. 43, p. 1085–1117. 2006.

Percival, J. and Easton, M., 2007. Geology of the Canadian Shield in Ontario: an update. Ontario Geological Survey MRD 216/Geological Survey of Canada Open File 5511, scale 1:1 000 000. 2007.

Potvin, Y., 1988. Empirical Open Stope Design in Canada. Ph.D. thesis, Dept. Min. & Min. Pro., University of British Columbia. 1988. Pratt, A.G.L., 2005. “Application of Conveyors for Underground Haulage.” Ninth Underground Operator’s Conference, Perth, Australia. 2005.

Rainy River Resources Ltd., 2011, Geotechnical Report – Rainy River UG Geotech Guidelines.pptx. Dated July 4, 2011.

Revay & Associates Ltd., 2013. Auditor Report. Rainy River Feasibility Study – Independent Review. Project Capital Cost Uncertainty and Risk Analysis. February 11, 2013.

 

 

27-9


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Robert, F. and Poulsen, K.H., 2001. Vein Formation and Deformation in Greenstone Gold Deposits, in Richards, J.P., and Tosdal, R.M., eds., Structural Controls on Ore Genesis: Society of Economic Geologists, Reviews in Economic Geology, v. 14, p. 111-155. 2001.

Ross Archaelogical Research Associates. 2011. Stage 1 Archaelogical Assessment, Rainy River Advanced Exploration Project, Richardson Township, District of Rainy River.

R.S. Means, CostWorks 2011. Cost data version 15,16.

Salzer, KN. 2010 Canadian Mine, Salaries Wages and Benefits: 2010 Survey Results. InfoMine USA. 2010.

Siddorn, J., 2007. Structural Investigations, Rainy River Project, Ontario, Canada. Internal presentation by SRK Consulting (Canada) presented to Rainy River personnel, October 2007.

SGS Geostat Ltd., 2013. Geometallurgical Block Modelling of the Rainy River Gold Deposit. 58 pages. February 28, 2013.

SGS Lakefield Research Ltd., 2013. A Geometallurgical Investigation into the Rainy River Deposit prepared for Rainy River Resources Ltd. Project 11736-004-Draft. Addition if infill sampling, 35 pages. April 2012.

SGS Lakefield Research Ltd., 2012. An Investigation into The Grindability Characteristics of Samples from the Rainy River Project prepared for Rainy River Resources. Project 11736-004-Comminution Report., 265 pages. October 22, 2012.

SGS Lakefield Research Ltd., 2008. The Characterization of Gold-Bearing Samples from the Rainy River Project, Ontario, Canada. Project 11736-001-Report 1 for Rainy River Resources Ltd., 252 pages. 2008.

SGS Lakefield Research Ltd., 2011. An Investigation of Metallurgical Testing of Samples from the Rainy River Project, Ontario, Canada. Project 11736-003-Final Report for Rainy River Resources Ltd., 252 pages. 2011.

SGS Lakefield Research Ltd., 2012. IsaMill Fine Grinding Test Report. Prepared for BBA, dated September 8, 2011.

SGS Lakefield Research Ltd., 2011. Progress Summary Rainy River – Sept 13.xls, “JK Data” E-mail from James MacDonald (SGS) to Garett Macdonald (Rainy River Resources), Received September 13, 2011.

SGS Lakefield Research Ltd., 2012. Philips Impact Tests NZ and Z433 Comp. Prepared for Rainy River Resources Ltd., dated February 3, 2012.

SGS Lakefield Research Ltd., 2011. Geometallurgical Investigation into Rainy River Gold Deposit. Project CALR-11736-002, March 2010.

 

 

27-10


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

SGS Lakefield Research Limited, 2012. A Deportment Study of Gold in the ODM Master Comp and the Z433 Master Comp from the Rainy River Project. Prepared for Rainy River Resources Ltd., dated April 16, 2012.

SGS Lakefield Research Limited, 2012. High Grade Silver Head Analysis, Remaining Mine Life Head Analysis, Bulk CN Test Details and Telluride Evaluation Reports prepared for Rainy River Resources Ltd. April 2012.

SGS Lakefield Research Limited, 2012. Grindability Summary – May 23 2013.xls, “CWI Test Rocks” E-mail from Tyler Crary (SGS) to Paolo Toscano (Rainy River Resources), Received May 24, 2012.

SGS Lakefield Research Limited, 2012. Impact Tests – May 23 2013.xls, “CWI Test Rocks” E-mail from Tyler Crary (SGS) to Paolo Toscano (Rainy River Resources), Received May 24, 2012.

SGS Lakefield Research Limited, 2012. Quantitative X-Ray Diffraction by Rietveld Refinement. Report prepared for Enviro-Met, dated May 8, 2012.

SGS Lakefield Research Limited, 2012. Quantitative X-Ray Diffraction by Rietveld Refinement. Report prepared for Enviro-Met, dated July 20, 2012.

SGS Lakefield Research Limited, 2012. Drop Weight Test Report on Four Samples from Rainy River. Report prepared for Rainy River Resources Ltd., November 2012.

SGS Lakefield Research Limited, 2012. Drop Weight Test Report on Seven Samples from Rainy River. Report prepared for Rainy River Resources Ltd., June 2012.

SGS Lakefield Research Limited, 2012. Drop Weight Test Report on Two Samples from Rainy River. Report prepared for Rainy River Resources Ltd., March 2012.

SGS Lakefield Research Limited, 2012. Remaining Mine Life CND Results and Starter Pit CND Results Reports. Report prepared for Rainy River Resources Ltd., August 2012.

SGS Lakefield Research Limited, 2013. Gold and Silver Recovery from Rainy River Project Samples, Report prepared for Rainy River Resources Ltd., March 2013.

SGS Lakefield Research Limited, 2013. Gold and Silver Recovery from Intrepid Zone Project Samples, Report prepared for Rainy River Resources Ltd., November 2013.

Sparks, K.E. & Wartman, J.M., 2012 – Rainy River, Ontario: Exploration and development of a new gold resource – New Gold Mines and Projects in the Canadian Shield, PDAC 2012.

SRK Consulting (Canada) Inc., 2008. Due Diligence Review of the Rainy River Resource Estimate, Ontario, Canada. Project 3CR009.002. Internal Report for Rainy River Resources Ltd., 41 pages. 2008.

 

 

27-11


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

SRK Consulting (Canada) Inc., 2009. Mineral Resource Evaluation, Rainy River Gold Project, Western Ontario, Canada prepared for Rainy River Resources Ltd. Public document filed on SEDAR, 135 pages, dated July 10, 2009.

SRK Consulting (Canada) Inc., 2011. Mineral Resource Evaluation, Rainy River Gold Project, Western Ontario, Canada prepared for Rainy River Resources Ltd. Public document filed on SEDAR, 133 pages, dated April 8, 2011.

SRK Consulting (Canada) Inc., 2011. Mineral Resource Evaluation, Rainy River Gold Project, Western Ontario, Canada prepared for Rainy River Resources Ltd., 56 pages, dated August 11, 2011.

SRK Consulting (Canada) Inc., 2012. Mineral Resource Evaluation, Rainy River Gold Project, Western Ontario, Canada prepared for Rainy River Resources Ltd., 299 pages, dated April 9, 2012.

SRK Consulting (Canada) Inc., 2012. Rainy River Gold ProectProject Resources Estimate Update. Memo to Kerry Sparkes and Garett Macdonald, Rainy River Resource Ltd. December 3, 2012.

Stanley, J.E. 2012. Layout & Design Equipment Budget Estimate Pre-Engineering Specifications. Report compiled and presented to Paolo A. Toscano (Rainy River Resources), Director of Metallurgy. June 2012.

Stanley, J.E. 2013. Layout & Design Equipment Budget Estimate Pre-Engineering Specifications (25 K Plant), Report compiled and presented to Paolo A. Toscano (Rainy River Resources), Director of Metallurgy. February 2013.

Starkey & Associates, 2012. SAGDesign Test Work Results for 7 Samples. Test Work Validation Report prepared for BBA and Rainy River Resources Ltd, dated June 11, 2012.

Statistics Canada, Capital Expenditure Price Statistics (Volume 26, No. 4). April 2010

TBT Engineering Consulting Group, 2012. Highway 600 Realignment. Feasibility Study prepared for Rainy River Resources Ltd., dated February 9, 2012.

Unterman McPhail Associates. 2013. Cultural Heritage Assessment Report: Cultural Landscapes & Built Heritage Resources, Rainy River Project.

Wartman, Jakob, M., 2011 – Physical Volcanology and Hydrothermal Alteration of the Rainy River Gold Project, northwest Ontario. 154 pages. http://www.d.umn.edu/geology/research/thesis.html.

Whittle Consulting Pty Ltd. (Australia), 2012. Enterprise Optimization Rainy River Resources Ltd Rainy River Gold Project. Prepared by Richard Peevers. Reviewed by Gerald Whittle. July 2012.

Woodland Heritage Services. 2012. Stage 1 Archaeological and Cultural Heritage Resource Assessment of the Rainy River Resources Advanced Exploration Project Northwest of Fort Frances, Rainy River District, Ontario.

 

 

27-12


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

Woodland Heritage Services Limited. 2013. Stage 2 Archaeological and Cultural Heritage Resource Assessment of Rainy River Resources’ Proposed Mining Site, Richardson Township, in the Chapple Township Municipality, Rainy River District, Ontario. MTCS PIF #P208-037-2012 (in progress).

 

 

27-13


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

APPENDIX A

Rainy River Resources Title Opinion

(November 27, 2013)

 

 


LOGO

November 27, 2013

Rainy River Resources Ltd.

1 Richmond Street West, Suite 701

Toronto, ON M5H 3W4

Dear Sirs/Mesdames:

 

Re: Confirmation of title to or other interest in land holdings related to NI 43-101 Filing by Rainy River Resources Ltd.

Our Reference 06312-50011

We have acted as counsel to Rainy River Resources Ltd. (“Rainy River”) for the purpose of providing this opinion in connection with the above-noted matter.

Scope of Examination and Searches

For the purpose of providing this opinion, we have examined:

 

(a) registered title to the patented lands described in Schedule “A” to this opinion (the “Patented Lands”) for the sole purpose of noting the registered owner noted thereon, as disclosed by the relevant records (the “Registers”) of the Land Registry Office for the Land Titles Division of Rainy River (No. 48) (the “LRO”);

 

(b) registered title to the patented leasehold lands described in Schedule “B” to this opinion (the “Leasehold Lands”) for the sole purpose of noting the registered leasehold owner noted thereon, as disclosed by the relevant Registers;

 

(c) the relevant Registers for the patented lands described in Schedule “C” to this opinion (the “Option Lands”) for the sole purpose of noting whether notice of an option to purchase in favour of Rainy River is noted thereon;

 

(d) copies of the active mining claims abstract summaries and transactions listings current to November 27, 2013 maintained by the Mining Recorder’s Office of the Ontario Ministry of Northern Development and Mines (the “Records”) for each of the unpatented claims described in Schedule “D” (the “Unpatented Claims”) and for the unpatented claims described in the English Option Agreements, the Roisin Option Agreement and the Timberridge Land & Forestry Services Inc. and described on Schedule “D1” (the “Optioned Unpatented Claims”) for the sole purpose of noting the recorded holder thereof;

 

(e) photostatic copies of two purchase option agreements dated March 3, 2010 between Perry English for Rubicon Minerals Corporation, as optionor and Rainy River, as optionee (collectively, the “English Option Agreements”) relating to the applicable Optioned Unpatented Claims,

 

   

Davis LLP, Suite 6000, 1 First Canadian Place, PO Box 367, 100 King St W, Toronto ON M5X 1E2 CANADA

www.davis.ca

  TORONTO     VANCOUVER     MONTREAL     CALGARY     EDMONTON      WHITEHORSE     YELLOWKNIFE     TOKYO


LOGO

Page 2 of 22

 

(f) photostatic copy of an’ option agreement dated December 16, 2011 between Fred A. Roisin, as optionor and Rainy River, as optionee (collectively, the “Roisin Option Agreement”) relating to the applicable Optioned Unpatented Claims,

 

(g) photostatic copy of an option agreement dated March 29, 2012 between Timberridge Land & Forestry Services Inc., as optionor and Rainy River, as optionee (collectively, the “Timberridge Option Agreement”) relating to the applicable Optioned Unpatented Claims,

and our opinions expressed below are expressly subject and limited to the results of such examinations. With your concurrence, we have not conducted any other or more in depth reviews, examinations or searches, including of the relevant Registers or the Records, other than those indicated above and our opinion is therefore qualified as to any matters that would be revealed by any such other or more in depth reviews, examinations or searches.

Assumptions and Reliances

In connection with the opinions expressed in this letter, we have assumed:

 

(a) in the conduct of our examination above, the genuineness of all signatures, the legal capacity of all individuals who have executed documents or instruments, the authenticity of all documents and instruments submitted to or reviewed by us as originals, the conformity to originals of all documents and instruments submitted to or reviewed by us as certified, telecopied or photostatic copies or facsimiles thereof, and the authenticity of the originals of such certified copies, photocopies, telecopies or facsimiles, and the enforceability of all such original, certified, telecopied, photostatic or facsimile copies of such documents and instruments;

 

(b) that any persons purporting to have executed the documents or instruments examined in the course of our examinations noted above, are, in fact, the same persons named therein, and, when executed by a corporation or governmental authority, that the persons so executing on behalf of the corporation or governmental authority have been duly and validly authorized to do so as signing officers of the corporation or governmental authority;

 

(c) any previous or current registered or recorded corporate owners of the Patented Lands, Leasehold Lands, Unpatented Claims or Optioned Unpatented Claims, or of an interest in and to the Patented Lands, Leasehold Lands or Unpatented Claims or Optioned Unpatented Claims, were duly incorporated and validly existing in their jurisdiction of incorporation, were extra-provincially registered in the Province of Ontario and were entitled to own, and had the corporate power and capacity to own, property or an interest in property in the Province of Ontario and to execute and deliver all agreements or instruments, and that such corporations were not dissolved or wound up, voluntarily or involuntarily, during the period that such corporations were the registered or recorded owners or holders of the Patented Lands, Leasehold Lands, Unpatented Claims or Optioned Unpatented Claims or of an interest in and to the Patented Lands, Leasehold Lands, Unpatented Claims or Optioned Unpatented Claims;


LOGO

Page 3 of 22

 

(d) the accuracy and currency of the indices and filing systems maintained at any public offices where we have conducted reviews, examinations or searches or made enquiries or caused such reviews, examinations or searches or enquiries to be conducted or made;

 

(e) that the Registers and Records pertaining to title to the Patented Lands, Leasehold Lands, Option Lands, Unpatented Claims and Optioned Unpatented Claims are accurate and that there are no unrecorded transfers, assignments, agreements or other unrecorded encumbrances or rights, title or interests affecting such lands or the registered or recorded owners’ or holders’ interest therein;

 

(f) each party to the English Option Agreements, the Roisin Option Agreement and the Timberridge Option Agreement (collectively, the “Option Agreements”), including Rainy River, is a validly created and subsisting legal entity, has all necessary power and capacity to execute, deliver and perform the Option Agreements, has duly authorized, executed and delivered the Option Agreements and such Option Agreements constitute legal, valid and binding obligations of such parties, enforceable against them in accordance with their terms; and

 

(g) the Option Agreements and the underlying leases for the Leasehold Lands are in good standing and in full force and effect as of the dates noted in paragraph 2 below, have not been cancelled or terminated or assigned, and all parties to such agreements have performed all obligations thereunder.

 

(h) We are solicitors qualified to carry on the practice of law in the Province of Ontario. The opinion expressed herein extends only to the laws of the Province of Ontario and the federal laws of Canada applicable therein in force as of the date of this opinion.

Opinion

Based upon and subject to the foregoing, and subject to the exceptions and qualifications to title set out in Schedule “E”, we are of the opinion that:

 

1. as of November 22, 2013, Rainy River is noted on the relevant Registers as the registered owner in fee simple of each of the Patented Lands described on Schedule “A”;

 

2. as of November 25, 2013, Rainy River is noted on the relevant Registers as the registered holder of a leasehold estate for each of the Leasehold Lands described on Schedule “B”;

 

3. as of November 26, 2013, certain notices of an option to purchase in favour of Rainy River have been registered against the relevant Registers for each of the Option Lands described on Schedule “C”;

 

4. as of November 27, 2013, Rainy River is noted on the relevant Records as the recorded holder of the Unpatented Claims described in Schedule “D”; and

 

5. as of November 27, 2013, the Option Agreements create a contractual interest in the nature of an option to acquire a 100% interest in favour of Rainy River in and to the Optioned Unpatented Claims described in Schedule “D1”. We note that as of such date, the Option Agreements are not recorded against the relevant Records for the Optioned Unpatented Claims.

 


LOGO

Page 4 of 22

This opinion is provided solely for the internal use of the addressees hereof and may not be quoted or otherwise referred to in other documents or relied upon by either of you for any purpose or in conjunction with any matter or transaction, other than the matter noted above, nor may it be quoted or used or relied on by any other person in conjunction with any matter or transaction, without our express written permission.

Yours truly,

LOGO

 


LOGO

Page 5 of 22

Schedule “A”

Patented Lands

 

1. 56036-0084 (LT)

PCL 17371 SEC RAINY RIVER; N 1/2 LT 9 CON 6 MATHER EXCEPT PT COVERED BY WATERS OF PINE RIVER; CHAPPLE

 

2. 56036-0077 (LT)

PCL 16847 SEC RAINY RIVER; N 1/2 LT 12 CON 6 MATHER EXCEPT PT 2, 48R1197; CHAPPLE

 

3. 56046-0128 (LT)

PCL 25847 SEC RAINY RIVER; N 1/2 OF NE 1/4 SEC 26 PATULLO SURFACE RIGHTS ONLY; MORLEY

 

4. 56035-0248 (LT)

MINING RIGHTS ONLY; E 1/2 OF S 1/2 LT 9 CON 5 POTTS; CHAPPLE

 

5. 56035-0244 (LT)

MINING RIGHTS ONLY; PT W 1/2 OF S 1/2 LT 9 CON 5 POTTS AS IN SLT74194; CHAPPLE

 

6. 56035-0246 (LT)

MINING RIGHTS ONLY; S 1/2 LT 9 CON 5 POTTS EXCEPT SLT40477, SLT74194 & SLT46701; CHAPPLE

 

7. 56035-0066 (LT)

PCL 16077 SEC RAINY RIVER; N 1/2 LT 12 CON 1 POTTS; CHAPPLE

 

8. 56035-0098 (LT)

PCL 18689 SEC RAINY RIVER; S 1/2 LT 12 CON 3 POTTS; CHAPPLE

 

9. 56035-0176 (LT)

PCL 5899 SEC RAINY RIVER; S 1/2 LT 12 CON 1 POTTS; CHAPPLE

 

10. 56035-0090 (LT)

PCL 17941 SEC RAINY RIVER; S 1/2 LT 12 CON 2 POTTS; CHAPPLE

 

11. 56035-0242 (LT)

SURFACE RIGHTS ONLY; N 1/2 LT 11 CON 2 POTTS; CHAPPLE

 


LOGO

Page 6 of 22

 

12. 56035-0009 (LT)

PCL 10286 SEC RAINY RIVER; S 1/2 LT 10 CON 2 POTTS; CHAPPLE

 

13. 56042-0082 (LT)

PCL 22495 SEC RAINY RIVER; E 1/2 OF N 1/2 LT 7 CON 2 RICHARDSON EXCEPT A55914 BEING THE MINING RIGHTS; CHAPPLE

 

14. 56042-0189 (LT)

MINING RIGHTS ONLY, E 1/2 OF S 1/2 LT 9 CON 2 RICHARDSON EXCEPT PT 5 48R1985 & PL S-439; CHAPPLE

 

15. 56042-0187 (LT)

MINING RIGHTS ONLY, E 1/2 OF N 1/2 LT 9 CON 1 RICHARDSON EXCEPT PT 6 PL S-439, PT 4 48R1985; CHAPPLE

 

16. 56042-0160 (LT)

SURFACE RIGHTS ONLY, S 1/2 LT 4 CON 2 RICHARDSON EXCEPT PL S-391, SLT30449; CHAPPLE

 

17. 56042-0161 (LT)

MINING RIGHTS ONLY, S 1/2 LT 4 CON 2 RICHARDSON EXCEPT PL S-391, SLT30449; CHAPPLE

 

18. 56042-0162(LT)

SURFACE RIGHTS ONLY, N 1/2 LT 4 CON 3 RICHARDSON; CHAPPLE

 

19. 56042-0163 (LT)

MINING RIGHTS ONLY, N 1/2 LT 4 CON 3 RICHARDSON; CHAPPLE

 

20. 56042-0097 (LT)

PCL 25891 SEC RAINY RIVER; PT LT 6 CON 1 RICHARDSON AS IN A68613; MINING RIGHTS ONLY; CHAPPLE

 

21. 56042-0034 (LT)

PCL 14408 SEC RAINY RIVER; PT LT 6 CON 1 RICHARDSON AS IN SLT53957 EXCEPT PL S-391, PT 1 48R1961 & A68613 BEING THE MINING RIGHTS; CHAPPLE

 

22. 56042-0173 (LT)

MINING RIGHTS ONLY; S 1/2 LT 9 CON 3 RICHARDSON; CHAPPLE

 

23. 56042-0139 (LT)

PCL 26007 SEC RAINY RIVER MRO; N 1/2 LT 7 CON 2 RICHARDSON EXCEPT THE E 1/2; CHAPPLE


LOGO

Page 7 of 22

 

24. 56042-0104 (LT)

PCL 4534 SEC RAINY RIVER; N 1/2 LT 7 CON 2 RICHARDSON EXCEPT THE E 1/2 & A73222 BEING THE MINING RIGHTS; CHAPPLE

 

25. 56042-0102 (LT)

PCL 26007 SEC RAINY RIVER MRO; S 1/2 LT 8 CON 2 RICHARDSON EXCEPT PT 3 PL S-439, THE N 1/2, & PT 1 & 2 48R1985; CHAPPLE

 

26. 56042-0113 (LT)

PCL 5483 SEC RAINY RIVER; S 1/2 LT 8 CON 2 RICHARDSON EXCEPT PT 3, PL S439, THEN 1/2, PT 1 & 2 48R1985, A73222 BEING THE MINING RIGHTS; CHAPPLE

 

27. 56042-0179 (LT)

MINING RIGHTS ONLY; W 1/2 OF N 1/2 LT 12 CON 3 RICHARDSON; TOWNSHIP OF CHAPPLE

 

28. 56042-0177 (LT)

MINING RIGHTS ONLY; PT LT 3 CON 1 RICHARDSON AS IN SLT76289; CHAPPLE

 

29. 56042-0100 (LT)

PCL 25984 SEC RAINY RIVER; N 1/2 LT 6 CON 2 RICHARDSON MINING RIGHTS ONLY; CHAPPLE

 

30. 56042-0128 (LT)

PCL 8825 SEC RAINY RIVER; N 1/2 LT 5 CON 2 RICHARDSON EXCEPT A72814 BEING THE SURFACE RIGHTS; CHAPPLE

 

31. 56042-0098 (LT)

PCL 25892 SEC RAINY RIVER; S 1/2 LT 5 CON 2 RICHARDSON MINING RIGHTS ONLY; CHAPPLE

 

32. 56042-0175 (LT)

MINING RIGHTS ONLY; S 1/2 LT 11 CON 2 RICHARDSON EXCEPT THE W 1/2 & PT 11 PL S-439; CHAPPLE

 

33. 56042-0171 (LT)

MINING RIGHTS ONLY; S 1/2 LT 12 CON 2 RICHARDSON EXCEPT PT 11 PL S446, PT 17, PL S439, SLT50657; CHAPPLE

 

34. 56042-0169 (LT)

MINING RIGHTS ONLY; N 1/2 LT 12 CON 2 RICHARDSON EXCEPT PT 15 PL S446; TOWNSHIP OF CHAPPLE


LOGO

Page 8 of 22

 

35. 56042-0033 (LT)

PCL 14407 SEC RAINY RIVER; PT LT 6 CON 1 RICHARDSON AS IN SLT53956 EXCEPT PL S-391 & A68696 BEING THE MINING RIGHTS; CHAPPLE

 

36. 56042-0099 (LT)

PCL 25894 SEC RAINY RIVER; FIRSTLY W 1/2 LT 6 CON 1 RICHARDSON SECONDLY E 1/2 LT 6 CON 1 RICHARDSON AS IN SLT53956 MINING RIGHTS ONLY; CHAPPLE

 

37. 56042-0058 (LT)

PCL 16927 SEC RAINY RIVER; N 1/2 OF S 1/2 LT 6 CON 3 RICHARDSON; CHAPPLE

 

38. 56042-0166 (LT)

SURFACE RIGHTS ONLY; N 1/2 LT 11 CON 2 RICHARDSON; CHAPPLE

 

39. 56042-0167 (LT)

MINING RIGHTS ONLY; N 1/2 LT 11 CON 2 RICHARDSON; CHAPPLE

 

40. 56042-0158 (LT)

MINING RIGHTS ONLY; N 1/2 LT 4 CON 2 RICHARDSON TOWNSHIP OF CHAPPLE

 

41. 56042-0159 (LT)

SURFACE RIGHTS ONLY; N 1/2 LT 4 CON 2 RICHARDSON; TOWNSHIP OF CHAPPLE

 

42. 56042-0116 (LT)

PCL 5939 SEC RAINY RIVER; N 1/2 LT 5 CON 1 RICHARDSON EXCEPT PL S-391, PT 5-7 48R1717 & PT 1 48R1728; CHAPPLE

 

43. 56042-0114 (LT)

PCL 5614 SEC RAINY RIVER; S 1/2 LT 5 CON 1 RICHARDSON EXCEPT PL S-391 & PT 2 48R1717; CHAPPLE

 

44. 56042-0063 (LT)

PCL 17725 SEC RAINY RIVER; E 1/2 OF S 1/2 LT 7 CON 3 RICHARDSON; CHAPPLE

 

45. 56042-0064 (LT)

PCL 17726 SEC RAINY RIVER; S 1/2 LT 3 CON 3 RICHARDSON; CHAPPLE

 

46. 56042-0060 (LT)

PCL 17110 SEC RAINY RIVER; S 1/2 LT 6 CON 2 RICHARDSON EXCEPT PL S-391; CHAPPLE


LOGO

Page 9 of 22

 

47. 56042-0036 (LT)

PCL 14462 SEC RAINY RIVER; PT LT 7 CON 1 RICHARDSON AS IN SLT53727; CHAPPLE

 

48. 56042-0146 (LT)

MINING RIGHTS IN AND UNDER PT LT 6 CON 3 RICHARDSON AS IN SP3235; CHAPPLE

 

49. 56042-0147 (LT)

PT LT 6 CON 3 RICHARDSON AS IN SP3235 EXCEPT MINING RIGHTS IN AND UNDER AS IN RD2483; CHAPPLE

 

50. 56042-0077 (LT)

PCL 21129 SEC RAINY RIVER; PT LT 6 CON 3 RICHARDSON AS IN SLT97369; CHAPPLE

 

51. 56042-0145 (LT)

PCL 16779 SEC RAINY RIVER; N 1/2 OF N 1/2 LT 4 CON 1 RICHARDSON EXCEPT PL S391; CHAPPLE

 

52. 56042-0053 (LT)

PCL 16630 SEC RAINY RIVER; W 1/2 OF S 1/2 LT 9 CON 2 RICHARDSON EXCEPT PT 7, PL S439; CHAPPLE

 

53. 56042-0164 (LT)

SURFACE RIGHTS ONLY; PT LT 3 CON 1 RICHARDSON AS IN SLT57341; TOWNSHIP OF CHAPPLE

 

54. 56042-0165 (LT)

MINING RIGHTS ONLY; PT LOT 3 CON 1 RICHARDSON AS IN SLT57341; CHAPPLE

 

55. 56042-0180 (LT)

SURFACE RIGHTS ONLY; PT LT 3 CON 1 RICHARDSON AS IN SLT30924; CHAPPLE

 

56. 56042-0181 (LT)

MINING RIGHTS ONLY; PT LT 3 CON 1 RICHARDSON AS IN SLT30924; CHAPPLE

 

57. 56042-0184 (LT)

SURFACE RIGHTS ONLY; N 1/2 OF S 1/2 LT 4 CON 1 RICHARDSON EXCEPT PL S-391, PT 3 48R1717; CHAPPLE

 

58. 56042-0185 (LT)

MINING RIGHTS ONLY; N 1/2 OF S 1/2 LT 4 CON 1 RICHARDSON EXCEPT PL S-391, PT 3 48R1717; CHAPPLE


LOGO

Page 10 of 22

 

59. 56042-0182 (LT)

SURFACE RIGHTS ONLY; S 1/2 OF S 1/2 LT 4 CON 1 RICHARDSON EXCEPT PL S-391, PT 1-4 48R1191, PT 1 48R1717; CHAPPLE

 

60. 56042-0183 (LT)

MINING RIGHTS ONLY; S 1/2 OF S 1/2 LT 4 CON 1 RICHARDSON EXCEPT PL S-391, PT 1-4 48R1191, PT 1 48R1717; CHAPPLE

 

61. 56042-0149 (LT)

MINING RIGHTS ONLY; N PT BROKEN LT 7 CON 1 RICHARDSON BEING ALL THAT PT OF THE SAID LT LYING N OF THE LINE DRAWN ACROSS SAID LT ON A COURSE W ASTRONOMICALLY FROM A POINT ON THE E LIMIT THEREOF. 40 CHAINS S OF THE NW ANGLE OF SAID LT EXCEPT PT 2, PL S439; TOWNSHIP OF CHAPPLE

 

62. 56042-0148 (LT)

SURFACE RIGHTS ONLY; N PT BROKEN LT 7 CON 1 RICHARDSON BEING ALL THAT PT OF THE SAID LT LYING N OF THE LINE DRAWN ACROSS SAID LT ON A COURSE W ASTRONOMICALLY FROM A POINT ON THE E LIMIT THEREOF 40 CHAINS S OF THE NW ANGLE OF SAID LT EXCEPT PT 2, PL S439; TOWNSHIP OF CHAPPLE

 

63. 56042-0047 (LT)

PCL 15881 SEC RAINY RIVER; S 1/2 LT 2 CON 2 RICHARDSON; CHAPPLE

 

64. 56042-0012 (LT)

PCL 11853 SEC RAINY RIVER; N 1/2 LT 2 CON 1 RICHARDSON; CHAPPLE

 

65. 56042-0062 (LT)

PCL 17392 SEC RAINY RIVER; W 1/2 OF S 1/2 LT 8 CON 1 RICHARDSON; CHAPPLE

 

66. 56042-0037 (LT)

PCL 14604 SEC RAINY RIVER; N 1/2 OF S 1/2 LT 4 CON 3 RICHARDSON; CHAPPLE

 

67. 56042-0129 (LT)

PCL 9080 SEC RAINY RIVER; S 1/2 LT 4 CON 3 RICHARDSON EXCEPT THE N 1/2; CHAPPLE

 

68. 56042-0061 (LT)

PCL 17154 SEC RAINY RIVER; N 1/2 LT 6 CON 2 RICHARDSON EXCEPT A72582 BEING THE MINING RIGHTS; CHAPPLE

 

69. 56042-0044 (LT)

PCL 15282 SEC RAINY RIVER; S 1/2 OF S 1/2 LT 7 CON 4 RICHARDSON; CHAPPLE


LOGO

Page 11 of 22

 

70. 56042-0088 (LT)

PCL 23322 SEC RAINY RIVER; PT LT 6 CON 1 RICHARDSON PT 1 48R1961; CHAPPLE

 

71. 56042-0065 (LT)

PCL 17752 SEC RAINY RIVER; W 1/2 OF S 1/2 LT 9 CON 1 RICHARDSON RESERVING A STRIP OF LAND TEN FT ALONG THE SHORES OF THE PINE RIVER; CHAPPLE

 

72. 56042-0101 (LT)

PCL 25991 SEC RAINY RIVER; N 1/2 LT 5 CON 2 RICHARDSON SURFACE RIGHTS ONLY; CHAPPLE

 

73. 56042-0021 (LT)

PCL 13137 SEC RAINY RIVER; S 1/2 LT 11 CON 1 RICHARDSON; CHAPPLE

 

74. 56042-0003 (LT)

PCL 10273 SEC RAINY RIVER; N 1/2 LT 12 CON 1 RICHARDSON EXCEPT PT 16, PL S439; CHAPPLE

 

75. 56042-0024 (LT)

PCL 13467 SEC RAINY RIVER; N 1/2 LT 11 CON 1 RICHARDSON EXCEPT THE E 1/2 PT 14, PL S439; CHAPPLE

 

76. 56042-0050 (LT)

PCL 16307 SEC RAINY RIVER; N 1/2 LT 10 CON 3 RICHARDSON; CHAPPLE

 

77. 56042-0052 (LT)

PCL 16343 SEC RAINY RIVER; W 1/2 OF S 1/2 LT 11 CON 2 RICHARDSON EXCEPT PT 12 & 13, S439; CHAPPLE

 

78. 56042-0011 (LT)

PCL 11409 SEC RAINY RIVER; S 1/2 LT 5 CON 2 RICHARDSON EXCEPT PL S-391, PT 8 48R1717 & A68624 BEING THE MINING RIGHTS; CHAPPLE

 

79. 56042-0018 (LT)

PCL 12324 SEC RAINY RIVER; N 1/2 LT 5 CON 3 RICHARDSON; CHAPPLE

 

80. 56042-0081 (LT)

PCL 22190 SEC RAINY RIVER; S 1/2 LT 5 CON 3 RICHARDSON; CHAPPLE

 

81. 56042-0038 (LT)

PCL 14665 SEC RAINY RIVER; W 1/2 OF N 1/2 LT 9 CON 1 RICHARDSON EXCEPT PT 8, PL S439; CHAPPLE


LOGO

Page 12 of 22

 

82. 56042-0056 (LT)

PCL 16820 SEC RAINY RIVER; S N/2 OF N 1/2 LT 8 CON 2 RICHARDSON; CHAPPLE

 

83. 56042-0002 (LT)

PCL 10152 SEC RAINY RIVER; N 1/2 LT 11 CON 3 RICHARDSON; CHAPPLE

 

84. 56042-0055 (LT)

PCL 16754 SEC RAINY RIVER; S 1/2 LT 11 CON 3 RICHARDSON; CHAPPLE

 

85. 56042-0059 (LT)

PCL 16956 SEC RAINY RIVER; S 1/2 OF N 1/2 LT 8 CON 2 RICHARDSON; CHAPPLE

 

86. 56042-0029 (LT)

PCL 14200 SEC RAINY RIVER; S 1/2 LT 12 CON 3 RICHARDSON EXCEPT PT 16, PL S446, PT 2 & 3, PL S455; CHAPPLE

 

87. 56042-0005 (LT)

PCL 10746 SEC RAINY RIVER; N 1/2 LT 10 CON 2 RICHARDSON; CHAPPLE

 

88. 56042-0117 (LT)

PCL 6520 SEC RAINY RIVER; N 1/2 LT 9 CON 2 RICHARDSON; CHAPPLE

 

89. 56042-0112 (LT)

PCL 5455 SEC RAINY RIVER; S 1/2 LT 10 CON 2 RICHARDSON EXCEPT PT 9 PL S439; CHAPPLE

 

90. 56042-0016 (LT)

PCL 12083 SEC RAINY RIVER; S 1/2 LT 10 CON 1 RICHARDSON; CHAPPLE

 

91. 56042-0121 (LT)

PCL 7654 SEC RAINY RIVER; N 1/2 LT 10 CON 1 RICHARDSON EXCEPT PT 10, PL S439; CHAPPLE

 

92. 56042-0133 (LT)

PCL 9665 SEC RAINY RIVER; S 1/2 LT 2 CON 1 RICHARDSON; CHAPPLE

 

93. 56042-0025 (LT)

PCL 13514 SEC RAINY RIVER; E 1/2 OF N 1/2 2 LT 11 CON 1 RICHARDSON EXCEPT PT 12, PL S439; CHAPPLE


LOGO

Page 13 of 22

 

94. 56042-0190 (LT)

SURFACE RIGHTS ONLY; S 1/2 OF N 1/2 LT 4 CON 1 RICHARDSON EXCEPT PL S391 & PT 4 48R1717; CHAPPLE

 

95. 56042-0078 (LT)

PCL 21213 SEC RAINY RIVER; N 1/2 OF S 1/2 LT 7 CON 4 RICHARDSON; CHAPPLE

 

96. 56042-0014 (LT)

PCL 11912 SEC RAINY RIVER; S 1/2 LT 7 CON 2 RICHARDSON EXCEPT PL S439 & A55914 BEING THE MINING RIGHTS; CHAPPLE

 

97. 56042-0030 (LT)

PCL 14238 SEC RAINY RIVER; N 1/2 LT 8 CON 3 RICHARDSON EXCEPT A55914 BEING THE MINING RIGHTS; CHAPPLE

 

98. 56042-0083 (LT)

PCL 22496 SEC RAINY RIVER; N 1/2 OF S 1/2 LT 8 CON 2 RICHARDSON EXCEPT A55914 BEING THE MINING RIGHTS; CHAPPLE

 

99. 56042-0103 (LT)

PCL 4259 SEC RAINY RIVER; N 1/2 LT 8 CON 1 RICHARDSON EXCEPT PT 4 PL S439, PT 3 48R1985 & A55914 BEING THE MINING RIGHTS; CHAPPLE

 

100. 56042-0108 (LT)

PCL 4947 SEC RAINY RIVER; S 1/2 LT 8 CON 3 RICHARDSON EXCEPT A55914 BEING THE MINING RIGHTS; CHAPPLE

 

101. 56042-0122 (LT)

PCL 8070 SEC RAINY RIVER; S 1/2 LT 7 CON 3 RICHARDSON EXCEPT THE E 1/2 & A55914 BEING THE MINING RIGHTS; CHAPPLE

 

102. 56042-0111 (LT)

PCL 5279 SEC RAINY RIVER; E 1/2 OF S 1/2 LT 8 CON 1 RICHARDSON EXCEPT A62973 BEING THE MINING RIGHTS; CHAPPLE

 

103. 56042-0026 (LT)

PCL 13681 SEC RAINY RIVER; PT LT 12 CON 2 RICHARDSON BEING THE E 100 ACRES OF THE S 1/2 EXCEPT PT 15, PL S439; CHAPPLE

 

104. 56042-0027 (LT)

PCL 13804 SEC RAINY RIVER; S 1/2 LT 1 CON 2 RICHARDSON; CHAPPLE


LOGO

Page 14 of 22

 

105. 56042-0131 (LT)

PCL 9656 SEC RAINY RIVER; N 1/2 LT 1 CON 1 RICHARDSON; CHAPPLE

 

106. 56032-0280 (LT)

MINING RIGHTS ONLY OF PT MINING CLAIM FF-5877 SENN NOT COVERED BY THE WATERS OF OFF LAKE AS IN SP4199; DISTRICT OF RAINY RIVER

 

107. 56045-0182 (LT)

MINING RIGHTS ONLY; PT LT 1 CON 2 SIFTON AS IN SLT48145 EXCEPT PT 7, PL S446; UNORGANIZED

 

108. 56045-0184 (LT)

MINING RIGHTS ONLY; PT LT 1 CON 2 SIFTON AS IN SLT48174 EXCEPT PT 6, PL S446; UNORGANIZED

 

109. 56045-0186 (LT)

MINING RIGHTS ONLY; PT LT 1 CON 2 SIFTON AS IN SLT48600 EXCEPT PT 3, 5 & 8, PL S446; UNORGANIZED

 

110. 56045-0180 (LT)

MINING RIGHTS ONLY; S 1/2 LT 2 CON 3 SIFTON; UNORGANIZED

 

111. 56045-0172 (LT)

MINING RIGHTS ONLY; N 1/2 LT 2 CON 3 SIFTON EXCEPT PT 10, PL S447; UNORGANIZED

 

112. 56045-0174 (LT)

MINING RIGHTS ONLY; S 1/2 OF N 1/2 LT 1 CON 3 SIFTON EXCEPT SLT41820 & PT 11, PL S446; UNORGANIZED

 

113. 56045-0176 (LT)

MINING RIGHTS ONLY; N 1/2 LT 2 CON 2 SIFTON; UNORGANIZED

 

114. 56045-0178 (LT)

MINING RIGHTS ONLY; S 1/2 LT 1 CON 3 SIFTON EXCEPT PT 9 & 10, PL S446; UNORGANIZED

 

115. 56045-0052 (LT)

PCL 15876 SEC RAINY RIVER; S 1/2 OF S 1/2 LT 5 CON 4 SIFTON EXCEPT PT 3, PL S447; UNORGANIZED


LOGO

Page 15 of 22

 

116. 56041-0159 (LT)

PCL 6721 SEC RAINY RIVER; SW 1/4 SEC 35 TAIT; CHAPPLE

 

117. 56041-0222 (LT)

SURFACE RIGHTS ONLY; PT SEC 35 TAIT BEING THE NE SUBDIVISION; TOWNSHIP OF CHAPPLE

 

118. 56041-0221 (LT)

MINING RIGHTS ONLY; PT SEC 35 TAIT BEING THE NE SUBDIVISION TOWNSHIP OF CHAPPLE

 

119. 56041-0223 (LT)

SURFACE RIGHTS ONLY; NW 1/4 SEC 36 TAIT; CHAPPLE

 

120. 56041-0224 (LT)

MINING RIGHTS ONLY; NW 1/4 SEC 36 TAIT; CHAPPLE

 

121. 56041-0225 (LT)

SURFACE RIGHTS ONLY; PT SEC 35 TAIT BEING THE NW 1/4; CHAPPLE

 

122. 56041-0226 (LT)

MINING RIGHTS ONLY; PT SEC 35 TAIT BEING THE NW 1/4; CHAPPLE

 

123. 56041-0215 (LT)

SURFACE RIGHTS ONLY; PT SE 1/4 SEC 35 TAIT PART 1, 48R4044; CHAPPLE

 

124. 56041-0164 (LT)

PCL 4153 SEC RAINY RIVER; PT SEC 36 TAIT BEING THE NE SUBDIVISION EXCEPT PL S390 & PT 5, 6, 8 & 9, 48R1197; CHAPPLE

 

125. 56041-0002 (LT)

PCL 17230 SEC RAINY RIVER; PT SEC 32 TAIT BEING THE W 1/2 OF THE NEW 1/4; CHAPPLE

 

126. 56041-0152 (LT)

PCL 13528 SEC RAINY RIVER; SW 1/4 SEC 32 TAIT; CHAPPLE


LOGO

Page 16 of 22

Schedule “B”

Leasehold Lands

 

1. 56042-0140 (LT)

PCL L1078 SEC RAINY RIVER LEASEHOLD; LT 8 CON 3 RICHARDSON; PT LT 7 CON 3 RICHARDSON BEING THE W 1/2 OF THE S 1/2; MRO; CHAPPLE

 

2. 56042-0141 (LT)

PCL L1078 SEC RAINY RIVER LEASEHOLD; PT LT 8 CON 2 RICHARDSON BEING ALL OF THE N 1/2 OF THE S 1/2; PT LT 7 CON 2 RICHARDSON BEING THE E 1/2 OF THE N 1/2, & ALL OF THE S 1/2; MRO; CHAPPLE

 

3. 56042-0142 (LT)

PCL L1078 SEC RAINY RIVER LEASEHOLD; PT LT 8 CON 1 RICHARDSON BEING THE N 1/2; MRO; CHAPPLE


LOGO

Page 17 of 22

Schedule “C”

Option Lands

 

1. 56035-0249 (LT) (formerly 56035-0036 (LT))

SURFACE RIGHTS ONLY; E 1/2 OF S 1/2 LT 9 CON 5 POTTS; CHAPPLE

 

2. 56035-0245 (LT) (formerly 56035-0089 (LT))

SURFACE RIGHTS ONLY; PT W 1/2 OF S 1/2 LT 9 CON 5 POTTS AS IN SLT74194; CHAPPLE

 

3. 56035-0247 (LT) (formerly 56035-0168 (LT))

SURFACE RIGHTS ONLY; S 1/2 LT 9 CON 5 POTTS EXCEPT SLT40477, SLT74194 & SLT46701; CHAPPLE

 

4. 56042-0188 (LT)

SURFACE RIGHTS ONLY; E 1/2 OF S 1/2 LT 9 CON 2 RICHARDSON EXCEPT PT 5 48R1985 & PL S-439; CHAPPLE

 

5. 56042-0186 (LT)

SURFACE RIGHTS ONLY; E 1/2 OF N 1/2 LT 9 CON 1 RICHARDSON EXCEPT PT 6, PL S439, PT 4 48R1985; CHAPPLE

 

6. 56042-0172 (LT)

SURFACE RIGHTS ONLY; S 1/2 LT 9 CON 3 RICHARDSON; CHAPPLE

 

7. 56042-0178 (LT)

SURFACE RIGHTS ONLY; W 1/2 OF N 1/2 LT 12 CON 3 RICHARDSON; CHAPPLE

 

8. 56042-0176 (LT)

SURFACE RIGHTS ONLY; PT LT 3 CON 1 RICHARDSON AS IN SLT76289; CHAPPLE

 

9. 56042-0174 (LT)

SURFACE RIGHTS ONLY; S 1/2 LT 11 CON 2 RICHARDSON EXCEPT THE W 1/2 & PT 11 PL S-439; CHAPPLE

 

10. 56042-0170 (LT)

SURFACE RIGHTS ONLY; S 1/2 LT 12 CON 2 RICHARDSON EXCEPT PT 14, PL S446, PT 17, PL S439, SLT50657; CHAPPLE


LOGO

Page 18 of 22

 

11. 56042-0168 (LT)

SURFACE RIGHTS ONLY; N 1/2 LT 12 CON 2 RICHARDSON EXCEPT PT 15, PL S446; CHAPPLE

 

12. 56042-0123 (LT)

PCL 8071 SEC RAINY RIVER; N 1/2 LT 2 CON 3 RICHARDSON; CHAPPLE

 

13. 56042-0124 (LT)

PCL 8235 SEC RAINY RIVER; N 1/2 LT 3 CON 3 RICHARDSON; CHAPPLE

 

14. 56032-0281 (LT)

SURFACE RIGHTS ONLY OF PT MINING CLAIM FF-5877 SENN NOT COVERED BY THE WATERS OF OFF LAKE AS IN SP4199; DISTRICT OF RAINY RIVER

 

15. 56032-0240 (LT)

PCL 9145 SEC RAINY RIVER; SUMMER RESORT LOCATION G2958 SENN ON OFF LAKE EXCEPT A12802; DISTRICT OF RAINY RIVER

 

16. 56045-0181 (LT)

SURFACE RIGHTS ONLY; PT LT 1 CON 2 SIFTON AS IN SLT48145 EXCEPT PT 7, PL S446; UNORGANIZED

 

17. 56045-0183 (LT)

SURFACE RIGHTS ONLY; PT LT 1 CON 2 SIFTON AS IN SLT48174 EXCEPT PT 6, PL S446; UNORGANIZED

 

18. 56045-0185 (LT)

SURFACE RIGHTS ONLY; PT LT 1 CON 2 SIFTON AS IN SLT48600 EXCEPT PT 3, 5, & 8, PL S446; UNORGANIZED

 

19. 56045-0179 (LT)

SURFACE RIGHTS ONLY; S 1/2 LT 2 CON 3 SIFTON; UNORGANIZED

 

20. 56045-0171 (LT)

SURFACE RIGHTS ONLY; N 1/2 LT 2 CON 3 SIFTON EXCEPT PT 10, PL S447; UNORGANIZED

 

21. 56045-0173 (LT)

SURFACE RIGHTS ONLY; S 1/2 OF N 1/2 LT 1 CON 3 SIFTON EXCEPT SLT41820 & PT 11, PL S446; UNORGANIZED


LOGO

Page 19 of 22

 

22. 56045-0175 (LT)

SURFACE RIGHTS ONLY; N 1/2 LT 2 CON 2 SIFTON; UNORGANIZED

 

23. 56045-0177 (LT)

SURFACE RIGHTS ONLY; S 1/2 LT 1 CON 3 SIFTON EXCEPT PT 9 & 10, PL 8446; UNORGANIZED

 

24. 56045-0039 (LT)

PCL 14386 SEC RAINY RIVER; N 1/2 LT 3 CON 2 SIFTON; UNORGANIZED

 

25. 56045-0098 (LT)

PCL 24968 SEC RAINY RIVER; S 1/2 LT 3 CON 3 SIFTON SURFACE RIGHTS ONLY; UNORGANIZED

 

26. 56041-0163 (LT)

PCL 8386 SEC RAINY RIVER; PT SEC 36 TAIT BEING THE SW SUBDIVISION; CHAPPLE

 

27. 56041-0219 (LT)

SURFACE RIGHTS ONLY; SE 1/4 SEC 35 TAIT EXCEPT PT 1 48R4044; CHAPPLE

 

28. 56041-0220 (LT)

MINING RIGHTS ONLY; SE 1/4 SEC 35 TAIT; CHAPPLE

 

29. 56041-0117 (LT)

PCL 14468 SEC RAINY RIVER; NE 1/4 SEC 22 TAIT; CHAPPLE

 

30. 56041-0138 (LT)

PCL 9519 SEC RAINY RIVER; NE 1/4 SEC 26 TAIT; CHAPPLE

 

31. 56041-0140 (LT)

PCL 8719 SEC RAINY RIVER; PT SEC 25 TAIT BEING THE SW SUBDIVISION; CHAPPLE

 

32. 56041-0023 (LT)

PCL 19642 SEC RAINY RIVER; PT SEC 26 TAIT BEING THE NE 1/4 OF THE SE 1/4; CHAPPLE

 

33. 56041-0158 (LT)

PCL 14464 SEC RAINY RIVER; PT SEC 34 TAIT BEING THE SE SUBDIVISION EXCEPT SLT68553; CHAPPLE


LOGO

Page 20 of 22

Schedule “D”

Unpatented Claims

See Attached.


Mining Claim Client Reports       Page 1 of 4

 

 

LOGO

 

   

Home

 

   

Mines and Minerals

 

   

Northern Development

 

   

News

 

   

Site Map

 

   

Contact Us

Mining Claim Client Reports

|  Main Menu  |  Back  |

KENORA Mining Division - 402288 - RAINY RIVER RESOURCES LTD.

 

Township/Area

   Claim
Number
   Recording
Date
   Claim
Due Date
   Status    Percent
Option
    Work
Required
     Total
Applied
     Total
Reserve
     Claim
Bank
 

FLEMING

   3019809    2004-May-17    2015-May-17    A      100   $ 4,800       $ 43,200       $ 377,465       $ 0   

FLEMING

   4211671    2006-Jun-26    2015-Jun-26    A      100   $ 400       $ 2,800       $ 0       $ 0  

FLEMING

   4244241    2009-Jan-28    2015-Jan-28    A      100   $ 6,400       $ 25,600       $ 25,806       $ 0  

FLEMING

   4244243    2009-Jan-28    2015-Jan-28    A      100   $ 1,200       $ 4,800       $ 0       $ 0   

FLEMING

   4245258    2009-Jan-28    2015-Jan-28    A      100   $ 400       $ 1,600       $ 0       $ 0   

FLEMING

   4245259    2009-Jan-28    2015-Jan-28    A      100   $ 800       $ 3,200       $ 0       $ 0   

FLEMING

   4245260    2009-Jan-28    2014-Jan-28    A      100   $ 3,200       $ 9,600       $ 0       $ 0   

MENARY

   4208866    2005-Oct-26    2014-Oct-26    A      100   $ 6,400       $ 44,800       $ 0       $ 0   

MENARY

   4208867    2005-Oct-26    2014-0ct-26    A      100   $ 4,800       $ 33,600       $ 0       $ 0   

MENARY

   4208868    2005-Oct-26    2014-Oct-26    A      100   $ 6,400       $ 44,800       $ 14,468       $ 0   

MENARY

   4208869    2005-Oct-26    2014-Oct-26    A      100   $ 6,400       $ 44,800       $ 0       $ 0   

MENARY

   4208870    2005-Oct-26    2014-Oct-26    A      100   $ 6,400       $ 44,800       $ 0       $ 0   

MENARY

   4208871    2005-Oct-26    2014-Oct-26    A      100   $ 6,000       $ 42,000       $ 1,954       $ 0   

MENARY

   4208872    2005-Oct-26    2014-Oct-26    A      100   $ 6,400       $ 44,800       $ 26,723       $ 0   

MENARY

   4208873    2005-Oct-26    2014-Oct-26    A      100   $ 6,400       $ 44,800       $ 11,233       $ 0   

MENARY

   4208874    2005-Oct-26    2014-Oct-26    A      100   $ 6,400       $ 44,800       $ 9,951       $ 0  

MENARY

   4208875    2005-Oct-26    2014-Oct-26    A      100   $ 6,400       $ 44,800       $ 2,015       $ 0   

MENARY

   4208876    2005-Oct-26    2014-Oct-26    A      100   $ 5,600       $ 39,200       $ 61       $ 0   

MENARY

   4244244    2009-Jan-28    2014-Jan-28    A      100   $ 4,800       $ 14,400       $ 0       $ 0   

MENARY

   4244245    2009-Jan-28    2016-Jan-28    A      100   $ 4,800       $ 24,000       $ 0       $ 0   

MENARY

   4244247    2009-Jan-28    2016-Jan-28    A      100   $ 6,400       $ 32,000       $ 0       $ 0   


Mining Claim Client Reports       Page 2 of 4

 

MENARY

   4244248    2009-Jan-28    2016-Jan-28    A      100   $ 6,400       $ 32,000       $ 0       $ 0   

POTTS

   3012554    2007-Mar-13    2015-Mar-13    A      100   $ 1,200       $ 7,200       $ 0       $ 0   

POTTS

   4207826    2006-Feb-20    2015-Feb-20    A      100   $ 1,600       $ 11,200       $ 0       $ 0   

POTTS

   4211670    2006-Jun-26    2015-Jun-26    A      100   $ 1,600       $ 11,200       $ 0       $ 0   

POTTS

   4211672    2006-Jun-26    2014-Jun-26    A      100   $ 2,000       $ 12,000       $ 0       $ 0   

POTTS

   4218605    2007-Apr-19    2014-Apr-19    A      100   $ 1,600       $ 8,000       $ 562       $ 0   

POTTS

   4224810    2008-May-06    2015-May-06    A      100   $ 6,400       $ 32,000       $ 1,525       $ 0   

POTTS

   4224811    2008-May-06    2015-May-06    A      100   $ 1,600       $ 8,000       $ 427       $ 0   

POTTS

   4224812    2008-May-06    2015-May-06    A      100   $ 4,800       $ 24,000       $ 2,655       $ 0   

POTTS

   4224813    2008-May-15    2015-May-15    A      100   $ 800       $ 4,000       $ 334       $ 0   

POTTS

   4244242    2009-Jan-28    2014-Jan-28    A      100   $ 2,800       $ 8,400       $ 0       $ 0   

POTTS

   4245251    2009-Jan-28    2016-Jan-28    A      100   $ 4,800       $ 24,000       $ 0       $ 0   

POTTS

   4245252    2009-Jan-28    2016-Jan-28    A      100   $ 3,200       $ 16,000       $ 0       $ 0   

POTTS

   4245253    2009-Jan-28    2016-Jan-28    A      100   $ 3,200       $ 16,000       $ 0       $ 0   

POTTS

   4245254    2009-Jan-28    2014-Jan-28    A      100   $ 400       $ 1,200       $ 0       $ 0   

POTTS

   4245255    2009-Jan-28    2014-Jan-28    A      100   $ 2,400       $ 7,200       $ 0       $ 0   

POTTS

   4249688    2010-Mar-01    2015-Mar-01    A      100   $ 1,600       $ 4,800       $ 0       $ 0   

RICHARDSON

   1105422    1992-Oct-09    2014-Oct-09    A      100   $ 864       $ 32,736       $ 1,583       $ 0   

RICHARDSON

   1105423    1992-Oct-09    2014-Oct-09    A      100   $ 1,600       $ 32,000       $ 670       $ 0   

RICHARDSON

   1105425    1992-Oct-09    2014-Oct-09    A      100   $ 3,200       $ 64,000       $ 298       $ 0   

RICHARDSON

   1105426    1992-Oct-09    2014-Oct-09    A      100   $ 800       $ 16,000       $ 0       $ 0   

RICHARDSON

   1105427    1992-Oct-15    2014-Oct-15    A      100   $ 1,600       $ 32,000       $ 0       $ 0   

RICHARDSON

   1105428    1992-Oct-15    2015-Oct-15    A      100   $ 4,800       $ 100,800       $ 0       $ 0   

RICHARDSON

   1105430    1992-Oct-15    2015-Oct-15    A      100   $ 4,800       $ 100,800       $ 0       $ 0   

RICHARDSON

   1161073    1991-Dec-19    2014-Dec-19    A      100   $ 3,200       $ 67,200       $ 1,389       $ 0   

RICHARDSON

   1161074    1991-Dec-19    2014-Dec-19    A      100   $ 1,600       $ 33,600       $ 0       $ 0   

RICHARDSON

   1161075    1991-Dec-19    2014-Dec-19    A      100   $ 800       $ 16,800       $ 0       $ 0   

RICHARDSON

   1161076    1991-Dec-19    2015-Dec-19    A      100   $ 4,800       $ 105,600       $ 1,209       $ 0   

RICHARDSON

   1161079    1991-Dec-19    2014-Dec-19    A      100   $ 3,200       $ 67,200       $ 1,456       $ 0   

RICHARDSON

   1161080    1991-Dec-19    2014-Dec-19    A      100   $ 3,200       $ 67,200       $ 0       $ 0   

RICHARDSON

   1161081    1991-Dec-19    2014-Dec-19    A      100   $ 3,200       $ 67,200       $ 0       $ 0   


Mining Claim Client Reports       Page 3 of 4

 

 

RICHARDSON

   1161100    1991-Dec-19    2014-Dec-19    A      100   $ 3,200       $ 67,200       $ 0       $ 0   

RICHARDSON

   1161592    1994-Mar-01    2015-Mar-01    A      100   $ 1,600       $ 30,400       $ 0       $ 0   

RICHARDSON

   1161604    1994-Mar-01    2015-Mar-01    A      100   $ 800       $ 15,200       $ 0       $ 0   

RICHARDSON

   1178215    1995-Feb-24    2017-Feb-24    A      100   $ 6,400       $ 128,000       $ 439       $ 0   

RICHARDSON

   1210106    1996-May-27    2015-May-27    A      100   $ 800       $ 13,600       $ 425       $ 0   

RICHARDSON

   4251442    2010-Jun-02    2017-Jun-02    A      100   $ 1,600       $ 8,000       $ 679       $ 0   

SENN

   3008455    2004-Jun-21    2015-Jun-21    A      100   $ 5,600       $ 50,400       $ 0       $ 0   

SENN

   3008456    2004-Jun-21    2015-Jun-21    A      100   $ 1,600       $ 14,400       $ 0       $ 0   

SENN

   3012529    2006-Feb-13    2014-Feb-13    A      100   $ 6,400       $ 38,400       $ 0       $ 0   

SENN

   3012530    2006-Feb-13    2014-Feb-13    A      100   $ 6,400       $ 38,400       $ 0       $ 0   

SENN

   3016066    2006-Feb-13    2014-Feb-13    A      100   $ 6,400       $ 38,400       $ 0       $ 0   

SENN

   3016067    2006-Feb-13    20I4-Feb-13    A      100   $ 6,400       $ 38,400       $ 0       $ 0   

SENN

   3016068    2006-Feb-13    2014-Feb-13    A      100   $ 6,400       $ 38,400       $ 0       $ 0   

SENN

   3016069    2006-Feb-13    2015-Feb-13    A      100   $ 6,400       $ 44,800       $ 0       $ 0   

SENN

   3016070    2006-Feb-13    2015-Feb-13    A      100   $ 6,400       $ 44,800       $ 0       $ 0   

SENN

   4244246    2009-Jan-28    2016-Jan-28    A      100   $ 5,200       $ 26,000       $ 0       $ 0   

SENN

   4244249    2009-Jan-28    2014-Jan-28    A      100   $ 6,400       $ 19,200       $ 0       $ 0   

SIFTON

   1218904    2012-Jan-09    2019-Jan-09    A      100   $ 400       $ 2,000       $ 0       $ 0   

TAIT

   4253992    2011-Jan-11    2015-Jan-11    A      100   $ 2,000       $ 4,000       $ 277       $ 0   

TAIT

   4253993    2011-Jan-11    2015-Jan-11    A      100   $ 1,600       $ 3,200       $ 869       $ 0   


Mining Claim Client Reports       Page 4 of 4

 

 

   

Home

 

   

Mines and Minerals

 

   

Northern Development

 

   

News

 

   

Site Map

 

   

Contact Us

 

LOGO

 

   

Accessibility

 

   

Privacy

 

   

Important Notices

Copyright information: © Queen’s Printer for Ontario, 2008


LOGO

Page 21 of 22

Schedule “D1”

Optioned Unpatented Claims (re English Option Agreements)

Mining Claim No. K 4200490

Mining Claim No. K 4200492

Mining Claim No. K 4200493

Mining Claim No. K 4200494

Mining Claim No. K 4214437

All in the Kenora Mining Division

Optioned Unpatented Claims (re Fred Roisin Option Agreement)

Mining Claim No. K 3016858

Mining Claim No. K 3016859

Mining Claim No. K 3016838

All in the Kenora Mining Division

Optioned Unpatented Claims (re Timberridge Option Agreement)

Mining Claim No. K 3016793

In the Kenora Mining Division


LOGO

Page 22 of 22

Schedule “E”

Qualifications

 

1. Any reservations, limitations, provisos and conditions expressed in the original grants from the Crown as the same may be varied by statute.

 

2. The exceptions and qualifications contained in section 44(1) of the Land Titles Act (Ontario), paragraphs 7, 8, 9, 10, 12 and 14.

 

3. No investigation has been made of the original application for filing in respect of, or the location of the boundaries of any of the Patented Lands, the Leasehold Lands, the Unpatented Claims or the Optioned Unpatented Claims.

 

4. No examination of the ground was made to determine if any of the Patented Lands, the Leasehold Lands, the Unpatented Claims or Optioned Unpatented Claims were validly staked and assessment work carried out in compliance with the Mining Act (Ontario) and the regulations thereunder.

 

5. The rights, title and interests of the registered or recorded holders and/or Rainy River in and to the Patented Lands, the Leasehold Lands, the Unpatented Claims and Optioned Unpatented Claims are subject to the following:

 

  (a) compliance with the terms of the Mining Act (Ontario) and the regulations pursuant thereto;

 

  (b) the terms of each lease underlying the Leasehold Lands;

 

  (c) the reservations and exceptions contained in the Mining Act (Ontario) and the regulations pursuant thereto, including those noted on the Records;

 

  (d) statutory priorities and preferences and liens, encumbrances or other charges which are extent and are still within the time for recording, or which are valid without recording, in the Mining Recorders Office or Mining Lands Section of the Ontario Ministry of Northern Development and Mines;

 

  (e) any unregistered or unrecorded rights;

 

  (f) we have assumed, without verification, that the grant or creation of any and all rights, title or interests in and to the Patented Lands was in compliance with the Planning Act (Ontario);

 

  (g) the existence of any possible conflict with aboriginal title or rights; and

 

  (h) applicable bankruptcy, insolvency or similar laws affecting creditors’ rights generally.

 

6. The enforceability of the Option Agreements may be limited by applicable bankruptcy, insolvency, reorganization, moratorium and other laws affecting creditors’ rights generally and general principles of equity and the discretion that a court of competent jurisdiction may exercise in the granting of equitable remedies.


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

APPENDIX B

Rainy River Resources Patented, Leasehold and Mining Claims

(November 22, 2013)

 

 


Patented/Leased Claims On The Rainy River Property:

 

      

Township/Area

  

Parcel

  

PIN (Parcel

Identification

Number)

  

Owner and/or

Option Name

  1       MATHER    17371    56036-0084    RR
  2       MATHER    16847    56036-0077    RR
  3       PATTULLO    SRO    56046-0128    RR
  4       POTTS    SRO (former 12658)    56035-0249    HUTIKKA
  5       POTTS    MRO (former 12658)    56035-0248    RR
  6       POTTS    SRO (former 17905)    56035-0245    PETKAU
  7       POTTS    MRO (former 17905)    56035-0244    RR
  8       POTTS    SRO (former 5301)    56035-0247    PETKAU
  9       POTTS    MRO (former 5301)    56036-0246    RR
  10       POTTS    16077    56035-0066    RR
  11       POTTS    18689    56035-0098    RR
  12       POTTS    5899    56035-0176    RR
  13       POTTS    17941    56035-0090    RR
  14       POTTS    SRO (former 16784)    56035-0242    RR
  15       POTTS    10286    56035-0009    RR
  16       RICHARDSON    L1078    56042-0140    RR
  17       RICHARDSON    L1078    56042-0141    RR
  18       RICHARDSON    L1078    56042-0142    RR
  19       RICHARDSON    22495 (SRO)    56042-0082    RR
  20       RICHARDSON    SRO (former 18580)    56042-0188    BURKELAND/HANN
  21       RICHARDSON    MRO (former 18580)    56042-0189    RR
  22       RICHARDSON    SRO (former 16342)    56042-0186    BURKELAND
  23       RICHARDSON    MRO (former 16342)    56042-0187    RR
  24       RICHARDSON    SRO (former 7064)    56042-0160    RR
  25       RICHARDSON    MRO (former 7064)    56042-0161    RR
  26       RICHARDSON    SRO (former 11087)    56042-0162    RR
  27       RICHARDSON    MRO (former 11087)    56042-0163    RR
  28       RICHARDSON    25891 (MRO)    56042-0097    RR
  29       RICHARDSON    14408 (SRO)    56042-0034    RR
  30       RICHARDSON    SRO (former 13275)    56042-0172    ELIUK
  31       RICHARDSON    MRO (former 13275)    56042-0173    RR
  32       RICHARDSON    26007 (MRO)    56042-0139    RR
  33       RICHARDSON    4534 (SRO)    56042-0104    RR
  34       RICHARDSON    26007 (MRO)    56042-0102    RR
  35       RICHARDSON    5483 (SRO)    56042-0113    RR
  36       RICHARDSON    SRO (former 20561)    56042-0178    GERULA, B
  37       RICHARDSON    MRO (former 20561)    56042-0179    RR
  38       RICHARDSON    SRO (former 18204)    56042-0176    GIBB
  39       RICHARDSON    MRO (former 18204)    56042-0177    RR
  40       RICHARDSON    25984 (MRO)    56042-0100    RR
  41       RICHARDSON    8825 (MRO)    56042-0128    RR
  42       RICHARDSON    25892 (MRO)    56042-0098    RR
  43       RICHARDSON    SRO (former 4801)    56042-0174    JSD LOGGING
  44       RICHARDSON    MRO (former 4801)    56042-0175    RR
  45       RICHARDSON    SRO (former 7320)    56042-0170    LEBLANC
  46       RICHARDSON    MRO (former 7320)    56042-0171    RR
  47       RICHARDSON    SRO (former 7180)    56042-0168    LEBLANC
  48       RICHARDSON    MRO (former 7180)    56042-0169    RR
  49       RICHARDSON    14407 (SRO)    56042-0033    RR
  50       RICHARDSON    25894 (MRO)    56042-0099    RR
  51       RICHARDSON    16297    56042-0058    RR


      

Township/Area

  

Parcel

  

PIN (Parcel

Identification

Number)

  

Owner and/or

Option Name

  52       RICHARDSON    SRO (former 14196)    56042-0166    RR
  53       RICHARDSON    MRO (former 14196)    56042-0167    RR
  54       RICHARDSON    MRO (former 10029)    56042-0158    RR
  55       RICHARDSON    SRO (former 10029)    56042-0159    RR
  56       RICHARDSON    5939    56042-0116    RR
  57       RICHARDSON    5614    56042-0114    RR
  58       RICHARDSON    17725    56042-0063    RR
  59       RICHARDSON    17726    56042-0064    RR
  60       RICHARDSON    17110    56042-0060    RR
  61       RICHARDSON    14462    56042-0036    RR
  62       RICHARDSON    MRO (former 10843)    56042-0146    RR
  63       RICHARDSON    SRO (former 10843)    56042-0147    RR
  64       RICHARDSON    21129    56042-0077    RR
  65       RICHARDSON    16779    56042-0145    RR
  66       RICHARDSON    16630    56042-0053    RR
  67       RICHARDSON    SRO (former 14986)    56042-0164    RR
  68       RICHARDSON    MRO (former 14986)    56042-0165    RR
  69       RICHARDSON    SRO (former 10961)    56042-0180    RR
  70       RICHARDSON    MRO (former 10961)    56042-0181    RR
  71       RICHARDSON    SRO (former 9771)    56042-0184    RR
  72       RICHARDSON    MRO (former 9771)    56042-0185    RR
  73       RICHARDSON    SRO (former 4768)    56042-0182    RR
  74       RICHARDSON    MRO (former 4768)    56042-0183    RR
  75       RICHARDSON    MRO (former 4950)    56042-0149    RR
  76       RICHARDSON    SRO (former 4950)    56042-0148    RR
  77       RICHARDSON    15881    56042-0047    RR
  78       RICHARDSON    11853    56042-0012    RR
  79       RICHARDSON    17392    56042-0062    RR
  80       RICHARDSON    14604    56042-0037    RR
  81       RICHARDSON    9080    56042-0129    RR
  82       RICHARDSON    SRO (former 17154)    56042-0061    RR
  83       RICHARDSON    8071    56042-0123    1530600 ONTARIO
  84       RICHARDSON    8235    56042-0124    1530600 ONTARIO
  85       RICHARDSON    15282    56042-0044    RR
  86       RICHARDSON    23322    56042-0088    RR
  87       RICHARDSON    17752    56042-0065    RR
  88       RICHARDSON    25991(SRO)    56042-0101    RR
  89       RICHARDSON    13137    56042-0021    RR
  90       RICHARDSON    10273    56042-0003    RR
  91       RICHARDSON    13467    56042-0024    RR
  92       RICHARDSON    16307    56042-0050    RR
  93       RICHARDSON    16343    56042-0052    RR
  94       RICHARDSON    11409(SRO)    56042-0011    RR
  95       RICHARDSON    12324    56042-0018    RR
  96       RICHARDSON    22190    56042-0081    RR
  97       RICHARDSON    14665    56042-0038    RR
  98       RICHARDSON    16820    56042-0056    RR
  99       RICHARDSON    10152    56042-0002    RR
  100       RICHARDSON    16754    56042-0055    RR
  101       RICHARDSON    16956    56042-0059    RR
  102       RICHARDSON    14200    56042-0029    RR
  103       RICHARDSON    10746    56042-0005    RR
  104       RICHARDSON    6520    56042-0117    RR


      

Township/Area

  

Parcel

  

PIN (Parcel
Identification
Number)

  

Owner and/or

Option Name

  105       RICHARDSON    5455    56042-0112    RR
  106       RICHARDSON    12083    56042-0016    RR
  107       RICHARDSON    7654    56042-0121    RR
  108       RICHARDSON    9665    56042-0133    RR
  109       RICHARDSON    13514    56042-0025    RR
  110       RICHARDSON    SRO (former 15916)    56042-0190    RR
  111       RICHARDSON    21213    56042-0078    RR
  112       RICHARDSON    11912 (SRO)    56042-0014    RR
  113       RICHARDSON    14238 (SRO)    56042-0030    RR
  114       RICHARDSON    4947 (SRO)    56042-0108    RR
  115       RICHARDSON    8070 (SRO)    56042-0122    RR
  116       RICHARDSON    22496 (SRO)    56042-0083    RR
  117       RICHARDSON    4259 (SRO)    56042-0103    RR
  118       RICHARDSON    5279 (SRO)    56042-0111    RR
  119       RICHARDSON    13681    56042-0026    RR
  120       RICHARDSON    13804    56042-0027    RR
  121       RICHARDSON    9656    56042-0131    RR
  122       SENN    MRO (former 14979)    56032-0280    RR
  123       SENN    SRO (former 14979)    56032-0281    KATRIN/STRAND
  124       SENN    9145    56032-0240    KATRIN/STRAND
  125       SIFTON    SRO (former 13001)    56045-0181    GERULA, M & N
  126       SIFTON    MRO (former 13001)    56045-0182    RR
  127       SIFTON    SRO (former 13015)    56045-0183    GERULA, M & N
  128       SIFTON    MRO (former 13015)    56045-0184    RR
  129       SIFTON    SRO (former 13117)    56045-0185    GERULA, M & N
  130       SIFTON    MRO (former 13117)    56045-0186    RR
  131       SIFTON    SRO (former 8683)    56045-0179    GERULA, B
  132       SIFTON    MRO (former 8683)    56045-0180    RR
  133       SIFTON    SRO (former 10271)    56045-0171    LEBLANC
  134       SIFTON    MRO (former 10271)    56045-0172    RR
  135       SIFTON    SRO (former 10798)    56045-0173    LEBLANC
  136       SIFTON    MRO (former 10798)    56045-0174    RR
  137       SIFTON    SRO (former 13448)    56045-0175    LEBLANC
  138       SIFTON    MRO (former 13448)    56045-0176    RR
  139       SIFTON    SRO (former 8201)    56045-0177    LEBLANC
  140       SIFTON    MRO (former 8201)    56045-0178    RR
  141       SIFTON    14386    56045-0039    GERULA, B
  142       SIFTON    24968 (SRO)    56045-0098    TIMBERRIDGE
  143       SIFTON    15876    56045-0052    RR
  144       TAIT    6721    56041-0159    RR
  145       TAIT    SRO (former 5490)    56041-0222    RR
  146       TAIT    MRO (former 5490)    56041-0221    RR
  147       TAIT    SRO (former 16623)    56041-0223    RR
  148       TAIT    MRO (former 16623)    56041-0224    RR
  149       TAIT    SRO (former 21172)    56041-0225    RR
  150       TAIT    MRO (former 21172)    56041-0226    RR
  151       TAIT    8386    56041-0163    TEEPLE, D & J
  152       TAIT    SRO – SE  1/4 Sec 35 except Pt 1,48 R4044    56041-0219    TEEPLE, D & V
  153       TAIT    MRO – SE  1/4 Sec 35    56041-0220    TEEPLE, D & V


      

Township/Area

  

Parcel

  

PIN (Parcel

Identification

Number)

  

Owner and/or

Option Name

  154       TAIT   

SRO – Pt SE  1/4 Sec 35

except Pt 1, 48R4044

   56041-0215    RR
  155       TAIT    14468    56041-0117    SCHRAM, K
  156       TAIT    9519    56041-0138    BRAGG, D
  157       TAIT    8719    56041-0140    BRAGG, D & J
  158       TAIT    19642    56041-0023    BRAGG/PAQUETTE
  159       TAIT    7153    56041-0164    RR
  160       TAIT    14464    56041-0158    ROISIN
  161       TAIT    17230    56041-0002    RR
  162       TAIT    13528    56041-0152    RR

Unpatented Mining Claims On The Rainy River Property:

All claims are active and held 100 percent by Rainy River.

 

    

Township/Area

  

Claim Number

  

Recording

Date

    

Claim Due

Date

    

Work

Required

    

Total

Applied

    

Total

Reserve

 
1    FLEMING    3019809      2004-May-17         2015-May-17       $ 4,800       $ 43,200       $ 377,465   
2    FLEMING    4211671      2006-Jun-26         2015-Jun-26       $ 400       $ 2,800       $ 0   
3    FLEMING    4244241      2009-Jan-28         2015-Jan-28       $ 6,400       $ 25,600       $ 25,806   
4    FLEMING    4244243      2009-Jan-28         2015-Jan-28       $ 1,200       $ 4,800       $ 0   
5    FLEMING    4245258      2009-Jan-28         2015-Jan-28       $ 400       $ 1,600       $ 0   
6    FLEMING    4245259      2009-Jan-28         2015-Jan-28       $ 800       $ 3,200       $ 0   
7    FLEMING    4245260      2009-Jan-28         2014-Jan-28       $ 3,200       $ 9,600       $ 0   
8    MENARY    4208866      2005-Oct-26         2014-Oct-26       $ 6,400       $ 44,800       $ 0   
9    MENARY    4208867      2005-Oct-26         2014-Oct-26       $ 4,800       $ 33,600       $ 0   
10    MENARY    4208868      2005-Oct-26         2014-Oct-26       $ 6,400       $ 44,800       $ 14,468   
11    MENARY    4208869      2005-Oct-26         2014-Oct-26       $ 6,400       $ 44,800       $ 0   
12    MENARY    4208870      2005-Oct-26         2014-Oct-26       $ 6,400       $ 44,800       $ 0   
13    MENARY    4208871      2005-Oct-26         2014-Oct-26       $ 6,000       $ 42,000       $ 1,954   
14    MENARY    4208872      2005-Oct-26         2014-Oct-26       $ 6,400       $ 44,800       $ 26,723   
15    MENARY    4208873      2005-Oct-26         2014-Oct-26       $ 6,400       $ 44,800       $ 11,233   
16    MENARY    4208874      2005-Oct-26         2014-Oct-26       $ 6,400       $ 44,800       $ 9,951   
17    MENARY    4208875      2005-Oct-26         2014-Oct-26       $ 6,400       $ 44,800       $ 2,015   
18    MENARY    4208876      2005-Oct-26         2014-Oct-26       $ 5,600       $ 39,200       $ 61   
19    MENARY    4244244      2009-Jan-28         2014-Jan-28       $ 4,800       $ 14,400       $ 0   
20    MENARY    4244245      2009-Jan-28         2016-Jan-28       $ 4,800       $ 24,000       $ 0   
21    MENARY    4244247      2009-Jan-28         2016-Jan-28       $ 6,400       $ 32,000       $ 0   
22    MENARY    4244248      2009-Jan-28         2016-Jan-28       $ 6,400       $ 32,000       $ 0   
23    POTTS    3012554      2007-Mar-13         2015-Mar-13       $ 1,200       $ 7,200       $ 0   
24    POTTS    4207826      2006-Feb-20         2015-Feb-20       $ 1,600       $ 11,200       $ 0   
25    POTTS    4211670      2006-Jun-26         2015-Jun-26       $ 1,600       $ 11,200       $ 0   
26    POTTS    4211672      2006-Jun-26         2014-Jun-26       $ 2,000       $ 12,000       $ 0   
27    POTTS    4218605      2007-Apr-19         2014-Apr-19       $ 1,600       $ 8,000       $ 562   
28    POTTS    4224810      2008-May-06         2015-May-06       $ 6,400       $ 32,000       $ 1,525   
29    POTTS    4224811      2008-May-06         2015-May-06       $ 1,600       $ 8,000       $ 427   
30    POTTS    4224812      2008-May-06         2015-May-06       $ 4,800       $ 24,000       $ 2,655   
31    POTTS    4224813      2008-May-15         2015-May-15       $ 800       $ 4,000       $ 334   
32    POTTS    4244242      2009-Jan-28         2014-Jan-28       $ 2,800       $ 8,400       $ 0   


    

Township/Area

  

Claim Number

  

Recording

Date

    

Claim Due

Date

    

Work

Required

    

Total

Applied

    

Total

Reserve

 
33    POTTS    4245251      2009-Jan-28         2016-Jan-28       $ 4,800       $ 24,000       $ 0   
34    POTTS    4245252      2009-Jan-28         2016-Jan-28       $ 3,200       $ 16,000       $ 0   
35    POTTS    4245253      2009-Jan-28         2016-Jan-28       $ 3,200       $ 16,000       $ 0   
36    POTTS    4245254      2009-Jan-28         2014-Jan-28       $ 400       $ 1,200       $ 0   
37    POTTS    4245255      2009-Jan-28         2014-Jan-28       $ 2,400       $ 7,200       $ 0   
38    POTTS    4249688      2010-Mar-01         2015-Mar-01       $ 1,600       $ 4,800       $ 0   
39    RICHARDSON    1105422      1992-Oct-09         2014-Oct-09       $ 864       $ 32,736       $ 1,583   
40    RICHARDSON    1105423      1992-Oct-09         2014-Oct-09       $ 1,600       $ 32,000       $ 670   
41    RICHARDSON    1105425      1992-Oct-09         2014-Oct-09       $ 3,200       $ 64,000       $ 298   
42    RICHARDSON    1105426      1992-Oct-09         2014-Oct-09       $ 800       $ 16,000       $ 0   
43    RICHARDSON    1105427      1992-Oct-15         2014-Oct-15       $ 1,600       $ 32,000       $ 0   
44    RICHARDSON    1105428      1992-Oct-15         2015-Oct-15       $ 4,800       $ 100,800       $ 0   
45    RICHARDSON    1105430      1992-Oct-15         2015-Oct-15       $ 4,800       $ 100,800       $ 0   
46    RICHARDSON    1161073      1991-Dec-19         2014-Dec-19       $ 3,200       $ 67,200       $ 1,389   
47    RICHARDSON    1161074      1991-Dec-19         2014-Dec-19       $ 1,600       $ 33,600       $ 0   
48    RICHARDSON    1161075      1991-Dec-19         2014-Dec-19       $ 800       $ 16,800       $ 0   
49    RICHARDSON    1161076      1991-Dec-19         2015-Dec-19       $ 4,800       $ 105,600       $ 1,209   
50    RICHARDSON    1161079      1991-Dec-19         2014-Dec-19       $ 3,200       $ 67,200       $ 1,456   
51    RICHARDSON    1161080      1991-Dec-19         2014-Dec-19       $ 3,200       $ 67,200       $ 0   
52    RICHARDSON    1161081      1991-Dec-19         2014-Dec-19       $ 3,200       $ 67,200       $ 0   
53    RICHARDSON    1161100      1991-Dec-19         2014-Dec-19       $ 3,200       $ 67,200       $ 0   
54    RICHARDSON    1161592      1994-Mar-01         2015-Mar-01       $ 1,600       $ 30,400       $ 0   
55    RICHARDSON    1161604      1994-Mar-01         2015-Mar-01       $ 800       $ 15,200       $ 0   
56    RICHARDSON    1178215      1995-Feb-24         2017-Feb-24       $ 6,400       $ 128,000       $ 439   
57    RICHARDSON    1210106      1996-May-27         2015-May-27       $ 800       $ 13,600       $ 425   
58    RICHARDSON    4251442      2010-Jun-02         2017-Jun-02       $ 1,600       $ 8,000       $ 679   
59    SENN    3008455      2004-Jun-21         2015-Jun-21       $ 5,600       $ 50,400       $ 0   
60    SENN    3008456      2004-Jun-21         2015-Jun-21       $ 1,600       $ 14,400       $ 0   
61    SENN    3012529      2006-Feb-13         2014-Feb-13       $ 6,400       $ 38,400       $ 0   
62    SENN    3012530      2006-Feb-13         2014-Feb-13       $ 6,400       $ 38,400       $ 0   
63    SENN    3016066      2006-Feb-13         2014-Feb-13       $ 6,400       $ 38,400       $ 0   
64    SENN    3016067      2006-Feb-13         2014-Feb-13       $ 6,400       $ 38,400       $ 0   
65    SENN    3016068      2006-Feb-13         2014-Feb-13       $ 6,400       $ 38,400       $ 0   
66    SENN    3016069      2006-Feb-13         2015-Feb-13       $ 6,400       $ 44,800       $ 0   
67    SENN    3016070      2006-Feb-13         2015-Feb-13       $ 6,400       $ 44,800       $ 0   
68    SENN    4244246      2009-Jan-28         2016-Jan-28       $ 5,200       $ 26,000       $ 0   
69    SENN    4244249      2009-Jan-28         2014-Jan-28       $ 6,400       $ 19,200       $ 0   
70    SIFTON    1218904      2012-Jan-09         2019-Jan-09       $ 400       $ 2,000       $ 0   
71    TAIT    4253992      2011-Jan-11         2015-Jan-11       $ 2,000       $ 4,000       $ 277   
72    TAIT    4253993      2011-Jan-11         2015-Jan-11       $ 1,600       $ 3,200       $ 869   


Unpatented Mining Claims Of The “English Option” Agreement:

 

    

Township/Area

  

Claim

Number

  

Recording

Date

  

Claim Due Date

  

Work

Required

    

Total

Applied

    

Total

Reserve

 
1    TAIT    4200492    2006-Oct-27    2014-Oct-27    $ 1,600       $ 9,600       $ 78,536   
2    TAIT    4200494    2006-Oct-27    2014-Oct-27    $ 5,200       $ 31,200       $ 94,336   
3    TAIT    4214437    2010-Mar-03    2015-Mar-03    $ 1,600       $ 4,800       $ 41,783   
4    TAIT    4200490    2006-Oct-27    2014-Oct-27    $ 800       $ 4,800       $ 0   
5    TAIT    4200493    2006-Oct-27    2014-Oct-27    $ 3,600       $ 21,600       $ 86,914   

Unpatented Mining Claims Of The “Roisin Option” Agreement:

 

    

Township/Area

  

Claim

Number

  

Recording

Date

  

Claim Due Date

  

Work

Required

    

Total

Applied

    

Total

Reserve

 
1    POTTS    3016858    2010-Jul-08    2016-Jul-08    $ 1,600       $ 6,400       $ 0   
2    RICHARDSON    3016838    2010-Jul-08    2015-Jul-08    $ 3,200       $ 9,600       $ 0   
3    RICHARDSON    3016859    2010-Jul-08    2014-Jul-08    $ 1,600       $ 3,200       $ 0   

Unpatented Mining Claims Of The “Timberridge Option” Agreement:

 

    

Township/Area

  

Claim
Number

  

Recording
Date

  

Claim Due Date

  

Work
Required

    

Total
Applied

    

Total
Reserve

 
1    SIFTON    3016793    2009-Sep-25    2015-Sept-25    $ 1,600       $ 6,400       $ 1,165   


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

APPENDIX C

Nuinsco Exploration Activities (1993 to 2002)

 

 


Summary of Nuinsco Exploration Activities at the Rainy River Gold Project (1993 – 2002)

 

Activity 1

  

Date

  

Performed by:

Rotasonic drilling    26/06/93 - 01/07/93    Midwest Drilling
IP survey    December, 1993    Val d’Or Géophysique
Magnetometer survey    December, 1993    Val d’Or Géophysique
Landsat linear study    August, 1993    DOZ Consulting Group
Reconnaissance mapping and sampling    04/07/93-27/08/93    Nuinsco Resources
Rotasonic drilling    March, 1994    Midwest Drilling
Reverse circulation drilling    06/03/94 - 01/04/94    Bradley Bros. - Overburden Drilling
Diamond drilling    08/11/94 - 20/12/94    Ultra Mobile Diamond Drilling
Grid mapping and sampling    May-June, 1994    Nuinsco Resources
Soil Sampling/Enzyme Leach    June-August, 1994    Nuinsco Resources
Reverse circulation drilling    Winter, 1995    Bradley Bros. - Overburden Drilling
Diamond drilling    04/01/95 - 16/12/95    Ultra Mobile Diamond Drilling
IP survey    25/10/95 - 10/12/95    JVX Geophysics
Trenching and stripping, mapping    Field season, 1995    Nuinsco Resources
Soil Sampling/Enzyme Leach    Field season, 1995    Nuinsco Resources
Reverse circulation drilling    Winter, 1996    Bradley Bros. - Overburden Drilling
Diamond drilling    Throughout year, 1996    Ultra Mobile Diamond Drilling
Diamond drilling    26/01/96 - 22/07/96    Bradley Brothers Diamond Drilling
UTEM survey    28/03/96 - 23/04/96    Lamontagne Geophysics
Surface pulse EM    June, 1996    Crone Geophysics
Surface pulse EM    25/09/96 - 18/12/96    JVX Geophysics
Borehole pulse EM    17/06/96 - 10/08/96    Crone Geophysics
Borehole pulse EM    26/09/96 - 21/10/96    Crone Geophysics
Borehole pulse EM    25/09/96 - 18/12/96    JVX Geophysics
IP survey    25/09/96 - 18/12/96    JVX Geophysics
Magnetometer survey    25/09/96 - 18/12/96    JVX Geophysics
Outcrop stripping    October, 1996    Nuinsco Resources
Reverse circulation drilling    Winter, 1997    Bradley Bros. - Overburden Drilling
Reverse circulation drilling    September, October, 1997    Bradley Bros. - Overburden Drilling
Diamond drilling    Throughout year, 1997    Ultra Mobile Diamond Drilling
Diamond drilling    22/01/97 - 07/04/97    Bradley Brothers Diamond Drilling
Airborne EM and Magnetic survey    04/10/97 - 08/10/97    Geoterrex-Dighem
Surface pulse EM    December, 1997    Crone Geophysics
Borehole pulse EM    03/17/97 - 03/19/97    Crone Geophysics
Borehole pulse EM    September, December 1997    Crone Geophysics
IP survey    28/09/97 - 06/10/97    Quantec IP
Local detailed mapping    May-September, 1997    Nuinsco Resources
Outcrop stripping    October, 1997    Nuinsco Resources
Surface PEM survey    Jan. Feb., 1998    Crone Geophysics
Diamond drilling    01/04/98 - 15/03/98    Ultra Mobile Diamond Drilling.
Reverse circulation drilling    Jan - Feb 1998    Bradley Bros. - Overburden Drilling
Line cutting/Magnetometer survey    March, 1998    Mtec Geophysics Inc.
Diamond Drilling    04/01/98-28/04/98    Ultra Mobile Diamond Drilling
Diamond Drilling    15/06/99-19/07/99    Ultra Mobile Diamond Drilling
Diamond Drilling    08/08/99-01/09/99    Bradley Brothers Diamond Drilling
Airborne EM and Magnetic Survey    15-19 August 2000    Aeroquest Limited
Geochemical Compilation    2000-2001    Franklin Geoscience and Nuinsco Personnel
Magnetotelluric Geophysical Survey    2001-2002    Phoenix Geophysics
Mapping/Prospecting    May 2001 - Sept 2001    Nuinsco Resources
Diamond Drilling    15/11/01 - 18/02/02    Diamond Drilling, Bradley Brothers

 

1

From Mackie et al. 2003


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

APPENDIX D

Analytical Quality Control Data and Relative Precision Charts

(December 2011 – July 2013)

 

 


Time Series Plots for Field Blank and Certified Standard Samples Assayed by ALS Chemex Laboratories during December 2011 to July 2012 – Gold Assays.

LOGO


Time Series Plots for Field Blank and Certified Standard Samples Assayed by ALS Chemex Laboratories during December 2011 to July 2012 – Gold Assays.

LOGO


Time Series Plots for Field Blank and Certified Standard Samples Assayed by ALS Chemex Laboratories during December 2011 to July 2012 – Silver Assays.

LOGO


Bias Charts, Quantile-Quantile and Relative Precision Plots for Field Duplicate Samples Assayed by ALS Chemex Laboratories during December 2011 and July 2012 – Gold Assays.

LOGO


Bias Charts, Quantile-Quantile and Relative Precision Plots for Check Assay Samples (ALS Chemex Laboratories versus Activation Laboratories) – Gold Assays.

LOGO


Time series plots for Field Blank and Standard samples from the Intrepid Zone assayed by ALS Minerals, between December 2011 and June 2013.

LOGO


Time series plots for Field Blank and Standard samples from the Intrepid Zone assayed by ALS Minerals, between December 2011 and June 2013

LOGO


Time series plots for Field Blank and Standard samples from the Intrepid Zone assayed by ALS Minerals, between December 2011 and June 2013

LOGO


Time series plots for Field Blank and Standard samples from the Intrepid Zone assayed by ALS Minerals, between December 2011 and June 2013

LOGO


Bias Charts, Quantile-Quantile and Relative Precision Plots for Field Duplicate Samples From the Intrepid Zone Assayed by ALS Minerals during December 2011 and June 2013.

LOGO


Bias Charts, Quantile-Quantile and Relative Precision Plots for Field Duplicate Samples From the Intrepid Zone Assayed by ALS Minerals during December 2011 and June 2013.

LOGO


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

APPENDIX E

Domain Variograms

 

 


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


LOGO


NI 43-101 Technical Report

Feasibility Study of the Rainy River Project

 

 

APPENDIX F

Rainy River Project Site Plan

 

 


LOGO