XML 30 R19.htm IDEA: XBRL DOCUMENT v3.25.3
Restructuring Charges
9 Months Ended
Sep. 30, 2025
Restructuring Charges.  
Restructuring Charges

12. Restructuring Charges

During the second quarter of 2025, management approved and initiated a plan to exit certain facilities that were no longer deemed economical for our business, and during the three and nine months ended September 30, 2025, we incurred $0.7 million and $0.8 million, respectively of costs to exit these facilities. The facility closure costs incurred under the above restructuring plan were recorded to restructuring charges in our condensed consolidated statements of operations. We expect to incur additional restructuring charges of $1.0 million over the next nine months related to these restructuring activities.

During the first quarter of 2025, management approved and executed a plan to exit a facility no longer deemed economical for our business, and in the first quarter of 2025, we incurred $0.7 million of costs to exit this facility. The severance and property disposal costs incurred under this restructuring plan were recorded to restructuring charges in our condensed consolidated statements of operations. We do not expect to incur additional restructuring charges related to these restructuring activities.

The following table presents the changes to our accrued liability balance related to restructuring charges during the nine months ended September 30, 2025:

(in thousands)

Total

Balance at December 31, 2024

    

$

Charges incurred

 

1,497

Payments

(1,246)

Balance at September 30, 2025

$

251

The following table presents restructuring charges incurred by segment during the three and nine months ended September 30, 2025:

    

Contract

Aftermarket

(in thousands)

Operations

Services

Other(1)

Total

Three months ended September 30, 2025

Facility closure

$

$

$

688

$

688

Total restructuring charges

$

$

$

688

$

688

Nine months ended September 30, 2025

Facility closure

$

520

$

$

977

$

1,497

Total restructuring charges

$

520

$

$

977

$

1,497

(1)Represents expense incurred within our corporate function and not directly attributable to our segments.

The following table presents restructuring charges incurred by cost type:

Three months ended

Nine months ended

(in thousands)

September 30, 2025

    

September 30, 2025

Facility closure

Severance costs

$

$

596

Property disposal and closure costs

688

901

Total restructuring costs

$

688

$