XML 76 R60.htm IDEA: XBRL DOCUMENT v3.22.0.1
Regulatory Matters: Electric Utilities Regulatory Activity (Details)
$ in Thousands
12 Months Ended 24 Months Ended
Oct. 15, 2020
MW
Dec. 31, 2021
USD ($)
Dec. 31, 2021
USD ($)
Black Hills Energy - South Dakota Electric | Federal Energy Regulatory Commission (FERC) Common Use System (CUS)      
Public Utilities, General Disclosures [Line Items]      
Annual Revenue Requirement, as Required by the FERC Joint-Access Transmission Tariff   $ 26,000  
Capital Addition Requirements by the FERC Joint-Access Transmission Tariff     $ 5,000
Black Hills Wyoming and Wyoming Electric | Federal Energy Regulatory Commission (FERC)      
Public Utilities, General Disclosures [Line Items]      
Number of Megawatts Capacity Purchased | MW 60    
Long-term Purchase Commitment, Period 11 years