XML 74 R54.htm IDEA: XBRL DOCUMENT v3.23.1
Commitments and contingencies (Tables)
12 Months Ended
Dec. 31, 2022
Commitments and Contingencies Disclosure [Abstract]  
Schedule of Estimates of Future Commitments
Detailed below are estimates of future commitments under these arrangements: 
Year 1Year 2Year 3Year 4Year 5ThereafterTotal
Power purchase (i)$89,846 $32,490 $32,726 $12,274 $12,520 $142,586 $322,442 
Natural gas supply and service agreements (ii)113,775 81,719 57,014 40,372 31,457 188,138 512,475 
Service agreements67,477 57,886 55,835 49,596 46,511 298,516 575,821 
Capital projects7,163 — — — — — 7,163 
Land easements13,295 13,316 13,503 13,667 13,837 463,785 531,403 
Total$291,556 $185,411 $159,078 $115,909 $104,325 $1,093,025 $1,949,304 
(i)    Power purchase: AQN’s electric distribution facilities have commitments to purchase physical quantities of power for load serving requirements. The commitment amounts included in the table above are based on market prices as of December 31, 2022. However, the effects of purchased power unit cost adjustments are mitigated through a purchased power rate-adjustment mechanism.
(ii)    Natural gas supply and service agreements: AQN’s natural gas distribution facilities and thermal generation facilities have commitments to purchase physical quantities of natural gas under contracts for purposes of load serving requirements and of generating power.