XML 198 R173.htm IDEA: XBRL DOCUMENT v3.24.1.u1
Commitments - Contracts (Detail)
12 Months Ended
Dec. 31, 2023
Cargo contract one [member]  
Summary of contract commitments [line items]  
Port Aratu [1]
Minimum movement in tons per years 900,000
Maturity 2022
Cargo contract two [member]  
Summary of contract commitments [line items]  
Port Suape
Minimum movement in tons per years 250,000
Maturity 2027
Cargo contract three [member]  
Summary of contract commitments [line items]  
Port Suape
Minimum movement in tons per years 400,000
Maturity 2029
Cargo contract four [member]  
Summary of contract commitments [line items]  
Port Aratu
Minimum movement in tons per years 465,403
Maturity 2031
Cargo contract five [member]  
Summary of contract commitments [line items]  
Port Itaqui
Minimum movement in tons per years 1,468,105
Maturity 2049
[1] Contract in the process of being renewed with the appropriate body, being judicialized by favorable decision, until the public entity completes the analysis so that the new amendment is signed. In a decision by the Ministry of Infrastructure, the investment plans presented by Ultracargo were preliminarily approved, and the Waterway Transport Regulatory Agency (ANTAQ) approved the technical, economic and environmental feasibility study of this extension project.