XML 123 R69.htm IDEA: XBRL DOCUMENT v2.4.0.6
Commitments, Guarantees and Contingencies - Transmission (Details) (USD $)
In Millions, unless otherwise specified
Dec. 31, 2012
Dec. 31, 2011
CapX2020 [Member]
   
Transmission [Line Items]    
Number of Projects 3  
Minimum Amount Expected to be Invested in Transmission Projects $ 100  
Maximum Amount Expected to be Invested in Transmission Projects 110  
Capital Cost Spent to Date 48.2 27.8
CapX2020 Fargo to Monticello Project [Member]
   
Transmission [Line Items]    
Transmission Line Length (Miles) 238  
Transmission Line Capacity (kV) 345  
Capital Cost Spent to Date 37.3 20.4
CapX2020 Monticello to St. Cloud Project [Member]
   
Transmission [Line Items]    
Transmission Line Length (Miles) 28  
Transmission Line Capacity (kV) 345  
CapX2020 Bemidji to Grand Rapids Project [Member]
   
Transmission [Line Items]    
Transmission Line Length (Miles) 70  
Transmission Line Capacity (kV) 230  
Capital Cost Spent to Date $ 10.9 $ 7.4