XML 31 R12.htm IDEA: XBRL DOCUMENT v3.8.0.1
Regulatory Matters
12 Months Ended
Dec. 31, 2017
Regulated Operations [Abstract]  
Regulatory Matters [Text Block]
REGULATORY MATTERS

Electric Rates. Entities within our Regulated Operations segment file for periodic rate revisions with the MPUC, PSCW or FERC. As authorized by the MPUC, Minnesota Power also recognizes revenue under cost recovery riders for transmission, renewable and environmental investments and expenditures. (See Transmission Cost Recovery Rider, Renewable Cost Recovery Rider and Environmental Improvement Rider.) Revenue from cost recovery riders was $96.9 million in 2017 ($97.1 million in 2016; $89.6 million in 2015).
NOTE 4. REGULATORY MATTERS (Continued)
Electric Rates (Continued)

2016 Minnesota General Rate Case. In November 2016, Minnesota Power filed a retail rate increase request with the MPUC seeking an average increase of approximately 9 percent for retail customers. The rate filing sought a return on equity of 10.25 percent and a 53.81 percent equity ratio. On an annualized basis, the requested final rate increase would have generated approximately $55 million in additional revenue. In December 2016, Minnesota Power filed a request to modify its original interim rate proposal reducing its requested interim rate increase to $34.7 million from the original request of approximately $49 million due to a change in its electric sales forecast. In December 2016 orders, the MPUC accepted the November 2016 filing as complete and authorized an annual interim rate increase of $34.7 million beginning January 1, 2017.

On February 23, 2017, Minnesota Power filed an additional request to further reduce its requested interim rate increase. In an order dated April 13, 2017, the MPUC approved Minnesota Power’s updated retail rate request resulting in a reduction in the annual interim rate increase to $32.2 million beginning May 1, 2017. As a result of working with intervenors and further developments as the rate review progressed, Minnesota Power’s final rate request was adjusted to approximately $49 million on an annualized basis. At a hearing on January 18, 2018, the MPUC made determinations regarding Minnesota Power’s general rate case including allowing a return on common equity of 9.25 percent and a 53.81 percent equity ratio. Upon commencement of final rates, we expect additional revenue of approximately $13 million on an annualized basis. Final rates are expected to commence in the fourth quarter of 2018; interim rates will be collected through this period which will be fully offset by the recognition of a corresponding reserve. As a result of the MPUC’s decisions on January 18, 2018, Minnesota Power has recorded a reserve for an interim rate refund of approximately $32 million as of December 31, 2017. The MPUC also disallowed recovery of Minnesota Power’s regulatory asset for deferred fuel adjustment clause costs due to the anticipated adoption of a forward-looking fuel adjustment clause methodology resulting in a $19.5 million pre-tax charge to Fuel, Purchased Power and Gas – Utility in 2017. An order from the MPUC setting forth the effective date of final rates is expected by March 12, 2018. Minnesota Power will review this order for potential reconsideration of certain issues at that time.

As part of its decision in Minnesota Power’s 2016 general rate case, the MPUC extended the depreciable lives of Boswell Unit 3, Unit 4 and common facilities to 2050 primarily to mitigate rate increases for our customers, and shortened the depreciable lives of Boswell Unit 1 and Unit 2 to 2022, resulting in a net decrease to depreciation expense of approximately $25 million pre-tax in 2017.

Energy-Intensive Trade-Exposed Customer Rates. An EITE customer ratemaking law was enacted in 2015 which established that it is the energy policy of Minnesota to have competitive rates for certain industries such as mining and forest products. In 2015, Minnesota Power filed a rate schedule petition with the MPUC for EITE customers and a corresponding rider for EITE cost recovery. In a March 2016 order, the MPUC dismissed the petition without prejudice. In June 2016, Minnesota Power filed a revised EITE petition with the MPUC which included additional information on the net benefits analysis, limits on eligible customers and term lengths for the EITE discount. The rate adjustments were intended to be revenue and cash flow neutral to Minnesota Power. The MPUC approved a reduction in rates for EITE customers in a December 2016 order and subsequently approved cost recovery in an order dated April 20, 2017; collection of the discount was subject to the MPUC’s review of Minnesota Power’s compliance filing implementing approval of a recovery mechanism, with the subsequent order issued on October 13, 2017, that modified the order dated April 20, 2017. During 2017, Minnesota Power provided discounts of $8.6 million which were recorded as a receivable. On September 29, 2017, Minnesota Power informed its EITE customers that it has suspended the EITE discount due to a concern that it was not revenue and cash flow neutral to Minnesota Power based on an MPUC decision at a hearing on September 7, 2017, as well as the interim rate reduction and decisions in its 2016 general rate case. Based on the MPUC’s decisions at a hearing on January 18, 2018, as part of Minnesota Power’s 2016 general rate case, Minnesota Power reinstated the EITE discount effective January 1, 2018. Minnesota Power expects the discount to EITE customers to be approximately $15 million annually based on EITE customer current operating levels. While interim rates are in effect for Minnesota Power’s 2016 general rate case, EITE discounts will offset interim rate refund reserves for non-EITE customers.

FERC-Approved Wholesale Rates. Minnesota Power has 16 non-affiliated municipal customers in Minnesota. SWL&P is a Wisconsin utility and a wholesale customer of Minnesota Power. All wholesale contracts include a termination clause requiring a three-year notice to terminate.
NOTE 4. REGULATORY MATTERS (Continued)
Electric Rates (Continued)

Minnesota Power’s wholesale electric contract with the Nashwauk Public Utilities Commission is effective through at least December 31, 2032. No termination notice may be given for this contract prior to July 1, 2029. The wholesale electric service contracts with SWL&P and another municipal customer are effective through at least February 28, 2021, and through June 30, 2019, respectively. Under the agreement with SWL&P, no termination notice has been given. The other municipal customer provided a contract termination notice in June 2016. Minnesota Power currently provides approximately 29 MW of average monthly demand to this customer. The rates included in these three contracts are set each July 1 based on a cost-based formula methodology, using estimated costs and a rate of return that is equal to Minnesota Power’s authorized rate of return for Minnesota retail customers. The formula-based rate methodology also provides for a yearly true-up calculation for actual costs incurred.

Minnesota Power’s wholesale electric contracts with 14 municipal customers are effective through at least December 31, 2024. No termination notices may be given prior to three years before maturity. These contracts include fixed capacity charges through 2018; beginning in 2019, the capacity charge will be determined using a cost-based formula methodology with limits on the annual change from the previous year’s capacity charge. The base energy charge for each year of the contract term will be set each January 1, subject to monthly adjustment, and will also be determined using a cost-based formula methodology.

Transmission Cost Recovery Rider. Minnesota Power has an approved cost recovery rider in place for certain transmission investments and expenditures. In a February 2016 order, the MPUC approved Minnesota Power’s updated customer billing rates which allows Minnesota Power to charge retail customers on a current basis for the costs of constructing certain transmission facilities plus a return on the capital invested. As a result of the MPUC approval of the certificate of need for the GNTL in 2015, the project is eligible for cost recovery under the existing transmission cost recovery rider. Minnesota Power is funding the construction of the GNTL with a subsidiary of Manitoba Hydro (see Great Northern Transmission Line), and anticipates including its portion of the investments and expenditures for the GNTL in future transmission bill factor filings.

Renewable Cost Recovery Rider. Minnesota Power has an approved cost recovery rider in place for investments and expenditures related to Bison, and the restoration and repair of Thomson. The cost recovery rider allows Minnesota Power to charge retail customers on a current basis for the costs of constructing certain renewable investments plus a return on the capital invested. Updated customer billing rates for the renewable cost recovery rider were approved by the MPUC in an order dated November 8, 2017.

In a November 2016 order, the MPUC directed Minnesota Power to attribute all North Dakota investment tax credits realized from Bison to Minnesota Power regulated retail customers. As a result of the adverse regulatory outcome, Minnesota Power recorded a regulatory liability and a reduction in Operating Revenue of approximately $15 million in 2016. The North Dakota investment tax credits previously recognized as income tax credits in Corporate and Other were reversed in 2016 resulting in an $8.8 million charge to net income in 2016. In December 2016, Minnesota Power submitted a request for reconsideration with the MPUC. In an order dated February 14, 2017, the MPUC decided to reconsider its November 2016 order.

In an order dated December 7, 2017, the MPUC modified its November 2016 order to allow Minnesota Power to account for North Dakota investment tax credits based on the long-standing regulatory precedents of stand-alone allocation methodology of accounting for income taxes. As a result of the favorable regulatory outcome, Minnesota Power recorded a reduction in its regulatory liability and an increase in Operating Revenue of approximately $14 million in 2017. The North Dakota investment tax credits were reestablished as income tax credits in Corporate and Other, resulting in a $7.9 million increase to net income in 2017.

The stand-alone method provides that income taxes (and credits) are calculated as if Minnesota Power was the only entity included in ALLETE’s consolidated federal and unitary state income tax returns. Minnesota Power has recorded a regulatory liability for North Dakota investment tax credits generated by its jurisdictional activity and expected to be realized in the future. North Dakota investment tax credits attributable to ALLETE’s apportionment and income of ALLETE’s other subsidiaries are included in Corporate and Other operations.

Minnesota Power also has approval for current cost recovery of investments and expenditures related to compliance with the Minnesota Solar Energy Standard. (See Minnesota Solar Energy Standard.) Currently, there is no approved customer billing rate for solar costs.
NOTE 4. REGULATORY MATTERS (Continued)
Electric Rates (Continued)

Environmental Improvement Rider. Minnesota Power has an approved environmental improvement rider in place for investments and expenditures related to the implementation of the Boswell Unit 4 mercury emissions reduction plan completed in 2015. Updated customer billing rates for the environmental improvement rider were approved by the MPUC in a December 2016 order; however, in an order dated March 22, 2017, the MPUC approved a request by Minnesota Power to delay implementation of the updated rates until resolution of its 2016 general rate case. (See 2016 Minnesota General Rate Case.)

Fuel Adjustment Clause Reform Pilot. In an order dated December 19, 2017, the MPUC adopted a three-year pilot program to implement certain procedural reforms to the Minnesota utilities’ automatic fuel adjustment clause (FAC) for fuel and purchased power. The order changes the method of accounting for all Minnesota electric utilities to a monthly budgeted, forwarded-looking FAC with an annual prudence review and true-up to actual allowed costs. The MPUC is seeking input from Minnesota electric utilities and other stakeholders on the implementation and transition accounting needed to adopt the change. The three-year pilot program is expected to begin in 2019. At a hearing on January 18, 2018, the MPUC disallowed recovery of Minnesota Power’s regulatory asset for deferred fuel adjustment clause costs due to the anticipated adoption of the forward-looking fuel adjustment clause methodology in this proceeding resulting in a $19.5 million pre-tax charge to Fuel, Purchased Power and Gas – Utility in 2017.

Tax Cuts and Jobs Act of 2017. On December 29, 2017, the MPUC opened a docket to review the effects of the TCJA on electric and natural gas rates and services in Minnesota, including the legislation’s impact on tax rates and utilities’ deferred income tax assets and liabilities. On January 19, 2018, the MPUC issued a notice of request for information and established comment periods with an initial filing required by March 2, 2018. On January 10, 2018, the PSCW also opened a docket to review the effects of this legislation and directed Wisconsin utilities to defer its impacts until further direction is provided by the PSCW. We have recorded the impact of the remeasurement of deferred income tax assets and liabilities resulting from the federal income tax rate change of the TCJA for Minnesota Power and SWL&P as regulatory assets and liabilities as the benefits of the TCJA are expected to be passed back to our customers over time. (See Regulatory Assets and Liabilities.) The final amount and timing over which the benefits of the TCJA will be passed back to customers is expected to be determined in these dockets; however, we are unable to predict the outcome of these regulatory proceedings.

2016 Wisconsin General Rate Case. SWL&P’s current retail rates are based on a 2017 PSCW retail rate order effective August 14, 2017, that allows for a 10.5 percent return on common equity and a 55 percent equity ratio. SWL&P’s retail rates prior to August 14, 2017, were based on a 2012 PSCW retail rate order that provided for a 10.9 percent return on equity. The 2017 PSCW retail rate order authorizes SWL&P to collect on average a 2.9 percent increase in rates for retail customers (3.8 percent increase in electric rates; 4.8 percent decrease in natural gas rates; and 9.8 percent increase in water rates). On an annualized basis, SWL&P expects to collect additional revenue of $2.5 million.

Integrated Resource Plan. In 2015, Minnesota Power filed its 2015 IRP with the MPUC which included an analysis of a variety of existing and future energy resource alternatives and a projection of customer cost impact by class. The 2015 IRP also contained steps in Minnesota Power’s EnergyForward strategic plan including the economic idling of Taconite Harbor Units 1 and 2 which occurred in September 2016, the ceasing of coal-fired operations at Taconite Harbor in 2020, and the addition of between 200 MW and 300 MW of natural gas-fired generation in the next decade. In a July 2016 order, the MPUC approved Minnesota Power’s 2015 IRP with modifications. The order accepted Minnesota Power’s plans for Taconite Harbor, directed Minnesota Power to retire Boswell Units 1 and 2 no later than 2022, required an analysis of generation and demand response alternatives to be filed with a natural gas resource proposal, and required Minnesota Power to conduct request for proposals for additional wind, solar and demand response resource additions subject to further MPUC approvals. In October 2016, Minnesota Power announced Boswell Units 1 and 2 will be retired in 2018.

On July 28, 2017, Minnesota Power submitted a resource package to the MPUC requesting approval of PPAs for the output of a 250 MW wind energy facility and a 10 MW solar energy facility as well as approval of a 250 MW natural gas energy PPA. These agreements will be subject to MPUC approval of the construction of a 525 MW to 550 MW combined-cycle natural gas-fired generating facility which will be jointly owned by Dairyland Power Cooperative and a subsidiary of ALLETE. Minnesota Power would purchase approximately 50 percent of the facility's output starting in 2025. In an order dated September 19, 2017, the MPUC approved Minnesota Power’s request to extend the next IRP filing deadline until October 1, 2019, and Minnesota Power’s request that approval for the natural gas energy PPA be decided through an administrative law judge process. The administrative law judge is expected to provide a recommendation by July 2018, and the Company anticipates a MPUC decision in the second half of 2018. The MPUC did not take any action regarding the wind and solar energy PPAs which will be refiled separately from the natural gas energy PPA.
NOTE 4. REGULATORY MATTERS (Continued)

Great Northern Transmission Line. Minnesota Power and Manitoba Hydro have proposed construction of the GNTL, an approximately 220-mile 500-kV transmission line between Manitoba and Minnesota’s Iron Range. In 2015, a certificate of need was approved by the MPUC. Based on this approval, Minnesota Power’s portion of the investments and expenditures for the project are eligible for cost recovery under its existing transmission cost recovery rider and are anticipated to be included in future transmission cost recovery filings. (See Transmission Cost Recovery Rider.) Also in 2015, the FERC approved our request to recover on construction work in progress related to the GNTL from Minnesota Power’s wholesale customers. In an April 2016 order, the MPUC approved the route permit for the GNTL which largely follows Minnesota Power’s preferred route, including the international border crossing, and in November 2016, the U.S. Department of Energy issued a presidential permit to cross the U.S.-Canadian border, which was the final major regulatory approval needed before construction in the U.S. could begin. Site clearing and pre-construction activities commenced in the first quarter of 2017 with construction expected to be completed in 2020. Total project cost in the U.S., including substation work, is estimated to be between $560 million and $710 million, of which Minnesota Power’s portion is expected to be between $300 million and $350 million; the difference will be recovered from a subsidiary of Manitoba Hydro as contributions in aid of construction. Total project costs of $152.4 million have been incurred through December 31, 2017, of which $67.6 million has been recovered from a subsidiary of Manitoba Hydro.

Manitoba Hydro must obtain regulatory and governmental approvals related to a new transmission line in Canada. In 2015, Manitoba Hydro submitted the final preferred route and EIS for the transmission line in Canada to the Manitoba Conservation and Water Stewardship for regulatory approval. In December 2016, Manitoba Hydro filed an application with the National Energy Board in Canada requesting authorization to construct and operate an international transmission line. Both provincial and federal approvals are pending. Construction of Manitoba Hydro’s hydroelectric generation facility commenced in 2014 and is anticipated to be in service by early 2021.

Conservation Improvement Program. Minnesota requires electric utilities to spend a minimum of 1.5 percent of gross operating revenues from service provided in the state on energy CIPs each year and establish an annual energy-savings goal of 1.5 percent of annual retail energy sales. These investments are recovered from certain retail customers through a combination of the conservation cost recovery charge included in retail base rates and a conservation program adjustment, which is adjusted annually through the CIP consolidated filing. The MPUC allows utilities to accumulate, in a deferred account for future cost recovery, all CIP expenditures, any financial incentive earned for cost-effective program achievements and a carrying charge on the deferred account balance. Minnesota Power refers to its conservation programs collectively as the “Power of One”. On November 16, 2017, the Minnesota Department of Commerce approved Minnesota Power’s modified CIP triennial filing for 2017 through 2019, which outlines Minnesota Power’s CIP spending and energy-saving goals for 2017 through 2019. Minnesota Power’s CIP investment goal was $10.3 million for 2017 ($7.3 million for 2016; $7.1 million for 2015), with actual spending of $8.1 million in 2017 ($7.4 million in 2016; $6.6 million in 2015). The investment goals for 2018 and 2019 are $10.3 million and $10.5 million, respectively.

On April 3, 2017, Minnesota Power submitted its 2016 CIP consolidated filing, which detailed Minnesota Power’s CIP program results and requested a CIP financial incentive of $5.5 million based upon MPUC procedures. In an order dated June 22, 2017, the MPUC approved Minnesota Power’s CIP consolidated filing, including the requested CIP financial incentive which was recorded as revenue and as a regulatory asset in 2017. The approved financial incentive will be recovered through customer billing rates in 2017 and 2018. In 2016 and 2015, the CIP financial incentives recognized were $7.5 million and $6.2 million, respectively. CIP financial incentives are recognized in the period in which the MPUC approves the filing.

MISO Return on Equity Complaints. In 2013, several customer groups located within the MISO service area filed complaints with the FERC requesting, among other things, a reduction in the base return on equity used by MISO transmission owners, including ALLETE and ATC, to 9.15 percent. In 2015, a federal administrative law judge ruled on the complaint proposing a reduction in the base return on equity to 10.32 percent, or 10.82 percent including an incentive adder for participation in a regional transmission organization. In September 2016, the FERC issued an order affirming the administrative law judge’s recommendation.

In 2015, an additional complaint was filed with the FERC seeking an order to further reduce the base return on equity to 8.67 percent. In June 2016, a federal administrative law judge ruled on the additional complaint proposing a further reduction in the base return on equity to 9.70 percent, or 10.20 percent including an incentive adder for participation in a regional transmission organization, subject to approval or adjustment by the FERC. A final decision from the FERC on the administrative law judge’s recommendation is pending, which is not expected to have a material impact on our Consolidated Financial Statements.
NOTE 4. REGULATORY MATTERS (Continued)

Minnesota Solar Energy Standard. Minnesota law requires at least 1.5 percent of total retail electric sales, excluding sales to certain customers, to be generated by solar energy by the end of 2020. At least 10 percent of the 1.5 percent mandate must be met by solar energy generated by or procured from solar photovoltaic devices with a nameplate capacity of 40kW or less and community solar garden subscriptions. In a 2016 order, the MPUC approved Camp Ripley, a 10 MW utility scale solar project at the Camp Ripley Minnesota Army National Guard base and training facility near Little Falls, Minnesota, as eligible to meet the solar energy standard and for current cost recovery. Camp Ripley was completed in the fourth quarter of 2016. In a July 2016 order, the MPUC approved a community solar garden project in northeastern Minnesota, which is comprised of a 1 MW solar array owned and operated by a third party with the output purchased by Minnesota Power and a 40 kW solar array that is owned and operated by Minnesota Power. Minnesota Power believes Camp Ripley and the community solar garden arrays will meet approximately one‑third of the overall mandate. Additionally, in an order dated February 10, 2017, the MPUC approved Minnesota Power’s proposal to increase the amount of solar rebates available for customer-sited solar installations and recover costs of the program through Minnesota Power’s renewable cost recovery rider. The proposal to incentivize customer‑sited solar installations and the community solar garden subscriptions is expected to meet a portion of the required small scale solar mandate.

Regulatory Assets and Liabilities. Our regulated utility operations are subject to accounting guidance for the effect of certain types of regulation. Regulatory assets represent incurred costs that have been deferred as they are probable for recovery in customer rates. Regulatory liabilities represent obligations to make refunds to customers and amounts collected in rates for which the related costs have not yet been incurred. The Company assesses quarterly whether regulatory assets and liabilities meet the criteria for probability of future recovery or deferral. No regulatory assets or liabilities are currently earning a return. The recovery, refund or credit to rates for these regulatory assets and liabilities will occur over the periods either specified by the applicable regulatory authority or over the corresponding period related to the asset or liability.
NOTE 4. REGULATORY MATTERS (Continued)
Regulatory Assets and Liabilities
 
 
As of December 31
2017

2016

Millions
 
 
Current Regulatory Assets (a)
 
 
Deferred Fuel Adjustment Clause


$18.6

Non-Current Regulatory Assets
 
 
Defined Benefit Pension and Other Postretirement Benefit Plans (b)
$220.3
226.1

Income Taxes (c)(d)
112.8

33.8

Asset Retirement Obligations (e)
29.6

26.0

Manufactured Gas Plant (f)
8.1

1.0

PPACA Income Tax Deferral
5.0

5.0

Conservation Improvement Program (g)
3.3

4.0

Cost Recovery Riders (h)

30.5

Other
5.6

3.7

Total Non-Current Regulatory Assets
384.7

330.1

Total Regulatory Assets

$384.7


$348.7

Non-Current Regulatory Liabilities
 
 
Income Taxes (d)

$411.2


$19.1

Wholesale and Retail Contra AFUDC (i)
57.9

56.8

Provision for Interim Rate Refund (j)
23.7


Plant Removal Obligations
20.3

19.1

North Dakota Investment Tax Credits (k)
14.1

28.2

Cost Recovery Riders (h)
2.2


Other
2.6

2.6

Total Non-Current Regulatory Liabilities

$532.0


$125.8

(a)
Current regulatory assets are presented within Prepayments and Other on the Consolidated Balance Sheet. At a hearing on January 18, 2018, the MPUC disallowed recovery of Minnesota Power’s regulatory asset for deferred fuel adjustment clause costs resulting in a $19.5 million pre-tax charge to Fuel, Purchased Power and Gas – Utility in 2017. (See 2016 Minnesota General Rate Case.)
(b)
Defined benefit pension and other postretirement items included in our Regulated Operations, which are otherwise required to be recognized in accumulated other comprehensive income as actuarial gains and losses as well as prior service costs and credits, are recognized as regulatory assets or regulatory liabilities on the Consolidated Balance Sheet. The asset or liability will decrease as the deferred items are amortized and recognized as components of net periodic benefit cost. (See Note 15. Pension and Other Postretirement Benefit Plans.)
(c)
See Note 1. Operations and Significant Accounting Policies – Revision of Prior Balance Sheet.
(d)
These costs represent the difference between deferred income taxes recognized for financial reporting purposes and amounts previously billed to our customers. The increase in 2017 is primarily due to the remeasurement of deferred income tax assets and liabilities for our Regulated Operations resulting from the TCJA. The benefits of the TCJA for Minnesota Power and SWL&P are expected to be passed back to customers over time primarily based upon the normalization provisions of the U.S. Internal Revenue Code over the life of the related property, plant and equipment with the remainder passed back based upon the determinations of regulatory authorities. (See Note 1. Operations and Significant Accounting Policies, and Tax Cuts and Jobs Act of 2017.) The balances not related to remeasurement will decrease over the remaining life of the related temporary differences and flow through current income taxes.
(e)
Asset retirement obligations will accrete and be amortized over the lives of the related property with asset retirement obligations.
(f)
The manufactured gas plant regulatory asset represents costs of remediation for a former manufactured gas plant site located in Superior, Wisconsin, and formerly operated by SWL&P. We expect recovery of these remediation costs to be allowed by the PSCW in rates over time.
(g)
The conservation improvement program regulatory asset represents CIP expenditures, any financial incentive earned for cost-effective program achievements and a carrying charge deferred for future cost recovery over the next year following MPUC approval.
(h)
The cost recovery rider regulatory assets and liabilities are revenues not yet collected from our customers and cash collections from our customers in excess of the revenue recognized, respectively, primarily due to capital expenditures related to Bison, investment in CapX2020 projects, the Boswell Unit 4 environmental upgrade and the GNTL, and are recognized in accordance with the accounting standards for alternative revenue programs. The cost recovery rider regulatory assets and liabilities as of December 31, 2017, will be recovered or returned within the next two years.
(i)
Wholesale and Retail Contra AFUDC represents amortization to offset AFUDC Equity and Debt recorded during the construction period of our cost recovery rider projects prior to placing the projects in service. The regulatory liability will decrease over the remaining depreciable life of the related asset.
(j)
This amount is expected to be refunded to Minnesota Power’s regulated retail customers in the first quarter of 2019 and includes $8.6 million of EITE discounts that will be offset against interim rate refunds. (See 2016 Minnesota General Rate Case and Energy-Intensive Trade‑Exposed Customer Rates.)
(k)
North Dakota investment tax credits expected to be realized from Bison that will be credited to Minnesota Power’s regulated retail customers through future renewable cost recovery rider fillings as the tax credits are utilized.