Commitments And Contingencies
12 Months Ended
Dec. 31, 2019
Commitments and Contingencies Disclosure [Abstract]  
Commitments And Contingencies COMMITMENTS AND CONTINGENCIES

Capital Commitments

The following table summarizes the estimated timing of our remaining contractual payments of our rigs under construction as of December 31, 2019 for our rigs under construction and (in millions): 
 
 
2020
 
2021
 
2022
 
Thereafter
 
Total(1)
VALARIS DS-13(2)
 
$

 
$
83.9

 
$

 
$

 
$
83.9

VALARIS DS-14(2)
 

 

 
165.0

 

 
165.0

 
 
$


$
83.9


$
165.0

 
$

 
$
248.9



(1) 
Total commitments are based on fixed-price shipyard construction contracts, exclusive of costs associated with project management, commissioning and systems integration testing. Total commitments also exclude holding costs and interest.

Based on our current projections, excluding integration-related capital expenditures, we expect capital expenditures during 2020 to approximate $160 million for newbuild construction, rig enhancement projects and minor upgrades and improvements. Approximately $30 million of our projected capital expenditures is reimbursable by our customers. Depending on market conditions and opportunities, we may reduce our planned expenditures or make additional capital expenditures to upgrade rigs for customer requirements or acquire additional rigs.

(2) 
During the third quarter of 2019, we entered into amendments to our construction agreements with the shipyard for VALARIS DS-13 and VALARIS DS-14 to provide for, among other things, two-year extensions of the delivery date of each rig in exchange for payment of all accrued holding costs through March 31, 2019, totaling approximately $23 million. The new delivery dates for the VALARIS DS-13 and VALARIS DS-14 are September 30, 2021 and June 30, 2022, respectively. We can elect to request earlier delivery in certain circumstances. The interest rate on the final milestone payments increased from 5% to 7% per annum from October 1, 2019, for the VALARIS DS-13, and from July 1, 2020, for the VALARIS DS-14, until the actual delivery dates. The final milestone payments and interest are due at the new delivery dates (or, if accelerated, the actual delivery dates) and are estimated to be approximately $313.3 million in aggregate for both rigs, inclusive of interest, assuming we take delivery on the new delivery dates. In lieu of making the final milestone payments, we have the option to take delivery of the rigs and issue a promissory note for each rig to the shipyard owner for the amount due. If we issue the promissory note to the shipyard owner, we would also be required to provide a guarantee from Valaris plc.

Upon delivery, the remaining milestone payments and accrued interest thereon may be financed through a promissory note with the shipyard for each rig. The promissory notes will bear interest at a rate of 9% per annum with a maturity date of December 30, 2022 and will be secured by a mortgage on each respective rig. The remaining milestone payments for VALARIS DS-13 and VALARIS DS-14 are included in the table above in the period in which we expect to take delivery of the rig. However, we may elect to execute the promissory notes and defer payment until December 2022.

DSA Dispute

On January 4, 2016, Petrobras sent a notice to us declaring the drilling services agreement with Petrobras (the "DSA") for VALARIS DS-5, a drillship ordered from Samsung Heavy Industries, a shipyard in South Korea ("SHI"), void effective immediately, reserving its rights and stating its intention to seek any restitution to which it may be entitled. The previously disclosed arbitral hearing on liability related to the matter was held in March 2018. Prior to the arbitration tribunal issuing its decision, we and Petrobras agreed in August 2018 to a settlement of all claims relating to the DSA. No payments were made by either party in connection with the settlement agreement. The parties agreed
to normalize business relations and the settlement agreement provides for our participation in current and future Petrobras tenders on the same basis as all other companies invited to these tenders. No losses were recognized during 2018 with respect to this settlement as all disputed receivables with Petrobras related to the DSA were fully reserved in 2015.

In April 2016, we initiated separate arbitration proceedings in the U.K. against SHI for the losses incurred in connection with the foregoing Petrobras arbitration and certain other losses relating to the DSA. In January 2018, the arbitration tribunal for the SHI matter issued an award on liability fully in our favor. The January 2018 arbitration award provides that SHI is liable to us for $10 million or damages that we can prove. We submitted our claim for damages to the tribunal, and the arbitral hearing on damages owed to us by SHI took place during the first quarter of 2019.

In May 2019, the arbitration tribunal for the SHI matter awarded us $180.0 million in damages. Further, we are entitled to claim interest on this award and costs incurred in connection with this matter. In June 2019, we and SHI filed separate applications with the English High Court to seek leave to appeal the damages awarded.

In December 2019, the English High Court denied the parties’ applications for leave to appeal the tribunal’s $180.0 million damages award. Following this decision, the parties reached an agreement and SHI paid us $200.0 million in cash. Collection of this payment resulted in the recognition of a gain of the same amount, which is included in other, net, in our consolidated statement of operations for the year ended December 31, 2019. This payment, along with the previously disclosed settlement and normalization of our business relationship with Petrobras, concludes our dispute surrounding VALARIS DS-5.

Indonesian Well-Control Event

In July 2019, a well being drilled offshore Indonesia by one of our jackup rigs experienced a well-control event requiring the cessation of drilling activities. The operator could seek to terminate the contract under certain circumstances. If this drilling contract were to be terminated for cause, it would result in an approximate $8.5 million decrease in our backlog as of December 31, 2019.

Indonesian authorities have initiated a preliminary investigation into the event and have contacted the customer, us and other parties involved in drilling the well for additional information. We are cooperating with the Indonesian authorities. We cannot predict the scope or ultimate outcome of this preliminary investigation or whether the Indonesian authorities will open a full investigation into our involvement in this matter. If the Indonesian authorities determine that we violated local laws in connection with this matter, we could be subject to penalties including environmental or other liabilities, which may have a material adverse impact on us.

Middle East Dispute

On July 30, 2019, we received notice that a local partner of legacy Ensco plc in the Middle East filed a lawsuit in the U.K. against the Company alleging it induced the breach of a non-compete provision in an agreement between the local partner and a subsidiary of the Company.  The lawsuit included a claim for an unspecified amount of damages in excess of £100 million and other relief.  The Company expects to reach an agreement to settle this matter and to acquire the local partner's interest in the subsidiary for an aggregate amount of $27.5 million. Of this amount, we concluded that $20.3 million was attributable to the settlement of the dispute and was recognized as a loss included in other, net, in our consolidated statement of operations for the year ended December 31, 2019. The remaining amount is attributable to the acquisition of the local partner's interest in the subsidiary and will be recorded to equity in 2020.

ARO Funding Obligations

Valaris and Saudi Aramco have agreed to take all steps necessary to ensure that ARO purchases at least 20 newbuild jackup rigs ratably over an approximate 10-year period. In January 2020, ARO ordered the first two newbuild jackups for delivery scheduled in 2022. The partners intend for the newbuild jackup rigs to be financed out of available
cash from ARO's operations and/or funds available from third-party debt financing. In the event ARO has insufficient cash from operations or is unable to obtain third-party financing, each partner may periodically be required to make additional capital contributions to ARO, up to a maximum aggregate contribution of $1.25 billion from each partner to fund the newbuild program. Each partner's commitment shall be reduced by the actual cost of each newbuild rig, on a proportionate basis. The partners agreed that Saudi Aramco, as a customer, will provide drilling contracts to ARO in connection with the acquisition of the newbuild rigs. The initial contracts for each newbuild rig will be determined using a pricing mechanism that targets a six-year payback period for construction costs on an EBITDA basis. The initial eight-year contracts will be followed by a minimum of another eight years of term, re-priced in three-year intervals based on a market pricing mechanism.

  Other Matters

In addition to the foregoing, we are named defendants or parties in certain other lawsuits, claims or proceedings incidental to our business and are involved from time to time as parties to governmental investigations or proceedings, including matters related to taxation, arising in the ordinary course of business. Although the outcome of such lawsuits or other proceedings cannot be predicted with certainty and the amount of any liability that could arise with respect to such lawsuits or other proceedings cannot be predicted accurately, we do not expect these matters to have a material adverse effect on our financial position, operating results and cash flows.

In the ordinary course of business with customers and others, we have entered into letters of credit to guarantee our performance as it relates to our drilling contracts, contract bidding, customs duties, tax appeals and other obligations in various jurisdictions. Letters of credit outstanding as of December 31, 2019 totaled $99.5 million and are issued under facilities provided by various banks and other financial institutions. Obligations under these letters of credit and surety bonds are not normally called, as we typically comply with the underlying performance requirement. As of December 31, 2019, we had not been required to make collateral deposits with respect to these agreements.