Commitments and Contingencies Disclosure [Abstract]  
Commitments And Contingencies COMMITMENTS AND CONTINGENCIES
Capital Commitments

The following table summarizes the timing of our remaining current contractual commitments for VALARIS DS-13 and VALARIS DS-14, which were under construction as of December 31, 2020 (in millions): 
20212022Thereafter
Total(1)
VALARIS DS-13$83.9 $— $— $83.9 
VALARIS DS-14— 165.0 — 165.0 
$83.9 $165.0 $— $248.9 

(1)    Total commitments are based on fixed-price shipyard construction contracts, exclusive of our internal costs associated with project management, commissioning and systems integration testing. Total commitments also exclude holding costs and interest.

As of December 31, 2020, the contractual delivery dates for the VALARIS DS-13 and VALARIS DS-14 were September 30, 2021 and June 30, 2022, respectively. The remaining milestone payments for VALARIS DS-13 and VALARIS DS-14 are included in the table above in the period in which they were contractually owed.

The Amended RSA provides that on or before the effective date of the reorganization, the construction contracts for these rigs shall be rejected under Section 365 of the Bankruptcy Code, unless otherwise agreed between the shipyard and the Company with the consent of required Consenting Noteholders. If rejected, it is contemplated that we would have to pay an amount equal to the liquidation recovery, which is the amount the contract counterparty would be entitled to receive or retain if the applicable Company entity was liquidated under chapter 7 of the Bankruptcy Code. Prior to December 31, 2020, a Stipulation was filed with the Bankruptcy Court which included an Assumption Term Sheet stating amended terms of these construction agreements.

Following further negotiations, we entered into amended agreements with the shipyard on February 26, 2021 that become effective upon our emergence from bankruptcy. The amendments provide for, among other things, an option construct whereby the Company has the right, but not the obligation, to take delivery of either or both rigs on or before December 31, 2023. Under the amended agreements, the purchase price for the rigs are estimated to be approximately $119.1 million for the VALARIS DS-13 and $218.3 million for the VALARIS DS-14, assuming a December 31, 2023 delivery date. Delivery can be requested any time prior to December 31, 2023 with a downward purchase price adjustment based on predetermined terms. If the Company elects not to purchase the rigs, the Company has no further obligations to the shipyard. The amended agreements remove any Company guarantee.

Angola Non-Drilling Event

In March 2020, VALARIS DS-8 experienced a non-drilling incident while operating offshore Angola, resulting in the blowout preventer (BOP) stack being disconnected from the riser while the rig was moving between well locations. The BOP stack, which we later recovered, dropped to the seabed floor, clear of any subsea
structures. No injuries, environmental pollution or third-party damage resulted from the BOP stack being disconnected.

As a result of the incident, the operator terminated the contract. The termination resulted in a decline in our contracted revenue backlog of approximately $150 million. We carried loss of hire insurance covering $602,500 per day, after a 45-day deductible waiting period, through the end of the contract in November 2020. The waiting period expired on April 22, 2020. We received loss of hire insurance recoveries of $118.1 million, which represents the total amount owed to us under the applicable insurance policy. The recovery was recognized and recorded in Other Operating Income on our Consolidated Statements of Operations in the year ended December 31, 2020.

Indonesian Well-Control Event

In July 2019, a well being drilled offshore Indonesia by one of our jackup rigs experienced a well-control event requiring the cessation of drilling activities. In February 2020, the rig resumed operations. Indonesian authorities initiated an investigation into the event and have contacted the customer, us and other parties involved in drilling the well for additional information. We are cooperating with the Indonesian authorities. We cannot predict the scope or ultimate outcome of this investigation. If the Indonesian authorities determine that we violated local laws in connection with this matter, we could be subject to penalties including environmental or other liabilities, which may have a material adverse impact on us.

Middle East Dispute

On July 30, 2019, we received notice that a local partner of legacy Ensco plc in the Middle East filed a lawsuit in the U.K. against the Company alleging it induced the breach of a non-compete provision in an agreement between the local partner and a subsidiary of the Company.  The lawsuit included a claim for an unspecified amount of damages in excess of £100 million and other relief.  We reached an agreement to settle this matter and to acquire the local partner's interest in the subsidiary for an aggregate amount of $27.5 million, which was paid in April 2020. Of this amount, we concluded that $20.3 million was attributable to the settlement of the dispute and was recognized as a loss included in other, net, in our consolidated statement of operations for the year ended December 31, 2019. The remaining amount is attributable to the acquisition of the local partner's interest in the subsidiary and was recognized in 2020 as an adjustment to Additional paid-in-capital and is included on our Consolidated Balance Sheet as of December 31, 2020.

ARO Funding Obligations

Valaris and Saudi Aramco have agreed to take all steps necessary to ensure that ARO purchases 20 newbuild jackup rigs ratably over an approximate 10-year period. In January 2020, ARO ordered the first two newbuild jackups for delivery scheduled in 2022. The partners intend for the newbuild jackup rigs to be financed out of available cash from ARO's operations and/or funds available from third-party debt financing. ARO paid a 25% down payment from cash on hand for each of the newbuilds ordered in January 2020. In the event ARO has insufficient cash from operations or is unable to obtain third-party financing, each partner may periodically be required to make additional capital contributions to ARO, up to a maximum aggregate contribution of $1.25 billion from each partner to fund the newbuild program. The Company's capital contributions to ARO pursuant to this requirement may require approval of the Bankruptcy Court during the Chapter 11 Cases. Each partner's commitment shall be reduced by the actual cost of each newbuild rig, on a proportionate basis. The partners agreed that Saudi Aramco, as a customer, will provide drilling contracts to ARO in connection with the acquisition of the newbuild rigs. The initial contracts for each newbuild rig will be determined using a pricing mechanism that targets a six-year payback period for construction costs on an EBITDA basis. The initial eight-year contracts will be followed by a minimum of another eight years of term, re-priced in three-year intervals based on a market pricing mechanism.
  Other Matters

In addition to the foregoing, we are named defendants or parties in certain other lawsuits, claims or proceedings incidental to our business and are involved from time to time as parties to governmental investigations or proceedings, including matters related to taxation, arising in the ordinary course of business. Although the outcome of such lawsuits or other proceedings cannot be predicted with certainty and the amount of any liability that could arise with respect to such lawsuits or other proceedings cannot be predicted accurately, we do not expect these matters to have a material adverse effect on our financial position, operating results and cash flows.

In the ordinary course of business with customers and others, we have entered into letters of credit to guarantee our performance as it relates to our drilling contracts, contract bidding, customs duties, tax appeals and other obligations in various jurisdictions. Letters of credit outstanding as of December 31, 2020 totaled $115.1 million and are issued under facilities provided by various banks and other financial institutions. Obligations under these letters of credit are not normally called, as we typically comply with the underlying performance requirement. As of December 31, 2020, we had insignificant collateral deposits with respect to these agreements.