XML 104 R78.htm IDEA: XBRL DOCUMENT v3.19.3.a.u2
Note 9 - Commitments and Contingencies - Amounts of Commitments (Details)
$ in Thousands
Dec. 31, 2019
USD ($)
Otter Tail Power Company [Member]  
2020, Land Easement Payments $ 630
2021, Land Easement Payments 642
2022, Land Easement Payments 655
2023, Land Easement Payments 668
2024, Land Easement Payments 682
Beyond 2024, Land Easement Payments 6,931
Total, Land Easement Payments 10,208
Construction Program and Other Commitments [Member] | Subsidiaries [Member]  
2020, Commitments Other than Operating Leases 269,774
2021, Commitments Other than Operating Leases 47,230
2022, Commitments Other than Operating Leases 22
2023, Commitments Other than Operating Leases 11
2024, Commitments Other than Operating Leases 6
Beyond 2024, Commitments Other than Operating Leases 0
Total, Commitments Other than Operating Leases 317,043
Capacity and Energy Requirements [Member] | Otter Tail Power Company [Member]  
2020, Commitments Other than Operating Leases 24,844
2021, Commitments Other than Operating Leases 12,988
2022, Commitments Other than Operating Leases 11,827
2023, Commitments Other than Operating Leases 11,827
2024, Commitments Other than Operating Leases 11,801
Beyond 2024, Commitments Other than Operating Leases 131,913
Total, Commitments Other than Operating Leases 205,200
Coal Purchase Commitments [Member] | Otter Tail Power Company [Member]  
2020, Commitments Other than Operating Leases 22,644
2021, Commitments Other than Operating Leases 22,935
2022, Commitments Other than Operating Leases 22,793
2023, Commitments Other than Operating Leases 23,955
2024, Commitments Other than Operating Leases 24,369
Beyond 2024, Commitments Other than Operating Leases 479,123
Total, Commitments Other than Operating Leases $ 595,819