XML 56 R23.htm IDEA: XBRL DOCUMENT v3.24.0.1
Commitments and Contingencies
12 Months Ended
Dec. 31, 2023
Commitments and Contingencies Disclosure [Abstract]  
Commitments and Contingencies Commitments and Contingencies
Commitments
Construction and Other Commitments. As of December 31, 2023, we had commitments under contracts for construction project materials, equipment, plant maintenance, and other services extending into 2046 which totaled approximately $17.1 million.
Electric Utility Capacity and Energy Requirements. OTP has commitments for the purchase of capacity and energy requirements under contractual agreements, including wind power purchase agreements extending into 2048. Generally, the terms of OTP's wind power purchase agreements require OTP to purchase all of the electricity generated by a particular wind farm and do not include fixed or minimum payments. The required payments are variable and the amounts due are determined based upon the amount of electricity generated. Capacity and energy requirement costs under these agreements totaled $5.6 million, $13.1 million and $11.5 million for the years ended December 31, 2023, 2022 and 2021.
Coal Purchase Commitments. OTP has contracts providing for the purchase and delivery of its coal requirements. OTP’s current coal purchase agreement with CCMC for Coyote Station expires December 31, 2040. All of Coyote Station’s coal requirements for the period covered must be purchased under this agreement. The agreement is structured so that the price of the coal covers all of CCMC's operating, financing, and future
mine reclamation costs. In the table below we have estimated the future payments to be made under the terms of the agreement until its maturity. OTP has an agreement for the purchase of Big Stone Plant’s coal requirements through December 31, 2024. There is no fixed minimum purchase requirement, and no amounts for this agreement have been included in the table below; however, under this agreement all of Big Stone Plant’s coal requirements for the period covered must be purchased under this agreement. Coal purchase costs under these two agreements totaled $43.7 million, $45.1 million and $40.4 million for the years ended December 31, 2023, 2022 and 2021.
Land Easement Payments. OTP has commitments to make payments for land easements not classified as leases. The contractual terms of these easements are generally 99 years or do not have a stated maturity date, however, per the terms of the agreements, our requirement to make payment ends once we cease use of the land. As such, in the table below, we have included payments under these easements through the estimated useful lives of the facilities associated with the easement. The commitments under these arrangements extend into 2055 and total approximately $62.4 million. Land easement costs under these agreements totaled $1.8 million, $1.4 million and $1.3 million for the years ended December 31, 2023, 2022 and 2021.
Our future commitments as of December 31, 2023 were as follows:
(in thousands)Construction Program
and Other Commitments
Capacity and Energy
Requirements
Coal Purchase
Commitments
Land
 Easement
Payments
2024$4,374 $245 $24,691 $1,804 
20254,051 217 24,593 1,840 
20261,377 197 25,374 1,845 
2027594 197 25,786 1,882 
2028550 197 25,344 1,921 
Beyond 20286,165 3,939 359,610 53,107 
Total$17,111 $4,992 $485,398 $62,399 
Contingencies
FERC ROE. In November 2013 and February 2015, customers filed complaints with the FERC seeking to reduce the ROE component of the transmission rates that MISO transmission owners, including OTP, may collect under the MISO tariff rate. FERC's most recent order, issued on November 19, 2020, adopted a revised ROE methodology and set the base ROE at 10.02% (10.52% with an adder) effective for the fifteen-month period from November 2013 to February 2015 and on a prospective basis beginning in September 2016. The order also dismissed any complaints covering the period from February 2015 to May 2016. On August 9, 2022, the U.S. Court of Appeals for the District of Columbia Circuit vacated the FERC order citing a lack of reasoned explanation by FERC in its adoption of its revised ROE methodology as outlined in its November 2020 order. The U.S. Court of Appeals remanded the matter to FERC to reopen the proceedings.
Significant uncertainty exists as to how FERC will proceed on remand and there is no prescribed timeline under which FERC must act. We have deferred recognition and recorded a refund liability of $2.8 million as of December 31, 2023. This refund liability reflects our best estimate of amounts previously collected from customers under the MISO tariff rate that may be required to be refunded to customers once all regulatory and judicial proceedings are complete and a final ROE is established for the periods outlined above.
Regional Haze Rule (RHR). The RHR was adopted in an effort to improve visibility in national parks and wilderness areas. The RHR requires states, in coordination with the EPA and other governmental agencies, to develop and implement plans to achieve natural visibility conditions. The second RHR implementation period covers the years 2018-2028. States are required to submit a state implementation plan (SIP) to assess reasonable progress with the RHR and determine what additional emission reductions are appropriate, if any.
Coyote Station, OTP's jointly owned coal-fired power plant in North Dakota, is subject to assessment in the second implementation period under the North Dakota SIP. The NDDEQ submitted its SIP to the EPA for approval in August 2022. In its plan, the NDDEQ concluded it is not reasonable to require additional emission controls during this planning period. The EPA has previously expressed disagreement with the NDDEQ's recommendation to forgo additional emission controls and has indicated that such a plan is not likely to be accepted.
We cannot predict with certainty the impact the SIP may have on our business until the SIP has been approved or otherwise acted on by the EPA. However, significant emission control investments could be required and the recovery of such costs from customers would require regulatory approval. Alternatively, investments in emission control equipment may prove to be uneconomic and result in the early retirement or the sale of our interest in Coyote Station, subject to regulatory approval. We cannot estimate the ultimate financial effects such a retirement or sale may have on our consolidated operating results, financial position or cash flows, but such amounts could be material and the recovery of such costs in rates would be subject to regulatory approval.
Self-Funding of Transmission Upgrades. The FERC has granted transmission owners within MISO the unilateral authority to determine the funding mechanism for interconnection transmission upgrades that are necessary to accommodate new generation facilities connecting to the electrical grid. Under existing FERC orders, transmission owners can unilaterally determine whether the generator pays the transmission owner in advance for the transmission upgrade or, alternatively, the transmission owner can elect to fund the upgrade and recover over time from the generator the cost of and a return on the upgrade investment (a self-funding). FERC’s orders granting transmission owners this unilateral funding authority has been judicially contested on the basis that transmission owners may be motivated to discriminate among generators in making
funding determinations. In the most recent judicial hearing, the petitioners argued to the U.S. Court of Appeals for the District of Columbia that FERC did not comply with a previous judicial order to fully develop a record regarding the risk of discrimination and the financial risk absorbed by transmission owners for generator-funded upgrades. On December 2, 2022, the Court of Appeals ruled in favor of the petitioners remanding the matter to FERC, instructing the agency to adequately explain the basis of its orders. The Court of Appeals decision did not vacate transmission owners’ unilateral funding authority.
OTP, as a transmission owner in MISO, has exercised its authority and elected to self-fund previous transmission upgrades necessary to accommodate new system generation. Under such an election, OTP is recovering the cost of the transmission upgrade and a return on that investment from the generator over a contractual period of time. Should FERC, on remand from the Court of Appeals, eliminate transmission owners’ unilateral funding authority, on either a prospective or retrospective basis, our financial results would be impacted. We cannot at this time reasonably predict the outcome of this matter given the uncertainty as to how and when FERC may respond to the judicial remand.
Other Contingencies. We are party to litigation and regulatory enforcement matters arising in the normal course of business. We regularly analyze relevant information and, as necessary, estimate and record accrued liabilities for matters in which a loss is probable of occurring and can be reasonably estimated. We believe the effect on our consolidated operating results, financial position and cash flows, if any, for the disposition of all matters pending as of December 31, 2023 will not be material.