XML 35 R40.htm IDEA: XBRL DOCUMENT v2.4.0.6
Contingencies and Commitments (Details) (USD $)
6 Months Ended 6 Months Ended
Jun. 30, 2012
Dec. 31, 2011
Jun. 30, 2012
Tutor-Saliba-Perini Joint Venture vs. Los Angeles MTA Matter [Member]
Jun. 30, 2012
Tutor Saliba Perini Joint Venture vs Los Angeles MTA Matter - Tunnel Handrail Verdict [Member]
Jun. 30, 2012
Perini/Kiewit/Cashman Joint Venture-Central Artery/Tunnel Project Matter [Member]
Jun. 30, 2012
Long Island Expressway/Cross Island Parkway Matter [Member]
Jun. 30, 2012
Queensridge Matter [Member]
Jun. 30, 2012
Gaylord Hotel and Convention Center Matter [Member]
Jun. 30, 2012
Fontainebleau Matter [Member]
Jun. 30, 2012
MGM CityCenter Matter [Member]
acre
Mar. 31, 2010
MGM CityCenter Matter [Member]
Jun. 30, 2012
Honeywell Street/Queens Boulevard Bridges Matter [Member]
Jun. 30, 2012
Westgate Planet Hollywood Matter [Member]
Jun. 30, 2012
Brightwater Matter [Member]
Jun. 30, 2012
156 Stations Matter [Member]
Jun. 30, 2012
156 Stations Matter [Member]
Minimum [Member]
Jun. 30, 2012
156 Stations Matter [Member]
Maximum [Member]
Loss Contingencies [Line Items]                                  
Settlement on judgment     $ 3,000,000 $ (500,000)                     $ 11,900,000    
Value of claim filed           53,800,000 35,000,000 40,000,000       8,750,000 22,300,000   25,000,000    
Ownership percentage in joint venture (in hundredths)         56.00%                 20.00%      
Period over which series of claims instituted         10 years                        
Estimated costs of owner-directed changes to work         100,000,000                        
Number of construction experts in Disputes Review Board         3                        
Total number of Disputes Review Board panels         5                        
Total value of DRB awards issued in PKC's favor         128,000,000                        
Total value of binding DRB awards issued in PKC's favor         110,000,000                        
Amount of Third DRB awards previously awarded to PKC which have been vacated by Court         56,500,000                        
Amount of Fourth DRB awards that MHD moved to vacate         13,700,000                        
Amount of Fourth DRB awards previously awarded to PKC which have been vacated by Court         8,000,000                        
Interest award payment received by PKC from MHD         22,000,000                        
Estimated value of project           130,000,000                      
Amount receivable as per final agreement           500,000                      
Value of counterclaim filed           151,000,000           74,600,000 45,000,000 (75,000,000)   25,000,000 36,000,000
Subcontractors' liens on the property             19,000,000                    
Outstanding liens on property             24,000,000   44,000,000 313,000,000 491,000,000   19,300,000        
Arbitration demand filed by PBC for contract damages             25,000,000                    
Arbitration demand filed by PBC for punitive damages             10,000,000                    
Business interruption costs assigned to PTJV               11,000,000                  
Number of rooms in hotel/casino complex                 3,800                
Amount of court order in favor of plaintiff                 45,000,000                
Amount set aside from approved sale for distribution to satisfy creditor claims                 125,000,000                
Estimated sustainable lien amount                 350,000,000                
Number of contracts in project                   19              
Area allotted to the project (in acres)                   66              
Estimated cost to repair facility                   21,000,000              
Estimated cost to repair facility due to design defects                   15,000,000              
Amount settled at discount with MGM                   301,000,000              
Contracts receivable recorded by entity 1,198,764,000 1,275,031,000               192,000,000              
Partial collection of amounts owed                   15,000,000              
Pass-through subcontractor billings                   61,000,000     12,000,000        
Value of mechanic's lien release bond                         22,300,000        
Amount alleged for non conforming and defective work                         51,000,000        
Value of alleged damages sought                           74,000,000      
Amended value of alleged damages sought                           $ 132,000,000      
Number of stations for the New York City Transit Authority                             156    
Maximum number of days awarded claim must be paid (in days)                             45 days