XML 48 R36.htm IDEA: XBRL DOCUMENT v3.25.2
Commitments and Contingencies (Tables)
6 Months Ended
Jun. 30, 2025
Commitments and Contingencies Disclosure [Abstract]  
Schedule of Warranty Reserves
Warranty reserve activity consisted of the following (in thousands):
 
 Three Months Ended June 30,Six Months Ended June 30,
 2025202420252024
Warranty reserves, beginning of period$113,865 $106,602 $116,150 $106,993 
Warranty reserves accrued9,344 9,834 16,532 17,734 
Warranty expenditures(14,804)(9,240)(24,277)(17,531)
Warranty reserves, end of period$108,405 $107,196 $108,405 $107,196 
Schedule of Lease Costs and Other Information See below for additional information on leases (dollars in thousands):
Three Months Ended June 30, 2025Three Months Ended June 30, 2024Six Months Ended June 30, 2025Six Months Ended June 30, 2024
Lease Cost
Operating lease cost (included in SG&A expense)$3,411 $3,050 $6,633 $5,904 
Ground lease cost (included in other operations expense)793 765 1,587 1,530 
Sublease income, operating leases— — — — 
Sublease income, ground leases (included in other operations revenue)(805)(777)(1,610)(1,553)
Net lease cost$3,399 $3,038 $6,610 $5,881 
Other information
Cash paid for amounts included in the measurement of lease liabilities:
Operating lease cash flows (included in operating cash flows)$3,439 $3,410 $6,673 $5,912 
Ground lease cash flows (included in operating cash flows)$664 $664 $1,327 $1,327 
Right-of-use assets obtained in exchange for new operating lease liabilities$17,095 $3,374 $17,925 $5,264 
June 30, 2025December 31, 2024
Weighted-average discount rate:
Operating leases5.3 %5.0 %
Ground leases10.2 %10.2 %
Weighted-average remaining lease term (in years):
Operating leases5.95.6
Ground leases43.043.4
Schedule of Future Minimum Lease Payments
The future minimum lease payments under our operating leases are as follows (in thousands):
Property, Equipment and Other Leases
Ground Leases (1)
Remaining in 2025$5,684 $1,619 
202613,477 3,237 
202713,072 3,237 
202812,723 3,237 
202911,218 3,237 
Thereafter17,784 72,165 
Total lease payments$73,958 $86,732 
Less: Interest11,141 59,280 
Present value of operating lease liabilities$62,817 $27,452 
 __________
(1)    Ground leases are fully subleased through 2041, representing $52.9 million of the $86.7 million future ground lease obligations.