XML 63 R47.htm IDEA: XBRL DOCUMENT v3.24.1.1.u2
Electric utility segment - Utility Projects (Details)
$ in Millions
1 Months Ended 3 Months Ended
Jan. 31, 2024
USD ($)
Sep. 30, 2020
MW
Mar. 31, 2024
USD ($)
Dec. 31, 2023
USD ($)
Aug. 29, 2023
USD ($)
Nov. 30, 2021
USD ($)
Oct. 31, 2020
transmission_line
generationUnit
kV
Hawaiian Electric Company, Inc. and Subsidiaries              
Public Utilities, General Disclosures [Line Items]              
Public utilities, project cost recovery cap         $ 95.0    
Project costs incurred     $ 1.5        
Waena Switchyard/Synchronous Condenser Project | Hawaiian Electric Company, Inc. and Subsidiaries              
Public Utilities, General Disclosures [Line Items]              
Number of extended transmission lines | transmission_line             2
Number of kilovolts | kV             69
Number of generating units converting to synchronous condensers | generationUnit             2
Renewable energy generation project, approved funds           $ 38.8  
Renewable energy generation project, incurred cost     25.3        
Waena Battery Energy Storage System Project              
Public Utilities, General Disclosures [Line Items]              
Total contracted battery energy storage system capacity | MW   40          
Waena Battery Energy Storage System Project | Hawaiian Electric Company, Inc. and Subsidiaries              
Public Utilities, General Disclosures [Line Items]              
Renewable energy generation project, approved funds       $ 82.1      
Renewable energy generation project, incurred cost     $ 0.6        
Climate Adaptation Transmission And Distribution Resilience Program | Hawaiian Electric Company, Inc. and Subsidiaries              
Public Utilities, General Disclosures [Line Items]              
Public utilities, electric grid project, approved funds $ 189.7            
Project period 5 years