XML 50 R39.htm IDEA: XBRL DOCUMENT v3.25.3
Leases (Tables)
9 Months Ended
Sep. 30, 2025
Leases [Abstract]  
Schedule of Primary Office Leases and Maturity of Lease Liabilities
The following table summarizes our primary office leases as of September 30, 2025 (in thousands, other than term):
LocationLease Termination Term (in years)Future Minimum Lease CommitmentsLetter of Credit Amount Required
Arlington, VA5.3$2,846 $— 
Edison, NJ0.6349 222 
Makati City, Philippines2.71,815 — 
Pune, India2.51,416 — 
Brea, CA1.61,649 — 
Maturity of lease liabilities including future lease termination payments (in thousands) is as follows:
Operating lease expense
2025$3,323 
202615,802 
20272,204 
2028977 
2029548 
Thereafter609 
Total lease payments23,463 
Less:
Interest1,088 
Present value of lease liabilities$22,375 
Schedule of Components of Lease Expense, Weighted-Average Discount Rate and Weighted-Remaining Lease Terms
The following table summarizes the components of our lease expense (in thousands):
For the Three Months Ended September 30,For the Nine Months Ended September 30,
2025202420252024
Operating lease cost, net of sublease income$1,033 $1,131 $883 $2,590 
Variable lease cost777 1,314 2,699 4,387 
Total lease cost$1,810 $2,445 $3,582 $6,977 
Our weighted-average discount rate and our weighted remaining lease terms (in years) are as follows:

September 30, 2025December 31, 2024
Weighted average discount rate8.17 %9.09 %
Weighted average remaining lease term2.34.3