NOTE 6 – REGULATORY MATTERS

UNITIL'S REGULATORY MATTERS ARE DESCRIBED IN NOTE 6 TO THE FINANCIAL STATEMENTS IN ITEM 8 OF PART II OF UNITIL CORPORATION'S FORM 10-K FOR DECEMBER 31, 2010 AS FILED WITH THE SECURITIES AND EXCHANGE COMMISSION ON FEBRUARY 3, 2011.

Regulatory Matters

Fitchburg – Base Rate Case Filings – On January 14, 2011, Fitchburg filed a petition with the MDPU requesting approval of a comprehensive revenue decoupling proposal and for an increase in its electric and gas distribution rates. The Company's revenue decoupling proposal is modeled closely on proposals already approved by the Department for other gas and electric utilities operating in the Commonwealth of Massachusetts and is intended to facilitate the achievement of important public policy objectives of fostering energy efficiency, conservation and protecting the environment. The proposed rates are scheduled to change in conjunction with the implementation of revenue decoupling and are subject to the review and approval of the MDPU.

In its rate filing the Company made a request for an increase of $7.1 million in its annual electric distribution revenues, including the recovery of deferred emergency storm restoration costs incurred as a result of the December 2008 ice storm and subsequent restoration. The MDPU had earlier approved Fitchburg's petition to defer and record as a regulatory asset costs associated with the repair of its electric distribution system from the ice storm damage for future recovery in rates. The order of approval made no findings as to whether the subject expenses were reasonable or whether they can be recovered from ratepayers, and confirmed that the MDPU would consider the subsequent ratemaking treatment of the expense as part of Fitchburg's rate case, along with the Company's rate of return. As of June 30, 2011, Fitchburg has deferred approximately $13.4 million associated with the repair of its electric distribution system for future recovery in rates.

Also in the rate filing, the Company proposed a rate-impact mitigation alternative in order to offset, in whole, the electric distribution rate increase with a corresponding decrease in its Transition Charge. The Transition Charge is the means by which Fitchburg recovers its power supply-related stranded costs and other restructuring-related regulatory assets, discussed above. Any offsetting decrease in the Transition Charge would allow for the recovery of the restructuring related stranded costs over an extended term.

The Company also filed a request for an increase of $4.4 million in its annual gas distribution revenues. The MDPU issued an order suspending and deferring the use of the rates for both the electric division and gas division until August 2, 2011. Hearings on the rate requests were held during April 2011, and briefs have been filed. A final decision from the MDPU is expected on August 2, 2011.

Granite State Gas Transmission, Inc. – Base Rate Case Filing – On June 29, 2010, Granite State filed a base transportation rate increase of $2.3 million in annual revenue with the Federal Energy Regulatory Commission ("FERC"), which is Granite State's first request for a rate change since its last general rate case in 1997. On July 30, 2010, the FERC ordered the rate increase to be effective on January 1, 2011, subject to refund and hearing and settlement procedures. On November 30, 2010, a settlement was filed on behalf of Granite State and all intervenors in the proceeding, resolving all issues in the docket. The settlement provided for an increase of approximately $1.7 million in annual revenue, based on new gas transportation rates to be effective January 1, 2011. The settlement was approved by the FERC on January 31, 2011.

On July 26, 2011, an amendment to the rate settlement agreement was filed on behalf of Granite State and the parties to this proceeding. If approved by the FERC, the amended settlement agreement will result in an additional increase of approximately $0.5 million in Granite State's annual revenues effective August 1, 2011. Under the amended settlement agreement, beginning in 2012, Granite State would also be permitted to file limited rate adjustment filings to recover the revenue requirements for future capital cost additions to transmission plant for major planned projects as stipulated in the amended settlement. The limited rate adjustment filings would be made annually on or about June 29 of each year to be effective August 1 of each year, and are projected to conclude in 2014 when these major projects will be completed. The estimated annual revenue increases for these limited rate adjustment filings of approximately $0.3 million, $0.3 million and $0.6 million would occur on August 1, 2012, August 1, 2013 and August 1, 2014, respectively.

Unitil Energy Base Rate Case Filing – On April 15, 2010, Unitil Energy filed a proposed increase of $10.1 million in annual base revenue, an increase of 6.5 percent above annual operating revenue. In addition, Unitil Energy's filing included a proposed long-term rate plan establishing future rate step adjustments for utility plant investments and enhanced reliability and vegetation management program expenditures.

On April 26, 2011, the NHPUC approved a final rate settlement which had been reached among the Company, the NHPUC Staff and the Office of Consumer Advocate, resolving all matters concerning the base rate filing. The settlement makes permanent a temporary increase of $5.2 million in annual revenue which went into effect on July 1, 2010. The settlement also provides for an additional increase of $5.0 million in annual revenue which went into effect on May 1, 2011.

The settlement extends through May 1, 2016 and provides for a long-term rate plan and earnings sharing mechanism, with estimated future increases of $1.5 million, $1.9 million and $1.4 million in annual revenue to occur on May 1, 2012, May 1, 2013 and May 1, 2014, respectively, to support Unitil Energy's continued capital improvements to its distribution system. The rate plan allows Unitil to file for additional rate relief if its return on equity is less than seven percent and a sharing of earnings with customers if its return on equity is greater than ten percent in a calendar year. The settlement provides that Unitil Energy's authorized return on equity would remain at 9.67%, and that the Company will use a common equity ratio of 45.45% and an overall weighted cost of capital of 8.39% to determine changes to distribution rate levels.

 

The settlement approved Unitil's proposal for an augmented vegetation management program and reliability enhancement program. Under the augmented vegetation management program, Unitil Energy will be increasing its vegetation management spending from a current spending level of approximately $1.0 million to $3.1 million by 2013. Under the new reliability enhancement program, Unitil Energy will spend $1.8 million annually towards targeted projects designed to enhance system reliability. The funding for both of these programs is included in the future rate increases discussed above.

The settlement provides for recovery of deferred December 2008 ice storm and February 2010 wind storm costs of approximately $7.6 million, including carrying charges. These costs will be recovered over eight years in the form of a tariff surcharge. Finally, the settlement establishes a major storm reserve of $400,000 annually, which will be used to recover costs associated with responding to and recovering from future qualifying major storm events.

Northern Utilities Base Rate Case Filings – In May 2011, Northern Utilities filed two separate rate cases requesting approval to change its natural gas distribution base rates in New Hampshire and Maine, with the NHPUC and the MPUC, respectively.

The filings represent the first rate case in approximately 10 years for Northern's New Hampshire gas distribution operations and 28 years for its Maine gas distribution operations. In New Hampshire, the Company has requested an increase of $5.2 million in annual gas distribution base revenue, which represents an increase of approximately 8.1 percent over annual operating revenue. In Maine, the Company has requested an increase of $10.1 million in annual gas distribution base revenue or an increase of approximately 16.7 percent over current operating revenue. Both filings include a proposed capital cost recovery tracking mechanism to recover the future costs associated with Northern's cast iron and bare steel pipe replacement programs. The rate case filings are subject to regulatory review and approval with final rate orders expected in the first half of 2012. Northern has also requested temporary rates in both states. In New Hampshire, a settlement of temporary rates was reached among the Company, the NHPUC Staff and the Office of Consumer Advocate. It provides for a temporary increase of approximately $1.7 million in annual revenue to become effective as of August 1, 2011. On July 22, 2011, the NHPUC approved the temporary revenue increase as filed. In New Hampshire, once permanent rates are approved by the NHPUC, they will be reconciled to the date temporary rates were established, August 1, 2011. The request for temporary rates in Maine remains pending before the MPUC.

Fitchburg – Management Audit – As a result of its investigation of Fitchburg's preparation for, and response to, the December 2008 Ice Storm, the MDPU ordered a comprehensive independent management audit of Fitchburg's management practices. The management audit, which was performed by Jacobs Consultancy, Inc. (Jacobs), was completed and the audit report was submitted by Jacobs to the MDPU on April 13, 2011. The Audit Report found Unitil's management practices to be comprehensive, sound and in-line with industry practice. It also included sixteen recommendations intended to further improve the results of Unitil's management strategy, and acknowledged that many of these recommendations were already being implemented by the Company.

Fitchburg – Electric Operations – On November 24, 2010, Fitchburg submitted its annual reconciliation of costs and revenues for Transition and Transmission under its restructuring plan (the Annual Reconciliation Filing). In addition, the Standard Offer Service and Default Service Costs incurred during the seven year Standard Offer Service period that ended February 28, 2005 have been combined and recovery continues through a Transition Charge Surcharge of $0.00400 per kWh. Changes to the Pension/PBOP Adjustment, Residential Assistance Adjustment Factor, and Net Metering Recovery Surcharge were proposed in other proceedings. The rates were approved effective January 1, 2011, subject to reconciliation pending investigation by the MDPU. This matter remains pending. A final order on Fitchburg's 2009 Annual Reconciliation Filing also remains pending.

Fitchburg – Gas Operations – On November 2, 2009 the MDPU issued an order finding that Fitchburg engaged in certain price stabilization practices for the 2007 / 2008 and 2008 / 2009 heating seasons without the MDPU's prior approval and that Fitchburg's gas purchasing practices were imprudent. As a result, the MDPU required Fitchburg to refund $4.6 million of natural gas costs, plus an appropriate carrying charge based on the prime lending rate, to its gas customers. The Company recorded a pre-tax charge of $4.9 million in the fourth quarter of 2009 based on the MDPU's order. On November 30, 2009, the MDPU approved Fitchburg's proposal to amortize its refund of natural gas costs to customers over a five-year period. Fitchburg has appealed the gas procurement order to the Massachusetts Supreme Judicial Court (SJC). Fitchburg believes that its gas-procurement practices were consistent with those of other Massachusetts natural gas distribution companies and all relevant MDPU rules and orders and Massachusetts law. The Company filed its initial brief in this matter on January 10, 2011. This appeal remains pending before the Massachusetts SJC.

Fitchburg – Other – On July 2, 2008, the Governor of Massachusetts signed into law "The Green Communities Act" (the GC Act), an energy policy statute designed to substantially increase energy efficiency and the development of renewable energy resources in Massachusetts. The GC Act provides for utilities to recover in rates the incremental costs associated with its various mandated programs. Several regulatory proceedings have been initiated to implement various provisions of the GC Act, including provisions for each distribution company to file enhanced three-year energy efficiency investment plans, plans to establish smart grid pilot programs, proposals to purchase long-term contracts for renewable energy, special tariffs to allow the net metering of customer-owned renewable generation, and terms and conditions for purchasing supplier receivables. Three year energy efficiency investment plans, plans to establish smart grid pilot programs, and net metering tariffs have been approved by the MDPU. On June 16, 2011, the MDPU issued its final order with respect to the terms and conditions for purchasing supplier receivables (POR). Under POR, the electric distribution companies purchase the billing accounts receivable of competitive suppliers operating in their service territories.

On January 26, 2011, the MDPU issued orders with respect to Fitchburg's 2008 and 2009 Service Quality Reports for its electric division. Fitchburg failed to meet certain of its service quality benchmarks in 2008, and a penalty of $100,478 was ordered to be refunded to its electric customers. The Company refunded this amount to customers in their June and July 2011 billings. For 2009 performance, no net penalty was assessed. As required by the Order, on February 16, 2011 Fitchburg filed a report regarding the actions it has taken to improve its performance in the metrics it had not met.

On March 1, 2011, Fitchburg submitted its 2010 Service Quality Reports for both its gas and electric divisions. Fitchburg reported that it met or exceeded its benchmarks for service quality performance in all metrics for both its gas and electric divisions.

Unitil Energy – Other – In July 2008, the State of New Hampshire enacted legislation that allows electric utilities to make investments in distributed energy resources, including energy efficiency and demand reduction technologies, as well as clean cogeneration and renewable generation. On August 5, 2009 Unitil Energy filed a plan for approval of investment in and rate recovery for Distributed Energy Resources (DER). An order approving a settlement agreement for a time-of-use pilot program was issued on February 26, 2010. On June 11, 2010, the NHPUC issued an order on the remaining two proposed projects and cost recovery. The NHPUC denied one of the two projects, citing that the costs outweighed the benefits but found the other project to be in the public interest. On November 1, 2010 Unitil Energy filed adjustments to base distribution rates to collect actual costs associated with authorized DER projects. The first step adjustment was approved and became effective on April 1, 2011.

Unitil Energy – Billing – In early February 2011, Unitil Energy discovered that the electricity consumption of one of its larger customers, The Riverwoods Company at Exeter, had been incorrectly billed since September 10, 2004. The cause of the billing error has been determined to be a current transformer connected to the customer's meter, which had been mislabeled by the manufacturer, and caused the Company to overcharge the customer for bills issued from October 2004 through January 2011. The amount of the customer's overpayment is calculated to be approximately $1.8 million. The Company has taken steps to correct the problem by changing its existing billing procedures for this customer. The Company has filed a petition with the NHPUC requesting a declaratory ruling confirming the time period for calculation of a refund to the customer. Statutory provisions may limit the time period for which the Company is responsible for reparations. The Company has also requested authorization to adjust certain account balances in order to correct for this over-collection, which resulted in other customers' bills being artificially lower than they should have been. The Company believes that an adjustment to the balances of these accounts is appropriate to bring them to the levels they would have been but for the over-collection, and to permit recovery from other customers of approximately $1.4 million, the amount by which they benefited as a result of the over-collection. This would limit the Company's responsibility of the overcharge to approximately $350,000. In the meantime, the Company has provided a refund to the customer of $611,699, which was calculated based upon the Company's understanding of the statutory limitation on reparations for such overcharges. The Company has indicated that it is willing to refund to the customer the full amount of the overcharge, provided that the Commission issues a final ruling that such payment will not run afoul of the statutory limitation on such reparations, and that the Company is authorized to adjust its account balances for the entire period in order to permit collection from other customers of the amount they were undercharged. This matter remains pending. See additional discussion on this matter below in "Legal Proceedings."

Northern Utilities – Other – On November 21, 2008, the MPUC issued an order approving a settlement agreement resolving a number of Notices of Probable Violation (NOPVs) of certain safety related procedures and rules by Northern Utilities. Under the Settlement, Northern Utilities will incur total expenditures of approximately $3.8 million for safety related improvements to Northern Utilities' distribution system to ensure compliance with the relevant state and federal gas safety laws, for which no rate recovery will be allowed. These compliance costs were accrued by Northern Utilities prior to the acquisition date and the remaining amount on the Company's unaudited consolidated balance sheet at June 30, 2011 was $0.7 million.

On June 27, 2008 the MPUC opened an investigation of Northern Utilities' cast iron pipe replacement activities and the benefits of an accelerated replacement program for cast iron distribution pipe remaining in portions of Northern Utilities' Maine service areas. In an order issued on July 30, 2010, the MPUC approved a Settlement Agreement resolving this matter, filed on behalf of Northern Utilities, the Maine Office of the Public Advocate, and several state legislator intervenors, which was filed with the MPUC on July 6, 2010. Under the Agreement, Northern Utilities will proceed with a comprehensive upgrade and replacement program (the Program), which will provide for the systematic replacement of cast iron, wrought iron and bare steel pipe in Northern Utilities' natural gas distribution system in Portland and Westbrook, Maine and the conversion of the system to intermediate pressure. The Agreement establishes the objective of completing the Program by the end of the 2024 construction season. Under the Agreement, the parties agreed to support a cost recovery mechanism that will provide for the timely recovery of prudently-incurred costs of the Program. The features of this cost recovery mechanism will be finalized during Northern Utilities' next base rate case proceeding, which is underway, as described above.

Northern Utilities – Maine Sales Tax Under–Collection – As part of a routine internal financial review related to 2010, it was determined that during the conversion of the Northern Utilities customer portfolio from the prior owner to Unitil's customer information system, a portion of Northern Utilities' commercial and industrial customers were incorrectly converted as exempt from Maine sales tax. As a result, the Company did not bill and collect sales tax from those customers as of the conversion of the customer portfolio in July 2009. The Company promptly contacted the Maine Revenue Service (MRS) to advise them of the error. A Settlement Agreement between Northern Utilities and MRS was executed on January 31, 2011. Among other things, the Settlement Agreement allowed the Company time to amend all sales tax returns for all relevant periods affected by the sales tax conversion error provided that at the time amended returns were filed that the Company would pay all additional sales tax due plus interest. The Settlement Agreement also provided a waiver from the MRS of any civil penalties for failure to pay such sales taxes at the time when they were due. Accordingly, on May 26, 2011, Northern filed amend sales tax returns and paid sales tax due of $1.0 million to the MRS pursuant to the settlement agreement. Pursuant to state law, the tax shortfall is a debt of the customer to the utility and the Company has a right to recover the sales tax from customers. On June 2, 2011, the Company reached agreement with the MPUC concerning the methodology and procedure by which customers who were incorrectly converted as exempt from Maine sales tax would be billed for their sales tax arrears. The billing and collection of the tax arrears began in June 2011 and the Company anticipates that it will recoup substantially all of the arrears as a result of the collection effort.

Legal Proceedings

The Company is involved in legal and administrative proceedings and claims of various types, which arise in the ordinary course of business. The Company believes, based upon information furnished by counsel and others, that the ultimate resolution of these claims will not have a material impact on the Company's financial position.

 

A putative class action complaint was filed against Fitchburg on January 7, 2009 in Worcester Superior Court in Worcester, Massachusetts, captioned Bellerman v. Fitchburg Gas and Electric Light Company. On April 1, 2009, an Amended Complaint was filed in Worcester Superior Court and served on Fitchburg. The Amended Complaint seeks an unspecified amount of damages, including the cost of temporary housing and alternative fuel sources, emotional and physical pain and suffering and property damages allegedly incurred by customers in connection with the loss of electric service during the ice storm in Fitchburg's service territory in December, 2008. The Amended Complaint includes M.G.L. ch. 93A claims for purported unfair and deceptive trade practices related to the December 2008 Ice Storm. On September 4, 2009, the Superior Court issued its order on the Company's Motion to Dismiss the Complaint, granting it in part and denying it in part. The Company anticipates that the court will decide whether the lawsuit is appropriate for class action treatment in the fall of 2011. The Company continues to believe the suit is without merit and will defend itself vigorously.

A civil suit was filed against Unitil Energy on June 20, 2011 in Rockingham County Superior Court in Brentwood, New Hampshire, captioned The Riverwoods Company at Exeter v. Unitil Energy Systems, Inc. The suit alleges damage claims for negligence, breach of contract and violation of the New Hampshire Consumer Protection Act, RSA chapter 358-A. Riverwoods seeks recovery of $1.2 million, representing its claim for the balance of overpayments incurred as a result of a billing error, as well as interest, fees and costs, and double or treble damages pursuant to RSA chapter 358-A. The dispute which is the subject matter of this action is also the subject of a petition filed by Unitil Energy with the NHPUC, and which is described more fully above in "Regulatory Matters."