NOTE 6 – REGULATORY MATTERS

UNITIL’S REGULATORY MATTERS ARE DESCRIBED IN NOTE 8 TO THE FINANCIAL STATEMENTS IN ITEM 8 OF PART II OF UNITIL CORPORATION’S FORM 10-K FOR DECEMBER 31, 2014 AS FILED WITH THE SECURITIES AND EXCHANGE COMMISSION ON JANUARY 28, 2015.

Regulatory Matters

Northern UtilitiesBase RatesMaine – On December 27, 2013, the Maine Public Utilities Commission (MPUC) approved a settlement agreement providing for a $3.8 million permanent increase in annual revenue for Northern Utilities’ Maine division, effective January 1, 2014. The settlement agreement also allowed the Company to implement a Targeted Infrastructure Replacement Adjustment (TIRA) rate mechanism to adjust base distribution rates annually to recover the revenue requirements associated with targeted investments in gas distribution system infrastructure replacement and upgrade projects. The TIRA has an initial term of four years and covers targeted capital expenditures in 2013 through 2016. The 2014 TIRA provided for an annual increase in base distribution revenue of $1.3 million, effective May 1, 2014. The 2015 TIRA provided for an annual increase in base distribution revenue of $1.2 million, effective May 1, 2015.

Northern UtilitiesBase RatesNew Hampshire – On April 21, 2014, the NHPUC approved a settlement agreement providing for an increase of $4.6 million in distribution base revenue, effective May 1, 2014. The settlement agreement provided for additional step adjustments in 2014 and 2015 to recover the revenue requirements associated with investments in gas mains extensions and infrastructure replacement projects. The 2014 step adjustment provided for an annual increase in revenue of $1.4 million, effective May 1, 2014. The 2015 step adjustment provided for an annual increase of $1.8 million in revenue effective May 1, 2015.

Northern UtilitiesPipeline Refund – On February 19, 2015 the FERC issued Opinion No. 524-A, the final order in Portland Natural Gas Transmission’s (PNGTS) Section 4 rate case, requiring PNGTS to issue refunds to shippers. Northern Utilities received a pipeline refund of $22.0 million on April 15, 2015. As a gas supply-related refund, the entire amount refunded will be credited to Northern Utilities’ customers. In New Hampshire, the refund will be credited to all customers over a three year period as directed by the NHPUC. In Maine, the refund has been divided into two parts, as directed by the MPUC. Maine retail customers who purchase their gas directly from Northern Utilities will be credited their portion of the refund over a three year period. The second part of the refund was paid on October 5, 2015 as a one-time lump sum payment directly to marketers who transport gas on Northern Utilities’ distribution system. The Company has recorded current and noncurrent Regulatory Liabilities of $11.1 million and $10.9 million, respectively, on its Consolidated Balance Sheets as of September 30, 2015.

Unitil Energy – On April 26, 2011, the NHPUC approved a rate settlement that extends through May 1, 2016 and provides for a long-term rate plan and earnings sharing mechanism, with a series of step adjustments to increase revenue in future years to support Unitil Energy’s continued capital improvements to its distribution system. The third and final step increase of $1.5 million in annual revenue was effective May 1, 2014.

Granite StateBase Rates – Granite State has in place a FERC approved amended settlement agreement under which it has been permitted each June to file for a rate adjustment to recover the revenue requirements associated with specified capital investments in gas transmission projects up to a specific cost cap. The final rate adjustment under this agreement was effective August 1, 2014. Granite State has received FERC approval of a second amended settlement agreement under which it will continue to be permitted to file annually, each June, for a rate adjustment to recover the revenue requirements associated with specified capital investments in gas transmission projects up to a cost cap. The FERC approval of the second amended settlement included a rate increase of $0.4 million, effective August 1, 2015.

FitchburgBase RatesElectric – On June 16, 2015 Fitchburg filed for a $3.8 million increase in electric base revenue, which represents a 5.6 percent increase over 2014 test year operating electric revenues. The filing included a request for approval of a capital cost recovery mechanism to recover prudently incurred additions to utility plant on an annual basis. The matter has been docketed by the MDPU and a procedural schedule has been established. By statute, the MDPU is afforded ten months to act on a request for a rate increase. A decision is expected by the end of April, 2016.

FitchburgBase RatesGas – On June 16, 2015 Fitchburg filed for a $3.0 million increase in gas base revenue, which represents an 8.3 percent increase over 2014 test year total gas operating revenues. The matter has been docketed by the MDPU and a procedural schedule has been established. By statute, the MDPU is afforded ten months to act on a request for a rate increase. A decision is expected by the end of April, 2016.

Major Storms – Fitchburg and Unitil Energy

Thanksgiving 2014 Snow Storm – Both Fitchburg and Unitil Energy experienced a significant snow storm that began the afternoon of November 26, 2014 and ended the morning of November 27, 2014, Thanksgiving Day. Unitil Energy spent approximately $2.1 million for the repair and replacement of electric distribution systems damaged during the storm, including $0.4 million related to capital construction and $1.7 million for which Unitil Energy will seek recovery through its approved storm reserve fund, subject to review by the NHPUC in a future regulatory proceeding. Fitchburg spent approximately $0.3 million for the repair and replacement of electric distribution systems damaged during the storm, including $0.1 million related to capital construction and $0.2 million in storm expense. As Fitchburg does not have an approved storm reserve fund, these expenses resulted in a pre-tax charge against 2014 earnings of $0.2 million. The Company does not believe these storm restoration expenditures and the timing of cost recovery will have a material adverse impact on the Company’s financial condition or results of operations.

FitchburgElectric Operations – On November 24, 2014, Fitchburg submitted its annual reconciliation of costs and revenues for transition and transmission under its restructuring plan. The filing also includes the reconciliation of costs and revenues for a number of other surcharges and cost factors which are subject to review and approval by the MDPU. All of the rates were approved effective January 1, 2015 for billing purposes, subject to reconciliation pending investigation by the MDPU. This filing was approved on June 16, 2015.

FitchburgGas Operations – On June 26, 2014, the Governor of Massachusetts signed into law a gas leak bill providing for the following, among other items: amends MDPU’s ability to fine gas companies for violations of gas pipeline safety rules consistent with federal law; establishes a uniform natural gas leak classification standard for the Commonwealth; provides that the MDPU investigate new programs and policies to facilitate customer conversions to natural gas; and establishes an infrastructure replacement program to address aging natural gas pipeline infrastructure. The infrastructure replacement program allows gas distribution companies to accelerate the replacement of eligible infrastructure in order to improve public safety or infrastructure reliability, and to reduce or potentially reduce lost and unaccounted for natural gas. The law also authorizes gas companies to begin to recover through rates the estimated costs associated with infrastructure plans once they are approved by the MDPU, subject to reconciliation to actual prudently incurred costs. Pursuant to this new law, on October 31, 2014, Fitchburg Gas filed with the MDPU a 20 year gas system enhancement plan to replace aging natural gas pipeline infrastructure. On April 30, 2015, the MDPU approved the Company’s plan and allowed the Company to collect $0.3 million to recover the estimated cost to be incurred in calendar year 2015, the first year of the program, to replace eligible leak-prone infrastructure, effective May 1, 2015. The second annual filing, to recover the estimated costs to be incurred in calendar year 2016, will be made on October 31, 2015, for rates effective May 1, 2016.

FitchburgService Quality – On March 1, 2015, Fitchburg submitted its 2014 Service Quality Reports for both its gas and electric divisions. Fitchburg reported that it met or exceeded its benchmarks for service quality performance in all metrics for its gas division except for the metric related to consumer complaints. As a result of penalty offsets earned, no net penalty was assessed. The electric division met or exceeded all metric benchmarks. On December 22, 2014, the MDPU approved Fitchburg’s 2011 electric division Service Quality Report as filed. On July 7, 2015, the MDPU approved Fitchburg’s 2013 gas division Service Quality Report as filed. Fitchburg’s 2012, 2013, and 2014 electric division Service Quality Reports remain pending, as does its 2014 gas division Service Quality Report.

Amendments to MDPU Service Quality Guidelines – On December 22, 2014, the MDPU issued an order adopting new Service Quality Guidelines. The new guidelines, which are to be implemented over several years, establish state-wide standards for most metrics, impose new methods for calculating penalty thresholds, eliminate the ability to offset subpar performance in one metric by exemplary performance in another, and add several new or enhanced metrics. The joint utilities have filed a motion with the MDPU to reconsider the adoption of state-wide standards and have requested reconsideration and clarification on other technical issues. The Company does not believe that the MDPU’s new Service Quality Guidelines will have a material adverse impact on the Company’s financial condition or results of operations.

 

FitchburgOther – On February 5, 2013, there was a natural gas explosion in the city of Fitchburg, Massachusetts in an area served by Fitchburg’s gas division resulting in property damage to a number of commercial and residential properties. The MDPU, pursuant to its authority under state and federal law, commenced an investigation of the incident, with which Fitchburg cooperated. The MDPU released its report of the incident on May 7, 2015, without finding of fault. No further action or investigation by the MDPU is anticipated. The Company does not believe this incident or investigation will have a material adverse impact on the Company’s financial condition, results of operations or cash flows.

On December 23, 2013, the MDPU opened an investigation into Modernization of the Electric Grid. The stated objective of the Grid Modernization proceeding is to ensure that the electric distribution companies “adopt grid modernization policies and practices.” On June 12, 2014, the MDPU issued its first Grid Modernization order, setting forth a requirement that each electric distribution company submit a ten-year strategic Grid Modernization Plan (GMP). As part of the GMP, each company must include a five-year Short-Term Investment Plan (STIP), which must include an approach to achieving advanced metering functionality within five years of the Department’s approval of the GMP. The filing of a GMP will be a recurring obligation and must be updated as part of subsequent base distribution rate cases, which by statute must occur no less often than every five years. Capital investments contained in the STIP are eligible for pre-authorization, meaning that the MDPU will not revisit in later filings whether the Company should have proceeded with these investments. On November 5, 2014, the MDPU issued two inter-related orders regarding Grid Modernization. The first order provided guidance and filing requirements for the business case justification that the electric companies must file as part of their GMPs. The second order required the electric companies to implement sufficient advanced metering functionality to enable the sale of electricity to Basic Service customers via time varying rates (rates which vary depending upon the period or time of day that the electricity is consumed). The MDPU determined that time varying rates will establish pricing signals that will enable customers to save money by altering usage patterns and reducing peak load, among other enumerated benefits. Fitchburg and the Commonwealth’s three other electric distribution companies filed their initial GMPs on August 19, 2015 and are awaiting commencement of the MDPU’s review. The MDPU is addressing in separate proceedings (1) cybersecurity, privacy, and access to meter data, and (2) electric vehicles. These matters remain pending.

Legal Proceedings

The Company is involved in legal and administrative proceedings and claims of various types, which arise in the ordinary course of business. The Company believes, based upon information furnished by counsel and others, that the ultimate resolution of these claims will not have a material impact on the Company’s financial position.

In early 2009, a putative class action complaint was filed against Unitil’s Massachusetts based utility, Fitchburg, in Massachusetts’ Worcester Superior Court (the “Court”), (captioned Bellermann et al v. Fitchburg Gas and Electric Light Company). The Complaint seeks an unspecified amount of damages, including the cost of temporary housing and alternative fuel sources, emotional and physical pain and suffering and property damages allegedly incurred by customers in connection with the loss of electric service during the ice storm in Fitchburg’s service territory in December 2008. The Complaint, as amended, includes M.G.L. ch. 93A claims for purported unfair and deceptive trade practices related to the December 2008 ice storm. Following several years of discovery, the plaintiffs in the complaint filed a motion with the Court to certify the case as a class action. On January 7, 2013, the Court issued its decision denying plaintiffs’ motion to certify the case as a class action. The plaintiffs appealed this decision to the Massachusetts Supreme Judicial Court (the “SJC”), and the SJC upheld the lower Court’s order. Subsequently, Plaintiffs filed a renewed motion to certify a class under a different theory than previously argued. The Company filed its opposition to this motion and also filed a motion for summary judgment. On July 27, 2015, the Court issued its decision allowing class certification and denying the Company’s motion for summary judgment. The Company appealed this decision to the SJC, and on October 15, 2015, the SJC granted the Company’s motion for direct review of the case. The Town of Lunenburg has filed a separate action in the Court arising out of the December 2008 ice storm. The Court accepted the parties’ joint schedule with discovery continuing into 2016 and trial likely in late 2016. The Company continues to believe that both of these suits are without merit and will continue to defend itself vigorously.