XML 145 R119.htm IDEA: XBRL DOCUMENT v3.8.0.1
Commitments, Contingencies and Legal Proceedings - Additional Information (Detail)
12 Months Ended
Dec. 31, 2017
USD ($)
Operable_Unit
Dec. 31, 2016
USD ($)
Dec. 31, 2015
USD ($)
Commitments Contingencies And Litigation [Line Items]      
Annual payments due under operating leases $ 37,600,000    
Aggregate contractual obligation $ 167,500,000    
Number of operable units | Operable_Unit 5    
Reserve for Environmental liabilities, current portion $ 28,500,000 $ 25,000,000  
Other Long-Term Liabilities [Member]      
Commitments Contingencies And Litigation [Line Items]      
Reserve for Environmental liabilities, remaining portion 14,600,000    
NCR/Appvion Consent Decree [Member]      
Commitments Contingencies And Litigation [Line Items]      
Contribution payment towards remedial action and natural resource damages 75,000,000    
Anticipated cost to complete work for remaining site remedy 200,000,000    
Expected payments for governments unreimbursed past costs which are under dispute     $ 34,000,000
Unreimbursed costs     0
Unspent settlement money     4,000,000
NADAR [Member]      
Commitments Contingencies And Litigation [Line Items]      
Expected payments for governments unreimbursed past costs which are under dispute 104,000,000    
Unspent settlement money 60,000,000    
Georgia Pacific [Member]      
Commitments Contingencies And Litigation [Line Items]      
Settlement payable amount $ 9,500,000    
Payment due date 2017-08    
Maximum [Member]      
Commitments Contingencies And Litigation [Line Items]      
NCR costs and damages percentage 100.00%    
Maximum [Member] | NCR/Appvion Consent Decree [Member]      
Commitments Contingencies And Litigation [Line Items]      
Estimated cost related to Fox River matter $ 30,000,000    
Minimum [Member] | December 2009 - Long Term Monitoring Plan [Member]      
Commitments Contingencies And Litigation [Line Items]      
Period over which cash expenditure to be incurred for monitoring activities 30 years    
Minimum [Member] | GLT, GP and NCR [Member] | NCR/Appvion Consent Decree [Member]      
Commitments Contingencies And Litigation [Line Items]      
Contribution payment towards remedial action and natural resource damages $ 1,000,000,000    
OU2-5 [Member]      
Commitments Contingencies And Litigation [Line Items]      
Estimated future cost of cleanup work   $ 13,400,000 $ 13,400,000
Expected cleanup work continuation year through 2019    
NCR costs and damages percentage 100.00%    
OU2-5 [Member] | Whiting Litigation [Member]      
Commitments Contingencies And Litigation [Line Items]      
NCR costs and damages percentage 100.00%